Post-mortem of Experience with LEIR Controls. Sergio Pasinelli on behalf of the LEIR commissioning team. Outlines. Introduction Generalities Needs Schedules Status in 2005 Request for 2006 Conclusions. The Deal. - PowerPoint PPT Presentation
Citation preview
Post-mortem of Experience with LEIR Controls
Sergio Pasinelli
on behalf of the LEIR commissioning team
Chamonix 2006 - 26/01/2006
S. Pasinelli 2
Outlines
Introduction Generalities Needs Schedules
Status in 2005 Request for 2006 Conclusions
Chamonix 2006 - 26/01/2006
S. Pasinelli 3
The Deal
From CO: To test and validate, in an operational environment, certain choices suggested for the control of the LHC
From OP: The new tools will have to provide the same functionalities, availability and reliability which are currently proposed by the CPS.
Chamonix 2006 - 26/01/2006
S. Pasinelli 4
Description
LEIR is between LINAC 3 and the PS.
The Control system of the LINAC 3 and PS, is that of the CPS
LEIR is a hybrid control system, composed of elements from the CPS and LHC
Chamonix 2006 - 26/01/2006
S. Pasinelli 5
We are Here
Chamonix 2006 - 26/01/2006
S. Pasinelli 6
Control needs for commissioning Sequencing / Timing Basic controls (WS + Knobs) Observation & Instrumentation Function editor / Cycle editor (LSA) Tools Alarms Archives / References
Chamonix 2006 - 26/01/2006
S. Pasinelli 7
Structure for the commissioning
LEIR Equipments
CBCM
Cycle&
FunctionEditor
Working set&
KnobsAlarms
Observations&
InstrumentationsTools Passerelle
Application Server (if necessary)
Archives&
Ref.
Middleware
DSCGM FESA
Chamonix 2006 - 26/01/2006
S. Pasinelli 8
Schedule
Hardware Commissioning : Basic control & Sequencing available at the beginning of May
Beam injection : Partial Controls & Observation of the injection lines available at the beginning of June.
Ring : Full Controls & Observation available at the beginning of August.
Ejection : Control available at the beginning of February 2006.
Chamonix 2006 - 26/01/2006
S. Pasinelli 9
Status Hardware Commissioning (May)Controls with Xmotif/C++
Console manager On time Working set / Knobs On time Function editor On time Alarms On time FE software GM On time
CBCM On time
Chamonix 2006 - 26/01/2006
S. Pasinelli 10
Status Hardware Commissioning (May)Controls with Java
CCM Debugging
Working set / Knobs NOT READY
FE Framework FESA NOT READY
LTIM On time
POWDF7000 NOT READY
Reboot DSC NOT READY
Chamonix 2006 - 26/01/2006
S. Pasinelli 11
Status Injection (June)
Controls with Java MTV On time CCM Debugging
OASIS Hard Debugging
Working set / Knobs NOT READY
Alarms (LASER) NOT READY
Workstation memory leak 1GB not enough
Chamonix 2006 - 26/01/2006
S. Pasinelli 12
Status Injection (June)
FE Framework FESA NOT READY
POWDF7000 NOT READY
BTV On time
Reboot DSC NOT READY
Chamonix 2006 - 26/01/2006
S. Pasinelli 13
Status Ring (September)
Controls with Java CCM WS memory leak Increase memory to 2GB Orbit correction On time Working set / Knobs Debugging Alarms (LASER) Partial OASIS Debugging Cycle editor (LSA) Debugging
References NOT READY
Archives NOT READY
Chamonix 2006 - 26/01/2006
S. Pasinelli 14
Status Ring (September)
Controls with Java (con’t)
PPM Copy NOT READY
EQP Survey NOT READY
Passerelle Partial only GM FE Framework FESA Debugging
POWDF7000 Debugging Septa Semgrid PLC Reboot DSC
Chamonix 2006 - 26/01/2006
S. Pasinelli 15
Status end 2005
Controls with Java CCM WS memory leak Working set / Knobs Orbit correction References OASIS Optimization Cycle editor (LSA) Optimization & GUI Alarms (LASER) Partial
Chamonix 2006 - 26/01/2006
S. Pasinelli 16
Status end 2005
Controls with Java (con’t)Archives NOT READYPPM Copy Partial only for GMEQP Survey NOT READYPasserelle Partial only for GM
FE Framework FESA FESA Classes
POWDF7000 Septa Semgrid PLC Orbit
Chamonix 2006 - 26/01/2006
S. Pasinelli 17
Objectives 2006
Controls with Java1. Cycle editor (LSA) Optimization
2. Archives Ready
3. Alarms Full functionalities
4. PPM Copy For GM and FESA
5. Passerelle For GM and FESA
6. OASIS Improve speed connection
6. EQP Survey Ready
7. Cycle editor (LSA) GUI improvement
Chamonix 2006 - 26/01/2006
S. Pasinelli 18
Conclusions
Use of LHC controls for LEIR very ambitious Schedules not respected Many softwares not ready
Communication lack between CO projects The CO priorities for LEIR softwares to low
CO effort for LEIR in autumn Tests TI8 and TT40 was not enough for LEIR
Chamonix 2006 - 26/01/2006
S. Pasinelli 19
Conclusions
There can be an inconsistency between the supercycle from “Cycle Editor" and from the MTG with the long plateau
CPS & CSL knowledge used in the LEIR softwares
Excellent support and reactivity from softwares developers
The effort must continue, the commisionning is not finished!
Chamonix 2006 - 26/01/2006
S. Pasinelli 20
Conclusions
A Control system allowing working (but not yet perfect)
is available
Chamonix 2006 - 26/01/2006
S. Pasinelli 21
Acknowledgements
Thanks to all people involved in the LEIR softwares.
Specially E. Roux, I. Kozsar, M. Pace, V. Baggiolini CO Team LSA Team BDI Team PO Team Vacuum Team OP Team
Chamonix 2006 - 26/01/2006
S. Pasinelli 22
LEIR GM - FESA
Module GM POW-V / POWP GFA CTIM Sampler SKSU BBTRM Etc …
Module FESA LTIM Dpow7000 LeirSeptaStatic BCTFT QMeter MTV Etc…
Chamonix 2006 - 26/01/2006
S. Pasinelli 23
Chamonix 2006 - 26/01/2006
S. Pasinelli 24
Chamonix 2006 - 26/01/2006
S. Pasinelli 25
Chamonix 2006 - 26/01/2006
S. Pasinelli 26
Chamonix 2006 - 26/01/2006
S. Pasinelli 27
Chamonix 2006 - 26/01/2006
S. Pasinelli 28
Chamonix 2006 - 26/01/2006
S. Pasinelli 29
Chamonix 2006 - 26/01/2006
S. Pasinelli 30
Chamonix 2006 - 26/01/2006
S. Pasinelli 31
Chamonix 2006 - 26/01/2006
S. Pasinelli 32
Chamonix 2006 - 26/01/2006
S. Pasinelli 33