Upload
kristian-fernandez
View
3
Download
2
Embed Size (px)
DESCRIPTION
Plan
Citation preview
CONSTRUCTION ACTIVITY
Project: FABRA RESIDENCE, PONDEROSA LEISURE FARM, SILANG, CAVITE
#OF DAYS Cal Days SCOPE OF WORK RESPONSIBLE DATES
ACTUAL DATES
REMARKS/ISSUES
1.0 14 CD
1 -14th
Preparation of Final Layout to
include Elev. and Perspective Designer 01/24/15 02/07/15
- To have Designer present
revised schemes within this
period for Owners approval.
2.0 7 CD 15-21st For Approval of Final Layout Owner 02/08/15 02/14/15 - To include revisions
3.0 14 CD 22- 35th Preparation of Working Drawings Designer 02/14/15 02/28/15
4.0 7 CD 36-42nd Preparation of Check Print Designer 03/01/15 03/07/15 - In Blue Print Form
5.0 7 CD 43-49th Checking Of Check Print Owner / PM 03/08/15 03/14/15
6.0
6 CD 50-56th
Preparation of Bid Plans
Designer 03/15/15 03/20/15
6 CD 50-56th Issuance of Invitation to Bid to
Contractors Owner/PM 03/15/15 03/20/15
PM to issue Invitation-to-Bid.
E. 1 CD 57nd Pre-bid at Site Architect
PM / Owner 3/21/15 03/21/15
Blue Prints to be distributed at
site.
F. (3CD) (58--60th) Architects Estimate/BOQ Designer 03/22/15 03/24/15
Sealed envelope to be submitted
to Ms. Cynthia F. Fabra. in 3
copies
** To include only material
breakdown. Price/amount not
included.
G. 10 CD 58-67nd Submission of Bids to Owner Bidders 03/22/15 03/31/15
H. 1 CD 68nd Opening of Bids
Start of Tabulation
Owner / PM
04/01/15 04/01/15
- Owner to open Bids/Countersign
I. 5 CD 68-73rd Evaluation / Negotiation PM / AFI 04/02/15 04/06/15
J. 5 CD 74-78th Approval of Budget Owner 04/07/15 04/11/15
K. 5 CD 79-83th NTP / Contract PM 04/12/15 04/16/15
Project: FABRA RESIDENCE, PONDEROSA LEISURE FARM, SILANG, CAVITE
#OF DAYS Cal Days SCOPE OF WORK RESPONSIBLE DATES
ACTUAL DATES
REMARKS/ISSUES
L. 7 CD 84-90rd Mobilization Contractor 04/17/15 04/23/15 -To include application of Permits
M. 180 CD
(240 CD)
270rd
(330th)
Construction Period
Contractor /
PM
04/24/15
(04/24/15)
10/22/15
(12/12/15)
14 CD 2844h
(344th)
Punchlisting/Corrective Works
Turn-over of Project
285 Calendar Days Total Construction Activity
Prepared by : ______________________
tinasantos