Upload
eustace-jordan
View
220
Download
0
Embed Size (px)
DESCRIPTION
EU Fast Track Strategy In response to criticism from various European scientists that fusion would take 50 years, and the “87 questions from the Bundestag”, the EU initiated a study in 2001 led by Sir David King. Bottom Line - 35 years to a non commercial DEMO References: Fire Fusion Library Accelerated Development of Fusion Power, I Cook, N Taylor, D Ward, L Baker, T Hender, UKAEA FUS 521 EURATOM/UKAEA Fusion, Feb 2005, D. Maisonnier ISFNT 2005 Excerpts from Cris Lewellyn Smith’s IAEA 2004 Talk, and US visit in 2005
Citation preview
http://fire.pppl.gov
Possible Strategies for a Broadened Fast Track Approach to Fusion Energy
Dale MeadePrinceton Plasma Physics laboratorySymposium on Fusion Engineering
Knoxville, TNSeptember 28, 2005
The Most Frequently Asked Questions
• Q - When will we get fusion energy?
• A - 35 years to a non commercial DEMO
• Q - Why is something so important taking so long?
• A - Tougher than we thought, not enough money,
various excuses.
• End of Conversation
EU Fast Track Strategy• In response to criticism from various European scientists that fusion would
take 50 years, and the “87 questions from the Bundestag”, the EU initiated a study in 2001 led by Sir David King.
• Bottom Line - 35 years to a non commercial DEMO
References: Fire Fusion Library
• Accelerated Development of Fusion Power, I Cook, N Taylor, D Ward, L Baker, T Hender, UKAEA FUS 521 EURATOM/UKAEA Fusion, Feb 2005, D. Maisonnier ISFNT 2005
• Excerpts from Cris Lewellyn Smith’s IAEA 2004 Talk, and US visit in 2005
PRELIMINARYyear 0
2005 2010 2015 2020 2025 2030 2035 2040 2045 2050
4525 30 35 405 10 15 20
conceptual design
construction
operateToday's expts
licenseH & D operation low-duty D-T
operationhigh-duty D-T operation
TBM: checkout and characterisation
TBM performance tests
second D-T operation phaseITER
EVEDA (design)
IFMIF
engineering designconstruction phase 1 blanket
construct & install
phase 2 blanket
construct & install
blanket:
operation phase 1operation phase 2blanket design &
prototypingphase 2 blanket
designlicense
DEMO
engineering design construction operateconceptual designlicense
Power plant
blanket optimisation
plasma performance confirmation
materials characterisation
materials optimisation
plasma optimisation
design optimisation for high availability
plasma optimisation
technology issues (e.g. plasma-surface interactions)
plasma issues (e.g. disruption avoidance)
operation: steels testingconstruction other materials testing
C. Lewellyn Smith IAEA 2004
EU Fast Track Strategy
2. JA / EU roadmap to Fusion DEMO
2010 2015 2020 2025 2035
DecomissioningConstruction
Development of breeding blanket
Fusion material development (inc. IFMIF)
Achieve Q=20, 400sAchieve Q~5 steady-state operationProof of principle of breeding blanket
Confirm physics database
Confirm material database
DEMO physics input for starting EDA
construction power production
Grid connection
licencing
2005FY
ITER program
Satelite TokamaksAnd other devices
Fusion technology development
DEMO
Basic performance phase
Decision of construction
JT-60 and JET
2030
Performance extension phase
Test of breeding blanket
Coordination of DEMO physics and tech. R&D
CDA-like EDA/R&DConcept exploration
- 3 -
US 35 Year Plan
• Requested by DOE to bolster case for US joining ITER negotiations.
• 35 years to first electricity production using MFE or IFE
• Report generally characterized as DOA in Washington
Official Plans are Really “Slow track”
• Its been 30 years to DEMO for 55 years.
• Twenty years since the start of ITER discussions, and construction has not yet started.
• As a result fusion gets one paragraph in serious books or article about future energy sources.
• We used to have more ambitious plans
• 1976 Plan
• 1980 MFE act
• Mid 80s Plans e.g., Technical Planning Activity
1976 US Plan for Fusion
• Logic V became the basis for the MFE Act of 1980.
• The US Fusion Program evolved from Logic IV to Logic I - we never get there.
Fusion Power by Magnetic Fusion Program Plan July 1976 ERDA – 76/110/1
Base program only
The Magnetic Fusion Engineering Act of 1980
• Operation of Fusion Engineering Device (burning plasma and tests of components for engineering purposes) by 1990 ( 9 years)
• Operation of Fusion DEMO by 2000- prototype energy (electricity production) system of sufficient size to provide safety, availability and ready extrapolation to commercial size, need not be economically competitive with then existing energy sources. (19 years)
• Budget (relative to October 7, 1980 -start of FY 1981):
• 1982 +20%
• 1983 + 20%
• double budget within 7 years
• without inflation
.- How did we do relative to this plan?
Comparison of MFE Act with Actual Budget/Progress
The FED (burning plasma and technology tests) should have been done by end of 2001 according to the actual money spent on MFE).
DEMO
FEDFED
External Conditions are Changing
• Concerns about energy supplies have risen to awareness levels not seen since the mid 1970s.
• oil reserves
• growing demand
• global climate change
• Manhattan Project for Alternate Energy- T . Freidman NY Times Sep-05
• Fusion is seldom mentioned as an important part of the solution except near the end of this century - by then other energy sources will have filled the gap.
• If a second energy crisis appears, we should be ready. Fusion was able to catch the wave with the 1970’s Energy Crisis because“ we” were ready.
How fast could we find out if fusion energy is a possibility?
• Change the goal from DEMO date to a Proof of Fusion date. Did we establish the scientific feasibility of fusion or is it yet to be done??
• What are the two or three key issues that if settled would convince decision makers that fusion energy was credible?
• How fast could these be addressed?
• What could fusion do in a decade?
• Is a totally new paradigm needed?non-government involvementa new community approach
We should know the answer these questions!!!!
The Fusion in a Decade Challenge
• What could be done in the next decade to increase the credibility of fusion?
Make no little plans; they have no magic to stir men's blood and probably themselves will not be realized. D. Burnham, architect
J. Sethian 2003
Some Possibilities
• Operation of Fusion Engineering Device (burning plasma and tests of components for engineering purposes) within a decade
• Advanced FIRE described yesterday is an example
• other tokamak based systems
• ICF already has NIF delivering a burning plasma within 5 years.
ITER and FIRE would provide a strong basis for Adv. DEMO
FIRE ARIES-RSITER
ITER FIRE ARIES-RSFusion Gain 10(H), 5(AT) 10(H), 5(AT) 25 (AT)
Fusion Power (MW) 500 - 350 150 2170
Power Density(MWm-3) 0.6 5.6 6.2
Wall Loading n(MWm-2) 0.6 2 4
Pulse Duration (s) (CR, % equilibrated)
500 - 30002 -10, 86 - >99.9%
20 - 352 - 5, 86 - >99%
20,000,000steady
Mass of Fusion Core (tonnes) 23,000 1,400 13,000
High Power DensityPf/V~ 6 MWm-3
p ~10 atmn ≈ 4 MWm-2
High GainQ ~ 25 - 50
nET ~ 6x1021 m-3skeVP/Pheat = f ≈ 90%
Low rotation
Steady-State~ 90% Bootstrap
ARIES Studies have Defined the Critical Plasma and Technology Issues for Fusion Energy
Plasma ExhaustPheat/Rx ~ 100MW/m
Helium PumpingTritium Retention
Plasma ControlFueling
Current DriveRWM Stabilization
Significant advances are needed in each area. Metrics are needed in each area to measure progress.
Fusion Needs Metrics to Measure Progress
• need to be understandable
• need several metrics for each major issue
• track progress against plan
Some examples -
Fusion Power or Fusion Energy/pulse vs year
Lawson, BE
pressure, (which one ? Plasma , fusion
pulse length s, time constants
Power densities - plasma, wall, blanket, etc
I want you to get on with fusion,
Uncle Sam’s Thoughts on the Fast Track
and make a major step forward within a decade.