Power Station Projecy Report

Embed Size (px)

Citation preview

  • 8/7/2019 Power Station Projecy Report

    1/29

    A

    TRAINING REPORT

    AT

    132 KV SUBSTATION

    JIND (NEW)

    (24 July 2010 to 21 August 2010)

    Submitted to: Submitted by:

    Mr. Jugal Kishor Vikash Singh (0805809903)

    (H.O.D. of ELE Dept.) Branch ELE

    SCR Polytechnic GohiyanJind (Haryana)

  • 8/7/2019 Power Station Projecy Report

    2/29

    FOREWORD

    I was required to undergo on four weeks training during the July 2010

    to September 2010 towards the partial fulfillment of my diploma Being a

    student of Electrical Engineering. I choose to undertake this training at an

    Electrical Engineering, since it is a highly progressive sector these days, and

    the demand for power is on a rise. Therefore, I landed up at 132 KV

    substation Jind one of the good substation in Northern India and a fine

    source of Electric power distribution for the local areas The training was a

    great learning experience and I have tried to put what I learnt, through these

    pages.

  • 8/7/2019 Power Station Projecy Report

    3/29

    PREFACE

    Electricity is one of the most convenient and important source of energy

    electricity is used at home and in industry for various purposes such as

    lighting, heating operating machine and so on.

    Therefore, generation of electricity holds important place in our

    society. The generation of electricity and its per capita consumption is an

    index to the prosperity of a nation. Man has found a no. of ways to generate

    electricity. He began by tapping the energy generated by chemical reaction

    for e.g., in a Daniel cell. However, this form was suitable only for very small

    application. In addition, large amount of electricity could not be generated

    using this method and the output voltage was not suitable. Therefore, man

    sought new ways of electric power generation. In this question he invented

    huge power plants. The early plants used wood to generate steam for water,

    which in term used to drive an electric generation. However, this quick

    depletion of forests led man to look for alternative source of power. The

    power of falling water was used to generate electricity. However, a need was

    felt for more power generation. In addition, the Hydel-power station was

    costlier and tougher to establish, even though the cost of operations was

  • 8/7/2019 Power Station Projecy Report

    4/29

    lower consequently, in the mid twentieth century, coal was found to be a

    technologically and economically viable option for steam power generation.

    Today, most of the world's electric energy needs are met using coal

    Nevertheless, the progress can never stop. Even this cheap alternative has

    some limitation. The greatest problem is that of ash disposal. A huge amount

    of ash is generated in a coal-based station and it is highly harmful for man

    and his environment. Therefore, must of the new power station coming up in

    India are natural gas based. According to some experts, for sustainable

    development because of its low long-term availability can only be a

    transition fuel. Indeed, hydrogen is stipulated to be the fuel of the future.

    Clearly, the electric power requirement of man kind is on rise and therefore

    the need of looking at alternate and unconventional source of energy is being

    best. There are a no. of such sources, for instance, solar, geothermal, tidal

    wind etc. these source, though not sufficient all by themselves, can

    contribute significantly to our power needs.

    As such the consistent growth of power is vital to meet our day-to-

    day- requirements and improve the living standards.

  • 8/7/2019 Power Station Projecy Report

    5/29

    ACKNOWLEDGEMENT

    We as a group would like to express our heart filled gratitude to the various

    People those who have he pad us curing the entire training period. First of all

    We would spastically like to extend a word of thanks to J.E. Mr.Jyoti

    Sharma, Haryana Vidyut Para saran Nigam limited 132KV substation, Jind.

    It was under his able guidance and leadership that we are permitted to be a

    Part of this esteemed substation.

    We also would like to thanks ALM Mr.Rajbir Nain & Mr. Virender Kundu

    (SA), of the substation for their Instrumental in guiding us to the various

    Processes in the substation and Thus played vital role in enriching our

    Knowledge in the technical field.

  • 8/7/2019 Power Station Projecy Report

    6/29

    CONTENTS

    1. Introduction to HPGCL

    2. Introduction to substation JIND

    3. Switchyard

    Lightening Arrestor

    Capacitor Voltage Transformer

    Wave trap

    Current Transformer (CT)

    Potential Transformer (PT)

    Circuit Breaker

    Isolators

    Insulator

    Buses

    Power Transformer

    Neutral Current Transformer

    4. Power line Carrier Communication (PLCC)

    5. Battery Room

    6. Control Room

    7. Substation Auxiliaries Supply

    8. Earthing of Substation

  • 8/7/2019 Power Station Projecy Report

    7/29

    INTRODUCTIO N TO HPGCL

    Haryana Power Generation Corporation Limited (HPGCL) wasincorporated as a company under companies Act 1956on 17th March 1997

    and certificate for commencement of business was granted on 5 th August

    1997. The business of generation of power of erstwhile Haryana State

    Electrically Board was transferred to Haryana Power Generation

    Corporation Limited on 14th August 1998 pursuant to the implementation of

    power reforms in the state of Haryana. The main objective of HPGCL is to

    generate power in the state of Haryana from the existing station in most

    efficient manner on commercial lines and shell whole of the power

    generated exclusively to Haryana Vidyut Parasaran Nigam Limited and to

    setup new power project on the state sector.

    The main objectives of HPGCL are as under:

    1. To generate power from its existing Generating Stations in the

    most efficient manner on commercial lines and to sell the same to

    distribution companies.

    2. To setup new power generation projects.

    3. from June 2005 HPGCL is also responsible for the work of powertrading i.e. Procurement of power on long term and short term

    basis, signing of power purchase agreements with power

    producers/traders

  • 8/7/2019 Power Station Projecy Report

    8/29

    SUBSTATION (JIND)

    Haryana Vidyut Power Generation Corporation Limited (HVPNL) 132 KV

    substation Jind is an undertaking of Haryana Power Generation Corporation

    Limited Panchkula (HPGCL). Substation serve as a source of energy supply

    for the local areas of distribution in which these are located. Their main

    functions are to receive energy transmitted at high voltage from the

    generating stations, reduce the voltage to a value appropriate for local

    distribution and provide facilities for switching.

    It is established near milk plant on HANSI road, JIND. This substation

    required area of 15 acres. The input of the substation is mainly from threesubstations which are as follows:

    1. 132 KV from JHANJ

    2. 132 KV from PANIPAT

    3. 132 KV from SAFIDON

    Then this input power is stepped down and passes to the nearest substation.

    So the output of this substation is also going to the three substations which

    are as follows:

    1. 132 KV to JIND (OLD)

    2. 132 KV to KHERI

  • 8/7/2019 Power Station Projecy Report

    9/29

    SWITCHYARD

    Haryana Vidyut Power Generation Corporation Limited (HVPNL) 132 KV

    switchyard JIND is an undertaking of Haryana Power Generation (HPGCL)

    Corporation Limited Panchkula (HPGCL). Switchyard serve as a source of

    energy supply for the local areas of distribution in which these are located.

    Their main functions are to receive energy transmitted at high voltage from

    the generating stations, reduce the voltage to a value appropriate for local

    distribution and provide facilities for switching.

    A Highlight of Switchyard Of substation is given in Table Below:

  • 8/7/2019 Power Station Projecy Report

    10/29

    LIGHTNING ARRESTER

    The lightning arrester as a surge diverter is used forthe protection of power system against the high

    voltage surges. It is connected between the line and

    earths and so diverts the incoming high voltage wave

    to the earth. Lightning arrester act as safety valves

    designed to discharge electrical surges resulting from

    lightening strokes, switching or other disturbances,

    which would other wise flash over insulator or

    puncture insulation, resulting in a line voltage and

    possible failure of equipment. They are designed to

    absorb enough transient energy to prevent dangerousreflection and to cut off the flow of power frequency

    follow (or dynamic) current at the first current zero

    after the discharge of transient. They include one or

    more sets of gaps to establish the breakdown voltage,

    aid in interrupting the power follow current, and prevent any follow of

    current under normal condition(except that gap shunting resistor when

    used ton assume equal distribution of voltage across the gap, permits a

    very small leakage current). Either resistance element to limit the power

    follow current of values the gap can interrupt, or an additional arcextinguishing chamber of interrupt the power follow current are

    connected in series with gaps. Arresters have a short time lag of

    breakdown compared with the insulation of apparatus, the breakdown

    voltage nearly independent of the steepness of the wave front.

    Lightning protection by means of lightning arrestors and gaps and

    overhead ground wire is a mean of reducing outages and preventing

    damage to station equipments from lightning disturbances.

    The ground wire or earthling screen does not provide protection againstthe high voltage wave reaching the terminal equipment, so some

    protective devices are necessary to provide protection of power stations,

    substation and transmission line against the voltage wave reaching there.

    The most common device used for the protection of power system

    against the high voltage surge is sure diverter.

  • 8/7/2019 Power Station Projecy Report

    11/29

    CAPACITOR VOLTAGE TRANSFORMER

    A capacitor voltage transformer (CVT) is a transformer used in power

    system to step down extra high voltage signal and provide low voltagesignals either for measurement or to operate a protective relay. In its

    basic form the device consist of three parts: two capacitor across which

    the voltage signals is split, an inductive element to tune the device to the

    supply frequency and a transformer used to isolate and further step down

    the voltage for the instrumentation and protective relay. The device has at

    least four terminals, a high voltage terminal to connection to the high

    voltage signal, a ground terminal and at least one set of secondary

    terminals for the connection of the instrumentation and the protective

    relay. CVTs are typically single phase devices used for measuring

    voltage in excess of one hundred kilovolts where the use of voltagetransformer would e uneconomical. In practice the first capacitor, C1, is

    often replaced by a stack of capacitor connected in series. This result in

    large voltage drop across the stacks of capacitors that replaced the first

    capacitor and a comparatively small voltage drop across the second

    capacitor C2, and hence the secondary terminals.

  • 8/7/2019 Power Station Projecy Report

    12/29

    WAVETRAP

    Wave trap is a parallel tuned inductor capacitor tank Circuit made to be

    resonant at the desired communication frequency. It is the effort to utilizethe same transmission line between two substations for the purpose of

    communications. At these communication frequencies the tank ckt provides

    high impedance and does not allow passing through them & onto the

    substation bus & into transformers.

    The Line trap offers high impedance to the high frequency communication

    signals thus obstructs the flow of these signals in to the substation bus bars.

    If there were not to be there, then signal loss is more and communication

    will be ineffective/probably impossible.

  • 8/7/2019 Power Station Projecy Report

    13/29

    CURRENT TRANSFORMER

    These instrument transformers are connected in ac power circuits to feed

    the current coil of indicating and metering instrument (ammeter,wattmeter, and watt hours meter) protective relays. Thus the CTs

    broaden the limit of measurements and maintain a watch over the current

    flowing in the circuit and over the power loads. In high voltage

    installation CTs in addition to above, also insolate the indicating and

    metering instruments from high voltage. The current transformer

    basically consists of an iron core on which arc wound a primary and one

    or two secondary windings. The primary is directly inserted in the power

    circuit (the circuit in which the current is to be measured) and ton the

    secondary winding or windings the indicating and metering instruments

    and relays are connected. When the rated current of CT flows through itsprimary winding a current of 5 amperes will appears in its secondary

    windings. The primary windings are single turn windings and the number

    of turns on secondary winding depends upon the power circuit current to

    be measured. The larger current to be measured, more the number of

    turns on secondary. The ratio of primary current to the secondary current

    is known as the transformation ration.

  • 8/7/2019 Power Station Projecy Report

    14/29

    POTENTIAL TRANSFORMER (PT)

    The potential transformer are employed for voltage above 380 volts to feed

    the potential coils of indicating and metering instrument (voltmeter,Wattmeter, and watt hours meter) and relays. These transformers make the

    ordinary low voltage instrument suitable for measurement of high voltage

    and isolate them from high voltage.

    The primary windings of the potential transformer is connected to the main

    bus bar of the switchgear installation and to the secondary windings, various

    indicating and metering instrument and relays are connected.

    When rate high voltage is applied to the primary of PT the voltage of 10V

    appear at the secondary windings. The ration of rated primary voltage to the

    rated secondary voltage is known as turn or transformation ration.

  • 8/7/2019 Power Station Projecy Report

    15/29

    CIRCUIT BREAKER

    A circuit breaker is a mechanical device designed to close or open

    contact members, thus closing or opening an electrical circuit under

    normal or abnormal conditions. It is so designed that it can be operatemanually under normal condition or automatically under faulty condition.

    An automatic circuit breaker is equipped with a trip coil connected to a

    relay or other means designed to open or break automatically under

    abnormal condition, such as over current. When the circuit breaker is

    closed considerably energy stored in the springs. The connects are held

    together by means of toggles. To open the circuit breaker only a small

    pressure is required to be applied on the trigger. When t6hw trigger is

    actuated by the protective relay, it trips and potential energy of the

    springs is released and the contacts open in the fraction of second.

    HIGH VOLTAGE CIRCUIT BREAKER

    High voltage circuit breakers are broadly classified by the medium used to

    extinguish the arc.

    Oil filled (dead tank and liver tank)

    Oil filled, minimum oil volume

    Air blast

    SF6 Vacuum circuit breaker (manufacturing in ABB, AREVA, cutler-

    hammer (Eaton), Siemens, Toshiba)

    High voltage circuit breakers are routinely available up to 765 KV AC.

    Live tank circuit breaker are where the enclosure that contains the breaking

    mechanism is at line potential, that is, live. Dead tank circuit breaker

    enclosures are at earth potential.

    [Interrupting principle of high voltage circuit breakers

    Current interruption in high voltage circuit breaker is obtained by separating

    two contacts in a medium, such as SF6 having excellent dielectrical and arc

    quenching properties.

  • 8/7/2019 Power Station Projecy Report

    16/29

    SULPHUR HEXAFLUORIDE (SF6) CIRCUIT BREAKER

    In many type of circuit breakers the extinguishing

    force built up relatively slowly after the moment of

    contact separation, and hence arc is extinguishingafter a few half cycles current have passed zero. The

    prevention of arc re-igintioin needs a high

    dielectrical strength of the arc path and its fast

    recovery current zero. In the case of high voltage

    circuit breaker these properties are particularly

    required to have quick arc extinction and have less

    time for quick recovery voltage build up. Vacuum

    circuit breaker and Sf6 circuit breaker havebetter

    properties in this regard compared to conventional

    bulk oil minimum oil as well as air blast circuitbreakers hence modern trend is to employ vacuum

    circuit breaker and SF6 circuit breakers in HV

    system.

    Modern circuit breaker employs heavy gas SF6 as the medium for quenching

    the arc. Sf6 gas because its excellent dielectric, arc quenching, chemical and

    other physical properties, has proved its superiority over other mediums

    such as oil or air for use in circuit breakers. Several types of SF6 circuit

    breakers have been developed by different manufacturers during last two

    decades for rated voltages 3.6 to 760 Kv.

    Rated voltage 245 KV

    Frequency 50 HZ

    Current 200 A

    Opening voltage 220 V DC

    Total wt. 2400 KG

    Gas wt. 21 WG

    Include gas SF6

    Pressure 16.5 KG/cmg

    Short circuit 40 KV -3 sec.

    Made by Siemens, India

  • 8/7/2019 Power Station Projecy Report

    17/29

    ISOLATOR

    Isolator (or

    disconnect switches)are not equipped with

    arc quenching device

    and, therefore, not

    used to open circuits

    carrying current. As

    the name implies

    isolator isolates one

    portion of the circuit

    from another and is

    not intended to beopened while current

    is flowing. Isolators

    must not be opened

    until the circuit is interrupted by some other means. If an isolator is

    opened carelessly, when carrying a high current, the resulting arc could

    easily cause a flash over the earth. This may shatter the supporting

    insulator and may even cause a fatal accident to the operator, particularly

    in high voltage circuits. While closing a circuit, the isolator is closing

    first, then the circuit breaker. Isolators are necessary on supply side ofcircuit breaker in order to ensure isolation (disconnection) of the circuit

    breaker from the live parts for the purpose of maintenance.

  • 8/7/2019 Power Station Projecy Report

    18/29

    INSULATOR

    The porcelain insulators employed in substations

    are of the post and busing type. They sever as

    supports and insulation of the bus-bars.

    A post insulator consists of porcelain body, cast

    iron cap and flanged cast iron base, as shown in

    fig. the hole in the cap is threaded so that the bus-

    bar are either directly bolted to the cap or fixed by

    means of bus-bar clamp. Post insulators are

    available with round oval and square flanged bases

    for fixing respectively, with aid of one, two or four

    bolts. Each base in addition also has an earthing bolt. A bushing insulator consists of porcelain-

    shell body ,upper and lower locating washers used

    for fixing the position of the bus bar in shell, and

    mounting flange with holes drilled for fixing bolts and supplied with an

    earthing bolt, as shown in fig.

    For current rating above 2,000A, the bushings are designed to allow the

    main bus bars to be passed directly through them. Each phase of the bus bars

    is located with paint according to a fixed color code red, yellow and blue so

    that phase of main bus bars can be identified. But at Jind substation disk

    type insulators are used which is shown in fig.

  • 8/7/2019 Power Station Projecy Report

    19/29

    BUS-BARS

    Bus bar term is used for a main bar or conductor carrying an electric currentto which many connections may be made.

    Bus bars are merely convenient

    means of connecting switches and other equipment in to various

    arrangements .the usual arrangement of connections in most of the

    substations permits working on almost any piece of equipment without

    interruption to incoming or outgoing feeders.

    In some arrangement two

    buses are provided two which the incoming or outgoing feeder and theprincipal equipment may be connected. One bus is usually called the main

    bus and the other auxiliary or transfer bus. The main bus may have a more

    elaborate system of measuring instruments, relay etc.associated with it. The

    switches used for connecting feeders or equipment to one bus or the other

    are called transfer switches.

  • 8/7/2019 Power Station Projecy Report

    20/29

    POWER TRANSFORMER

    Power transformer are used for stepping-up the voltage for transmissionat generating stations and for stepping-down voltage for further

    distribution at main step down transformer substation. Usually naturally

    cooled, oil immersed, known as ON type, two winding, three

    transformers are used up to the rating of 10 MVA. The transformers of

    rating higher than 10MVA are usually cooled. For very high rating, the

    forced oil, water cooling and air blast cooling may be used. For

    regulating they voltage of transformers used are provided with on load

    tap changer. They are put in operation during load hours and disconnect

    during light load hours i.e. they are usually operated at approximately full

    load. This is possible because they are arranged in blank and can bethrown in parallel with other units or disconnect at will. So power

    transformers are designed to have maximum efficiency at or near full

    load (i.e. with iron loss to full load copper loss ratio of 1:1). Power

    transformer are designed to have considerable leakage reactance then is

    permissible in distribution transformer because in power transformers

    inherent voltage regulation is not as much important as current limiting

    of the higher leakage reactance. At 132 KV substation Jind two

    transformers are used for the stepping down purpose. Each of them is of

    100 MVA. These transformers steps down the voltage 132 KV into 33KV. This voltage is then transmitted to the 33 KV substations of KHERI

  • 8/7/2019 Power Station Projecy Report

    21/29

    NEUTRAL CURRENT TRANSFORMER

    This transformer is used after the power transformer. This transformer is asafety device. If there is any extra current in the transformer then this current

    is taken by the neutral current transformer and this current is grounded by

    the transformer. This is connected to the power transformer for grounding

    the extra current. If there is any type of current that current will be grounded

    by the neutral current transformer.

  • 8/7/2019 Power Station Projecy Report

    22/29

    CONTROL ROOMS

    The control room (or the operating room) is the nerve center of the power

    station. The various control performed from here are voltage adjustment,

    load control, emergency tripping of turbines etc. and the equipment and

    instruments housed in a control room are synchronizing equipment, voltage

    regulators, relays, ammeters, voltmeters, watt meters, KWh meters, kVARh

    meters, temperature gauges, water level indicator and other appliances, as

    well as a mimic diagram and suitable indicating equipment to show the

    opened or closed position of circuit breaker, isolators etc. the location of

    control room in relation to other section of the power station is also very

    important. It should be located away from the sources of noise and it should

    be near the switch house so as to save multi-core cablesUsed for interconnections. Of course, if there is any fire in switch house, the

    control room should remain unaffected. Also there is an access from the

    control room to the turbine house. The control room should be neat and

    clean, well ventilated, well lighted and free from draughts. There should be

    no glare and the color scheme should be soothing to eyes. The instrument

    should have scales clearly marked and properly calibrated and all the

    apparatus and circuit should be labeled so that they are clearly visible.

  • 8/7/2019 Power Station Projecy Report

    23/29

    BATTERY ROOM

    All power plant and substation require dc power supply for protection and

    control purposes and dc supply is obtained from secondary or storagebatteries. Battery room is the heart of a substation. Lead acid batteries are

    most commonly used in po0wer stations and substations because of their

    high cell voltage and lower cost.

    Station batteries are assembled of a certain number of accumulator cells

    depending on the operating voltage if the respective de circuits. Storage

    batteries are of two types viz lead acid and alkaline batteries. Lead acid

    batteries are most commonly used in power stations and substations because

    of their higher cell voltage and low cost. At substation 132KV Jind 110 cells

    are used each of 2 volts. And nickel cadmium alkaline batteries are used.

  • 8/7/2019 Power Station Projecy Report

    24/29

    TRANSMISSION TOWER

    MATERIAL USED IN LINE CONDUCTORS

    Aluminum conductor steel reinforced (or

    ACSR) cable is a specific type of high

    capacity, high strength standard cable

    used in overhead power lines. The outer

    standards are aluminum, chosen for its

    excellent conductivity, low weight, and

    low cost. The centre strand is of steel,

    providing extra strength. Simultaneously

    however, the tower electricalconductivity of the steel core has only a

    minimum effect on the overall current

    carrying capacity of the cable. Due to a

    skin effect, most of the current is carried

    by the outer, aluminum portion of the

    cable, so the higher Resistance of the

    inner, steel strand is largely immaterial.

  • 8/7/2019 Power Station Projecy Report

    25/29

    POWER LINE CARRIER COMMUNICATION (PLCC)

    Power line carrier communication (PLCC) is mainly used for

    telecommunication, tele-protection and tele-monitoring between electrical

    substations throughpower lines at high voltages, such as 110 Kv, 220 Kv,

    400 Kv. PLCC integrates the transmission of communication signal and

    50/60 Hz power signal through the same electric power cable. The major

    benefit is the union of two important applications in a single system.

    In a PLCC system the communication is established through the power line.

    The audio frequency is carried by a carrier frequency and the range of carrierfrequency is from 50 kHz to 500 kHz. The modulation generally used in

    these systems is amplitude modulation. The carrier frequency range is

    allocated to include the audio signal, protection and the pilot frequency. The

    pilot frequency is a signal in the audio range that is transmitted continuously

    for failure detection.

    The voice signal is converted/compressed into the 300 Hz to 4000 Hz range,

    and this audio frequency is mixed with the carrier frequency. The carrier

    frequency is again filtered, amplified and transmitted. The transmission of

    these HF carrier frequencies will be in the range of 0 to +32db. This range isset according to the distance between substations.

    PLCC can be used for interconnecting PBXs. The electricity board in India

    has an internal network PLCC between PBXs.

    Contents

    1 Line trap

    2 Coupling capacitor

    3 Line matching unit 4 Digital power line carrier

    http://en.wikipedia.org/wiki/Telecommunicationhttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/Power_linehttp://en.wikipedia.org/wiki/High_voltagehttp://en.wikipedia.org/wiki/Audio_frequencyhttp://en.wikipedia.org/wiki/Carrier_frequencyhttp://en.wikipedia.org/wiki/Amplitude_modulationhttp://en.wikipedia.org/wiki/Private_branch_exchangehttp://en.wikipedia.org/wiki/Power_line_carrier_communication#Line_trap%23Line_traphttp://en.wikipedia.org/wiki/Power_line_carrier_communication#Coupling_capacitor%23Coupling_capacitorhttp://en.wikipedia.org/wiki/Power_line_carrier_communication#Line_matching_unit%23Line_matching_unithttp://en.wikipedia.org/wiki/Power_line_carrier_communication#Digital_power_line_carrier%23Digital_power_line_carrierhttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/Power_linehttp://en.wikipedia.org/wiki/High_voltagehttp://en.wikipedia.org/wiki/Audio_frequencyhttp://en.wikipedia.org/wiki/Carrier_frequencyhttp://en.wikipedia.org/wiki/Amplitude_modulationhttp://en.wikipedia.org/wiki/Private_branch_exchangehttp://en.wikipedia.org/wiki/Power_line_carrier_communication#Line_trap%23Line_traphttp://en.wikipedia.org/wiki/Power_line_carrier_communication#Coupling_capacitor%23Coupling_capacitorhttp://en.wikipedia.org/wiki/Power_line_carrier_communication#Line_matching_unit%23Line_matching_unithttp://en.wikipedia.org/wiki/Power_line_carrier_communication#Digital_power_line_carrier%23Digital_power_line_carrierhttp://en.wikipedia.org/wiki/Telecommunication
  • 8/7/2019 Power Station Projecy Report

    26/29

    LINE TRAP

    It is also called Wave trap. It is connected in series with the power

    (transmission) line. It blocks the high frequency carrier waves (24 kHz to

    500 kHz) and let power waves (50 Hz 60 Hz) to pass through. It is

    basically an inductor of rating in mili henry.

    COUPLING CAPACITOR

    It provides low impedance path for carrier energy to HV line and blocks the

    power frequency circuit by being a high impedance path.

    LINE MATCHING UNIT

    LMU is a composite unit consisting of Drain Coil, Isolation transformer with

    Lightning Arrester on its both the sides, a Tuning Device and an earth

    switch. Tuning Device is the combination of R-L-C circuits which act as

    filter circuit. LMU is also known as Coupling Device. Together with

    coupling capacitor, LMU serves the purpose of connecting effectively the

    Audio/Radio frequency signals to either transmission line or PLC terminal

    and protection of the PLCC unit from the over voltages caused due to

    transients on power system.

    DIGITAL POWER LINE CARRIER

    A power line carrier using a power line as transmission media needs to

    change its transmission system from analog to digital to address rapid

    diffusion of IP devices and digital telecommunication devices. With this

    view, digital power line carrier (DPLC) was developed featuring several

    technological measures which enable digital transmission via power lines

    and performed a field evaluation test. As a result, DPLC has the required

    quality of bit error rate characteristics and transmission ability such as

    transmitting information from monitoredelectric-supply stations and images.

  • 8/7/2019 Power Station Projecy Report

    27/29

    SUBSTATION AUXILIARIES SUPPLY

    In small unattended substation only a small amount of power for electric

    lighting during regular periods of inspection, maintenance and repair is

    required. In regional substation the electric power is required for theauxiliaries:- the lighting circuit, air blast fan of transformer, battery

    charging sets oil servicing facilities, compressor unit in case of air blast

    circuit breakers, ventilating fans of the substation buildings water supply

    and heating system equipment etc. substation incorporating synchronous

    condensers the supply is also required for the operation of auxiliaries

    equipment of the synchronous condensers.

    At 132 KV substation Jind a stepping down transformer is used which

    step down 33 KV into 11 KV which is used for the substation auxiliaries

    supply. Feeders are also taken from this voltage.

  • 8/7/2019 Power Station Projecy Report

    28/29

    EARTHING OF SUBSTATION

    The term earthing mean connecting of the non current carrying parts ofthe electrical equipment or the neutral point of the supply system to the

    general mass of the earth in such a way that at all times am immediate

    discharge of electrical energy take place without a danger. The earthing is

    provided by the following activities:-

    1. for the safety of personnel form of electrical shock- insuring

    that non current carrying parts, such as equipment frames are

    always safely at ground potential even though insulation fails.

    2. For the safety of equipment and personnel against lightning and

    voltage surges- providing the discharge path for the lightningarresters, gaps and similar devices.

    3. For providing the ground connection for ground neutral system.

    4. For provide a mean of positively discharging or highly de-

    energizing feeders or equipment before proceeding with

    maintenance of them. The station earthing system should have

    low resistance.

    Grounding of power system is highly important. A substational and adequate

    ground that will not burn off or permit danger rise in voltage under abnormalconditions essential.

    Equipment earthing also help in the earth fault protection.

    Solid grounding will be done it means a direct connection of the neutral to

    the earth.

  • 8/7/2019 Power Station Projecy Report

    29/29