20
Underpinning Research Power Electronics in Distribution Networks Power Electronics Centre Imperial Open Day, July 2015 Thomas Frost

Power Electronics in Distribution Networks · Underpinning Research Power Electronics in Distribution Networks Power Electronics Centre Imperial Open Day, July 2015 Thomas Frost

Embed Size (px)

Citation preview

Underpinning Research

Power Electronics in Distribution Networks

Power Electronics Centre Imperial Open Day, July 2015

Thomas Frost

Underpinning Research

Overview

● Introduction

Low Carbon Technologies Growth

Drivers for PE in distribution systems

● Background

Voltage Control

Regulation Topologies

Loads, Networks & Limits

● Results

Increased DG penetration

Increased loading due to EV/HP

Comparison of regulation approaches

Active power filters

● Conclusions

Underpinning Research

Introduction

● Proliferation of domestic low carbon

technologies at LV has dramatically

increased and is projected to continue

● In many cases, the limits on power

delivery occur because the voltage

goes outside of tolerances (UK +10/-

6%), rather than due to thermal limits

● With power electronics:

Capacity can be released

Higher efficiency is possible

DNO investment can be deferred

● DNOs are aware of this and have

started to trial PE in LV networks

Underpinning Research

Domestic LCT Growth

● National grid predict [1] EV’s could

increase demand by 13%, whilst

HP’s could increase demand 30%,

all by 2035

● Installed PV capacity could exceed

30 GW by 2035

● All cases envisage a net growth in

domestic electrical energy demand

Underpinning Research

Drivers for PE Solutions

● High cost of network reinforcement,

and maintenance typically account

~40% of DNO expenditure (UKPN

estimate £2.7 billion in next 8 years)

● The solution of operating system

voltages high in the permissible band

is no longer feasible with DG

● Network scale is very large, and as

such upgrade is a continual process

● LCNF projects provide innovation

incentives for DNOs

Substation Costs (£1000) *

Voltage Type kVA Min Max

HV/LV Pole 100-200 11 22

HV/LV Pad < 200 21 34

HV/LV Ground 200-1000 20 57

EHV/HV Internal x2 - 1826 2730

Underground Cable Costs (£/m) *

Voltage CSA

(mm2)

Urban Rural

Min Max Min Max

LV ≤ 95 90 223 43 59

LV 95-185 100 360 55 73

LV ≥ 185 105 380 58 82

HV - 111 414 70 101

UKPN Eastern Network (3.6m customers)

Voltage Level Asset Volume

High Voltage Lines & Cables 38,882 km

Secondary Subs 67,772

Low Voltage Lines & Cables 49,319 km

Underpinning Research

Background & Methods

Underpinning Research

LV Voltage Control

● System X/R ratio is well below unity in

LV cable networks

● Active Power imparts greatest change

on system voltage

● Reactive compensation will be of

limited use for noteworthy voltage

control

∆𝑉 ≈ (𝑅𝑃 + 𝑋𝑄)/𝑉

● Existing voltage control finishes at the

primary substation OLTC

Underpinning Research

Regulation Solutions

● Electronic Substations (SST)

● Tap Changers (OLTC)

● Active Power Filtering (APF)

● Mid feeder compensation (MFC)

● Point of load regulation (PoL)

● Soft open points (SOP)

● Inline voltage regulators

● Deregulation

● Reinforcement

● Dynamic Rating

● Demand Response

● Energy Storage

● Active Network Management

● Many more …

Underpinning Research

PES

● Power electronic substations (PES) include primarily the solid state

transformer (SST) along with remote control, protection, and monitoring

functionality giving the DNO greater flexibly of the LV network

● High frequency isolation transformer reduces footprint, hence simplifies

retrofit

● A modular output converter facilitates per feeder regulation, staggered

LVDC implementation, and eases handling of load growth

Underpinning Research

MFC

● Functional as APF and DVR with a

common DC link

● High frequency DC link transformer

provides galvanic isolation with a

small size

● Four wire installation requires

processing of zero sequence

components, but only a small

faction of the total line power

● Assuming evenly distributed loading

the MFC is located at 1/3 of the

feeder length

● Decentralised control

● A compensation limit of 10% implies

a rating no larger than 15kVA

Underpinning Research

OLTC & APF

● Commercially produced OLTC transformers

for LV applications

Successfully trialled by ENWL

● Compared to PES, the OLTC is a proven

technology, that is efficient, economic and

reliable with suitable maintenance

● Commercial produced APF from

numerous manufactures

● Typically used by large end

users for either protection or

mitigation purposes

Underpinning Research

Loads, Networks & Limits

● Loads – Significant increase in energy

consumption with EV or HP

These are of high power and typically a

constant power nature with 3x peak load

Run the scenarios listed on the network

under study by assigning LCT to nodes

● Networks – Study of both generic and

real networks, results show for generic

Automation of analysis to investigate a

large numbers of real networks

● Limits – EN50160 for voltage quality

issues, G83 for DG connection, and

manufacture ratings

Differing monitoring, averaging and

acceptable limits for PQ issues

Proliferation of LCT (%)

Uptake DG EV HP

Low - 12.5 -

Mid 30 33 30

High 80 71 60

Underpinning Research

Results & Analysis

Underpinning Research

Results with DG

● Networks operate at upper end of

voltage range to allow for voltage drop

along the feeder

Substation LV voltages measured 6-8%

above nominal almost 50% of the time

● This has a detrimental effect when DG is

connected and small amounts of DG

cause voltage to exceed tolerances

● In the generic UK network over voltages

encountered with 30% nameplate rating

of PV (£35k upgrade for high PV)

● PV will not cause thermal limitations in

the network

Underpinning Research

Results with HP/EV

● Networks regulator set point lowered to

accommodate DG, but new loading

increases power flow

● Voltage limits are encountered prior to

current limits

● PES and OLTC slightly reduce thermal

limits due to new constant power loads

● Voltage optimisation less effective at

peak time as fewer large resistive loads

● Whole feeder upgrade cost (£64k)

removes all thermal and voltage issues

Underpinning Research

APF & MFC

● Compared to APF the MFC rating is

smaller (12kVA vs. 55kVA) and voltage

control is improved

● For reduction of losses the APF gives

annual savings of £120 with losses at

£0.06/kWh [2]

● In the MFC, when the series converter

is not inserting a compensating voltage

(or associated power is low) the shunt

converter acts as an APF

Improvements with APF

Scenario Losses (kWh/day)

Reduction Base w/ APF

No LCT 16.10 14.47 1.63 (10%)

High EV 60.93 55.14 5.79 (9.5%)

High HP 60.82 56.45 4.37 (7.1%)

Underpinning Research

Comparisons

● All topologies improve regulation

● PES & MFC are most effective

● OLTC suffers due to slow response

and simultaneous regulation of all

feeders (residential & commercial),

along with reduced tap range

Permissible Scenarios

Regulation Voltage Limits

Thermal Overall Over Under

Base 1 0 6 44

OLTC 3 2 6 69

PES 6 2 6 88

APF 2 1 6 56

MFC 5 2 6 81

● For certain substation demand

profiles the OLTC will be as

effective as the PES, thus 3 of the

regulation devices will all be able

to utilise network capacity up to

thermal limits.

Underpinning Research

Conclusions

● Power electronics at LV can improve voltage regulation, with economic

benefits compared to network reinforcement

● The MFC and PES offer best performance, but PES are expensive

● Thermal limits are the ultimate barrier to network capacity, but are not

easily increased by PE

● Harmonic limits not always exacerbated by LCT [3], but improved by APF

or MFC

● Short term DNOs want to be able to retrofit novel PE based equipment

not revolutionise LV networks [4] :

A barrier to PES

OLTC technology suitable for LV ready [5]

MFC is shown to be small and effective

Underpinning Research

References & Notes

[1] National Grid Future Energy Scenarios (FES) 2015

[2] J. Stewart, Review of WPD unit costs," tech. rep., Parsosn Brinckerhof, 2013.

[3] L. Kütt, E. Saarijärvi, M. Lehtonen, H. Mõlder, J. Niitsoo, Estimating the harmonic

distortions in a distribution network supplying EV charging load using practical source

data – case example

[4] B. O. Brewin, S. C. E. Jupe, M. G. Bartlett, K. T. Jackson, and C. Hanmer, New

Technologies for Low Voltage Distribution Networks

[5] D. Rogers and T. Green, “An active-shunt diverter for on-load tap changers,” Power

Delivery, IEEE Transactions on, vol. 28, no. 2, pp. 649–657, Apr. 2013.

* Cost derived from Southern Electrics, “Statement of Methodology and Charges for

Connection to Southern Electric Power Distributions Electricity Distribution System,”

May 2013.

Underpinning Research

Thanks for your attention

Questions?