20
DESIGN AND CONSTRUCTION OF A DRAINAGE IN A RURAL COMMUNITY ACMK Construction Company Alex E. Obi-Ugbo Karel Jie Tjoe Foek Carlton Ng Majid Almas

Power Point Presentation for (Advance Project Management)

Embed Size (px)

Citation preview

Page 1: Power Point Presentation for (Advance Project Management)

DESIGN AND CONSTRUCTION OF A

DRAINAGE IN A RURAL COMMUNITY

ACMK Construction Company

Alex E. Obi-UgboKarel Jie Tjoe Foek

Carlton NgMajid Almas

Page 2: Power Point Presentation for (Advance Project Management)

Introduction■ This designing and construction project became necessary due to

numerous complaints of flooding in the area of 500 km square. The area has a population of 150,000 people where 20% of the population are attributed to children between the ages of 4-13 years old.

Page 3: Power Point Presentation for (Advance Project Management)

Problem Statement■ Objectives• Using the SMART analysis:SPECIFIC• Construction would be in phases which

includes from start-to-finish of the project.

MEASURABLE• Our progress will be measured on a

weekly basis whereby we plan to excavate 50km square in trenches so as to pour the concrete mixtures before the pipes are been laid.

ASSIGNABLE• Project manager: Meetings, Resources,

Preparation of final reports

• Concrete Experts: All aspects of concrete for the project and analysis of results.

• Procurement; Ordering of all materials for the project

• Scheduling: Construction scheduling timeline and excavation

REALISTIC• The pipes come in standard form of 20

meters long. 20 pieces of pipes are produced every 6-hrs which comes out to be 80 pieces/day. A total of 381 pipes would be produced at an approximation of 5 days .

TIME RELATEDDuration of project is 9-months.

Page 4: Power Point Presentation for (Advance Project Management)

Scope (Constraints, Assumptions, Limits, Exclusion, & Inclusion)

■ Scope: The project consists of the design, permitting and construction, pollution control structures, water control structures, A or B Manhole 48” Diameter (up to 4’ deep), and 12 catch basins. System maintenance and repair will be done only up to one month after final inspection.

■ Assumptions: Steady & Uniform gravity flow, company personnel have adequate knowledge to carry out project, design will follow health, safety, quality, & performance requirements, all research information can be obtained from open sources. Etc.

■ Limits: We would be limited for only one month after inspection, Future modification or structural changes would not be the company’s responsibility.

Page 5: Power Point Presentation for (Advance Project Management)

Significance (Merit, Profit, and/ or Benefit)

■ Significance: The continuous flow of storm water which is caused by excess rainfall created flooding, erosion and transportation of potential pollutants to the local bodies of water in the rural area.

■ Benefit: • Erosion Control• Standardized Drainage for neighboring communities• Elimination of death rate between the ages of 4-13 years old.

Page 6: Power Point Presentation for (Advance Project Management)

Proposed ApproachSolution Approach

■ Dig the trenches in segments whereby we pour the concrete base before laying the first segment of pipes and connect all necessary fittings.

■ While digging the second segment, the previous segment would be backfilled which will work simultaneously for other sub-segments of the solution approach.

■ Less expensive

Work Breakdown Structure

■ Place Order■ Receive Procured Order■ Remove Existing Drainage■ Excavation of Trenches■ Pour Concrete■ Lay Pipes■ Backfill Trenches■ Asphalt■ Inspection

Page 7: Power Point Presentation for (Advance Project Management)

Proposed ApproachWBS

Page 8: Power Point Presentation for (Advance Project Management)

Contractual Aspects■ ACMK will hire consultants to provide an overall assessment of the

surrounding areas■ This aspect will facilitate the needs of the community while ensuring efficient

and effective project initiative■ The consultant will create line of communication with the community in order

to gain feedback and address unplanned issues that may arise during the length of the project

■ Field workers will meet the demand based on the timeframe of the project■ Contract with equipment company to provide all construction equipment

needs

Page 9: Power Point Presentation for (Advance Project Management)

ResourcesResource Name Group Hours Cost

Project Manager Administration 1440 $27,000

Civil Engineer Administration 1440 $27,000

Project Engineer Administration 1440 $27,000

Plumber Administration 1440 $27,000

Labor Personnel Field Workers 1080 $18,000

Labor Personnel Field Workers 1080 $18,000

Labor Personnel Field Workers 1080 $18,000

Labor Personnel Field Workers 1080 $18,000

Labor Personnel Field Workers 1080 $18,000

Labor Personnel Field Workers 1080 $18,000

Labor Personnel Field Workers 1080 $18,000

Labor Personnel Field Workers 1080 $18,000

Labor Personnel Field Workers 1080 $18,000

Labor Personnel Field Workers 1080 $18,000

Page 10: Power Point Presentation for (Advance Project Management)

Cost■ The linear meters of the total area where the pipes would be laid is 7,620 meters

which gives us a number of 381 pipes of 20 meters long.■ The total cost of the project is one million, four hundred and eighteen thousand,

five hundred and forty eight thousand dollars only ($1,418,548).■ A or B Manhole 48” Diameter (up to 4’ deep) would be installed at every 40-

meter for cleanup and future services.■ Since the project is a cost-plus proposal, it includes all materials and installation,

hiring of heavy duty equipment’s unless otherwise noted. The notation TDB = To Be Determined which indicates that it would be an industry accepted estimate as a standard cost-plus price has not be established.

■ This is an industry accepted and current estimate for any materials that are approved and permitted by the City but not included in this document.

■ Cost for manholes are assumed to be precast, unless otherwise noted. This is accepted and current estimate for any structures that are poured in place.

Page 11: Power Point Presentation for (Advance Project Management)

Cost  Cost Breakdown  

Demolition, Utility Adjustment and Relocation   $18,000 Sediment Control and Earthwork   $35,000

Storm water Management and Stream Restoration   $25,000 Strom Drainage   $43,000

Water and Sewer   $45,000 Paving   $15,000 Pipe (381pipes * 600) $228,600

A or B Manhole 48” Diameter (up to 4’ deep) (190pieces * 1500) $285,000 Pipe Brackets (380pieces * 78) $29,640

Elbows (380pieces *78) $29,640 Tees (380pieces *78) $29,640

Concrete (1000 cubic ft.) $80,000 Welding Torch (Rent for 4-month) $10,000

Argon gas (300 lbs.) $37,000 Staffing (2000 * 10persons * 9mths) $180,000

Administration ($3000 * 4persons * 9mths) $108,000 Other Expenses   $25,000

Insurance   $70,000 Total   $1,233,520

15% Contingency plan   $185,028.00 Overall Total   $1,418,548.00

Page 12: Power Point Presentation for (Advance Project Management)

SchedulePlace Order

Receive Procured Order

Remove Existing Drainage

Excavation of Trenches

Pour Concrete

Lay Pipes

Backfill Trenches

Asphalt

Inspection

1/4/16 2/8/16 3/14/16 4/18/16 5/23/16 6/27/16 8/1/16 9/5/16

Page 13: Power Point Presentation for (Advance Project Management)

Budget

Page 14: Power Point Presentation for (Advance Project Management)

PersonnelOrganizational Structure

Page 15: Power Point Presentation for (Advance Project Management)

PersonnelJob Description and Qualifications/Skills

Position Advanced Degree Bachelor Degree Certification Leadership Skills Experience

Project Manager Masters Required PMI Certification Yes 3-5 Years

Civil Engineer Not Necessary Required PE Certification Not Necessary 3-5 Years

Project Engineer Not Necessary Required Not Necessary Yes 2-3 Years

Plumber Not Necessary Not Necessary Plumbers License Not Necessary 4 or more Years

Labor Personal Not Necessary Not Necessary Not Necessary Not Necessary 0-2 Years

Welder Not Necessary Not Necessary Welding Certification Not Necessary 2 or more Years

Page 16: Power Point Presentation for (Advance Project Management)

PersonnelResponsibility Chart

Task

Project Team

Alex Carlton Karel Majid

Attend meetings to make plans R S S S

Determine resources R S S S

Construct schedule timeline S S S R

Order materials S S R S

Excavation S R S S

Concrete S R S S

Lay Pipes S S R S

Plumbing S S R S

Welding S R S S

Drainage S S S R

Asphalt R S S S

Miscellaneous S S S R

Analyze results S R S S

Prepare final report R S S S

Page 17: Power Point Presentation for (Advance Project Management)

Personnel Communication Plan

 What Information

 Target Audience

 When?

Method of Communication

 Provider

Milestones Reports Project Manager & Project Engineer Monthly E-mail & hard copy Alex

Project-Daily Status Reports Project Manager & Project Engineer Daily E-mail & hard copy Carlton

Weekly Status Reports Project Manager & Project Engineer Weekly Meeting & hard copy Karel

Outsourcing Performance Project Manager & Project Engineer Weekly Meeting & hard copy Alex

Accept Change Request Owner & Project Manager As required Attention E-mail & hard copy Majid

Issue Report Project Manager & Project Engineer Weekly E-mail & hard copy Majid

Budget Update Project Manager & Owner Monthly E-mail & hard copy Karel

Scheduled Periodic Owner and Management Team Meetings

Management Team & Owner Monthly E-mail & hard copy Carlton

Page 18: Power Point Presentation for (Advance Project Management)

Evaluation Methods■ Defining phase: Designers and Engineers will develop the project according to

the latest Florida Building Codes and create the plans and specifications.■ All submittals for materials and equipment shall be collected prior to the

execution and presented to the city for approval. ■ Executing phase: During construction of the project, regular inspections shall be

performed for certain work by a respective City Inspector.■ Inspectors shall make sure that the work being done is according to the plans

and specification■ Inspection = Pass → Work can continue as planned■ Inspection ≠ Pass → Work is stopped until necessary changes have been met

and pass re-inspection

Page 19: Power Point Presentation for (Advance Project Management)

Potential Problems

■ Weather

■ Utilities

■ Traffic

■ Site

Page 20: Power Point Presentation for (Advance Project Management)

Questions