Pope Francis Village - In-City Relocation

Embed Size (px)

DESCRIPTION

The integrated people-driven model community in Post Yolanda

Citation preview

  • POPE FRANCIS VILLAGE

    IntroductionPope Francis Village The implementation of an In-City

    relocation for 550 typhoon-affected

    families of Super Typhoon- Yolanda and

    the restoration of sources of income

    and regained self-sufficiency of the

    project beneficiaries

    September to October 2015

    With the continued campaign to empower the project beneficiaries with skills and knowledge onall aspects of the project, FRANCESCO closed the contracts with TESDA and DepEd to start thefirst step to the construction process. The Pope Francis Building, a two-storey six classroombuilding, will be built in Scandinavian Elementary School in Brgy 100, Diit, Tacloban City. TESDAtraining already commenced with a total of 125 trainees from the Pope Francis Villagebeneficiaries.

    Preparations for the upcoming construction process such as procurement of materials, obtainingof necessary permits, detailed planning and engineering works, coordination with DepEdtechnical staff and school officials, soil testing, and any other pre-construction groundworks aremeticulously undertaken by the project team to finally put up the Pope Francis Building.

    .

  • 550 displaced and affected households have access to safe, permanent and sustainable housing with resiliency features and complete with toilets, water pipes and electrical lines, better equipped to face natural disasters

    Objective 1

    Plan preparation is ongoing and is at 46.84%Contract for the Structural engineer to conductthe structural analysis of the school bldg.signed; 25 days duration;

    From 24% , Drawing plans for Temporaryfacilities is at 42%

    Chapel and Commercial bldg. designpresentation by Archt Albert to Fr. Leo, FrAlcris and to the community last 02, 03October, completed respectively;

    Multi-purpose Planning and design is at100%.

    Structural design for contract signing- 21 Oct2015; 20 working days duration;

  • .Site Development Works DPWH and AFPObjective 1

    Reproduction of Engineering drawingswas completed as of 16 Oct;

    DPWH Regional Office submitted thestandardized engineering drawings,program of works, and endorsementletter to the DPWH central office on19 October;

    Ongoing discussion with the AFP:program of works, PERT-CPM,road profiles and site dev plansubmitted as of 19 Oct

    ECC on process c/o Engr. Cabidog;(max 2 weeks)

  • ROW HOUSES

    CONTRACT WITH PROFESSIONAL ELECTRICAL ENGINEER TO BE SIGNED OCT. 22, 2015

    CONTRACT WITH MASTER PLUMBER TO BE SIGNED OCT. 22, 2015

    ELECTRICAL PLANS AND SANITARY/PLUMBING PLANS WILL PROCEED AFTER SIGNING OF CONTRACTS

    ARCHITECTURAL PLANS COMPLETE

    STRUCTURAL PLAN WILL BE DONE BY A SERVICE PROVIDER, QUOTATIONS TO STRUCTURAL/CIVIL ENGINEER ARE ALREADY OUT, WAITING FOR THE RESPONSE

    Objective 1

  • MULTI-PURPOSE BUILDING AND WAREHOUSE

    CONTRACT WITH STRUCTURAL ENGINEER TO BE SIGNED OCT. 22, 2015

    STRUCTURAL PLAN AND DETAILS WITH PROCEED UPON SIGNING OF CONTRACT

    Objective 1

  • WORKSHOP AREA

    Floor Area 250 sq.m.Estimated Cost : Php 1.25M to 2.00M

    Objective 1

  • DOLEDepartment of Labor and Employment

    - Safety & Health Program completed and

    approved

    - Certificate of Registration issued by DOLE

    - FRANCESO safety & health committee will

    conduct orientation prior to construction

    - Accident insurance for workers were

    secured valid until 15 October 2016

    FRANCESCO will provide first-aid kit and health care medicines and facilities for workers in

    the site in accordance with the requirements of Rule 1960 of the OSHS. Adequate medical

    supplies and facilities based on the total number of workers in the site will also be provided.

    Objective 1

  • .

    Coordination meeting with DepEd andschool officials on the construction ofSchool Buildings

    MOA signed on 29 Septemberbetween DepEd and FRANCESCO

    Building permit on process by DepEd

    Soil boring completed; lab test isongoing for the result; expected resultnot later than 25 Oct 2015;

    Structural analysis is ongoing;

    DepEdDepartment of Education

    Objective 1

  • Restored sources of income and regained self-sufficiency by providing livelihood recovery program and empowering the community to manage their own livelihood and enterprises, or gainfully employed in one of the enterprises developed under the program.

    TESDA Training Savings Forum Demo Farms Bagsakan

    Centers Cash-for-Work

    Objective 2

  • TESDA TrainingObjective 2

    MOA signed between TESDA andFRANCESCO last 29 September 2015;

    Training was conducted by STEFTI whichcommenced last 06 October 2015;

    TESDA budgeted a total of Php 850,000.00for the first batch of training in STEFTI;

    With the continuing discussion regardingthe possibility of the second batch ofbasic skills training, TESDA affirmedthat this may pursue provided thatFRANCESCO will be able to produce therequired number of participants and theirqualifications. This will include SMAW,Carpentry and Masonry.

  • Objective 2 Demo Farm

    There are 5 farms identifiedthat serve as a demo farm for theproject beneficiaries namely:

    1. Diit farm,2. Yaokasin,3. Cordero farm,4. Mahusay farm and5. Pretencio farm lot;

    UPA lead project funded by Christian Aid

  • Savings ForumObjective 2

    On October 9, 2015, a savingsforum was conducted attended by 500members of the community (both fromproject beneficiaries and communitymembers). The negotiation is that thesocial team will invest an amount equal tothe investment of the community member.

    The savings forum wants toelevate the savings of the community intosocial enterprise where they will be taughton how to use and increase their moneysaved for a period of 6-8 months.

    UPA lead project funded by Christian Aid

  • Objective 2

    Clearing /demarcation works

    DSWD sponsored a cash-for-work program

    that will include 600 participants from

    community; 182 pax were assigned to work

    at the Pope Francis Village; The program

    will last for 15 days.

    On the site, the markings are already

    identified, so it will not hinder the project

    beneficiaries from utilizing the area for

    natural farming.

    Cash-For-Work

  • Objective 2 Bagsakan Center

    The Bayanihan Food Garden was successfully conducted with the objective to incorporate sustainability from the community.

    Two (2) bagsakan centers were organized. The concept of bagsakan centers is to gather all the harvested products of the community from natural farming which in turn will be bought in lump sum by assigned individuals.

    UPA lead project funded by Christian Aid

  • Develop DRR measures to mitigate the effects of disasters

    Refresher course on BDRRMC structure and functions was conducted last 19 Sept 2015 by the Social Team

    Meeting with OCD upcoming meeting/workshop on revisiting the DRRM program of Tacloban;

    Schedule to be confirmed;

    Objective 3

  • Organize a strong community with a Community Council and empower them in the areas of estate management, local governance, networking, and advocacy for basic social services such as health and education and conflict resolution.

    Procurement Committee is functional

    Purchase team

    Finance team

    Construction team

    Supply team

    Under the Social Team, the following were also established

    Livelihood committee

    Savings committee

    Education committee

    (30 pax)Core leaders as decision policy making body

    First Aiders Committee was mobilized and is functionalFour (4) members from the community who completed andgraduated from the Community First-Aid training and Basic LifeSupport conducted by the Philippine Red Cross are actively on-duty regularly under the guidance of the Project Nurse. Theyare monitoring the health and welfare of the community whoare working under the Cash-for Work Program at Diit.

    Objective 4

  • Build a community that is ecologically, economically and socially sustainable. The eco-village will be adapted including the local building materials, recycling, wastewater treatment, use of renewal energy, organic farming and planting of trees.

    On the use of locally available materials, the team coordinated with the Cooperative Development Authority (CDA) and obtained contacts of local cooperatives that can supply the project with raw bamboo for proposed livelihood of project beneficiaries.

    The application of vermi-composting as a practice by the community;

    There is still the continued coordination with Oxfam for the waste water technology.

    As already implemented, the social team has incorporated the use of natural farming as part of the livelihood program.

    Objective 5

  • UPDATES on the Proposed

    ELEMENTARY SCHOOL BUILDING

    CONTRACT WITH THE STRUCTURAL ENGINEER IS ALREADY SIGNED LAST OCT. 19

    SOIL BEARING TEST RESULT WILL BE GIVEN ON THE 25TH OF OCTOBER

    SOIL BEARING TEST RESULT WILL BE USE BY THE STRUCTURAL ENGINEER AS BASIS FOR THE STRUCTURAL ANALYSIS OF THE SCHOOL

    BLDG. PERMIT APPLICATION IS ON PROCESS, BEING DONE BY DEP ED and SCANDINAVIAN SCHOOL FACULTY

    PERIMETER FENCE CONSTRUCTION WILL START 4TH WEEK OCT.

  • School Construction at the Scandinavian Elementary School

    Pre- Construction

    1. Final Site Identified

    2. MOA Signed

    3. Soil Tested

    4. Structural Analysis/Computation

    5. BOQ and complete working drawings

    6. Permits for Construction

    7. Demolition Permit and Actual Demolition

    8. Temporary Structures (Bunk House, Staging Area)

    9. CHB facility established

    10. Identified skilled workers

    11. Safety Program and Constrution Management and

    Monitoring System

    12. Procurement of Materials and PPEs for school

    construction

    13. Accident Insurance for wrokers

    Feb-16 Mar-16 Apr-16 May-16 Jun-16

    ACTIVITY/OUTPUT

    Sep-15 Oct-15 Nov-15 Dec-15 Jan-16

  • Actual Construction

    Earthworks & Site Preps (Ground Breaking & Ceremonial Rites)

    Formworks & Scaffoldings

    Reinforcing Steel works

    Concrete Works

    Masonry & Plastering

    Structural Steel & Roofing works

    Paint works

    Carpentry

    Tile works

    Plumbing

    Electrical

    Flagpole

    Photo, Video, and Narrative Stories

    Feb-16 Mar-16 Apr-16 May-16 Jun-16

    ACTIVITY/OUTPUT

    Sep-15 Oct-15 Nov-15 Dec-15 Jan-16

    School Construction at the Scandinavian Elementary School

  • Post-Construction

    Site Clearing

    Demolition of Temp Structures

    Procurement of Tables and Chairs

    Occupancy Permit(s)

    Turn-Over Ceremony (Preps and Actual Ceremony)

    Feb-16 Mar-16 Apr-16 May-16 Jun-16

    ACTIVITY/OUTPUT

    Sep-15 Oct-15 Nov-15 Dec-15 Jan-16

    School Construction at the Scandinavian Elementary School

  • STANDARD PROFESSIONAL FEES FOR

    ARCHITECTS (RA 9266)

    1st Unit= 10 % of Total Project Cost is MBF (Minimum Basic Fee) =A

    2nd unit to 10 units = A + (60% OF MBF x N)= B

    11 above = B + (30% OF MBF x N) N is No. of Units

    10% of Php 250,000.00= Php 25,000.00 = MBF

    1ST UNIT= Php 25,000.00 (A)

    2nd Unit- 10 Units= Php 25,000.00 + (P15,000.00 x 9 units) = Php

    160,000.00 (B)

    11 units Above = P 160,000.00 + ( P 7,500.00 x 540units)= Php

    4,210,000.00

    TOTAL AMOUNT = Php 4,395,000.00 for 550 Units

  • PROFESSIONAL FEES of ARCHITECTS

    House Designs

    1ST nth UNITS- Php 2,000.00/ unit

    First Tranche - 50% upon submission of the signed documents

    Second Tranche - 50% upon approval of Building Permit

    3 Architects will Sign the 3 Row House Designs compose of 550 units in total

    Design 1& 2 will be composed of 183 units each and Design 3 will be composed of 184 units

    550 units x Php 2,000.00= Php 1,100,000.00 in total

    BREAKDOWN for First tranche upon submission of documents FOR APPROVAL

    Php 366,000.00 : amount will proceed to TAMPEI (can refer to the contract with TAMPEI)

    Php 184,000.00 :amount will proceed to the other Architect (will make a contract with the Architect)

    Php 550,000.00 TOTAL AMOUNT TO BE APPROVED for the FIRST TRANCHE

  • CONCERNS

    Immediate approval of the requirements for the upcoming school construction:

    Warehousing (on-site and at the Pope Francis Village)

    Construction Materials

    Tools Engagement of Professional Services

    General Construction Equipment and tools

    Construction of Bunkhouse at the Pope Francis Village Site (see proposed locations

    Construction of Water Reservoir c/o Christian Aid (see proposed site)

    Second Batch of TESDA Training for 75 participants

    HMO/Medical Insurance of Staff

    List of Beneficiaries to be posted

    Date of Actual House Construction

  • PROPOSED LOCATION OF COMMUNITY FACILITIES

  • ADMIN MATTERS

    TASK TIMELINE STATUS OUTPUT

    BIR Registration

    TIN September 1-4 Done Certificate of Registration - TIN# 474-552-532

    Book of Account September 7-11 Done General Ledger, Journal, Cash Disburstment, Cash/Check already registered in the BIR

    Official Receipt September 11- 30 Done

    Witholding tax for compensation Done Payment made for the month of Sept

    SSS Registration

    SSS Employer's ID September 1-4 Done SSS # 06-1798843-4

    SSS Program September 23-25 Done Operational and monthly reporting

    HDMF Registration

    Payment Aug-Sept 2015 September 10-14 Done

    HDMF Program for Online Submission September 10-14 Done Operational and monthly reportingClearance/Certification from HDMF Cebu September 21-24 Done

    PHILHEALTH Registration

    Payment Aug-Sept 2015 September 1-4 Done PHILHEALTH # 013-000005915PHILHEALTH Program for Online Submission September 14-18 Done Operational and monthly reporting

    Clearance/Certification from Philhealth September 21-25 Done

  • UPCOMING ACTIVITIES

    Upcoming

    activities

    26 October Construction of Site

    Office

    02 November Construction of

    temporary warehouse for the

    school and fence

    03 November - On-site

    training/Construction of School

    04 November Fabrication of Steel

    trusses

    05 -06 November UPA Activity on

    Tide Embankment

    08 November Commemorative

    Celebration

    Securing of permits

    BOQ required for school,

    warehouse and

    Complete list of Bldg Permit

    requirements

    Follow-up bldg permit

    PPEs required

    Implementation of safety

    program

    Required manpower for the

    construction of satellite ofc

  • Thank You!

    POPE FRANCIS VILLAGE