Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Portland Community College
Facilities Plan - Phase 1
Monthly Report
January 31, 2017
Portland Community College Monthly Report-02
Facilities Plan – Phase 1 January 31, 2017
1
Summary The sections in this monthly report outline the status for each work group up through the current
month. This addresses the key activities, areas of focus, outstanding questions or information requests,
next steps and schedule progress. A work group summary may be followed directly with a team
consultant report update.
Overall Project Outstanding Items:
1. Team Access to the Google Drives will be critical for distributing project information and for
team communications. This is in progress by PCC and is close to completing.
2. Sample reports were requested by the task force. The planning team is assembling samples from
each consultant for reference and review by PCC.
Contents Space Utilization Work Group ....................................................................................................................... 2
Facilities Condition Work Group ................................................................................................................... 3
Capital Projects Work Group ........................................................................................................................ 5
Safety and Security ....................................................................................................................................... 6
Transportation and Parking Work Group ..................................................................................................... 7
Information Technology Work Group ........................................................................................................... 8
ADA Work Group........................................................................................................................................... 9
Sustainability Work Group .......................................................................................................................... 10
Updated Overall Project Schedule (attached) ............................................................................................ 11
Updated Schedule for site visits (attached) ................................................................................................ 12
Portland Community College Monthly Report-02
Facilities Plan – Phase 1 January 31, 2017
2
Space Utilization Work Group
1.31.17:
Summary of activities: See attached updated summary from Tom Hier of Biddison Hier.
Key Focus for month: See attached summary from Tom Hier of Biddison Hier.
Outstanding Items: See attached summary from Tom Hier of Biddison Hier.
Next Steps: See attached summary from Tom Hier of Biddison Hier.
Schedule: See attached summary from Tom Hier of Biddison Hier.
Chair Members Consultant Team
Kurt Simonds
Dean of Instruction
Cascade Campus
Laura Massey
Tonya Booker
Tricia Brand
Ken Dodge
Karen Sanders
Tatyana Batazhan
Nita Posada (SRG)
Robert Lochner (SRG)
Tom Hier (Biddison Hier)
BIDDISON HIER, LTD. Consultants to Higher Education 1515 Fifteenth Street, NW Ste 613 Washington, DC 20011 202.882.8700 202.726.2251 fax www.biddhier.com
C:\Users\hier\Dropbox (Biddison Hier)\Public\Portland Comm Coll Master Plan\08Project Notes\2017 01 10 Kurt Simonds Memo.docx As of 2 Feb 2017 3:08:13 PM
10 January 2017
Memorandum
To: Kurt Simonds
From: Tom Hier
RE: Follow-Up and Meetings with Deans
As per our conversation before the holiday, we would like to arrange meetings with Deans and Division
Deans, as appropriate, for the next level of review of classroom and course scheduling data that we have
been provided.
To that end, this memo sets out the primary questions we have regarding the data so that individuals at PCC
can review the questions, and the datasets, in preparation for in-person meetings where we can discuss the
data together and, we hope, resolve outstanding questions. The questions and areas of focus are described
below.
Q u e s t i o n s
1 Different Instructional Methods
There are four different instructional methods listed among the courses:
� CLASSROOM (87% of Fall 2015 courses)
� CLWEB (3%)
� TVWEB (0.01% -- 1 entry)
� WEB (10%)
For PCC: Should all of these instructional methods be included in our utilization analyses, or are there any
that should be excluded?
2 Meeting Day Patterns
Most courses have identify some combination of meeting days (e.g., MWF, TR, etc.). However, almost
30% of Fall 2015 courses show “No Phys Meetings” as the Meeting Day Pattern.
2
For PCC: How should courses that have no physical meetings be treated for our analyses – e.g., excluded
from utilization analyses by campus physical location? Excluded or included in other utilization analyses
that might be undertaken?
3 Definitions of “Campus”
As you will recall, our course data includes two different ways in which the course venue is designated, as
follows:
� by “Campus Physical Location of Building”: this is the campus on which the course is actually physically
held.
� by “Campus (or Area) of Record”: we understand this to mean the organizational entity with which the
course is associated, regardless of the physical location where the course is held.
More specifically, regularly-scheduled instructional activities are held at a variety of locations across the
city – some directly at the campuses, some at major centers, and others at satellite locations. Regardless of
physical location, all courses are also generally associated with one of the following campuses or areas
(called “Campus (or Area) of Record” for simplicity):
� Cascade
� Rock Creek
� Sylvania
� Southeast
� Workforce & Community Education
� Educational Services.
A chart in the 29 November presentation, reproduced below as Chart 1, shows the relationship between
Campus Physical Locations where courses are held and the Campus or Area of Record.
Chart 1. Crosswalk between Campus Physical Locations and Campus of Record
3
For PCC: To proceed with utilization analyses, we have the following questions:
A. Can we simplify the number of physical locations and determine which – if any – to exclude from
analyses?
In the chart above, there are 25 distinct categories of physical location, some with very few courses
identified. The table below offers an initial attempt at collapsing these 25 categories into 14 categories.
Detailed lists of courses included in each category are provided in an attached Excel spreadsheet. (Each
aggregated physical location is a separate tab in the Excel file.)
Please review the aggregation proposed in Chart 2 below and confirm or suggest updates, as required.
Further, it seems obvious that the first 11 major categories would be included in analyses. There is a
question about how to handle categories 12 (Distance Learning), 13 (Off-Campus) and 14 (Null or Other –
TBD). Please review courses in the Excel spreadsheet associated with these categories and advise as to
how they should be treated for space utilization analyses.
Chart 2. Physical Locations
Physical Locations
Physical Location Aggregated Physical Location
1 Cascade Cascade
Cascade (off campus)
2 Rock Creek Rock Creek
Rock Creek (off campus)
3 Southeast Southeast
Southeast (off campus)
4 Sylvania Sylvania
Sylvania (Distance Learning)
Sylvania (off campus)
5 CLIMB Climb Center
6 Downtown Center Downtown Center
7 Hillboro Center Hillsboro Center
8 Metro Center Metro Center (Portland Metropolitian Workforce Training Center)
9 Newberg Center Newberg Center
10 Swan Island Trades Center Swan Island Trades Center
11 Willow Creek Willow Creek Center
12 Distance Learning Distance Learning (Community Education)
Distance Learning (for Newberg Center)
Distance Learning (PCC District)
13 Off-Campus Off Campus
Off Campus (PCC District Wide)
14 Null or Other -- TBD Columbia Center
Null - location to be determined
Open Campus (PCC District Wide)
TBD
4
B. Beyond analyzing utilization by physical location, what other types of analyses would be helpful,
especially with respect to analyses by Campus (or Area) of Record?
Beyond analyzing space utilization by physical location, are there analyses that should be done by Campus
or Area of Record? For example, there are a substantial number of courses associated with the Workforce
and Community Education area, which are spread among various campuses and centers (e.g., CLIMB,
Southeast, Sylvania, Willow Creek). Please consider what types of analyses might be desirable and
informative, and advise how to proceed.
N e x t S t e p s The approach we have discussed for resolving the questions outlined here is as follows:
1 Individual data reviews by various deans.
You have suggested that various deans who are familiar with course offerings at the campuses and centers
should review the data in advance of meeting with us, so that they have an opportunity to contemplate the
questions posed in this memo (and to pull in others, as necessary, who may also be knowledgeable about
scheduling).
The attached Excel file lists all courses, broken out by the aggregated physical locations shown in Chart 2.
Please distribute course data for each aggregate location to the appropriate dean(s).
2 Schedule in-person meetings with relevant deans.
Once the deans have had a chance to consider and review the data, then we would like to schedule
individual meetings with each of them (or their representatives) to review the data. If possible, we would
like to arrange these meetings for the last week of January or the first week of February.
In the meantime, if you or others have any questions or need further explanation of anything in this memo,
please do not hesitate to get in touch with me. I can be reached via email at [email protected], or via
telephone at (202) 882-8700.
Thank you.
Attachment
Excel file include course lists by aggregated physical campus location
Cc: Rebecca Ocken
Bryan Higgins, SRG Partnership
Nita Posada, SRG Partnership
Portland Community College Monthly Report-02
Facilities Plan – Phase 1 January 31, 2017
3
Facilities Condition Assessment Work Group
1.31.17:
Summary of activities: The Facilities Work Group has met every 2 weeks since 10/31/16.
Key Focus for month: PAE and SRG have started their site visits with SE campus. Other consultants to
follow include; Catena, WH Pacific, 2.ink
Outstanding Items: As Consultants start their site visits other documentation could be needed. Since
that is just starting and some have just completed their first reviews this is under development.
Site Visits:
1. PCC has provided key cards (1/31/17) for consultants that need to access to buildings during site
visits.
2. Typically, each campus will kick off the site visits with a coordination meeting with that
campuses facilities group to review questions from the consultant team. This took place for SE
campus on 1/23/17 with SRG and PAE. A kick off meeting is scheduled for the Rockcreek campus
on 2/6/17 for PAE, Catena and SRG.
3. The task force identified contractor parking is available at Rockcreek campus near the
construction trailer that can be used for consultants doing site visits. Contractor parking is also
available at the Sylvania campus near the play fields for the same use. Parking passes may be
available for consultant use for the SE and Cascade campus.
SRG:
SRG has just completed (2/1/17) site tours of the SE Campus reviewing each room in each building on
campus. The next monthly report will include information on findings for that review.
PAE:
PAE has completed review of the SE campus and are developing results from that visit. Attached is a
report from PAE updating on this month’s activities and an example of an information logging matrix
developed by PAE to record items noted in during their site tours.
Catena (structural):
Catena structural engineers will be starting their review next week at the SE campus. Their review will
not include buildings already reviewed in previous seismic reports. This includes a 2012 kpff report for
Sylvania campus that reviewed 7 buildings and a catena report for Rockcreek issued in 2012 that
Chair Members Consultant Team
Tony Ichsan
Director
Facilities Support Services
John MacLean
Joe Gamble
Donna Bezio
Mark Erickson
Zahava Jones
Heidi VanBrocklin
Gary Danielson (SRG)
Bryan Higgins (SRG)
Jason Karam (SRG)
Nedzib Biberic (PAE)
Jared Lewis (Catena)
Tom Jaleski (Code Unlimited)
Brady Berry (WH Pacific)
Alex Simpson (WH Pacific)
Melinda Graham (2.ink)
Portland Community College Monthly Report-02
Facilities Plan – Phase 1 January 31, 2017
4
reviewed 2 buildings. Catena will review the balance of buildings in the PCC system and fold in the
existing information for a more compressive document.
Code Unlimited:
Code Unlimited Provide a list of applicable codes for accessibility for each of the buildings. Review
drawings of all the buildings in the inventory for accessibility compliance issues. Working with the ADA
group they have developed a list of buildings for their site visits.
2.ink:
Will be conducting meetings with the Staff and Student Leadership groups that would entail an initial
15-20 minute introduction to the type of information we are interested in discussing, a leave-behind
questionnaire for students/staff to then consider and then a follow-up discussion. There would be a
separate meeting per campus.
Will be meeting with Maintenance staff as related to each Campus and Center. A maintenance
questionnaire would be distributed ahead of these meetings and each meeting would discuss the
feedback from that and any other relevant information regarding maintenance.
Next Steps:
SRG will continue to coordinate consultant team site visits for each campus.
Schedule: The attached overall project schedule shows site visits occurring in the months of January,
February and March. Each team is currently in the process of visiting sites and scheduling upcoming site
visits.
Progress Report
pae-engineers.com | 1
DATE: February 2, 2017 PROJECT: PCC Campus-wide Master Plan PROJECT NO.: 16-1448 TO: Bryan Higgins FROM: Nedzib Biberic SUBJECT: January Progress Report - PAE
DISTRIBUTION: File
On January 16th the PAE team kicked off the Southeast campus site assessments with a meeting with PCC
facilities team and SRG. General campus rules were covered along with questions the PAE team had for
facilities. At the end of the meeting, the whole team conducted a site walk with facilities, who pointed out
current problem areas and equipment.
The mechanical team finished the site assessments on the Library, Commons, and Mt. Scott buildings. 50%
complete with the assessment on the Annex building. 95% complete with the assessment on Mt Tabor. Anticipate being completed with the site assessments by middle of next week. The plumbing tem has completed all site visits for the Southeast campus. Currently working on compiling of notes and images for assessment report. The electrical team has completed approximately 60% of the site assessments, with an additional visit for
testing of the normal and egress lightings scheduled for 2/12, as it requires testing to be completed during night time. The Rock Creek kickoff meeting has been scheduled with PCC and SRG for 2/6. Initial questions have been
forwarded to PCC and the team is currently compiling initial data for site visits.
[DISCIPLINE]CREATED DATE: 5 5 4 4 3 3 1
Finding
No.
Equipment
Tag/ID1
Location
Floor/Area System Description
Year of
Install
Area
Served2
Code
Deficiencies3
System Deficiency
Action that Mitigates
Deficiency Photo Cod
e V
iola
tion
Lif
e S
afe
ty
Cap
acit
y
Eq
uip
men
t
Con
dit
ion
Eq
uip
men
t
Lif
e
Exp
ecta
ncy
5
Main
ten
an
ce
En
erg
y
Eff
icie
ncy
Weig
hte
d
Tota
l
Su
gg
este
d
Prio
rit
y f
or
Mit
igati
on
Esti
mate
d
RO
M4
**Internal Notes**
M100 AHU-X
Roof, mechanical
room, etc
Central Equipment (AHU, DOAS,
etc)
Elec Data:
Airflow:
Cooling Capacity:
Heating Capacity:
Humidifier:
Control type:
CHWS/R Temp:
HWS/R Temp:
# of SA Fans:
SA Fan HP/each:
# of RA Fans:
RA Fan HP/each:
Pre/Final Filter Rating:
VFD:
Fuel Type:
Based on as
built schedule
L1
classrooms
Unit access:
Coil condition:
CHW/HW valve access:
UV lights:
Water carryover from coil:
Drain pan (corrosion, growth, etc):
Standing Water:
Filters present:
Filter condition (bypass?):
Pressure gauges:
Temperature gauges:
Fans operating:
Fans in balance:
Belt guard:
Access doors sealed:
Visible corrosion:
Duct connections:
Piping connections:
Dampers open when operating: 5 3 4 4 4 2 5 95 H
M200 FCU-X
Decentralized Equipment (FCU,
Split system, VRF)
Elec Data:
Indoor unit type:
Airflow:
Cooling Capacity:
Heating Capacity:
Control type:
CHWS/R Temp:
HWS/R Temp:
SA HP:
Filter:
FCU access:
Branch selector box access:
Outdoor unit access:
Outdoor unit airflow obstructions:
Control box elec clearance (30"):
Piping insulation:
Drain pan (corrosion, growth, etc):
Secondary drain pan (piped to visible location):
Filters present:
Filter condition (bypass?):
Fans operating:
Fans in balance:
Visible corrosion:
Duct connections:
Piping connections:
Unit vibration isolation: 0 3 5 4 4 5 5 83 M
M102 B-X
Boilers
Type:
Capacity:
Vent type:
Adequate access:
Flue condition:
Flue distance from OSA intake:
Combustion air:
Emergency stop: 0 L
M103 CH-X
Chillers
Elec Data:
Type:
Capacity:
Refrigerant:
CHW Flow:
CHWS/R temp:
CW Flow:
CWS/R temp:
Evap PD:
Cond PD:
# of compressors:
Vibration isolation:
Tube pull access:
Marine water box:
0 L
M104 CT-X
Cooling Towers
Elec Data:
Capacity:
Sump condition:
Excessive mist:
Distance from OSA intakes:
Blowdown/bleed:
0 L
M105 P-X
Pumps
Elec Data:
Type:
Flow:
Head:
HP:
VFD:
Adequate access:
Piping connections:
Vibration isolation:
Suction diffuser or strainer:
Pressure gauges: 0 L
M106 N/A
Generators (HVAC scope)
Heat rejection (unit mounted or
remote):
Fan assisted:
Acoustic treatment:
Muffler type:
Duct silencers:
Acoustic louvers:
Engine exhaust discharge location:
Insulation on engine exhaust:
OSA intake location:
Heat rejection location: 0 L
M107 EF-X
General Supply/Exhaust Fans
Elec Data:
Type:
Airflow:
TSP:
HP:
Belt or Direct:
VFD:
Gravity or motorized damper:
Distance to OSA intakes:
Birdscreen:
0 L
M108 EF-X
Lab Exhaust Fans
Elec Data:
Type:
Airflow:
TSP:
HP:
Belt or Direct:
VFD:
Redundancy:
Gravity or motorized damper:
Distance to OSA intakes:
Birdscreen:
Discharge nozzle height:
0 L
M109 EF-X
Kitchen Exhaust Fans
Elec Data:
Type:
Airflow:
TSP:
HP:
Belt or Direct:
VFD:
Drain type (piped or trap):
Distance to OSA intakes:
Duct connection to fan:
Vented curb/shaft:
UL 762 compliant: 0 L
M110 TU-X
Terminal Units (20%)
Elec Data:
Max airflow:
Min airflow:
Reheat coil type:
HWS/R temps:
Elec coil control type:
Sound attenuator:
Duct length at inlet (TU size):
Excessive inlet size duct (>3 duct diameters):
Distance to first branch duct:
HWS/R valves accessible:
Control box elec clearance (30"):
0 L
M111
Distribution Ductwork (20%)
Diffusers/grilles
FD/SD/FSD's open:
Flex duct on SA runouts:
Access doors closed:
Unintentional openings (uncapped ducts, etc):
Continuous insulation:
Audible leaks:
High PD fittings:
Diffusers/grilles clean:
Short circuiting: 0 L
M112 Grease Exhaust Ducts
Fire wrap:
Access doors:
Proper slope:
Cleanouts at elbows:
Material (SS vs galvanized):
0 L
M113 Distribution Piping (20%)
Isolation/shut off valves open:
Pipe shields at hangers:
Continuous insulation:
Visible leaks:
Expansion compensation: 0 LM114 5 3 5 4 1 1 2 84 M
Notes:
1. Equipment tags are aligned with labels in the field and/or BAS where possible. Most central equipment is consistently tagged. Most distributed equipment was not tagged in the field and has been assigned a tag based on AHU assignment and space served.
2. Service areas determined by as-built drawings and discussions with facilities staff where possible.
3. Deficiencies are based on current codes and do not necessarily reflect a deficiency at the time of construction.
4. ROM cost includes estimates for first cost of the equipment, demolition, controls and power, installation cost incured by mechanical contractor, soft cost, and contingency. Excludes cost due to infections controls, fire watch, permitting, and premium cost due to overtime or after hours work.
5. Life expectancies based on 2015 ASHRAE Applications Chapter 37 and the associated online database.
Facility Infrastructure Condition Assesment
Deficiency
Priority Multiplier (1 = low, 5 = high)
Category Score
Code Violation Priority Weight
Priority Score (1-5; 5 being high priority) 5 100%
0
5
Priority Score (1-5; 5 being high priority) 5 100%
1
2
3
4
5
Priority Score (1-5; 5 being high priority) 4 80%
1
3
5
Priority Score (1-5; 5 being high priority) 4 80%
1
2
3
4
5
Priority Score (1-5; 5 being high priority) 3 60%
1
2
3
4
5
Priority Score (1-5; 5 being high priority) 3 60%
2
3
4
5
Priority Score (1-5; 5 being high priority) 1 20%
1
2
3
4
5
Priority Level Max Poss Points 125 Low Limit High Limit
H 75% 100% 94 125
M 40% 74% 50 93
L 0% 39% 0 49
High
Medium
Low
Equipment Life Expectancy5
Maintenance
Complex Maintenance (Chillers, Boilers, AHUs)- Accessible
New
10+ Years Remaining
5-10 Years Remaining
0-5 Years Remaining
Past Typical Service Life
Complex Maintenance (Chillers, Boilers, AHUs)- Not Accessible
Energy Efficiency
Capacity
Life Safety
Equipment Condition
Serves Non-Critical Areas - Minor/Easily Correctible
Serves Non-Critical Areas - Major, or Serves Critical Areas and No Issues
Serves Critical Areas - Minor/Easily Correctible
Serves Critical Areas - Moderate
Serves Critical Areas - Major
Poor
Very Poor
Simple Maintenance - Accessible
Simple Maintenance - Not Accessible
Meets Current Code
Code Deficiencies
Excellent
Good
Fair
Extra Capacity Available
Meets Capacity
Does Not Meet Capacity
Level Percentage Range
Exceeds Current Code or N/A
Meets Current Code
Prior Code - Good
Prior Code - Fair
Prior Code - Poor
Portland Community College Monthly Report-02
Facilities Plan – Phase 1 January 31, 2017
5
Capital Projects Work Group
12.23.16:
Summary of activities: The SRG Planning Team has received pricing for the Tier I and select Tier II bond
projects from RLB and have distributed, projects include:
Tier I
01 Health Professions / IPT Building – Combined with 04 IT Location
02 Metro Center
03 OMIC Columbia County Center – Awaiting on PCC to provide original estimate, this will be a
verification from an existing report. We will send as soon as we receive from PCC sometime next week.
04 IT Location – Combined with 01 Health Professions / IPT Building
05 Cascade Public Safety Building
06 Sylvania Site Improvements
07 Student Housing Feasibility Study – Removed from scope
08 Rock Creek Events Center Parking Lot- Verification from existing estimate
09 Sylvania Health Technologies Building – This was previously a verification item, the scope has been
slightly modified since previous estimate was completed
Tier II
01 Sylvania Makerspace – Removed from Scope
02 Rock Creek CTE Building
03 Rock Creek Makerspace – Removed from scope
04 Hillsboro Center
05 Downtown Center
Key Focus for month: A summary of this pricing and capital projects status was presented at the board
meeting on 1/19/17, attached is the presentation from that meeting that includes a summary of all
capital bond projects and budgets.
Outstanding Items: NA
Next Steps: The board is reviewing.
Schedule: The attached overall project schedule shows the capital projects process, the work group is on
track with the schedule.
Chair Members Consultant Team
Linda Degman
Director
Bond Program
Zahava Jones
Debra Jarcho
Rebecca Ocken
Gary Sutton
Tony Ichsan
Nita Posada (SRG)
Jason Karam (SRG)
Susan Gust (SRG)
Portland Community College Monthly Report-02
Facilities Plan – Phase 1 January 31, 2017
6
Safety and Security Work Group
12.23.16:
Summary of activities: January 31,2017
Below is a summary from Layne Consultants on their site visit the week of January
Southeast Campus
Reviewed security subsystems:
• Video Surveillance and Recording (2 systems)
o Milestone IP video platform
o Legacy analog Integral Technologies DVR system
• Access Control System
• Intrusion Detection System
• Mass Notification System
• Incident Reporting System
• Public Safety Office Command/Control
Cascade Campus
Reviewed security subsystems:
• Video Surveillance and Recording (2 systems)
o Milestone IP video platform
o Legacy analog Dedicated Micros DVR system
• Access Control System
• Intrusion Detection System
• Mass Notification System
• Public Safety Office Command/Control
• CommScope/Andrews RF Enhancer-Distributed Antenna System (DAS) Garage
Sylvania Campus
Reviewed security subsystems:
• Security Command Center Operations
• Telex Vega Computer Aided Dispatch (CAD)
o C-soft DPS software (IP Dispatch)
o 800 MhZ Radios
• Video Surveillance and Recording
• Access Control System
Chair Members Consultant Team
Derrick Foxworth
Director
Public Safety
Debra Jarcho
Alan Bral
Mike Sturgill
Kevin Crowley
Tony Ichsan
Neal Naigus
Ryan Aiello
Gary Danielson (SRG)
Bryan Higgins (SRG)
Rob Layne (Layne)
Mark Peterson (Layne)
Portland Community College Monthly Report-02
Facilities Plan – Phase 1 January 31, 2017
7
• Intrusion Detection System
• Mass Notification System
January 19, 2017
Sylvania Campus
Public Safety operations interviews conducted with:
Sgt Alan Bral – Video Systems
Officer Danielle Parker – Access Control
Derrick Foxworth, Public Safety Director
January 20, 2017
SRG Partnership
Update to SRG project management
Overview
1. The electronic security systems are not consistently deployed across all PCC campuses.
2. Legacy analog video systems remain in place. Some of which are not available from security
control.
3. Currently, the Mass Notification System initiates canned messages from Sylvania. Cannot send
customized messages from another campus.
4. The Mass Notification System is being upgraded However the status/schedule of the upgrade,
and the specific functionality of the upgrade are not known.
5. PCC Public Safety staff lacks formal training on electronic security subsystems.
6. PCC Public Safety lacks documented policies and procedures for the configuration,
administration, and operation of electronic security subsystems. How systems are being used is
critical to establishing a technology roadmap as part of the Facilities Report.
7. PCC Public Safety has implemented electronic security subsystems without the benefit of a
documented strategy or plan; including staffing for configuration, administration, and operation
of systems.
8. M Sturgill to provide Layne with copies of previous RFPs for security systems for review.
Key Focus for month:
1. Layne will develop a strawman of facilities report
2. Inventory systems and version levels at each site
3. Develop a technology roadmap matrix to provide consistent deployment across PCC.
Outstanding Items: NA
Next Steps:
1. Review schedule for next site visit.
Schedule: The attached overall project schedule shows site visits occurring in the months of January,
February and March. Layne has already conducted one site visit, they are evaluating the information
gathered and will develop a schedule for the next site visit.
Portland Community College Monthly Report-02
Facilities Plan – Phase 1 January 31, 2017
8
Transportation and Parking Work Group
12.23.16:
Summary of activities: The Transportation and Parking Work Group has met every 2 weeks since
10/31/16.
Key Focus for month: The team is working on documentation of existing conditions, strategies and
solutions. A document outline has been submitted for review by the workgroup.
Outstanding Items: NA
Next Steps: The next work group meeting is scheduled for 2/28 and a work group chair meeting is
scheduled for 2/15.
Schedule: The attached overall project schedule shows site visits occurring in the months of January,
February and March. Each team is currently in the process of visiting sites and scheduling upcoming site
visits.
Chair Members Consultant Team
Kathleen McMullen
Manager
Transportation and Parking
Karissa Nickerson
Wendy Palmer
Jennifer deLaix
Mark Gorman
Michael Kuehn
Narce Rodriguez
Dean Halley
Bryan Higgins (SRG)
Gary Danielson (SRG)
Todd Mobley (Lancaster)
Miranda Wells (Lancaster)
Phil Worth (Kittelson)
Portland Community College Monthly Report-02
Facilities Plan – Phase 1 January 31, 2017
9
Information Technology Work Group
12.23.16:
Summary of activities: Vantage Consultants has made some final revisions to their proposal including
information regarding the number rooms to be evaluated for AV.
Key Focus for month: Once Vantage has access to the existing information from Google Drive they can
start to review and provide comments on other outstanding information needed for review.
Outstanding Items:
Vantage: At least 2-3 weeks prior to the initial site visit vantage will need the following information:
1. IT specific info which was being provided by the stakeholders on the Google Drive
2. The rest of the items requested in our proposal’s Methodology section
Next Steps: Vantage has scheduled their first site visit for 2/21 and is in the process of developing an
agenda for that visit. They will send that draft agenda out for review next week.
Schedule: The attached overall project schedule shows site visits occurring in the months of January,
February and March. Each team is currently in the process of visiting sites and scheduling upcoming site
visits.
Chair Members Consultant Team
Michael Northover,
Chief Information Officer
Information Technology
Val Moreno
Debra Jarcho
James Reece
Ed Hawkins
Payam Damghani
Andy Freed
Kevin Edwards
Charmagne Ehrenhaus
Hank Schottland
Bryan Higgins (SRG)
Bjorn Clouten (SRG)
Richard Bussell (Vantage)
Ken Godachy (Vantage)
Jon Young (Vantage)
Portland Community College Monthly Report-02
Facilities Plan – Phase 1 January 31, 2017
10
ADA Work Group
12.23.16:
Summary of activities:
After meetings on 1/10/17 it was agreed that summary of the ADA scope is the following:
Transportation (Lancaster and Kittelson Engineering): Review existing reports and confirm existing ADA
parking and required ADA parking and locations at all campuses and centers.
Site (SRG & WH Pacific Engineering): Provide an ADA assessment of the existing path of travel from ADA
parking and transit stops to the main entry at each building at all campuses and centers.
Building (SRG & Code Unlimited): Provide a list of applicable codes for accessibility for each of the
buildings. Review drawings of all of the buildings in the inventory for accessibility compliance issues.
Code Unlimited has developed with PCC and SRG a list of buildings they will focus on in their site visit
review. SRG will be reviewing all buildings in the PCC system.
Key Focus for month: All Consultants are currently reviewing the existing materials sent that consists of
existing plans and specifications. All consultants are also in the process of scheduling site visits.
Outstanding Items: All Consultants are currently reviewing the existing materials sent that consists of
existing plans and specifications. After review we will develop a list of outstanding items.
Next Steps: SRG and consultant team will schedule site visits.
Schedule: The attached overall project schedule shows site visits occurring in the months of January,
February and March. Each team is currently in the process of visiting sites and scheduling upcoming site
visits. The next work group meeting is scheduled for 2/21/17.
Chair Members Consultant Team
Alex Baldino (New Chair)
Jennifer Gossett (Previous Chair)
Accessibility Specialist
Disability Services
Wendy Palmer
Donna Bezio
Jody Giffen
Maria Mendez
Kathy McMullen
Jason Karam (SRG)
Gary Danielson (SRG)
Brady Berry (WH Pacific)
Alex Simpson (WH Pacific)
Joshua Klyber (Code Unlimited)
Portland Community College Monthly Report-02
Facilities Plan – Phase 1 January 31, 2017
11
Sustainability Work Group
12.23.16:
Summary of activities: The sustainability Work Group has met several times now and have developed a
scope of work vision as follows:
Version 3. We will develop a Sustainability Plan to include an assessment evaluating current college
systems and guidelines for college practices emphasizing sustainability in seven key areas:
● Energy & Emissions
● College Operations
● Construction & Renovation
● Grounds & Natural Systems
● Health & Well-being
● Education & Culture
● Resiliency (this item has been put on hold for now)
Key Focus for month:
Outstanding Items:
Next Steps: Next meeting is scheduled for 2/8.
Schedule: The attached overall project schedule shows site visits occurring in the months of January,
February and March.
Chair Members Consultant Team
Briar Schoon
Manager
Sustainability
Laura Ward
Julie Mast
Alyson Lighthart
Elaine Cole
Jack Lussier
Lisa Peterson (SRG)
Bryan Higgins (SRG)
PORTLAND COMMUNITY COLLEGE MASTER PLAN | SRG PARTNERSHIP
2016 2017
SEP OCT NOV DEC JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV DEC
PORTLAND COMMUNITY COLLEGE MASTER PLAN
PROJECT SCHEDULE � ��/��/��
B. WORK GROUPS
FACILITIES CONDITION ASSESSMENT
ARCHITECTURAL �SRG�
MEP �PAE�
STRUCTURE (Catena)
INFRASTRUCTURE (CIVIL-WH Pacifi c)
SITE (LANDSCAPE-2.ink)
TRAFFIC/TRANS (Lancaster/Ki! elson)
IT (Vantage)
SPACE UTILIZATION (Biddison Hier)
SUSTAINABILITY
ADA
SAFETY & SECURITY
A. CAPITAL BOND PROJECTS
TIER I
01-HEALTH PROFESSIONS (CLIMB)
02-METRO CENTER
03-COLUMBIA COUNTY (OMIC)
04-IT DEPARTMENT LOCATION
05-PUBLIC SAFETY BLDG (CASCADE)
06-SITE WORK (SYLVANIA)
07-STUDENT HOUSING STUDY
08-SITE WORK (ROCK CREEK)
09-HT BUILDING SYLVANIA
10-SCHEDULED MAINTENANCE
11-IT
12-SAFETY & SECURITY
MEETINGS
TASK FORCE (WEEKLY)
STEERING COMMITTEE (MONTHLY)
WORK GROUPS (WEEKLY)
PCC BOARD (MONTHLY)
COST ESTIMATES
BO
ND
RE
SO
LUT
ION
: "
/#/$
%
DR
AF
T R
EP
OR
T
BO
AR
D M
TG
: P
RIC
ING
RE
VIE
W:
$/$
%/$
%
INVESTIGATION SITE VISITS ASSESSMENT REFINEMENT
BO
ND
VO
TE
PROGRAM DESIGN PCC REVIEW
PCC PROVIDED INFORMATION
PCC PROVIDED INFORMATION
PCC PROVIDED INFORMATION
PCC PROVIDED INFORMATION
BO
ND
SU
BM
ISS
ION
BO
AR
D M
TG
: R
ES
OLU
TIO
N R
EV
IEW
: "
/$%
/$%
ESTIMATE' # WEEKS
DR
AF
T F
INA
L R
EP
OR
T
FIN
AL
RE
PO
RT
REVIEW REVIEW
DR
AF
T M
AT
ER
IAL
DU
E *
/$/$
%
DR
AF
T M
AT
ER
IAL
DU
E +
/$,
/$%
DR
AF
T M
AT
ER
IAL
DU
E $
"/$
/$%
C. MASTER PLANNING
e.priori® BRAINSTORM
CRITERIAAFFIRM
CRITERIAGOAL
SETTING
UPDATED !�."�.�#
FORMAL PROJECT KICK OFF $-/#$
EVALUATION REVIEW REVIEW
PLANNING PLANNINGPLANNING RECOMMENDATIONS