19
2018

PowerPoint Presentation · Conclusions from Study Results •The review of the IRP therefore imply that the pace and scale of new capacity developments needed up to year 2030 must

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PowerPoint Presentation · Conclusions from Study Results •The review of the IRP therefore imply that the pace and scale of new capacity developments needed up to year 2030 must

2018

Page 2: PowerPoint Presentation · Conclusions from Study Results •The review of the IRP therefore imply that the pace and scale of new capacity developments needed up to year 2030 must

INTRODUCTION

Objectives of IRP is to provide electricity infrastructure plan that aims to:

• The Integrated Resource Plan (IRP) 2010-30 was promulgated in March 2011;

• Following public consultation, a number of policy decisions were adopted

which resulted in the final policy adjusted IRP 2010-30;

• In line with S34 of the Electricity Act, Minister of Energy use the promulgated IRP to

issue Determinations for new capacity; and

• Assumptions made in the IRP 2010-30 have since changed and therefore

necessitated an update.

ensure security of supply

minimise water usage

minimise cost of supply

reduce emissions

Page 3: PowerPoint Presentation · Conclusions from Study Results •The review of the IRP therefore imply that the pace and scale of new capacity developments needed up to year 2030 must

IRP in the Context of IEP

GLOBAL PARAMETERS and ASSUMPTIONS

Global Parameters (e.g. GDP, Discount rate, Exchange Rate, Fuel Costs)

• Technology Costs (Capital, O&M) • Plant performance • Plant operational life • Other technology parameters

IRP

• Technology Costs (Capital, O&M) • Plant performance • Plant operational life • Production slates • Other technology parameters

Liquid Fuels

• Infrastructure costs • Legislative framework

Gas

Level of maturity of national planning

• Electricity generation build plan • Transmission build plan • System Adequacy • Electricity Price Path

• Liquid Fuel Supply Options • Liquid fuel supply infrastructure • Location and logistics

• Gas development scenarios • Gas price scenarios • Gas supply and infrastructure • Legislation and policy SC

OP

E

KEY

PA

RA

MET

ERS

All primary energy carriers All primary energy carriers Indigenous and imported gas

Page 4: PowerPoint Presentation · Conclusions from Study Results •The review of the IRP therefore imply that the pace and scale of new capacity developments needed up to year 2030 must

IRP Update Process Stages

The IRP Update process consisted of four stages:

9 Public

Workshops in 9 Provinces

Total number of presentations from the public: 63

Total number of people who attended: 640

Written submissions received: 190

Input Assumptions were subjected to a public

consultation process between December 2016

and March 2017:

The

development

of input

assumptions,

The

development

of a credible

base-case (starting point)

and scenario

analysis,

The

production

of a

balanced plan,

The

production

of policy

adjusted plan.

Page 5: PowerPoint Presentation · Conclusions from Study Results •The review of the IRP therefore imply that the pace and scale of new capacity developments needed up to year 2030 must

Inputs from Consultation on Assumptions

Process Issues

Demand Forecast

The timing of the start of

the consultation process

Demand Forecast is outdated and that it does not take into account

current GDP projections

Frequency

of revision

of IRP

The link

between

the IRP

and IEP

Page 6: PowerPoint Presentation · Conclusions from Study Results •The review of the IRP therefore imply that the pace and scale of new capacity developments needed up to year 2030 must

Inputs from Consultation on Assumptions

Technology Costs

Exchange Rate

The costs used for RE

The publication of the Ingerop report

used to derive nuclear costs

The use of R11.55/$ vs R16/$ during consultations

Page 7: PowerPoint Presentation · Conclusions from Study Results •The review of the IRP therefore imply that the pace and scale of new capacity developments needed up to year 2030 must

Inputs from Consultation on Assumptions

Demand side

RE Constraints on preliminary base case

Need to account for energy

efficiency, embedded

generation and fuel switching

The IRP2010 imposed 1000MW and 1600MW annual

build limits on Photovoltaic (PV) and Wind Power respectively

Page 8: PowerPoint Presentation · Conclusions from Study Results •The review of the IRP therefore imply that the pace and scale of new capacity developments needed up to year 2030 must

Key Assumptions

• Electricity demand outlook as forecasted in the IRP 2010-30 has not been realized;

• Electricity pricing and commodity price issues impacting energy intensive users;

• Reduced energy intensity - Improved energy efficiency, partly as a mitigation for the electricity price increases;

• Growing number of generation for use ( example: rooftop Photo-voltaic (PV) installations); and

• Fuel switching from electricity to LPG for cooking and space heating.

• Additional Capacity brought online

• 18000MW commitments already made (Eskom & REIPPP).

• Lower than anticipated Existing Eskom Plant Performance;

• Constrained Transmission Network Capacity; and

• Changes in technology and fuel costs.

Page 9: PowerPoint Presentation · Conclusions from Study Results •The review of the IRP therefore imply that the pace and scale of new capacity developments needed up to year 2030 must

Key Assumptions

• The Draft IRP2016 demand forecast namely 2015/16 High less energy intense scenario shown in red is now

revised downward by 143TWh.

• Demand 33% less than IRP2010-30

Page 10: PowerPoint Presentation · Conclusions from Study Results •The review of the IRP therefore imply that the pace and scale of new capacity developments needed up to year 2030 must

Scenarios Studied

Page 11: PowerPoint Presentation · Conclusions from Study Results •The review of the IRP therefore imply that the pace and scale of new capacity developments needed up to year 2030 must

Update Results Analysis Periods

Page 12: PowerPoint Presentation · Conclusions from Study Results •The review of the IRP therefore imply that the pace and scale of new capacity developments needed up to year 2030 must

Conclusions from Study Results

• The review of the IRP therefore imply that the pace and scale of new capacity developments

needed up to year 2030 must be curtailed compared to that in the IRP 2010-30 projections.

• Ministerial Determinations for capacity beyond bid window 4 (27 projects) issued under the IRP

2010–30 must be reviewed and revised in line with the projected system requirements.

• Without a policy intervention, all technologies included in IRP 2010–30 where prices have not

come down like in the case of PV and Wind cease to be deployed as the “Least Cost” option

only contain PV, Wind and Gas.

• The significant change in energy mix post 2030 indicates the sensitivity of the results observed

to the assumptions made. A slight change to the assumptions can therefore change the path

chosen. In-depth analysis of the assumptions and the economic implications of the electricity

infrastructure development path chosen post 2030 will contribute to the mitigation of this risk.

• Confirm the plant for the period ending 2030 and detailed studies must be undertaken to

better inform the energy mix plan post 2030.

Page 13: PowerPoint Presentation · Conclusions from Study Results •The review of the IRP therefore imply that the pace and scale of new capacity developments needed up to year 2030 must

Summary Additional Capacity pre 2030

Least Cost Plan Plan With Renewal Energy Annual Limits

• Considerations for Policy Adjusted Plan

• Adopt a plan with annual build limits for period up to 2030. This provides for smooth roll out of renewable energy which will help sustain industry.

• Make provision for 1000MW in 2023/24 of Coal to Power based on two already procured projects. Jobs created from the projects will go a long way in minimising the impact of job losses due to decommissioning of Eskom coal power plants.

• Make provision for 2500MW in 2030 of Hydro Power to facilitate the RSA-DRC treaty on Inga Hydro Power project.

• Adopt a position that all new technologies identified and endorsed for localisation will be enabled through determinations utilising existing allocations.

• Adopt a position that makes annual allocations of 200MW for generation for own use between 1MW to 10MW starting year 2018. This allocations will not initially be discounted off the plan but will be discounted during the issuing of determinations taking into account generation for own use filed with NERSA.

Page 14: PowerPoint Presentation · Conclusions from Study Results •The review of the IRP therefore imply that the pace and scale of new capacity developments needed up to year 2030 must

Recommended Policy Adjusted Plan

In order to ensure innovation, most efficient power system and evolution to lowest cost, any resource that can provide the required service to the power system (supply side characteristic) should be able to compete.

Page 15: PowerPoint Presentation · Conclusions from Study Results •The review of the IRP therefore imply that the pace and scale of new capacity developments needed up to year 2030 must

Recommended Studies - Post 2030

• The following studies are recommended to inform the discussions studies of the post 2030

electricity mix at next IRP Update iteration.

• Detailed analysis of gas supply options (international and local) to better understand the

technical and financial risks and required mitigations for a renewable energy and gas

dominated electricity generation mix post 2030.

• Detailed analysis of the appropriate level of penetration of renewable energy in the South

African national grid to better understand the technical risks and mitigations required to

ensure security of supply is maintained during the transition to low carbon future.

• Detailed analysis of other clean energy supply options (Coal, Hydro, Nuclear and others)

including their associated costs and economic benefits.

• Detailed socio-economic impact analysis of the decommissioning of old coal fired power

plants that would have reached their end of life.

• Any other study as recommended by stakeholders.

Page 16: PowerPoint Presentation · Conclusions from Study Results •The review of the IRP therefore imply that the pace and scale of new capacity developments needed up to year 2030 must

Embedded or Distributed Generation

• With the changing electricity landscape, the Department of Energy, NERSA, Eskom and Municipalities are

faced with the challenge of managing and regulating the increasing number of Embedded Generators.

• The challenge with the Embedded Generators emanate from the lack of regulatory framework, technical

and installation specifications which pose risks to electrical network planning and system operations.

• The Department is inundated with requests for the Minister of Energy for approval to deviate from the IRP in

line with section 10(2)(g) in order for NERSA to process their applications for licensing to generate power.

• In order to manage the challenges indicated above, the Department on the 10th November 2017

published amendments to Schedule 2 of the Act. This dealt with installations of up to 1MW.

• While the published amended Schedule 2 correctly exempts all listed activities from holding a license,

some of the activities were inadvertently included with those requiring registration with NERSA when that

should not have been the case. Hence the publication for comments of a revised draft in June 2018.

• Installations above 1MW are being addressed through the IRP.

• All installations outside of the defined categories will in line with the Act still require a Ministerial Deviation.

The Department working with NERSA will be putting a process in place to efficiently attend to requests for

deviations

Page 17: PowerPoint Presentation · Conclusions from Study Results •The review of the IRP therefore imply that the pace and scale of new capacity developments needed up to year 2030 must

Embedded or Distributed Generation

• With regard to installations below 1MW, comments received from the public have been

processed and the Department is in the process of soughing concurrence from NERSA in line

with the requirements of the Act.

• Some of the amendments in addition to corrections include:

• The recognition of hybrid systems (e.g. PV with storage) by not limiting installed capacity but

generating capacity;

• The exemption of installations of less than 100kW from the requirement to register;

• The requirement for generation facilities previously exempt from holding a license to register within 6

months of the publication of the amended notice. This is to ensure visibility of this facilities to the

Regulator and to Department for planning purposes.

• With regard to facilities above 1MW, provision has been made in the IRP to do away with the

need for request for deviation from the Minister for facilities that are for own use.

• All other facilities outside of those defined will still require Ministerial deviation. The Department

is working with NERSA to come up with a streamlined process in this regard.

• The Department will as part of the IRP finalisation relook at the embedded generation

allocation in the IRP in line with comments received.

Page 18: PowerPoint Presentation · Conclusions from Study Results •The review of the IRP therefore imply that the pace and scale of new capacity developments needed up to year 2030 must

Battery Storage

• It is our view that all battery storage facilities (generation own use) up to 10MW are covered

by the provisions of the notice and the IRP.

• It is our view that those provisions are sufficient to enable battery storage deployment within

the distribution networks.

• It is also our view that like pumped storage, battery storage is a sink and a source. As a source,

its installation in large sizes has the potential to impact grid operation and stability and must

therefore be subjected to grid code requirements and therefore be licenced.

Page 19: PowerPoint Presentation · Conclusions from Study Results •The review of the IRP therefore imply that the pace and scale of new capacity developments needed up to year 2030 must

DANKIE KE A LEBOGA

NDI KHOU

LIVHUHA

NGIYABONGA NDIYABULELA

Thank you INKOMU