27
Post-Fall AGU SWT Meeting 1 Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Embed Size (px)

Citation preview

Page 1: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 1 Dec. 18, 2010

THEMIS

ARTEMIS

Constellation Status,Plans for Future

Manfred Bester

University of California - Berkeley

Page 2: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 2 Dec. 18, 2010

THEMIS

ARTEMIS Outline

Outline• Mission Status Summary• Mission Networks• Flight Systems Performance• Anomaly Status• ARTEMIS P1 Dynamics Anomaly• Science Operations Metrics• ARTEMIS Navigation Status• Summary

Page 3: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 3 Dec. 18, 2010

THEMIS

ARTEMIS Mission Status Summary

Constellation Status• All five probes are very healthy in general and continue to collect

high quality science data after 3.75 years of successful on-orbit operations

• In general none of the five probes show any sign of degradation in any of the spacecraft subsystems

• One spacecraft lost an EFI sensor sphere• Few other minor issues with no impact to mission success• Fuel reserves continue to allow for ambitious mission extensions

Ground Systems & Operations Status• All ground systems are processing nominally• Hardware, software and procedures are kept up to date• Executed 430 individual thrust operations to date• Completed more than 23,000 passes to date (DSN: nearly 900) • All routine passes supported in lights-out mode

Page 4: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 4 Dec. 18, 2010

THEMIS

ARTEMIS

Berkeley Multi-mission Operations Center

White SandsComplex

GSFC GCC

THEMISProbes

SecureIntranet

TDRS

Open IONet T1 Line

HBK

Isolated Dial-up ISDN Line

AGO, MILA, WGS

USNHI, USNAU

BGSJPL DSN

GDSCC DSS-15, 24, 27CDSCC DSS-34, 45MDSCC DSS-54, 65

USN NMC

Mission Networks

Page 5: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 5 Dec. 18, 2010

THEMIS

ARTEMIS Spacecraft Bus Systems Status

Flight Systems Status Summary – Spacecraft Bus

System Subsystem Probe Status CommentsSpacecraft Bus

Bus Subsystems A - E Nominal

BAU FSW A - E Nominal All probes are running BAU FSW version 0x3701; upload completed on Nov. 7, 2009

Telecom A - E Antennas weaker than expected

Degraded operational link budgets(B: -3 dB; A,C,D: -4 dB; E: -5 dB)

Power A - E Nominal Power systems allow operation through 4-h shadows; longest penumbra ~8 h

Thermal A - E Nominal No issues in nominal mission attitude

E Thermal leak near Service Valve 2

Analysis shows no risk of freezing fuel lines

RCS A - E Nominal All RCS thrusters & valves function well, no leaks

ACS A - E Nominal All ACS sensors nominal

Page 6: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 6 Dec. 18, 2010

THEMIS

ARTEMIS Instrument Status

Flight Systems Status Summary – Instruments

System Subsystem Probe Status CommentsInstruments Instrument Suite A - E Nominal

IDPU FSW A - E Nominal All probes are running IDPU FSW version 0x56; upload completed on Nov. 19, 2010

EFI B Lost -X sensor sphere and part of the fine wire due to melting of the fine wire, likely as a result of micrometeorite impact, possibly from the Orionids (Oct. 14, 2010)

Reconfigured instrument to use ±Y sensors to obtain spin-fit DC electric field measurements and to trigger bursts; ±X pair continues to provide wave measurements; no significant science loss

ESA A - E Small degradation in sensitivity of electron sensor below 30 eV in certain angle sectors

Localized MCP degradation in angle sectors looking along the spin axis may be caused by emission of photo electrons from axial booms – probes A and B have least amount of degradation, had booms deployed later

SST A – E Noticeable degradation of sensitivity in all ion detectors

Caused by ion implantation; Increased sensor bias once to restore nominal sensitivity

D Attenuator B stuck in closed position due to a failure of the actuator mechanism (April 9, 2010)

While attenuator A is still functioning, both attenuators will likely be left in the closed position for the remainder of the mission; no significant science loss

Page 7: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 7 Dec. 18, 2010

THEMIS

ARTEMIS

Sequence of Events• On October 15, both GSFC/FDF and UCB/SSL observed

an unexplained range and range rate bias in their OD solutions.

THB/P1 Dynamics Anomaly

Note the range rate bias of -5.6 cm/s in the last two tracks (DS45, BRKS)!

This bias prevailed during subsequent tracks, i.e. the effect appeared to be real and suggested a ΔV event had occurred.

Reference: P. Morinelli,NASA/GSFC/FDF

Page 8: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 8 Dec. 18, 2010

THEMIS

ARTEMIS Deployed Instruments

THEMIS Probe with Deployed Instruments

Electric Field Instrument (EFI):Spin plane booms (SPBs):

X: ±25 m end-to-end (1-2)Y: ±20 m end-to-end (3-4)

Axial booms (AXBs): (5-6)

Preamplifier, fine wire and sphere sensor (−X)

Preliminary analysis indicates the EFI −X sphere actually departed from the spacecraft.

Page 9: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 9 Dec. 18, 2010

THEMIS

ARTEMIS EFI Dimensions

Engineering unit of preamplifier, fine wire, sphere and key reel

3.5 m

X: 24.39 m

Page 10: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 10 Dec. 18, 2010

THEMIS

ARTEMIS

∆Vsphere = 51.032 m/s

ω = 2 π / 3.0 s

Sun Sensor

Expected ∆V from Sphere Loss

∆Vspacecraft = 0.056 m/s EFI Preamp

−X Sphere

Note: This figure is not to scale.

Spin plane boom length: 24.39 m from s/c center to sphere, 21.39 m from s/c center to preamp

Page 11: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 11 Dec. 18, 2010

THEMIS

ARTEMIS Observed ∆V

Targeting Method ∆V [m/s] Azimuth [deg] Elevation [deg]

Position only 0.05654 79.751 -0.945

Velocity only 0.06925 78.338 31.277

Position and Velocity 0.05775 77.379 0.679

Reference: D. Folta, NASA/GSFC/NMDB

Elevation of the impulse should be near the spin plane, which may indicate the velocity-only targeting is an outlier.

Analysis based on post-event orbit solution

Page 12: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 12 Dec. 18, 2010

THEMIS

ARTEMIS Thrust Maneuver Summary

* ARTEMIS Probes

Maneuver and Fuel Budget Summary to Date

ParameterTHEMIS A

P5THEMIS B

P1*THEMIS C

P2*THEMIS D

P3THEMIS E

P4

Initial Fuel Load [kg] 48.800 48.780 48.810 48.810 48.820

Expended Fuel [kg] 32.486 39.373 40.240 22.647 22.467

Remaining Fuel [kg] 16.314 9.407 8.570 26.163 26.353

Remaining Fuel [%] 33.4 19.3 17.6 53.6 54.0

Total Expended ΔV [m/s]

654.536 838.075 849.600 442.761 430.354

Total executed thrust operations by end of prime mission: 296Total executed thrust operations to date: 430

Page 13: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 13 Dec. 18, 2010

THEMIS

ARTEMIS Geostationary Conjunctions

THD: Dec. 24 - 30, 2010 THE: Feb. 25 - Mar. 5, 2011 THA: Apr. 27 - May 8, 2011

Page 14: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 14 Dec. 18, 2010

THEMIS

ARTEMIS Science Operations Metrics

Science Instrument Commanding• Configuration changes discussed in weekly operations meetings• All instruments command sequences typically tested on FlatSat prior to

upload (FlatSat was moved from cleanroom to operations area)• Operations team implemented 117 Instrument Configuration Change

Requests (ICCRs) to date, based on input from the science team

Science Data Recovery Metrics• Data dumps near perigee typically at 128K, 512K or 1024K• Tohban monitors data quality and completeness• Required data volumes: 591-751 Mbits/orbit, varying with compression• Actual recovered data volumes (mostly with >99% completeness):

2007: 453 – 486 Mbits/orbit2008: 664 – 924 Mbits/orbit2009: 837 – 1050 Mbits/orbit2010: 907 – 919 Mbits/orbit (THEMIS-Low

probes)

Page 15: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 15 Dec. 18, 2010

THEMIS

ARTEMIS ARTEMIS Data Recovery Metrics

Page 16: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 16 Dec. 18, 2010

THEMIS

ARTEMIS

THEMIS / ARTEMIS Trajectories on 21-Sep-2009

THEMIS C orbit after ORM 13

THEMIS B orbit after ORM 5 and first lunar approach:347,000 x 19,300 km

16

Page 17: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 17 Dec. 18, 2010

THEMIS

ARTEMIS

THEMIS B / ARTEMIS P1 – First Lunar Approach

17-Sep-2009

THEMIS B orbit after ORM 5 and first lunar approach within 46,000 km, causing orbit to increase to 347,000 x 19,300 km

Moon

17

Page 18: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 18 Dec. 18, 2010

THEMIS

ARTEMIS

THEMIS B / ARTEMIS P1 – Second Lunar Approach

18

07/08-Dec-2009

Second lunar approach (the knee) within 18,800 km, causing inclination change from 10 to 58 deg

02-Dec-2009

Flyby Targeting Maneuver (FTM 2) near perigee of last equatorial orbit

02-Dec-2009

Contingency options for executing missed FTM 2

Moon

19-Dec-2009

Trajectory Correction Maneuver (TCM 1) near end of first high-inclination orbit

Page 19: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 19 Dec. 18, 2010

THEMIS

ARTEMIS

THEMIS B / ARTEMIS P1 – First and Second Lunar Flyby

19

13-Feb-2010

Second lunar flyby within 5,000 km, resulting in trans-lunar trajectory

31-Jan-2010

First lunar flyby within 14,300 km, resulting in back flip

Back flip

The kneeMoon

08-Dec-2009 − 31-Jan-2010

5 high-inclination orbits with 11-day periods

Page 20: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 20 Dec. 18, 2010

THEMIS

ARTEMIS

THEMIS B / ARTEMIS P1 – Largest Range from Earth

20

13-Feb-2010 - 23-Aug-2010

Weak stability boundary trajectory with two large excursions and one Earth flyby in between 06-Jun-2010

Largest range from Earth: 1,500,000 km

Page 21: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 21 Dec. 18, 2010

THEMIS

ARTEMIS

THEMIS B / ARTEMIS P1 – Libration Orbit Insertion

21

23-Aug-2010

Libration orbit insertion (LL2)

Page 22: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 22 Dec. 18, 2010

THEMIS

ARTEMIS

22

THEMIS B / ARTEMIS P1 Orbit Evolution

Page 23: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 23 Dec. 18, 2010

THEMIS

ARTEMIS

23

THEMIS C / ARTEMIS P2 – Final Earth Orbits

24-Mar-2010

Flyby targeting maneuver (FTM 1)

22-Mar-2010

Long partial Earth shadow

Lunar orbit

28-Mar-2010

Lunar flyby within10,200 km of center, resulting in trans-lunar trajectory

15-Mar-2010

Shadow deflection maneuver (SDM 2)

27-Feb-2010

Shadow deflection maneuver (SDM 1)

26-Feb-2010

Last orbit raise maneuver (ORM 27)

Moon

26-Mar-2010

Trajectory correction maneuver (TCM 1)

Page 24: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 24 Dec. 18, 2010

THEMIS

ARTEMIS

24

THEMIS C / ARTEMIS P2 Orbit Evolution

Page 25: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 25 Dec. 18, 2010

THEMIS

ARTEMIS

THEMIS B & C / ARTEMIS P1 & P2 – Libration Orbits

25

Libration orbit (LL2)

Libration orbit (LL1)

Moon

Page 26: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 26 Dec. 18, 2010

THEMIS

ARTEMIS

26

THEMIS B / ARTEMIS P1 Libration Orbits – Moon Centered CoordinatesCredit: NASA/GSFC

Page 27: Post-Fall AGU SWT Meeting1Dec. 18, 2010 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 27 Dec. 18, 2010

THEMIS

ARTEMIS

Summary• Overall Mission Status

– Completed THEMIS prime mission on November 19, 2009– Encountered 50 anomalies since launch - 39 closed– None of the anomalies caused a serious risk to mission success– Operations team staffing adequate for THEMIS & ARTEMIS support

• Flight Systems– All bus flight subsystems continued to perform very well– All science instruments are working very well in general

• Ground Systems– All ground systems continue to function well– Software tools are continually refined and extended as required

• ARTEMIS Mission Extension– Initiated Earth departure on July 20, 2009– Lissajous science phase started on October 22, 2010– Lunar orbit insertion likely delayed until July 2011 (details are TBD)– P1 to date: 5 ORMs, 2 FTMs, 8 TCMs, 1 DSM, 13 SKMs– P2 to date: 27 ORMs, 1 FTM, 2 SDMs, 5 TCMs, 3 DSMs, 8 SKMs

Summary