CONSTRUCTION ACTIVITY Project: FABRA RESIDENCE, PONDEROSA LEISURE FARM, SILANG, CAVITE #OF DAYS Cal Days SCOPE OF WORK RESPONSIBLE DATES ACTUAL DATES REMARKS/ISSUES 1.0 14 CD 1 -14 th Preparation of Final Layout to include Elev. and Perspective Designer 01/24/15 02/07/15 - To have Designer present revised schemes within this period for Owner’s approval. 2.0 7 CD 15-21 st For Approval of Final Layout Owner 02/08/15 02/14/15 - To include revisions 3.0 14 CD 22- 35 th Preparation of Working Drawings Designer 02/14/15 02/28/15 4.0 7 CD 36-42 nd Preparation of Check Print Designer 03/01/15 03/07/15 - In Blue Print Form 5.0 7 CD 43-49 th Checking Of Check Print Owner / PM 03/08/15 03/14/15 6.0 6 CD 50-56 th Preparation of Bid Plans Designer 03/15/15 03/20/15 6 CD 50-56 th Issuance of Invitation to Bid to Contractors Owner/PM 03/15/15 03/20/15 PM to issue Invitation-to-Bid. E. 1 CD 57 nd Pre-bid at Site Architect PM / Owner 3/21/15 03/21/15 Blue Prints to be distributed at site. F. (3CD) (58 -- 60 th) Architect’s Estimate/BOQ Designer 03/22/15 03/24/15 Sealed envelope to be submitted to Ms. Cynthia F. Fabra. in 3 copies ** To include only material breakdown. Price/amount not included. G. 10 CD 58-67 nd Submission of Bids to Owner Bidders 03/22/15 03/31/15 H. 1 CD 68 nd Opening of Bids Start of Tabulation Owner / PM 04/01/15 04/01/15 - Owner to open Bids/Countersign I. 5 CD 68-73 rd Evaluation / Negotiation PM / AFI 04/02/15 04/06/15 J. 5 CD 74-78 th Approval of Budget Owner 04/07/15 04/11/15 K. 5 CD 79-83 th NTP / Contract PM 04/12/15 04/16/15

Ponderosa Farm Timeline

Embed Size (px)

DESCRIPTION

Plan

Citation preview

  • CONSTRUCTION ACTIVITY

    Project: FABRA RESIDENCE, PONDEROSA LEISURE FARM, SILANG, CAVITE

    #OF DAYS Cal Days SCOPE OF WORK RESPONSIBLE DATES

    ACTUAL DATES

    REMARKS/ISSUES

    1.0 14 CD

    1 -14th

    Preparation of Final Layout to

    include Elev. and Perspective Designer 01/24/15 02/07/15

    - To have Designer present

    revised schemes within this

    period for Owners approval.

    2.0 7 CD 15-21st For Approval of Final Layout Owner 02/08/15 02/14/15 - To include revisions

    3.0 14 CD 22- 35th Preparation of Working Drawings Designer 02/14/15 02/28/15

    4.0 7 CD 36-42nd Preparation of Check Print Designer 03/01/15 03/07/15 - In Blue Print Form

    5.0 7 CD 43-49th Checking Of Check Print Owner / PM 03/08/15 03/14/15

    6.0

    6 CD 50-56th

    Preparation of Bid Plans

    Designer 03/15/15 03/20/15

    6 CD 50-56th Issuance of Invitation to Bid to

    Contractors Owner/PM 03/15/15 03/20/15

    PM to issue Invitation-to-Bid.

    E. 1 CD 57nd Pre-bid at Site Architect

    PM / Owner 3/21/15 03/21/15

    Blue Prints to be distributed at

    site.

    F. (3CD) (58--60th) Architects Estimate/BOQ Designer 03/22/15 03/24/15

    Sealed envelope to be submitted

    to Ms. Cynthia F. Fabra. in 3

    copies

    ** To include only material

    breakdown. Price/amount not

    included.

    G. 10 CD 58-67nd Submission of Bids to Owner Bidders 03/22/15 03/31/15

    H. 1 CD 68nd Opening of Bids

    Start of Tabulation

    Owner / PM

    04/01/15 04/01/15

    - Owner to open Bids/Countersign

    I. 5 CD 68-73rd Evaluation / Negotiation PM / AFI 04/02/15 04/06/15

    J. 5 CD 74-78th Approval of Budget Owner 04/07/15 04/11/15

    K. 5 CD 79-83th NTP / Contract PM 04/12/15 04/16/15

  • Project: FABRA RESIDENCE, PONDEROSA LEISURE FARM, SILANG, CAVITE

    #OF DAYS Cal Days SCOPE OF WORK RESPONSIBLE DATES

    ACTUAL DATES

    REMARKS/ISSUES

    L. 7 CD 84-90rd Mobilization Contractor 04/17/15 04/23/15 -To include application of Permits

    M. 180 CD

    (240 CD)

    270rd

    (330th)

    Construction Period

    Contractor /

    PM

    04/24/15

    (04/24/15)

    10/22/15

    (12/12/15)

    14 CD 2844h

    (344th)

    Punchlisting/Corrective Works

    Turn-over of Project

    285 Calendar Days Total Construction Activity