Upload
leon-howard
View
217
Download
0
Embed Size (px)
Citation preview
Potential Uses of OEF at PG&E
Norm AbrahamsonMar 16, 2015
OEF for Utilities and Critical Facilities
• No regulatory criteria or guidance for use of OEF for critical facilities– Utilities moving to risk-informed decision making• Need estimate of the risk, but huge uncertainties
– PG&E (large portfolio of infrastructure)• Not using cost-benefit to justify seismic risk mitigation• Instead, have goal of long-term risk reduction over
decades
Potential Uses of OEF at PG&E
• Emergency response following an earthquake• Scheduling of high-risk maintenance activities• Impacts of long-term changes in hazard that
may cause an immediate safety issue
Emergency Response
• Aftershock probabilities– PG&E’s Emergency Operation Center is looking for additional
information on the what to expect in terms of aftershocks beyond the generic USGS statements
– Probabilities of M>5 by day for first few weeks– How long to reduce rates of aftershocks by 90% from time of
mainshock? • Repairs and inspections – pipelines
– Main issue is additional ground deformation along pipelines• Afterslip for fault crossings• Continuing landslides due to aftershocks
– How long to get 90% of the final deformation?
Emergency Response
• Building Tagging (for PG&E facilities)– Using precomputed aftershock risk from generic
aftershock models for different damage• Want to avoid over-conservative tagging
– Have not planned on using OEF to improve the aftershock risk estimates
Emergency Response
• What to do with a large probability gain?• Lake Almanor Dam example– May 24, 2013, M5.7 earthquake under the dam
(within a few km)– Hazard increase by factor of ~1000 during the
Memorial Day weekend, but still a small risk of failure of the dam
– What should a responsible utility do?
Scheduling of High Risk Maintenance Activities
• If there is short-term increase in hazard, consider postponing high risk maintenance– This was done following the 2003 San Simeon
Earthquake at Diablo Canyon• Postponed some high-risk maintenance for one week• Not based on a formal evaluation
• A few weeks delay is practical, not months
Impacts of long-term changes in hazard
• Does the change lead to an immediate safety issue for existing critical facilities?– Change in the 50 yr hazard compared to national
hazard map– Significant increase for critical facilities• > 20% in GM• > 100% in probability for mean hazard at the GM
corresponding to the 1E-4 reference hazard level• What is the 5-95% uncertainty range on the increase?