Power Rachit

Embed Size (px)

Citation preview

  • 7/31/2019 Power Rachit

    1/4

    1

    Project Management of Small Hydropower Projects

    1

    INTRODUCTION

    In the recent years there has been a positive growth of the Indian economy. The infrastructure facilities

    have not been able to keep pace with the growth rate and there are severe power shortages all around the

    country.

    While there is a thrust on increasing the installed capacity of the power projects, for many reasons this has

    not happened. One such sector is the Hydropower sector. Many state Governments have granted

    permissions and licenses to various organizations to construct, commission and operate the plant for certain

    number of years and then transfer the same to the state Government.

    Most of the developers who have

    secured rights for the development of hydro power projects from the

    respective state Governments, are facing several problems in developing and implementing them. The

    hydropower projects require a mature understanding of the difficulties involved in setting up these projects

    as they are subjected to considerable challenges from the nature and from the human settlements alike.

    The nature presents risks like flooding, poor geology

    and other adverse natural forces. Since the developers

    have a limited knowledge and understanding of the problems and issues involved in setting up these

    projects, there has not been much development worth its name to date in the hydropower sector for projects

    allotted to IPPs. And whatever development has taken place, it has been done inefficiently with time and

    cost overruns. Out of a few hundred small projects allotted by various state Governments only a few have

    been able to generate power so far.

    The four important reasons that can be singled out are the lack of knowledge to develop the projects, delays

    in obtain ing Government Clearances and non-availability of the experienced engineers to construct and

    commission the projects. The other problem is non-availability of quality contractors also.

    Since the developers lack understandings of project management issues of the hydropower projects there

    have been problems and delays in setting up these projects.

    http://../contents.pol.invest.optnl.aspects.pdf
  • 7/31/2019 Power Rachit

    2/4

    2

    2 TYPICAL COMPONENTS OF SMALL HYDRO POWER PROJECTS

    i) Diversion Weirii) Desilting Basiniii) Water Conductor System.iv) Power Housev) Tail Race Tunnel or Channelvi) Switch Yardvii) Transmission line

    3 STEPS INVOLVED IN CONCEPT TO COMMISSIONING

    i) Design and Detailed engineering for the project.ii) Topographical, Geo-technical and Geological Survey of the project area.iii) Setting up of Gauge Discharge Site.iv) Conceptualization of Scheme.v) Confirmation of Layout on Ground. (This is not like marking a layout on a flat ground.

    Involves lot of accurate detailed surveys)

    vi) Detailed Project Report (DPR) and Approval of the Detailed Project Report from theconcerned Electricity Board or the concerned Government Authorities.

    vii) Identification of Land.viii) Tender Documents for Civil works and E&M works.ix) Financial Closure.x) Construction and Commissioning.

    4 PROJECT MANAGEMENT

    The Project Management of a hydropower project consists of several actions that are required to be taken

    for implementation of the project. These could be categorized as under:

    i) Government Clearancesii) Survey and Investigationsiii) Implementation Scheduleiv) Bid evaluation for Civil Works, TG Equipments and TG Auxiliaries.v) Vendor identification for miscellaneous itemsvi) Procurement actionvii) Inspection of equipmentsviii) Construction supervisionix) Construction of transmission linex) Commissioning trialsxi) Commissioningxii) Carbon Credit validation

  • 7/31/2019 Power Rachit

    3/4

    3

    5 NEED FOR PROJECT MANAGEMENT

    In order to implement the project, a project management team needs to be created and put inposition to manage different aspects of the Project at different stages. These stages have been

    described above.

    In the present scenario it is difficult to find experienced professionals who can manage theprojects. The hydropower projects are fraught with several external and natural risks such as

    Floods, Earthquake, Landslides and Social Unrest. These risks can be mitigated to a large

    extent by the experienced project management team.

    Until about a few years back almost the entire hydropower development has taken place in the

    Government Sector. A very few professionals have ventured out of the Government Sector totaas up assignments in the private sector in India. The trend seems to be reversing slowly but

    surely. Nevertheless it is going to take some more time. Every individual looks for the job

    security. It is difficult for the small hydropower developers to provide comfort of job securityand career enhancement prospective; and therefore, they do not find the right professionals tomanage their projects and so the progress of work on these projects is slow.

    If the projects are managed by the right professionals then there is less risk and the projectwould be commissioned on time. The early commissioning means that the revenues start

    accruing early for the developer. The debt burden and the fixed expenses costs get reducedconsiderably.

    This situation can be overcome by some agency which is willing to provide the ProjectManagement Services with experienced Engineers.

    6 OUTSOURCING OF PROJECT MANAGEMENT WORKThe best course for the developers would be to engage an agency that has the experienced

    hydropower professionals on its rolls to implement the project on their behalf.

    There are several advantages in doing this:

    Completion of project could be achieved in time. Early Accrual of Revenues.

    Early start of repayment of Debt. Saves cost and time due to proper management of issues. No Permanent Liability of Project Management Staff. No fear of Attrition. Saves Recruitment and Retention Expenses.

  • 7/31/2019 Power Rachit

    4/4

    4

    The approximate expenditure for effective project management has to be decided mutually

    between the client and the service provider for the Project Management.

    The costs of ProjectManagement Service Provider

    may look high to some of the developers; essentially due to

    lack of appreciation of the effort involved, but it should be realized that by doing the project

    on time and by reaping the benefits early, these costs would be insignificant.

    7 FINANCIAL IMPLICATION OF ENGAGING A PROJECT MANAGEMENT TEAM

    Each hydroelectric project is a different project and needs different control mechanisms. Therequirement of manpower differs from one project to the other depending largely on the

    topography and the components of the project.