30
Post Contract-Award Building Information Modelling (BIM) Execution Plan (BEP) Project Name: Super KTP Development Project Address: Atarri Developments Ltd Project Number: SKD Date: 21/01/2016 (This Document is modified from CPix On-line Post Contract-Award Building Information Modelling (BIM) Execution Plan (BEP)).

Post Contract-Award Building Information Modelling (BIM ... · Post Contract-Award Building Information Modelling (BIM) Execution Plan (BEP) Project Name: Super KTP Development Project

  • Upload
    ngotram

  • View
    230

  • Download
    0

Embed Size (px)

Citation preview

Post Contract-Award Building Information Modelling (BIM) Execution

Plan (BEP)

Project Name: Super KTP Development

Project Address: Atarri Developments Ltd

Project Number: SKD

Date: 21/01/2016

(This Document is modified from CPix On-line Post Contract-Award Building Information

Modelling (BIM) Execution Plan (BEP)).

The Post Contract-Award Building

Information Modelling Execution Plan (BEP)

Preface

The BEP shall list the agreed targets for responsibility, timely delivery, exchange, reuse and final handover to the clients. It will also list all of agreed elements as outlined in the Employers Information Requirements, the Brief, the BS1192:2007, PAS1192-2:2013, the CPIx Protocol and the contract documents.

This BEP is structured in accordance with PAS1192-2:2013.

Project Delivery Manager

This document is owned and maintained by the current Project Delivery Manager listed below.

Project Delivery Manager - Name Company Responsible

Andrew Turner Henry Riley LLP

Project Team Representatives and Role

Company Name Representative and

Authorized Responsible Agent

Role

Frank Whittle Partnership (FWP) Gavin Lea Architect 1 / Lead Designer / Information Originator

Heriot Watt University Frederic Bosche BIM /Visualisation Academic

University of Westminster Rob Garvey BIM Academic

Teesside University / Sotech Optima Ltd

Mohamad Jenaban Cladding Contractor / Task Team Manager

Henry Riley LLP / Reading University

Adrien Guillemet QS / Information Manager / Interface Manager

BIM4SME Tim Platts Client

BWB Consulting Jon Frost Client

Kent Council Terry Gough Client

Nunelah Design Consultant Raj Chawla Client

Elliottwood Steve Faulkner Client

DKS Architects Dave Knudsen Company Supervisor

Sotech OptimaLtd Richard Egginton Company Supervisor

Frank Whittle Partnership (FWP) Neil Ainsworth Consultant

Teesside University Nashwan Dawood Consultant

Teesside University Michael Crilly Consultant

University of Central Lancashire Abdulkadir Ganah Consultant

University of Central Lancashire Jack Goulding Consultant

University of Central Lancashire Jenni Barrett Consultant

University of Salford Jason Underwood Consultant

University of Reading Tim Lees Consultant

BSRIA David Churcher Consultant

Links Project Ian Roberts FF&E

Links Project Marina Machado FF&E

University of Wolverhampton Dave Heesom HVAC

Teesside University/ DKS Architects

David Craggs Architect 2 / Task Information Manager

M+W Hargreaves Tom Bilbe Mechanical Engineer

Document Authority

This project plan has been agreed by the representatives of the project team as listed above with the

authority of their parent companies to accept this document as the Agreed BIM Execution Plan.

Contents

1 Project Information ..................................................................................................................................................................... 6

2 Information required by the EIR ................................................................................................................................................. 7

2.1 Level Of Definition ............................................................................................................................................................ 7 2.2 Training .............................................................................................................................................................................. 7 2.3 Planning of work and data segregation .............................................................................................................................. 7 2.4 Co-ordination and clash detection ...................................................................................................................................... 7 2.5 Collaboration process ......................................................................................................................................................... 7 2.6 Health and safety/CDM management ................................................................................................................................ 7 2.7 Compliance plan ................................................................................................................................................................ 7

3 Management ............................................................................................................................................................................... 8

3.1 Roles, responsibilities and authorities ................................................................................................................................ 8 3.2 Major project milestones .................................................................................................................................................... 9 3.3 Project information model delivery strategy ...................................................................................................................... 9 3.4 Survey strategy ................................................................................................................................................................. 10 3.5 Existing legacy data use ................................................................................................................................................... 10 3.6 Approval of information .................................................................................................................................................. 10 3.7 PIM authorization process ............................................................................................................................................... 10

4 Planning and documentation ..................................................................................................................................................... 11

4.1 Revised Project Implementation Plan .............................................................................................................................. 11 4.2 Agreed project processes for collaboration and information modelling .......................................................................... 12 4.3 Agreed matrix of responsibilities across the supply chain ............................................................................................... 13 4.4 Task information delivery plan (TIDP) ............................................................................................................................ 17 4.5 Master information delivery plan (MIDP) ....................................................................................................................... 17

5 Standard method and procedure ................................................................................................................................................ 18

5.1 Volume strategy ............................................................................................................................................................... 18 5.2 PIM origin and orientation ............................................................................................................................................... 18 5.3 File naming convention .................................................................................................................................................... 19 5.3.1 File naming convention tool............................................................................................................................................. 19

5.3.2 Project .......................................................................................................................................................................... 19

5.4.3 Originator ..................................................................................................................................................................... 20

5.3.3 Volume ........................................................................................................................................................................ 21

5.3.4 Level or Location ......................................................................................................................................................... 23

5.3.5 File type ....................................................................................................................................................................... 23

5.3.6 Discipline ..................................................................................................................................................................... 25

5.3.7 Number ........................................................................................................................................................................ 26

5.3.8 Metadata ...................................................................................................................................................................... 27

5.4 Layer naming convention ................................................................................................................................................. 28 5.5 Agreed construction tolerances for all disciplines ........................................................................................................... 28 5.6 Drawing sheet templates .................................................................................................................................................. 28 5.7 Annotations, dimensions, abbreviations and symbols ...................................................................................................... 29 5.8 Attribute data ................................................................................................................................................................... 29

6 IT solutions ............................................................................................................................................................................... 30

6.1 Software versions ............................................................................................................................................................. 30 6.2 Exchange formats ............................................................................................................................................................. 30 6.3 Process and data management systems ............................................................................................................................ 30

7 Appendix .................................................................................................................................................................................. 31

7.1 Example of Deliverables expected. .................................................................................................................................. 31

List of Tables

Table 1 – Project Information .......................................................................................................................................................... 6 Table 2 – Roles and responsibilities .............................................................................................................................................. 8 Table 3 – Role authorities ................................................................................................................................................................ 8 Table 5 – Strategy for information delivery ................................................................................................................................... 9 Table 6 – Survey strategy .............................................................................................................................................................. 10 Table 7 – Schedule of information approval responsibilities .................................................................................................... 10 Table 8 – Supplier resource summary ......................................................................................................................................... 11 Table 9 – Processes for collaboration and information modelling ........................................................................................... 12 Table 10 – Clash rendition viewer ................................................................................................................................................ 12 Table 11 – Authorisations for security, extranet and document distribution .......................................................................... 12 Table 12 – Responsibility matrix for information production..................................................................................................... 13 Table 13 – Template for task information delivery plans .......................................................................................................... 17 Table 14 – Record of information model origin and orientation ............................................................................................... 18 Table 15 – Template for file naming ............................................................................................................................................ 19 Table 16 – Project code(s) ............................................................................................................................................................ 19 Table 17 – Originator codes .......................................................................................................................................................... 20 Table 18 – Template for defining project volumes ..................................................................................................................... 22 Table 19 – Level or location codes .............................................................................................................................................. 23 Table 20 – Agreed file types for drawings and models (see BS1192:2007, PAS1192-2) ................................................... 23 Table 21 – Agreed file types for documents (see BS1192:2007, PAS1192-2) ..................................................................... 23 Table 22 – Discipline codes (see BS1192-5) ............................................................................................................................. 25 Table 23 – Extended discipline codes for this project ............................................................................................................... 25 Table 24 – Metadata status codes from PAS1192-2 ................................................................................................................. 27 Table 25 – Layer naming convention ........................................................................................................................................... 28 Table 26 – Agreed tolerances for construction elements according to project discipline .................................................... 28 Table 27 – List of drawing sheet templates ................................................................................................................................ 28 Table 28 – Drawing sheet scales ................................................................................................................................................. 29 Table 29 – Agreed units of measurement ................................................................................................................................... 29 Table 30 – Agreed software versions .......................................................................................................................................... 30 Table 31 – Agreed exchange formats for models and drawings ............................................................................................. 30

1 Project Information

Table 1 – Project Information

Project Name KT4BIM Development

Project Address 1 St Chad’s Terrace Shrewsbury Shropshire SY1 1JL

Project Number (Clients Project Number or reference)

Contract Form Contract form to be determined CIC Building Information Model (BIM) Protocol: First Edition 2013

Project Design Start Date 04 / 09 / 2015

Project Construction Start Date

N/A

Project Completion and Handover Date

N/A

Project Description (EIR) (Copy from EIR) The KT4BIM Development comprises of the development of a greenfield site adjacent the River Severn in Shrewsbury. The site will be developed in 3 areas:

1. Development of ‘Selfbuild on a shoestring’ residential units 2. Mixed used development to provide new retail space and

Grade A office space 3. Public realm area adjacent to the River Severn

May be an additional document, please reference.

Project Brief and CDM requirements

See EIR.

Project Deliverable as defined in the EIR and COBie project templates (see also the CPIx Protocol)

See EIR.

2 Information required by the EIR

See EIR. Because of issues of duplication of information, this document isn’t showing information contained in the EIR. However, a summary of the EIR could be compiled here by bidding team.

2.1 Level Of Definition

2.2 Training

2.3 Planning of work and data segregation

2.4 Co-ordination and clash detection

2.5 Collaboration process

2.6 Health and safety/CDM management

2.7 Compliance plan

3 Management This section of the BEP covers the requirements of PAS1192-2 Clause 7.2.1 a).

3.1 Roles, responsibilities and authorities At the start of a project it is important to identify the roles and responsibilities of the design teams. Table 2 is used to record the names and contact details of the individuals fulfilling the necessary project roles

Table 2 – Roles and responsibilities

* Note – specify these roles for each task team involved in the project

The standard authorities of the different roles related to production and management of information are given in Table 3.

Table 3 – Role authorities

Role Authority

Project Information Manager Enforce the Project BIM Standard and ensure delivery of the Information requirement in the EIR.

Lead Designer Enforce spatial coordination

Task Team Manager Enforce documentation standards

Interface Manager Negotiate space allocation

Task Team Information Manager Reject non-compliant models, drawings & documents

CAD Coordinator Enforce CAD related Project BIM Standards

Role Company Name Email and Telephone number

Lead Designer

Frank Whittle Partnership

N/A

Project Delivery Manager

Adrien Guillemet

N/A

Construction Manager

N/A

Project Information Manager DKS

Atarii

DKS Architects

BIM4SME

N/A

Task Team Manager *

BIM4SME

N/A

Task Team Information Manager *

DKS Architects

N/A

Task Team Interface Manager *

BIM4SME

N/A

Task Team BIM Authors *

Frank Whittle Partnership

Hargreaves Ductwork Ltd

Billinghurst George + Partners

Links Project FF&E Ltd

Sotech-Optima Ltd

N/A

3.2 Major project milestones

MILESTONE - DATE

MILESTONE - NAME MILESTONE - I.D.

17/08/2015 MILESTONE - Project Start-Up. 001 04/09/2015 MILESTONE - Project Initiation. 002 07/09/2015 MILESTONE - Stage 0 - Strategic Definition; START MILESTONE 003 27/01/2016 MILESTONE - Stage 0 - Strategic Definition; END MILESTONE 004 27/01/2016 MILESTONE - Stage 1 - Preparation and Brief; START MILESTONE 005 15/02/2016 MILESTONE - DATA_DROP - CoBie - 01A (End OF Stage) 006 18/02/2016 MILESTONE - Stage 1 - Preparation and Brief; END MILESTONE 007 18/02/2016 MILESTONE - Stage 2 - Concept Design; START MILESTONE 008 26/02/2016 MILESTONE - DATA_DROP - Model Exchange - 02A 009 10/03/2016 MILESTONE - DATA_DROP - CoBie - 02B (End OF Stage) 010 27/01/2016 MILESTONE - DATA_DROP - H.&S. - "Drop_2" - Health and Safety and Construction

Design Management 011

15/03/2016 MILESTONE - Stage 2 - Concept Design; END MILESTONE 012 15/03/2016 MILESTONE - Stage 3 - Developed Design; START MILESTONE 013 15/03/2016 MILESTONE - DATA_DROP - Model Exchange - 03A 014 31/03/2016 MILESTONE - DATA_DROP - CoBie - 03B (End OF Stage) 015 04/05/2016 MILESTONE - DATA_DROP - H.&S. - "Drop_3" - Health and Safety and Construction

Design Management 016

06/04/2016 MILESTONE - Stage 3 - Developed Design; END MILESTONE 017 06/04/2016 MILESTONE - Stage 4 - Technical Design; START MILESTONE 018 14/04/2016 MILESTONE - DATA_DROP - Model Exchange - 04A 019 21/04/2016 MILESTONE - DATA_DROP - Model Exchange – 04B 020

28/04/2016 MILESTONE - DATA_DROP - CoBie – 04C (End OF Stage) 021 04/05/2016 MILESTONE - Stage 4 - Technical Design; END MILESTONE 022 03/06/2016 MILESTONE - Project De-Initiation. 023 03/06/2016 MILESTONE - Project Close-Down. 024

Only the Major milestones are listed. A more detail and co-ordinated MIDP and Project Plan must be developed and agreed with the stakeholders.

3.3 Project information model delivery strategy The major goals and objectives for the BIM implementation must be considered and stated as a project strategy document, append to this document, under the headings listed in Table 5.

Table 4 – Strategy for information delivery

Stage 0 - Strategic Definition;

Client documents issued

Stage 1 - Preparation and Brief; The PIM will exist as a design intent model, more of a graphical representation at

this stage, with minimal meta data attached. This will reduce the amount of wasted

effort at this stage of early design. Arch will have full control of elements of design

here LOD 1. The information produced and issued will answer the PLQs for Stage

1. Stage 2 - Concept Design; During this phase the Space allocation will become apparent. MIDP shows the Arch

will have control over most of the design whereas the Strt, MEP will take ownership

of their discipline here. Model should be at Level of Detail 2.

Stage 2 is split into a second half where a contractor is brought on. The contractor

takes ownership of the model here and keeps the same level of detail. The

information produced and issued will answer the PLQs for Stage 2. Stage 3 - Developed Design;

Contractor increases the LOD here to the next level. Level of Detail 3. The

contractor took ownership of the design at concept and takes it through to

Developed design. The information produced and issued will answer the PLQs for

Stage 3. Stage 4 - Technical Design; The information produced and issued will answer the PLQs for Stage 4.

3.4 Survey strategy

Table 5 – Survey strategy

Survey Method Delivery Format

Survey Origin

Details, notes

Point cloud N/A N/A

Light detecting and ranging

(LIDAR)

N/A N/A

Global navigation satellite

systems (GNSS)

N/A N/A

*others as appropriate*

3.5 Existing legacy data use As provided and defined by the EIR.

3.6 Approval of information To ensure that model, drawing files and spreadsheet extraction are adequately checked, some form of agreed approvals process needs to be in place to enable the design teams and the contractor (or client) to approve and sign-off the development of the design information for a project and to assign responsible team members.

Table 6 – Schedule of information approval responsibilities

Name Role or Title

Models Drawings Peer Review Lead

Designer

Client Review Team

Andrew Turner Client •

Gavin Lea Architect • • • •

David Craggs Information Manager • • • •

Mohamad Jenaban

Engineer / Design • • •

Thomas Bilbe HVAC Design • • •

Criss Nixon Structural Engineer • • •

Marina Machado FF&E Designer • • •

3.7 PIM authorization process The design and construction approval process should be specified, agreed and documented as early as possible in the project. This includes the sign off of specialist design completion information.

Sign off and authorisation process to be agreed and published in coordination with the abilities of the collaboration or EDMS solution and inserted here.

4 Planning and documentation This section of the BEP covers the requirements of PAS1192-2 Clause 7.2.1 b).

4.1 Revised Project Implementation Plan The revised PIP confirms the capability of the supply chain.

The PIP consists of the following completed CPIx documentation:

Supply chain capability summary form, which summarises the contents of …

Supplier building information management assessment form(s)

Supplier IT assessment form(s)

Supplier resource assessment form(s)

These forms should be incorporated into or appended to this pre-contract BEP (see individual documents).

The supplier resource for the project can also be summarised as per the example in Table 8.

Table 7 – Supplier resource summary

Supplier Discipline Resource Numbers

Levels of Competence

Years of Experience

Names of Individuals

Architecture 1 Certificate in BIM -Project Management, BIM Trained

5 Lea, Gavin

HVAC 1 3 Bilbe, Tom

Cladding 1 3 Jenaban, Mohamad

Fit-Out 1 3 Machiado, Marina

4.2 Agreed project processes for collaboration and information modelling

Table 8 – Processes for collaboration and information modelling

Company Solution Network Database File based Comments

FWP NBS Toolkit COBie

Cloud Newforma

Export Project to CDE

SotechOptima NBS Toolkit

COBie

Cloud Newforma

Export Project to CDE

Hargreaves NBS Toolkit COBie

Cloud Newforma

Export Project to CDE

The clash rendition viewer to be used across the whole project.

Table 9 – Clash rendition viewer

Agreed clash rendition viewer Version

Autodesk Navisworks 15/16

This section of the BEP also covers the agreed authorisations for security and extranet access and authority to distribute documents.

Table 10 – Authorisations for security, extranet and document distribution

Company Authorised Manager Authority (Upload, download, change Access/Distribution)

FWP Gavin Lea Upload, download.

Sotech Optima Mohamad Jenaban Upload, download.

Henry Riley Adrien Guillemet Upload, download, & change Access.

DKS Architects David Craggs Upload, download.

13

Post Contract BIM Execution Plan © (BIM4MSE)

21/01//2016

4.3 Agreed matrix of responsibilities across the supply chain It is important to define who models what (the BIM Author) and to what Level of Detail (LOD).

There are 7 levels of detail defined in the PAS1192-2 which do not reflect specific modelling guidelines for any particular software, rather a generic definition of model detail (graphical), how individual objects display themselves and the level of information as a minimum to answer the English question stated in t he EIR.

Table 11 – Responsibility matrix for information production

Plan of Work

Software

Native Format

Exchange Format(s)

1

Brief

2

Concept

3

Definition

4

Design

5

Build & Commission

6

Handover &

Closeout

7 Operation

Model Authoring

Space Planning

Site, Urban Design Context

Site and Existing Buildings

FWP Architectural Model Revit .rvt dwg .ifc .pdf • • •

Structural Design Model

HVAC Design Model Revit .rvt .dwg .ifc .pdf • • •

Building Services MEP Design Models

Lighting Design Model

Electrical Design Model

Hydraulics Design Model

Interior Layouts and Design Model

HVAC Fabrication Model SysQue/

CADduct

.rvt .maj n/a •

Sotech's Structural Steel Fabrication Model / Manufacture

Radan STEP PDF / DWG /

DFX

14

Post Contract BIM Execution Plan © (BIM4SME)

1/5/2016

Sotech's Cladding / Rainscreen Model

Solidworks .SDL .PDF / .IGES /

.DXF / .DWG

/ .STEP

• • •

Road and Civil Design

Landscaping and External Works Options

Renovation and Refurbishment

Facility Management Model

Construction Model

Model Analysis

Brief Development

Alternative Design Options Analysis

Design Performance Analysis

Sun and Shadow Studies

Structural Analysis

Thermal Simulation

Sustainability Analysis

LCA Analysis

Model Clash Detection Rendition

Cost Planning and Control

CostX .exf .xls

Construction Scheduling / 4D Animation

Security Analysis

Code Checking and Regulatory Compliance

15

Post Contract BIM Execution Plan © (BIM4SME)

1/5/2016

Acoustic Analysis and Design

Disabled Access and Egress

Fire Protection

FM, Operation and Maintenance

Automated/Linked Specifications

Heritage Documentation and Assessment

Solar Envelopes

Overshading

Daylight Analysis

Solar Analysis

Photovoltaic Collectors

21/01//2016 Post Contract BIM Execution Plan © (BIM3SME)

17

4.4 Task information delivery plan (TIDP) A task information delivery plan (TIDP) for each task within the project shall be prepared using the template below so that the format is consistent with the format required for the master information delivery plan.

Table 12 – Example for task information delivery plans

4.5 Master information delivery plan (MIDP) The master information delivery plan (MIDP) shall be developed from the separate TIDPs produced for each task within the project. This more detailed, co-ordinated MIDP must be developed and agreed with the stakeholders.

See MIDP file.

21/01//2016 Post Contract BIM Execution Plan © (BIM3SME)

18

5 Standard method and procedure This section of the BEP covers the requirements of PAS1192-2 Clause 7.2.1 c).

5.1 Volume strategy See Section 5.3 (file naming convention), sub-section Volume for the definitions and abbreviations of volumes to be used on the project.

5.2 PIM origin and orientation The origin and orientation of the project are based on the project location and its reference to other global or local grids, for example Ordnance Survey. Some projects have their own grid system: Crossrail, for instance, uses the London Grid specified for that project, as did the Olympics programme.

See the CPIc Production Information 2003 publication for specific requirements.

Table 13 – Record of information model origin and orientation

Point Grid intersection notation

Easting (m) Northing (m) Elevation or site Datum

Site local grid origin

Grid origin

Bottom Left Intersection

Grid Intersection Bottom Right

Grid Intersection Top Left

21/01//2016 Post Contract BIM Execution Plan © (BIM3SME)

19

5.3 File naming convention Table 14 – Template for file naming

See the ‘Guide to BS1192:2015’ for additional explanation.

5.3.1 File naming convention tool File naming convention tool “SKD-PDC-00-XX-SH-K-0000-BS_1192_Syntax_Jutsu-S3-P03” to be used by Project Team

Representatives.

5.3.1.1 Input;

5.3.1.1 Output;

5.3.2 Project The ‘project’ is an alphanumeric code that is used by the project team to identify the project.

It should not be confused with the Project Contract number which may be different for each company working on the project.

Table 15 – Project code(s)

Code Project

SKD KT4BIM

Where an organisation needs to use their own internal project numbers, then they can be Indicated in the drawing title block using a separate ‘project number’ box.

21/01//2016 Post Contract BIM Execution Plan © (BIM3SME)

20

5.4.3 Originator

Table 16 – Originator codes

Code (Abbreviate to either 2 or three digits)

Originator Company name

*****University;*****

UCL

UHW

URD

USF

UTS

UWL

UWS

ULM

*****Company;*****

ATT

BGP

BWB

DKS

FWP

HRL

LKN

LKS

MWH

NNL

SOL

KTC

BCM

*****People;*****

PAA

PAG

PAT

PCA

PCH

PCN

PDC

PDH

PDU

PDK

PDM

PDN

PFB

PGL

PHK

PHT

PIR

PJB

PJF

PJG

PJH

PJS

PJU

PMC

PMJ

*****University;*****

University of Central Lancashire

Heriot Watt University

University of Reading

University of Salford

Teesside University

University of Wolverhampton

University of Westminster

Liverpool John Moores University

*****Company;*****

Atarii

Billinghurst George + Partners

BWB Consulting

DKS Architects

Frank Whittle Partnership

Henry Riley LLP

LinkNode Ltd.

Links Project FF&E Ltd

Hargreaves Ductwork Ltd

NUNELAH

Sotech-Optima Ltd

Kent Council

Beverley Clifton Morris

*****People;*****

Abdulkadir Ganah

Adrien Guillemet

Andrew Turner

Chris Harty

Crispin Hoult

Chris Nixon

David J. Craggs

Dave Heesom

David Churcher

Dave Knudsen

Dianne Marsh

Dawood Nashwan

Frederic Bosche

Gavin Lea

Haniyeh M. Karbasi

Henry Fenby-Taylor

Ian Roberts

Jenni Barrett

Jon Frost

Jack Goulding

Jim Hendley

Jon Swales

Jason Underwood

Michael Crilly

Mohamad Jenaban

21/01//2016 Post Contract BIM Execution Plan © (BIM3SME)

21

PMM

PNA

PND

PRC

PRE

PRG

PSF

PTB

PTC

PTG

PTL

PTP

*****Team;*****

B4S

DGN

EXT

KTP

SKT

ERT

QST

KTN

Marina Machado

Neil Ainsworth

Nashwan Dawood

Raj Chawla

Richard Egginton

Rob Garvey

Steve Faulkner

Tom Bilbe

Terry Corner

Terry Gough

Tim Lees

Tim Platts

*****Team;*****

BIM4SME

Design_Team

External

Client_Team

SKTP_Team

EIR_Responding_Team

Quantity_Surveyors_Team

Knowlege_Transfer_Partners

Note; This Table (Originators Codes) was Extracted from,

“SKD-PDC-00-XX-SH-K-0000-BS_1192_Syntax_Jutsu-S0-P02.01.xlsm”

Note; Project Team Representatives and Role are encouraged to use company Originator Code instead of personal originator code, (this is not standard practice however it is applicable to this project).

5.3.2.1 Summary of Originators Codes;

08 No. Universities 13 No. Companies

36 No. People 07 No. Groups

5.3.3 Volume Each individual team will provide a copy of their volume strategy in the form of a drawing of each floor layout, section or site with volumes clearly marked named and inserted below. For volumes relating to infrastructure refer to PAS1192-2:2013.

Example:

When planning complex projects and determining the number of model files required, it is

commonplace and good practice for the project to be divided into volumes defined by

coordinates within an overall project model that will be held as separate model files. This

enables multiple users to work on the project efficiently. Volumes should be allocated using

cut lines to indicate their limits. Volume boundaries could be structural joints or grid lines; for

21/01//2016 Post Contract BIM Execution Plan © (BIM3SME)

22

road projects they could be chainage distances; or they could be defined by use

e.g. a vertical distribution shaft.

Each team will provide a copy of their volume strategy in the form of a drawing of each floor

layout with volumes clearly marked and inserted below.

Table 17 – Template for defining project volumes

Discipline/Originator:

Code Volume (Abbreviate to 2 No. alphanumeric characters)

00 All Zones

XX No zone applicable

PR Public Realm

RS

Residential Zoning

RE Retail Zoning

DA Document All (Formally DO1) (Used for Admin documents not BIM Models).

Note; This Table (Template For Defining Project Volumes) was Extracted from,

“SKD-PDC-00-XX-SH-K-0000-BS_1192_Syntax_Jutsu-S0-P02.01.xlsm”

5.3.3.1 Summary of Originators Codes;

02 No. Standard Codes

03 No. Project Specific Codes

01 No. Miscellaneous Code

21/01//2016 Post Contract BIM Execution Plan © (BIM3SME)

23

Code Location

M1 Mezzanine above level 01 M2 Mezzanine above level 02 M3 Mezzanine above level 03 M4 Mezzanine above level 04 M5 Mezzanine above level 05

B1 Below Ground Floor B2 Below Ground Floor B3 Below Ground Floor B4 Below Ground Floor B5 Below Ground Floor

5.3.4 Level or Location The ‘level’ code is a 2 or 3 character alphanumeric code that represents the level or storey of the building. For infrastructure (linear) the level is replaced by location defined as a chainage and offset.

Table 18 – Level or location codes

Note; This Table (Level or Location Codes) was Extracted from,

“SKD-PDC-00-XX-SH-K-0000-BS_1192_Syntax_Jutsu-S0-P02.01.xlsm” And based on BS 1192:2007+A1:2015.

5.3.5 File type

Table 19 – Agreed file types for drawings and models (see BS1192:2007, PAS1192-2)

Code File Type

***** File types for drawings and models;*****

AF Animation file

CM Combined Model

CR Specific for clash process

DR 2D drawing

M2 2D model file

M3 Model rendition file for other renditions, e.g. thermal analysis etc.

VS Visualisation

***** *****File type project Specific;*****

IM Image

VR Video

Table 20 – Agreed file types for documents (see BS1192:2007, PAS1192-2)

Code File Type

BQ Bill of quantities

Code Level

ZZ Multiple levels

XX No level applicable

GF Ground floor 00 Base level of building (where ground floor is not appropriate)

01 Floor 1 02 Floor 2 03 Floor 3 04 Floor 4 05 Floor 5

21/01//2016 Post Contract BIM Execution Plan © (BIM3SME)

24

CO Correspondence

CP Cost plan

FN File note

HS Health and safety

IE Information Exchange file

MI Minutes / action notes

MS Method statements

PP Presentation

PR Programme

RD Room data sheet

RI Request for information

RP Report

SA Schedule of accommodation

CA Calculations

SH Schedule

SN Snagging list

SP Specification

SU Survey

***** *****File type project Specific;*****

DC Document

21/01//2016 Post Contract BIM Execution Plan © (BIM3SME)

25

5.3.6 Discipline A list of discipline or role codes as recommended in BS1192 Part 5 are shown in the Table below.

Table 21 – Discipline codes (see BS1192-2007)

Code Discipline

A Architect

B Building Surveyor

C Civil Engineer

D Drainage, Highways Engineer

E Electrical Engineer

F Facilities Manager

G Geographical Information System Engineers and Land Surveyor

H Heating and Ventilation Designer

I Interior Designer

K Client

L Landscape Architect

M Mechanical Engineer

P Public Health Engineer

Q Quantity Surveyor

S Structural Engineer

T Town and Country Planner

W Contractor

X Sub-Contractor

Y Specialist Designer

Z General (non-disciplinary)

The ‘discipline’ code is a single character indicating the discipline. On larger projects it may be useful to extend the discipline code to 2 characters and listed here.

Table 22 – Extended discipline codes for this project

Code Discipline

***** *****Project specific codes for roles;***** J Legal (solicitors & lawyers) N_ Finance; accountants and financial institutions

N Finance; accountants and financial institutions O Undefined R Undefined U Undefined V Undefined

***** ****Role Additions*****

CB Bridge Engineer CR Road / Highway Engineer CW Water / Dam Engineer EC Cable Containment EF Fire Alarm

21/01//2016 Post Contract BIM Execution Plan © (BIM3SME)

26

EL Lighting EP Protection ES Security GA Aerial surveyors ME Combined Services MW Chilled Water MH Heating MV Ventilation PD Drainage PF Fire Services PH Public Health Services PS Sanitation and Rainwater EW Water Services RS Railways signaling RT Railways track SF Façade engineers SR Reinforcement detailers

Note; This Table (Extended Discipline Codes For This Project) was Extracted from,

“SKD-PDC-00-XX-SH-K-0000-BS_1192_Syntax_Jutsu-S0-P02.01.xlsm” And based on aecukbimprotocol-v2-0

5.3.7 Number The ‘number’ is a 5-character code. The number may be viewed in a number of ways:

1. Each design disciplines starts at 00001 and then allocates additional numbers to suit their own needs.

2. The first two or three characters of the number could be used to signify an ‘element code’ that further classifies the file. One classification code system should be chosen and consistently used by all project teams.

21/01//2016 Post Contract BIM Execution Plan © (BIM3SME)

27

5.3.8 Metadata Extend the standard Metadata status codes as required for the project, add to but do not change the codes in the PAS1192-2.

Table 23 – Metadata status codes from PAS1192-2

Status Description

Work in Progress

S0 Initial status or WIP Master document index of file identifiers uploaded into the extranet.

Shared (Non-Contractual)

S1

Suitable for Co-ordination The file is available to be „shared‟ and used by other disciplines as a background for their Information.

S2 Suitable for Information

S3 Suitable for Internal Review & Comment

S4 Suitable for Construction Approval

S5 Suitable for Manufacture

S6 Suitable for PIM Authorization (Information Exchanges 1-3)

S7 Suitable for AIM Authorization (Information Exchange 6)

D1 Suitable for Costing

D2 Suitable for Tender

D3 Suitable for Contractor Design

D4 Suitable for Manufacture/Procurement

AM As Maintained

Published Documentation (Contractual)

A Suitable for Construction

B

Partially signed-off: For Construction with minor comments from the Client. All minor comments should be indicated by the insertion of a cloud and a statement of “in abeyance” until the comment is resolved, then resubmitted for full authorization.

AB As-Built Handover documentation, PDF, native models, COBie etc.

Published for AIM Acceptance

CR As Construction Record documentation PDF, Models etc.

Project Specific Status

R0 Un-Ratified

R1 Ratified

21/01//2016 Post Contract BIM Execution Plan © (BIM3SME)

28

5.4 Layer naming convention Each discipline should provide the Design Manager and the CAD manager with a full list of all layer names to be used on the project. This list should be published to all members of the project team for information.

Table 24 – Layer naming convention

Field Discipline Classification Presentation Description

Name A - G23 - M2 _ Stairs

Example Architect Stairs (Uniclass) Model graphics (2D)

Some software solutions suggest that layer names are not necessary but it has been found that the convention shall be used when sharing or exchanging information.

5.5 Agreed construction tolerances for all disciplines

Table 25 – Agreed tolerances for construction elements according to project discipline

Discipline Element Tolerance

Architectural Model Wall/s, Door/s, Window/s, Floor/s Roof/s

Stage 2= +/- 0750mm

Stage4 = +/- 010mm

Structural Model Primary Columns Stage 3 = +/- 020mm

Stage 4 = +/- 005mm

Primary Beams Stage 3 = +/- 020mm

Stage 4 = +/- 005mm

Mechanical Model Services Stage 4 = +/- 010mm

Furniture Model Furniture Stage 4 = +/- 050mm

Cladding Model Fabrication Stage 4 =+/- 005mm

Landscape Model Boundary Lines Stage 2 = +/- 300mm

Note; BS 5606:1990 “Guide to Accuracy in Buildings” to override the table “Agreed tolerances for construction elements according to project discipline”.

5.6 Drawing sheet templates

Table 26 – List of drawing sheet templates

Sheet Size (String). Sheet File name (mm).

A0 0841 × 1189

A1 0594 × 0841

A2 0420 × 0594

A3 0297 × 0420

A4 0210 × 0297

21/01//2016 Post Contract BIM Execution Plan © (BIM3SME)

29

Table 27 – Drawing sheet scales

Drawing Sheet Scales

All drawings must be rendered and presented at one of a number of approved scales, which are typically defined by the ‘BIM Manager’. Scales other than those approved should not be used.

Scale Description of detail

1:1000 1:1000 Scale Detail shows shape and layout

1:500

1:200

1:100 1:100 Scale Detail shows shape, layout and construction elements

1:50 1:50 Scale Detail shows how the construction elements meet at junctions

1:20

1:10

1:5 1:5 Scale detail show shape, dimensions and assembly of the

separate construction elements

1:2 1:2 Scale detail show shape, dimensions and assembly of the

separate construction elements

1:1 All model files must be modelled at 1:1 Scale

5.7 Annotations, dimensions, abbreviations and symbols Each discipline should provide the Design Manager and the CAD manager with a full list to be used on the project. This list should be published to all members of the project team to ensure consistency of the document graphical presentation and shall be consistent throughout the project. Also see BS8541 Parts 1, 2, 3 and 4.

Dimensions should be derived automatically from the underlying CAD coordinates by using the 'associative dimensioning' function of CAD systems. Dimensions should not be entered as 'text' as they are purely graphic characters having no relationship with the underlying CAD coordinates and will cause the relative positions of elements in a drawing to be compromised.

The project team should agree common units of measurement. These should include distance (e.g. metre and millimetre) and angles (e.g. degrees/radians measured clockwise or counter clockwise).

Table 28 – Agreed units of measurement

Type of information

Millimetres Metres Degrees Radians Clockwise Counter

Survey • • •

Roads • • •

Models • • •

Drawings • • •

5.8 Attribute data Attribute data for the project as defined in the EIR and appropriate COBie templates.

21/01//2016 Post Contract BIM Execution Plan © (BIM3SME)

30

6 IT solutions This section of the BEP covers the requirements of PAS1192-2 Clause 7.2.1 d).

6.1 Software versions The CAD software and versions that will be used by the design teams shall be agreed before starting the project.

Table 29 – Agreed software versions

Company Database CAD software

Version Format Comments

FWP N/A Autodesk Revit

2016 & early

versions

.rvt Architecture

Sotech Optima

N/A Inventor - Pro /

Solidworks

2016 / 2016

.sdl Mechanical design / Cladding FF&E (Links) N/A Autodesk

Inventor/ Solidworks

2016 / 2016

.sdl Furniture

Henry Riley LLP

N/A CostX 5 .exf QS

6.2 Exchange formats The agreed formats for model and drawing file exchange are

Table 30 – Agreed exchange formats for models and drawings

DWG DGN DWF PDF IFC Other

Models • • • •

Drawings • •

Final drawing format

• •

Schedules or spreadsheets

• • •

6.3 Process and data management systems The process and data management systems shall be described under section 4.2 Agreed project processes for collaboration and information modelling.

21/01//2016 Post Contract BIM Execution Plan © (BIM3SME)

31

7 Appendix

7.1 Example of Deliverables expected.