superlight aggregates for the preparation of lightweight thermal insulating mortars for screeds
POLITERM BLU
Insulation & Chemicals DivisionTHERMAL
APPLICATION MANUAL . POLITERM® BLU
Technology for the use of lightweight aggregates in slabs and screeds pg. 03
Base for floors
·Forfloorslabsandtraditionalscreeds pg.04
·Insulatedsubstrateforunderfloorheating pg.06
Roofs
·Forroofslaidtofalls,flatroofsandwaffleslabs pg.08
· News Politerm Rain Defence System pg. 14
Asbestos fibre cement
·Encapsulationofasbestosfibrecement pg.17
Single layer flat screeds
· Direct laying of ceramic tiles pg. 19
·Pouringontoporoussubstrates pg.22
·Pouringthinscreeds~ 50 mm pg. 25
·Pouringmediumthicknessscreeds~ 75 mm pg. 29
Other applications
·Beneathasphaltdriveways pg.31
·Beneathindustrialfloors pg.33
Batching plants
· Mixing instructions pg. 35
Main products pg. 37
Complementary products pg. 38
Equipment
·Mixers,pumpsandtools pg.39
IND
EX
TECHNOLOGY FOR THE USEOF LIGHTWEIGHT AGGREGATES
IN SLABS AND SCREEDSE.I.A.isthespecialadditivethatwhenappliedontotheEPSvirginbeadsguaranteesaperfectmixingoftheEPSbeadswiththecementandwater.EPSisamongstthebest insulatingmaterialwiththemostcosteffectiveperformance.DuetothedifferentspecificweightsitisalmostimpossibletomixEPSbeadswithcementsincetheytendtoseparate.WithE.I.A.thisproblemiscompletelyremovedandahomogeneousmixwithahighthermalinsulationlevelandcon-stantqualitycanbeachieved.· Perfectmixingwiththewaterandbinders.· HomogeneousdistributionoftheEPSbeadsthroughthegrout.· Perfectpumpingcapability.· Preventionofpolystyrenebeadflotation.
APPLICATION MANUAL . POLITERM® BLU RANGEThe preparation of this manual is a complex operation requiring many checks of the text, images and graphics. Experience teaches us that it is almost impossible to publish a manual flawlessly. Should you notice any errors during the reading of this manual, please inform us promptly. (What is reported in the manual has to be intended as merely indicative and none guarantee can be given if not directly taken from certification and belonging to the workmanlike. All indication given are not binding for legal purposes). “Recommendations as to methods, use of materials and construction details are given as a service to contractors and designers, on the basis of Edilteco’s experience with the use of Politerm® Blu. Any drawings are meant only to illustrate the various possibilities of applications and should not be taken as the basis for design. Since Edilteco as a material supplier, exercises no control over the installation of Politerm® Blu, no responsibility is accepted for such drawings or recommendations. Edilteco’s legal obligations in respect of any sale of Politerm® Blu shall be determined solely by the terms of the respective sales contract” All data is derived from laboratory tests and is subject to change according to environmental conditions and work practices. The user is required to check the suitability of the product in accordance with the specific application, undertaking all liability implicit in and deriving from use of the product itself; moreover the operator has to respect all application instructions and safety advice, respecting all norms attributable to the good work practice. Edilteco has the right to change at its sole discretion and without any advice the content of the present manual. The present manual cancels and replaces any other previous version of any application manual of Politerm® Blu, or any other Technical documents previously issued. The dissemination of this manual in any way, totally or even partially, is strictly forbidden without the authorization of Edilteco S.p.A.
Mixture
E.I.A.with
4
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
Base Layer
FOR USE AS A BASE LAYER BENEATH SAND-CEMENT AND SIMILAR TYPES OF SCREEDS
APPLICATION:lightweightthermalinsulatingscreed,madeusingPoliterm®Blubeads,suppliedinbagsof500Land/or200L,laidbyskilledinstallersusingthe base layer method for beneath sand cement screed, sand anhydrite or premixed screed.
INTENDED USE:groundbearingfloorslabsonadequatelycompactedhardcore/sub-baseflatroofingwithorwithoutfallsvoidfilling,intermediatefloorsoncorrugatedsteelsheetingetc.
MINIMUM APPLICATION THICKNESS: 50 mm.For thicknesses less than 50 mm proceed as follows:· Thicknessesbetween30mmand50mmonwellconsolidatedsurfaces(e.g.:withelectricalconduitand/orpipessecurelyhau-nchedwithcementmortar):thelesserthicknessmaybeconsideredacceptable.
· Forthicknessesbetween10mmand30mm:addtothemixofcementandPoliterm®Bluabout200kg/m³ofaggregatewithamaximumgrainsizeof0,6mm(mixedmanually)andincludeanelectro-weldedmetalmesh(ø 2mm).
ITEM SPECIFICATION:CreationofthermalinsulatingbaseslabpreparedwithPoliterm®BlumanufacturedbyEdiltecoS.p.A.:superli-ghtaggregateinvirginexpandedpolystyrenebeadswithconstantparticlesize(beadsø3-6mmorø2mm(Politerm®BluFein)andwithcontrolleddensity;premixedpearlbypearlwithE.I.A.®additiveintheproductionphase,whichallowsperfectmixingwithwaterbinder,eliminatesthebeadfloatingphenomenonandguaranteestheirhomogeneousdistributioninthemix.Themixcanbebatchedwithadensityof200to350kg/m³usingPortland32.5CemIoCemII,withoutaddinganysandand/orotheradditives.Therefore,everycubicmetreofmortarwillbepreparedonlywith840LofPoliterm®Blubeads,Portland32.5CemIoCemIIcementinthedosagesprescribedandtherelevantvolumeofwaterrequiredforhydration.Thelightweightscreedobtained,issuitableforsubsequentscreedlayingmadeofsandandcementorsandandanhydrite.Edil-tecotechnologysuggestsalsothenewhighinsulatingliquidscreedwithadensityofjust130kg/m3.ItispossibletoobtainthismixingthePoliterm®BluFeinwith110kg/m3 of cement.
The screed produced will have the following characteristics:
FORMULA 110 200 250 300 350
Densityafter28dayskg/m3 approx.130a approx.215 approx.265 approx.315 approx.365
ThermalconductivityλD W/mK 0,043 0,065 0,067 0,080 0,103
CompressivestrenghtN/mm2 0,528 0,69 0,83 1,61 1,69
FlexuralstrenghtN/mm2 0,12 0,37 0,46 0,95 0,59
CohesionkPa n.a. 82,62 n.a. 127,17 n.a.
Hot-sealedmembraneruptureN/50mm n.a. 57 n.a. 62 n.a.
Cold-sealedmembraneruptureN/50mm n.a. 35 n.a. 47 n.a.
ElasticitymoduleN/mm2 n.a. 235,3 n.a. 551,1 n.a.
Permeabilitytowatervapourμ 5,1 5,9 6,9 7,2 9,2
SpecificheatJ/kgK 1000* 1000* 1000* 1000* 1000*
Shrinkage(NBN)mm/m n.a. 0,427 n.a. 0,352 0,270
Acoustic performance ΔLw
n.a. 14dB** 14dB** 26dB*** n.a.
ImpactnoiseinsulationL’nT,W
n.a. n.a. 61dBthick.11cm n.a. n.a.
Fire reactivity class n.a. A2-s1,d0
a-OnlywithPoliterm®BluFein.FormethodsandapplicationconsulttheEdiltecoTechnicalDepartment.*1000J/kgK=0,24kcal/kgK/**Valueobtainedinlaboratorywith5cmofPoliterm®Blu+5cmofscreed/***Valueobtainedinlaboratorywith7cmofPoliterm®Blu+Fonotech5
5
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
When placing Politerm® Blu screed over existing concrete slabs, concrete beam decks, compacted hardcore sub-base, etc: it can be done without using an electro welded mesh in the pour. If the receiving surface however comprises insulation boards, a bituminous and/or synthetic waterproofing layer, tiled floors, or corrugated steel sheet, etc., before pouring Politerm® Blu screed sheets of electro welded lath (minimum dimensions): wire ø 2 mm - mesh 50 x 50 mm) need to be included, appropriately tied and spaced from the laying surface.
WARNINGS AND PRECAUTIONS:· WhenlayingthePoliterm®Bluscreedanyexistingstructural jointsand/orexpansion joints inthereceivingsurfacemustbemaintainedandextendedupthroughthePoliterm®Bluscreed.
· BeforelayingthePoliterm®Bluscreed,thoroughlycleanthereceivingsurface.· WhenlayingonaporousorcementitiousexistingflooraftercleaningthesurfaceandbeforelayingthePoliterm®Bluscreed,wetthefloorwellbutwithoutleavingpuddles.
· Whenlayingonanonporousorwaterproofsurfacelikeplasticsheetingoverinsulationboards,waterprooflayersortiledfloorsdonotwetthesurface.
· Whenrequired,dayjointsinthePoliterm®Bluscreedshouldbecastvertically.· Whencontinuingthepourthedayjointsneedtobetreatedwith Edilstik latexadhesive,tobeused“freshonfresh”.· AvoidmixingandlayingPoliterm®Bluwhentemperaturesarebelow5°C.Anyantifreeze additivesthatmaybeusedmustbecompatiblewiththephysicalchemicalpropertiesofPoliterm®Blu.Thecontractorshouldhoweverevaluatethecostsandbene-fitsofusingantifreezeadditivesonacasebycasebasis.
· WhenmixingPoliterm®Blu,strictlyfollowthedosagesandmethodsindicatedinthetechnicalsheets,theproductpackagingandinthismanual.OnlythencanEdiltecoguaranteetheresultsandperformanceclaimed.
· In case of highly trafficked situations protect the Politerm® screed appropriately.· It is essential that you contact our Engineering Department when considering any application different from that described in
our technical data sheets and our manuals.
GROUND:LIGHTWEIGHT THERMAL INSULATING UNDERSCREED
SCREED:·Sand/Cement·Sand/Anhydride·Selflevelling
Politerm® Blu
FLOORING:Ceramic-Parquet-Marble-Moquette-Linoleum
Vapour Barrier
Vapour barrier
INTER FLOOR:INTERMEDIATE THERMAL INSULATING LAYER
FLOORING:Ceramic-Parquet-Marble-Moquette-Linoleum
Soundinsulating band Screed
Sound insulating element
Slab
Water pipes /electric cables
Politerm® Blu
WOOD CRAWL SPACE: INSULATING LAYER
FLOORING:Ceramic-Parquet-MarbleMoquette-Linoleum Politerm® Blu
Screed
Old masonry
Soundinsulating band
Screed
Galvanizedmesh
Wood crawl space, new or refurbished Politerm® Blu
FLOORING:Ceramic-Parquet-MarbleMoquette-Linoleum
SPECIAL APPLICATION:VAULTED OR WAFFLE FLOOR LEVELLING
HONEYCOMB
6
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
Intermediate Layer
FOR USE BENEATH SELF LEVELLING SCREEDS AND UNDERFLOOR HEATING SYSTEMS (UFH)
APPLICATION:lightweightthermalinsulatingscreed,madeusingPoliterm®Blubeads,suppliedinbagsof500Land/or200Llaidbyskilledinstallersusingthe base layer method for beneath self-levelling screed: that is to say it is suitable for the next base-scre-ed application of self-levelling mortar.
INTENDED USE:groundbearingfloorslabsonadequatelycompactedhardcore/sub-baseflatroofingwithorwithoutfallsabaseforunderfloorheatingsystems(wi,thorwithoutpanels)voidfilling,intermediatefloorsoncorrugatedsteelsheetingetc.
FOR USE BENEATH SELF LEVELLING SCREEDS:1. Thespecificcharacteristics(verylowwaterabsorption)ofPoliterm®Blubasemortars,whencorrectlymixedandinstalledas
perthemanufacturer’sinstructions,maketheuseofawaterprooflayerbetweenthePoliterm®Bluandtheselflevellingscreedunnecessary.
2. WhenPoliterm®BluistobeplaceddirectlyonthegroundorinsituationswheredampconditionsmayoccurbeneaththePoli-term®Bluscreeditwillbenecessarytoinstalladampproofmembrane(dpm).Incertaincircumstancesitmaybenecessarytoincorporateavapourcontrollayer(VCL)betweenthePoliterm®Blubaseandtheself-levellingscreed.
3. Incaseofparticularstaticsituationsuchasroofs,itisnecessarytoinstallaseparatinglayerbetweenthebasemadebyPoli-term®Bluandselflevellingscreed.
4. Thethicknessoftheselflevellingscreed,placedoverthePoliterm®Bluscreed,shouldbeinaccordancewiththerecommenda-tionsofthemanufacturersoftheself-levellingscreed.
FOR USE BENEATH UNDERFLOOR HEATING SYSTEMS:1. Thespecificcharacteristics(very lowwaterabsorption)ofPoliterm®Blubasemortars,whencorrectlymixedand installed
asperthemanufacturer’sinstructions,makestheuseofawaterproofinglayerbetweenthePoliterm®Bluandtheunderfloorheating system unnecessary.
2. Installationofufhpipingsysteminrigidinsulationpanels:followtheinstallationinstructionsofthesupplierofthethermalheating system.
3. Installationofufhpipingsystemwithoutpanel:usingthethermalperformancecharacteristicsofthePoliterm®BluinsulatingbaselayeritispossibletocalculateaPoliterm®basethicknessthatavoidstheneedforadditionalrigidinsulationboards.Inthiscaseitisnecessarytoinstallgalvanizedsheets,joinedtogetherontopofthePoliterm®Blubaseonwhichitispossibletofixtheufhpiping.
MINIMUM APPLICATION THICKNESS: 50 mm.For thicknesses less than 50 mm proceed as follows:· Thicknessesbetween30mmand50mmonwell‐consolidatedsurfaces(e.g.:withelectricalconduitand/orpipessecurelyhau-nchedwithcementmortar):thelesserthicknessmaybeconsideredacceptable.
· Forthicknessesbetween10mmand30mm:addtothemixofcementandPoliterm®Bluabout200kg/m³ofaggregatewithamaximumgrainsizeof0,6mm(mixedmanually)andincludeanelectro-weldedmetalmesh(2mmwirediameter).
ITEM SPECIFICATION:CreationofthermalinsulatingbaseslabpreparedwithPoliterm®BlumanufacturedbyEdiltecoS.p.A.:super-lightaggregateinvirginexpandedpolystyrenebeadswithconstantparticlesize(beadsø3/6mmorø2mm-Politerm®BluFein)andwithcontrolleddensity;premixedpearlbypearlwithE.I.A.®additiveintheproductionphase,whichallowsperfectmixingwithwaterbinder,eliminatesthebeadfloatingphenomenonandguaranteestheirhomogeneousdistributioninthemix.Themixcanbebatchedwithadensityof200to350kg/m³usingPortland32.5CemIoCemII,withoutaddinganysandand/orotheradditives.Therefore,everycubicmetreofmortarwillbepreparedonlywith840LofPoliterm®Blubeads,Portland32.5CemIoCemIIcementinthedosagesprescribedandtherelevantvolumeofwaterrequiredforhydration.Thelightweightscreedobtained,issuitableforsubsequentscreedlayingmadeofsandandcementorsandandanhydrite.Edil-tecotechnologysuggestsalsothenewhighinsulatingliquidscreedwithadensityofjust130kg/m3.ItispossibletoobtainthismixingthePoliterm®BluFeinwith110kg/m3 of cement.
7
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
The screed produced will have the following characteristics:
WARNINGS AND PRECAUTIONS:· WhenlayingthePoliterm®Bluscreedanyexistingstructuraljointsand/orexpansionjointsinthereceivingsurfacemustbemaintainedandextendedupthroughthePoliterm®Bluscreed.
· BeforelayingthePoliterm®Bluscreed,thoroughlycleanthereceivingsurface.· WhenlayingonaporousorcementitiousexistingflooraftercleaningthesurfaceandbeforelayingthePoliterm®Bluscreed,wetthefloorwellbutwithoutleavingpuddles.
· Whenlayingonanonporousorwaterproofsurfacelikeplasticsheetingoverinsulationboards,waterprooflayersortiledfloorsdonotwetthesurface.
· Whenrequired,dayjointsinthePoliterm®Bluscreedshouldbecastvertically.· WhencontinuingthepourthedayjointsneedtobetreatedwithEdilstiklatexadhesive,tobeused“freshonfresh”.· AvoidmixingandlayingPoliterm®Bluwhentemperaturesarebelow5°C.Anyantifreezeadditivesthatmaybeusedmustbecompatiblewiththephysical‐chemicalpropertiesofPoliterm®Blu.Thecontractorshouldhoweverevaluatethecostsandbenefitsofusingantifreezeadditivesonacasebycasebasis.
· WhenmixingPoliterm®Blu,strictlyfollowthedosagesandmethodsindicatedinthetechnicalsheets,theproductpackagingandinthisma-nual.OnlythencanEdiltecoguaranteetheresultsandperformanceclaimed.
· In case of highly trafficked situations protect the Politerm® screed appropriately.· It is essential that you contact our Engineering Department when considering any application different from that described in our technical
data sheets and our manuals.
FLOORING:Ceramic-Marble-Parquet-Moquette-Linoleum
Sound insulating band
Self levelling screed Autoliv SP or sand-cement fluidized screed
Floor heating panel
Slab
Water pipes / electric cables
Politerm® Blu
INTER FLOOR: LIGHTWEIGHT FILLING LAYER FOR RADIANT HEATING FLOOR SYSTEM
FLOORING:Ceramic-Marble- Parquet - Moquette - Linoleum
Soundinsulating band
Self levelling screed Autoliv SP or sand-cement fluidized screed
Layer of separation
Floor heating system
Slab
Water pipes / electric cables
Politerm® Blu
INTER FLOOR: LIGHTWEIGHT FILLING LAYER FOR RADIANT HEATING FLOOR SYSTEM
SPECIAL APPLICATION: INCLINED SINGLE LAYER LIGHTWEIGHT THERMAL INSULATED SCREED
Self levelling screedAutoliv SP
Politerm® Blu
FLOORING:Ceramic-Marble-Parquet-Moquette-Linoleum
Vapour barrier
GROUND:LIGHTWEIGHT THERMAL INSULATING UNDERSCREED
Self levelling screed Autoliv SP
Politerm® Blu
Vapour barrier
FLOORING:Ceramic-Parquet-Marble-Moquette-Linoleum
HONEYCOMB
FORMULA 110 200 250 300 350
Densityafter28dayskg/m3 approx.130a approx.215 approx.265 approx.315 approx.365
ThermalconductivityλD W/mK 0,043 0,065 0,067 0,080 0,103
CompressivestrenghtN/mm2 0,528 0,69 0,83 1,61 1,69
FlexuralstrenghtN/mm2 0,12 0,37 0,46 0,95 0,59
CohesionkPa n.a. 82,62 n.a. 127,17 n.a.
Hot-sealedmembraneruptureN/50mm n.a. 57 n.a. 62 n.a.
Cold-sealedmembraneruptureN/50mm n.a. 35 n.a. 47 n.a.
ElasticitymoduleN/mm2 n.a. 235,3 n.a. 551,1 n.a.
Permeabilitytowatervapourμ 5,1 5,9 6,9 7,2 9,2
SpecificheatJ/kgK 1000* 1000* 1000* 1000* 1000*
Shrinkage(NBN)mm/m n.a. 0,427 n.a. 0,352 0,270
Acoustic performance ΔLw
n.a. 14dB** 14dB** 26dB*** n.a.
ImpactnoiseinsulationL’nT,W
n.a. n.a. 61dBthick.11cm n.a. n.a.
Fire reactivity class n.a. A2-s1,d0
a-OnlywithPoliterm®BluFein.FormethodsandapplicationconsulttheEdiltecoTechnicalDepartment.*1000J/kgK=0,24kcal/kgK/**Valueobtainedinlaboratorywith5cmofPoliterm®Blu+5cmofscreed/***Valueobtainedinlaboratorywith7cmofPoliterm®Blu+Fonotech5
8
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
Roofing
FOR USE ON INCLINED OR FLAT ROOF (WITH OR WITHOUT FALLS) AND FACESDirectly beneath an applied waterproofing layer
APPLICATION:lightweightthermalinsulatingscreed,madeusingPoliterm®Blubeads,suppliedinbagsof500Land/or200L,laidbyskilledinstallersusingthe base layer method to directly receive a waterproofing layer either (poured on), bituminous (hot or cold) and/or synthetic.
INTENDED USE:flatroofsandnon-traffickedterraces(withorwithoutfalls),coveringcorrugatedroofingsheetsetc...
MINIMUM THICKNESS ON ABSORBENT SURFACES: 50 mm.For thicknesses less than 50 mm proceed as follows:· Thicknessesbetween30mmand50mmonwellconsolidatedsurfacese.g.:withelectricalconduitand/orpipessecurelyhaun-chedwithcementmortar:thelesserthicknessmaybeconsideredacceptable.
· Forthicknessesbetween10mmand30mm:addtothemixofcementandPoliterm®Bluabout200kg/m³ofaggregatewithamaximumgrainsizeof0,6mm(mixedmanually)andincludeanelectro-weldedmetalmesh(2mmwirediameter).
When creating falls, the minimum thickness must not be less than 50 mm.
MINIMUM APPLICATION THICKNESS ON NON-ABSORBENT SURFACES: 50 mm with galvanizedmesh(minimumsize:wireø3mm–mesh50x50mm)ataduedistancefromthelayingsurface.Our Edilteco Technical Department is available for any question.
ITEM SPECIFICATION: CreationofthermalinsulatingbaseslabpreparedwithPoliterm®BlumanufacturedbyEdiltecoS.p.A:superli-ghtaggregateinvirginexpandedpolystyrenebeadswithconstantparticlesize(beadsø3/6mmorø2mm-Politerm®BluFein)andwithcontrolleddensity;premixedpearlbypearlwithE.I.A.®additiveintheproductionphase,whichallowsperfectmixingwithwaterbinder,eliminatesthebeadfloatingphenomenonandguaranteestheirhomogeneousdistributioninthemix.Themixcanbebatchedwithadensityof200to350kg/m³usingPortland32.5CemIoCemII,withoutaddinganysandand/orotheradditives.Therefore,everycubicmetreofmortarwillbepreparedonlywith840LofPoliterm®Blubeads,Portland32.5CemIoCemIIcementinthedosagesprescribedandtherelevantvolumeofwaterrequiredforhydration.Thelightweightscreedobtained,issuitableforsubsequentscreedlayingmadeofsandandcementorsandandanhydrite.Edil-tecotechnologysuggestsalsothenewhighinsulatingliquidscreedwithadensityofjust130kg/m3.ItispossibletoobtainthismixingthePoliterm®BluFeinwith110kg/m3 of cement.
The screed produced will have the following characteristics:
FORMULA 200 250 300 350
Densityafter28dayskg/m3 approx.215 approx.265 approx.315 approx.365
ThermalconductivityλD W/mK 0,065 0,067 0,080 0,103
CompressivestrenghtN/mm2 0,69 0,83 1,61 1,69
FlexuralstrenghtN/mm2 0,37 0,46 0,95 0,59
CohesionkPa 82,62 n.a. 127,17 n.a.
Hot-sealedmembraneruptureN/50mm 57 n.a. 62 n.a.
Cold-sealedmembraneruptureN/50mm 35 n.a. 47 n.a.
9
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
When placing Politerm® Blu screed over existing concrete roofs, concrete beam decks, it can be done without using an electro wel-ded mesh in the pour. If the receiving surface however comprises insulation boards, a bituminous and/or synthetic waterproofing layer, or corrugated steel sheet, etc., before pouring Politerm® Blu screed sheets of electro welded mesh (minimum dimensions): wire ø 2 mm - mesh 50 x 50 mm need to be included, appropriately tied and spaced from the laying surface.
Before apply the waterproof finish, it is necessary to prepare the surface using one of the two following methods:a. Abrade the surface using an electric sander fitted with an abrasive disk and dust extraction; alternativelyb. Melt the surface polystyrene beads polystyrene beads, using an LPG roofing gas torch.Neither method to be employed until 7 days after the screed has been laid.
WARNINGS AND PRECAUTIONS:· WhenlayingthePoliterm®Bluscreedanyexistingstructuraljointsand/orexpansionjointsinthereceivingsurfacemustbe
maintainedandextendedupthroughthePoliterm®Bluscreed.· BeforelayingthePoliterm®Bluscreed,thoroughlycleanthereceivingsurface.· WhenlayingonaporousorcementitiousexistingroofaftercleaningthesurfaceandbeforelayingthePoliterm®Bluscreed,wet
thesurfacewellbutwithoutleavingpuddles.· Whenlayingonanonporousorwaterproofsurfacelikeplasticsheetingoverinsulationboardsorwaterprooflayersdonotwet
the surface.· Whenrequired,dayjointsinthePoliterm®Bluscreedshouldbecastvertically.· WhencontinuingthepourthedayjointsneedtobetreatedwithEdilstiklatexadhesive,tobeused“freshonfresh”.· ThemaximumgradientdependingonthemixstrengthofthePoliterm®Bluisbetween30and40%.· ThePoliterm®Bluscreedneedstobeprotectedfromrainforthefirst48hoursafterlaying.· ThesubsequentlayingofaheavyscreedoverthePoliterm®Bluscreedmaybepossibleafteraperiodof7days.Thisperiodof
timemayneedtobeextendedsubjecttothethicknessofthePoliterm®Bluscreedandweatherconditions.Theinstallationofthewaterproofingmembraneshouldbestrictlyinaccordancewiththeinstructionsofthemembranemanufacturers.TheapplicationofliquidwaterproofingmembranesonPoliterm®Blu,shouldbestrictlyinaccordancewiththeinstructionsofthemembranemanufacturers.SolventbasedliquidmembranesmustnotbeusedonPoliterm®Bluscreeds.
· AvoidmixingandlayingPoliterm®Bluwhentemperaturesarebelow5°C.Anyantifreezeadditivesthatmaybeusedmustbecompatiblewiththephysical/chemicalpropertiesofPoliterm®Blu.Thecontractorshouldhoweverevaluatethecostsandbe-nefitsofusingantifreezeadditivesonacasebycasebasis.
· WhenmixingPoliterm®Blu,strictlyfollowthedosagesandmethodsindicatedinthetechnicalsheets,theproductpackagingandinthismanual.OnlythencanEdiltecoguaranteetheresultsandperformanceclaimed.
· It is essential that you contact our Engineering Department when considering any application different from that described in our technical data sheets and our manuals.
FORMULA 200 250 300 350
ElasticitymoduleN/mm2 235,3 n.a. 551,1 n.a.
Permeabilitytowatervapourμ 5,9 6,9 7,2 9,2
SpecificheatJ/kgK 1000* 1000* 1000* 1000*
Shrinkage(NBN)mm/m 0,427 n.a. 0,352 0,270
Acoustic performance ΔLw
14dB** 14dB** 26dB*** n.a.
ImpactnoiseinsulationL’nT,W
n.a. 61dBthick.11cm n.a. n.a.
Fire reactivity class A2-s1,d0
a-OnlywithPoliterm®BluFein.FormethodsandapplicationconsulttheEdiltecoTechnicalDepartment.*1000J/kgK=0,24kcal/kgK/**Valueobtainedinlaboratorywith5cmofPoliterm®Blu+5cmofscreed/***Valueobtainedinlaboratorywith7cmofPoliterm®Blu+Fonotech5
10
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
COVER: LIGHTWEIGHT THERMAL INSULATING LEVELLINGON CORRUGATED DECK
SPECIAL APPLICATION:VAULTED OR WAFFLE FLOOR LEVELLING
Politerm® Blu
WATERPROOFING MEMBRANE:Bituminous precasted hot membrane; bituminous preca-stedcoldmembrane;liquidbituminousmembrane;synthe-ticprecastedmembrane; liquidsyntheticmembrane(con-tact Edilteco Technical Department)
Loading-cover made ofcorrugated sheet
Galvanized mesh
Politerm® Blu
Bituminous membrane
Old masonry
Waterpoofing element
Politerm® Blu
Slab
FLAT ROOF: SINGLE LAYER LIGHTWEIGHT THERMALINSULATING INCLINED SCREED
PITCHED ROOF: THERMAL INSULATING LAYER
Politerm® Blu
Tiles
Possiblewaterproofing element
Possiblewaterproofing element
Insole
11
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
Roofing
FOR USE ON INCLINED OR FLAT ROOF (WITH OR WITHOUT FALLS) AND WAFFLE SLABSBeneath sand-cement screed and waterproofing layer
APPLICATION:lightweightthermalinsulatingscreed,madeusingPoliterm®Blubeads,suppliedinbagsof500Land/or200L,laidbyskilledinstallersusingthe base layer method for beneath sand-cement screed to be followed by a waterproofing layer either (poured on), bituminous (hot or cold) and/or synthetic.
INTENDED USE:flatroofsandnon-traffickedterraces(withorwithoutfalls),coveringcorrugatedroofingsheetsetc...
MINIMUM THICKNESS ON ABSORBENT SURFACES: 50 mm.For thicknesses less than 50 mm proceed as follows:· Thicknessesbetween30mmand50mmonwellconsolidatedsurfaces(e.g.:withelectricalconduitand/orpipessecurelyhau-nchedwithcementmortar):thelesserthicknessmaybeconsideredacceptable.
· Forthicknessesbetween10mmand30mm:addtothemixofcementandPoliterm®Bluabout200kg/m³ofaggregatewithamaximumgrainsizeof0,6mm(mixedmanually)andincludeanelectro-weldedmetalmesh(2mmwirediameter).
When creating falls, the minimum thickness must not be less than 50 mm.
MINIMUM APPLICATION THICKNESS ON NON-ABSORBENT SURFACES: 50 mm withgalvanizedmesh(minimumsize:wireø3mm–mesh50x50mm)ataduedistancefromthelayingsurface.
Our Edilteco Technical Department is available for any question.
ITEM SPECIFICATION:CreationofthermalinsulatingbaseslabpreparedwithPoliterm®BlumanufacturedbyEdiltecoS.p.A.:super-lightaggregateinvirginexpandedpolystyrenebeadswithconstantparticlesize(beadsø3/6mmorø2mm-Politerm®BluFein)andwithcontrolleddensity;premixedpearlbypearlwithE.I.A.®additiveintheproductionphase,whichallowsperfectmixingwithwaterbinder,eliminatesthebeadfloatingphenomenonandguaranteestheirhomogeneousdistributioninthemix.Themixcanbebatchedwithadensityof200to350kg/m³usingPortland32.5CemIoCemII,withoutaddinganysandand/orotheradditives.Therefore,everycubicmetreofmortarwillbepreparedonlywith840LofPoliterm®Blubeads,Portland32.5CemIoCemIIcementinthedosagesprescribedandtherelevantvolumeofwaterrequiredforhydration.Thelightweightscreedobtained,issuitableforsubsequentscreedlayingmadeofsandandcementorsandandanhydrite.Edil-tecotechnologysuggestsalsothenewhighinsulatingliquidscreedwithadensityofjust130kg/m3.ItispossibletoobtainthismixingthePoliterm®BluFeinwith110kg/m3 of cement.
The screed produced will have the following characteristics:
FORMULA 110 200 250 300 350
Densityafter28dayskg/m3 approx.130a approx.215 approx.265 approx.315 approx.365
ThermalconductivityλD W/mK 0,043 0,065 0,067 0,080 0,103
CompressivestrenghtN/mm2 0,528 0,69 0,83 1,61 1,69
FlexuralstrenghtN/mm2 0,12 0,37 0,46 0,95 0,59
CohesionkPa n.a. 82,62 n.a. 127,17 n.a.
Hot-sealedmembraneruptureN/50mm n.a. 57 n.a. 62 n.a.
Cold-sealedmembraneruptureN/50mm n.a. 35 n.a. 47 n.a.
ElasticitymoduleN/mm2 n.a. 235,3 n.a. 551,1 n.a.
12
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
When placing Politerm® Blu screed over existing concrete roofs, concrete beam decks, it can be done without using an electro welded mesh in the pour. If the receiving surface however comprises insulation boards, a bituminous and/or synthetic waterproofing layer, or corrugated steel sheet, etc., before pouring Politerm® Blu screed sheets of electro welded mesh (minimum dimensions): wire ø 2 mm - mesh 50 x 50 mm) need to be included, appropriately tied and spaced from the laying surface.
WARNINGS AND PRECAUTIONS:· WhenlayingthePoliterm®Bluscreedanyexistingstructuraljointsand/orexpansionjointsinthereceivingsurfacemustbemaintai-
nedandextendedupthroughthePoliterm®Bluscreed.· BeforelayingthePoliterm®Bluscreed,thoroughlycleanthereceivingsurface.· WhenlayingonaporousorcementitiousexistingroofaftercleaningthesurfaceandbeforelayingthePoliterm®Bluscreed,wetthe
surfacewellbutwithoutleavingpuddles.· Whenlayingonanonporousorwaterproofsurfacelikeplasticsheetingoverinsulationboardsorwaterprooflayersdonotwetthe
surface.· Whenrequired,dayjointsinthePoliterm®Bluscreedshouldbecastvertically.· WhencontinuingthepourthedayjointsneedtobetreatedwithEdilstiklatexadhesive,tobeused“freshonfresh”.· ThemaximumgradientdependingonthemixstrengthofthePoliterm®Bluisbetween30and40%.· ThePoliterm®Bluscreedneedstobeprotectedfromrainforthefirst48hoursafterlaying.· L’utilizzodiguaineliquidesuimassetticonfezionaticonPoliterm®Blu,nonpotràprescinderedallaverificaedapprovazionedaparte
delproduttore/fornitoredellaguainastessa.NonsidovrannocomunqueapplicaresuimassetticonfezionaticonPoliterm®Bluguaineliquideabasedisolventi.
· ThesubsequentlayingofaheavyscreedoverthePoliterm®Bluscreedmaybepossibleafteraperiodof7days.ThisperiodoftimemayneedtobeextendedsubjecttothethicknessofthePoliterm®Bluscreedandweatherconditions.Theinstallationofthewater-proofingmembraneshouldbestrictlyinaccordancewiththeinstructionsofthemembranemanufacturers.TheapplicationofliquidwaterproofingmembranesonPoliterm®Blu,shouldbestrictlyinaccordancewiththeinstructionsofthemembranemanufacturers.SolventbasedliquidmembranesmustnotbeusedonPoliterm®Bluscreeds.
· AvoidmixingandlayingPoliterm®Bluwhentemperaturesarebelow5°C.Anyantifreezeadditivesthatmaybeusedmustbecompa-tiblewiththephysical‐chemicalpropertiesofPoliterm®Blu.Thecontractorshouldhoweverevaluatethecostsandbenefitsofusingantifreezeadditivesonacasebycasebasis.
· WhenmixingPoliterm®Blu,strictlyfollowthedosagesandmethodsindicatedinthetechnicalsheets,theproductpackagingandinthismanual.OnlythencanEdiltecoguaranteetheresultsandperformanceclaimed.
· It is essential that you contact our Engineering Department when considering any application different from that described in our technical data sheets and our manuals.
Waterpoofing element
Politerm® Blu
Cement Screed
Slab
FLAT ROOF: SINGLE LAYER LIGHTWEIGHT THERMALINSULATING INCLINED SCREED
PITCHED, FLAT (WITH OR WITHOUT INCLINATION FORMATION) AND VAULTED ROOFSwith the application of a sand-cement base-screed and the following waterproofing
FORMULA 110 200 250 300 350
Permeabilitytowatervapourμ 5,1 5,9 6,9 7,2 9,2
SpecificheatJ/kgK 1000* 1000* 1000* 1000* 1000*
Shrinkage(NBN)mm/m n.a. 0,427 n.a. 0,352 0,270
Acoustic performance ΔLw
n.a. 14dB** 14dB** 26dB*** n.a.
ImpactnoiseinsulationL’nT,W
n.a. n.a. 61dBthick.11cm n.a. n.a.
Fire reactivity class n.a. A2-s1,d0
a-OnlywithPoliterm®BluFein.FormethodsandapplicationconsulttheEdiltecoTechnicalDepartment.*1000J/kgK=0,24kcal/kgK/**Valueobtainedinlaboratorywith5cmofPoliterm®Blu+5cmofscreed/***Valueobtainedinlaboratorywith7cmofPoliterm®Blu+Fonotech5
13
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
COVER: LIGHTWEIGHT THERMAL INSULATING LEVELLINGON CORRUGATED DECK
SPECIAL APPLICATION:WAFFLE SLABS OR WAFFLE FLOOR LEVELLING
Politerm® Blu
Cement Screed
WATERPROOFING MEMBRANE:Bituminous precasted hot membrane; bituminous preca-stedcoldmembrane;liquidbituminousmembrane;synthe-ticprecastedmembrane; liquidsyntheticmembrane(con-tact Edilteco Technical Department)
Loading-cover made ofcorrugated sheet
Galvanized mesh
Politerm® Blu
Cement Screed
Bituminous membrane
Old masonry
14
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
LIGHTWEIGHT NON-ABSORBENT THERMAL INSULATING SYSTEM FOR ROOFING AT PITCHED, FLAT (WITH OR WITHOUT FALLS) AND VAULTED ROOFS
TIPOLOGY:realizationofasuperlightandnon-absorbentbasescreedforthermalinsulation,preparedwithPoliterm®Blu(suppliedinbagsofayieldof500Lor200Leach),mixedwithaspecificpowderedbinderB.R.DBluRainDefence(anadditivethatallowstoleavePolitermundertherain,withoutslowingdownthedrying)andcement.ItislaidbyaspecializedteamthroughtheRoofing castingmethodology.
INTENDED USES: Roofingatsloping/flatroofs(see par. Roofing pag. 11)EncapsulationAsbestosfibersheet(see par. Encapsulation pag. 17)Piano Zero single-layer for exterior (see par. Piano Zero pag. 19)Intermediatelayerforthelayingoftheasphalt(see par. Intermediate layer pag. 31).
MINIMUM THICKNESS OF APPLICATION: 50 mm.In case of under thickness, the procedure is the following (only for limited surfaces):· Forthicknessbetween30mm/50mmandforwell-stablesurfaces(ex:pipesforelectrical/hydraulicinstallationpreviouslycoveredwithcementmortar):theunderthicknesscanbeaccepted.
· Forthicknessbetween10mm/30mm:addtoPoliterm®Blumixapproximately200kg/m³ofaggregatehavingamaximumgrain-sizeof0,6mm(manualmix),andplacethegalvanizedmesh(ø2mm).
In case of gradient, the starting minimum thickness cannot be less then 50 mm.
SPECIFICATION:creationofalightweightnon-absorbentthermalinsulatingbasescreed,preparedwithPoliterm®Blu,producedbyEdilte-coS.p.A:superlightaggregatecomposedofvirginexpandedpolystyrenebeadswithconstantparticlesize(beadsofø3-6mm,orbeadsof ø2mm(Politerm®BluFein)andwithacontrolleddensity.Duringtheproduction,eachbeadismixedwithaspecialE.I.Aadditive,whichallowsaperfectmixingwiththehydrationbinder,eliminatestheproblemofbeadflotationandguaranteestheirperfecthomogenousdistributionthroughoutthemix.Themixcanbedosedfrom200to350kg/m³ofPortlandcement32.5CemIorCemIIandspecificpow-deredbinderBluRainDefence.Thequantityisof800gforeach50kgofcementbinder,andthereisnoneedtoaddsandand/orotheradditives.Eachm³ofmortarwillbepreparedonlywith840LofPoliterm®Blubeads,B.R.D.BluRainDefencebinderandPortlandcement32.5/42.5/52.5CemIorCemII,withtherelativedosagesandhydrationwater.Theresultingbasescreedwillbesuitableoffortheappli-cationtoroofing,respectingthespecifictechniquesofapplication.
New systemPOLITERM
RAINDEFENCE
POLITERM® BLU+
B.R.D. BLU RAIN DEFENCEcreate a unique and
NON-ABSORBENT SYSTEM!
15
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
INTRODUCTION ORDER OF COMPONENTS:1. Water.2. Politerm.3. Cement:expectedquantityaccordingtothespecificapplication.4. BluRainDefencebinderinthequantityof0,800kgper50kgofcementbinder.5. Mixfor10minuteslong(introductiontimeincluded).
For mixture with sand (density greater than 350 kg/m3), add 400 gr of additive each 50 kg of aggregate.
In case of laying surfaces composed of floors, cls castings, loose stone foundations, etc.. the application of the base screed prepared with Politerm® Blu doesn’t require the insertion of a galvanized mesh into the casting. In case of laying surfaces composed of insulating sheets, waterproofing synthetic layers, ceramic floors, linoleum floors, pvc, wood, moquette, corrugated sheets, etc.. before to laying of the base screed prepared with Politerm® Blu, it is necessary to lay the galvanized sheets (minimum size: wire ø 2 mm – diameter 50 x 50 mm), tied together and well-distanced from the laying surface.
WARNINGS:· Duringtherealizationofthescreed,preparedwithPoliterm®Blu,thestructuraland/orthepreexistingexpansionjointsonthelaying
surfacemustbemaintained.· BeforethelayingofthebasescreedpreparedwithPoliterm®Blu,carefullycleanthesurface.· AfterthecleaningofthelayingsurfaceandbeforetheapplicationofPoliterm®Blubasescreed,itisnecessarytomoistenthesurface
(ifcomposedofclsslab),withoutcausingpuddles.Thepriormoistendoesnothavetobedoneincaseoflayingsurfacescomposedofwaterproofingmembrane,othernon-absorbentsupportsorwoodboards.
· Anycastinginterruptionorexecutionoflevellingstripshavetobedoneverticallyrespecttothelayingsurface.· Anypossiblecasting recoveringorexecutionof levellingstripsmustbepreviously treatedwithEdilstick latexanddonewith fre-
sh-on-freshmethod.· TheapplicationonpitchedorvaultedroofofPoliterm®Blubasescreedispossibleforgradientsbetween30%-40%(alsoaccordingto
thelayingsurface’snature).· The base screed will be therefore able to overcome the run-off caused by weak rain, even after 24 hours from the application (clima-
tic conditions of +20°C and U.R 50%).· The base screed will be able to eliminate the water absorption caused by weak rain, even after 48 hours from the application (cli-
matic conditions of +20°C and U.R 50%).· ThePoliterm®Blubasescreedmustbeprotectedfrommeteoricprecipitation(ex.rain)forthefirst48hoursfromthecastingexecu-
tion.· ThelayingoftheheavyscreedonthebasescreedpreparedwithPoliterm®Bluispossibleapproximatelyafter7daysfromtherealiza-
tionofthescreed.Thetimemaychangeaccordingtothethicknessandtheclimaticconditions.Theapplicationofthewaterproofinglayersmustfollowtheinstructionsoflayers’producers.
The packaged screed has the following characteristics:
FORMULA 200 250 300 350
Densityafter28dayskg/m3 approx.215 approx.265 approx.315 approx.365
ThermalconductivityλD W/mK 0,065 0,067 0,080 0,103
CompressivestrenghtN/mm2 0,69 0,83 1,61 1,69
FlexuralstrenghtN/mm2 0,37 0,46 0,95 0,59
CohesionkPa 82,62 n.a. 127,17 n.a.
Hot-sealedmembraneruptureN/50mm 57 n.a. 62 n.a.
Cold-sealedmembraneruptureN/50mm 35 n.a. 47 n.a.
ElasticitymoduleN/mm2 235,3 n.a. 551,1 n.a.
Permeabilitytowatervapourμ 5,9 6,9 7,2 9,2
SpecificheatJ/kgK 1000* 1000* 1000* 1000*
Shrinkage(NBN)mm/m 0,427 n.a. 0,352 0,270
Acoustic performance ΔLw
14dB** 14dB** 26dB*** n.a.
ImpactnoiseinsulationL’nT,W
n.a. 61dBthick.11cm n.a. n.a.
Fire reactivity class A2-s1,d0
*1000J/kgK=0,24kcal/kgK/**Valueobtainedinlaboratorywith5cmofPoliterm®Blu+5cmofscreed/***Valueobtainedinlaboratorywith7cmofPoliterm®Blu+Fonotech5
16
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
· TheuseofliquidmembraneonthePoliterm®Blubasescreedscannotignorethetestandapprovalofthemembraneproducers/sup-plier.Liquidsolvent-basedmembranecannotbeappliedonPoliterm®Blubasescreeds.
· Withtemperatureinferiorto+5°CthescreedpreparationandapplicationwithPoliterm®Blushouldbeavoided.Thepossibleuseofanti-freezeadditivesiscompatiblewiththephysico-chemicalcharacteristicsofPoliterm®Blu.Anyway,itscostsandbenefitshavetobecarefullyanlysed,casebycase,bytheapplicator.
· DuringthepreparationofthescreedspreparedwithPoliterm®Bluitisnecessarytocarefullyfollowthedosagesandthemethodo-logiesindicatedonthetechnicaldatasheets,thepackagingoftheproductandthepresentmanual.OnlyinthiscasecanEdiltecoguarantees the results of its performances.
· In order to evaluate every different application from what is described in our manuals, please contact our Technical Department.
SOME PHASES OF THE new system POLITERM® RAIN DEFENCE
Waterproof strip
Politerm RainDefence
Slab
FLAT ROOFING: SINGLE-LAYERTHERMAL INSULATING LIGHT SLOPING SCREED
Politerm RainDefence
TERRACES AND BALCONIES: LIGHT THERMAL INSULATING SINGLE-LAYER
Piano ZeroGuide
FLOOR:ceramic/marble
Soundproof strip
WATERPROOFING LAYER SUI-TABLE FOR GLUE APPLICATION OF THE FLOOR·liquidsheath·prefabricatedmembrane
Slab
Installation(electrical, hydraulic, vacuum)
FLAT ROOFING: LIGHT SLOPING THERMAL INSULATING SIN-GLE-LAYER SCREED
Waterproofing layer
Cement screed
Slab
ROOFING AT PITCHED ROOF: LAYER OF THERMAL INSULATION
Shingles
Possible waterproofing layer
Possible waterproofing layer
Slab
17
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
FOR THE ENCAPSULATION OF ROOF SURFACESMADE UP WITH ASBESTOS FIBRE CEMENT BOARDS
APPLICATION:lightweightthermalinsulatingscreed,madeusingPoliterm®Blubeads,suppliedinbagsof500Land/or200L,laidbyskilledinstallersusingthe method to encapsulate roofs made up with asbestos fibre cement boards in order to avoid the air pollution by asbestos fibres and to offer a surface ready to receive a water proofing layer either (poured on), bituminous (hot or warm) and/or synthetic.
Usingthismethodtheencapsulationcanbedonewithoutusingthetraditionalhazardous,expensiveandcomplexwashingopera-tion,aswellasthescrapingandfixingofcracksandcrazing.Furthermore,usingthePoliterm®Bluencapsulationsystemthereisnoneedtoremove,cutordrilltheasbestosfibrecementboardsthusavoidingthecreationofhazardousdust.
INTENDED USE:pitchedroofsandshelters.
MINIMUM LAYER: 50 mm thickness above the top of the asbestos fibre cement corrugated sheet roof profile.The average thickness obtained will be approximately 80 mm depending on the corrugation profile.
ITEM SPECIFICATION:CreationofthermalinsulatingbaseslabpreparedwithPoliterm®BlumanufacturedbyEdiltecoS.p.A:superli-ghtaggregateinvirginexpandedpolystyrenebeadswithconstantparticlesize(beadsø3/6mmorø2mm-Politerm®BluFein)andwithcontrolleddensity;premixedpearlbypearlwithE.I.A.®additiveintheproductionphase,whichallowsperfectmixingwithwaterbinder,eliminatesthebeadfloatingphenomenonandguaranteestheirhomogeneousdistributioninthemix.Themixcanbebatchedwithadensityof200to350kg/m³usingPortland32.5CemIoCemII,withoutaddinganysandand/orotheradditives.Therefore,everycubicmetreofmortarwillbepreparedonlywith840LofPoliterm®Blubeads,Portland32.5CemIoCemIIcementinthedosagesprescribedandtherelevantvolumeofwaterrequiredforhydration.
The screed produced will have the following characteristics:
Asbestosfibre cement
encapsulation
FORMULA 200 250 300 350
Densityafter28dayskg/m3 approx.215 approx.265 approx.315 approx.365
ThermalconductivityλD W/mK 0,065 0,067 0,080 0,103
CompressivestrenghtN/mm2 0,69 0,83 1,61 1,69
FlexuralstrenghtN/mm2 0,37 0,46 0,95 0,59
CohesionkPa 82,62 n.a. 127,17 n.a.
Hot-sealedmembraneruptureN/50mm 57 n.a. 62 n.a.
Cold-sealedmembraneruptureN/50mm 35 n.a. 47 n.a.
ElasticitymoduleN/mm2 235,3 n.a. 551,1 n.a.
Permeabilitytowatervapourμ 5,9 6,9 7,2 9,2
SpecificheatJ/kgK 1000* 1000* 1000* 1000*
Shrinkage(NBN)mm/m 0,427 n.a. 0,352 0,270
Acoustic performance ΔLw
14dB** 14dB** 26dB*** n.a.
ImpactnoiseinsulationL’nT,W
n.a. 61dBthick.11cm n.a. n.a.
Fire reactivity class A2-s1,d0
*1000J/kgK=0,24kcal/kgK/**Valueobtainedinlaboratorywith5cmofPoliterm®Blu+5cmofscreed/***Valueobtainedinlaboratorywith7cmofPoliterm®Blu+Fonotech5
18
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
It isessentialandalegalrequirementtocheckregulationsinforcebeforestartinganyencapsulation.ItwillalsobenecessarybeforestartingencapsulationtostabilisethesurfaceoftheasbestosfibresmentboardsusinagacoatingofmodifiedlatexcalledEdilstikF.C.Aappliedusingalowpressurespray.TheEdilstikF.C.Atobedilutedincleanwater(1partEdilstikF.C.A.to2partscleanwater).
Before the laying the Politerm® Blu screed, it is necessary to place sheets of galvanized mesh (min dimension of the cable diam. 2 mm, mesh dimension 50 x 50 mm), appropriately tied and spaced from the roof surface. This system makes the cast screed monolithic and assists the installer when working on sloping roofs.
Before apply the waterproof finish, it is necessary to prepare the surface using one of the two following methods:a. Abrade the surface using an electric sander fitted with an abrasive disk and dust extraction; alternativelyb. Melt the surface polystyrene beads polystyrene beads, using an LPG roofing gas torch.Neither method to be employed until 7 days after the screed has been laid.
WARNINGS AND PRECAUTIONS:· WhenlayingthePoliterm®Bluscreedanyexistingstructuraljointsand/orexpansionjointsinthereceivingsurfacemustbe
maintainedandextendedupthroughthePoliterm®Bluscreed.· Anyremedialactionsinvolvingasbestosfibrecementroofsmustbeperformedstrictlyinaccordancewithanyregulationsin
place.· TheEncapsulationwithPoliterm®Bluscreedonroofsconstructedusingboardsspanningmetalframedstructuresmustonly
beundertakenhavebeenfullyassessedandsanctionedbyastructuralengineertoensurethestructuralintegrityandalsothesafetyaspectsofperformingsuchanoperationintheprovisionofpersonalprotectionequipment,safeaccess,workingplatformsifrequiredandscaffolding.
· Whenrequired,dayjointsinthePoliterm®Bluscreedshouldbecastvertically.· WhencontinuingthepourthedayjointsneedtobetreatedwithEdilstiklatexadhesive,tobeused“freshonfresh”· ThemaximumgradientdependingonthemixstrengthofthePoliterm®Bluisbetween30and40%.· ThePoliterm®Bluscreedneedstobeprotectedfromrainforthefirst48hoursafterlaying.· ThesubsequentlayingofaheavyscreedoverthePoliterm®Bluscreedmaybepossibleafteraperiodof7days.Thisperiodof
timemayneedtobeextendedsubjecttothethicknessofthePoliterm®Bluscreedandweatherconditions.Theinstallationofthewaterproofingmembraneshouldbestrictlyinaccordancewiththeinstructionsofthemembranemanufacturers.TheapplicationofliquidwaterproofingmembranesonPoliterm®Blu,shouldbestrictlyinaccordancewiththeinstructionsofthemembranemanufacturers.SolventbasedliquidmembranesmustnotbeusedonPoliterm®Bluscreeds.
· AvoidmixingandlayingPoliterm®Bluwhentemperaturesarebelow5°C.Anyantifreezeadditivesthatmaybeusedmustbecompatiblewiththephysical‐chemicalpropertiesofPoliterm®Blu.Thecontractorshouldhoweverevaluatethecostsandbe-nefitsofusingantifreezeadditivesonacasebycasebasis.
· WhenmixingPoliterm®Blu,strictlyfollowthedosagesandmethodsindicatedinthetechnicalsheets,ontheproductpacka-gingandinthismanual.OnlythencanEdiltecoguaranteetheresultsandperformanceclaimed.
· It is essential that you contact our Engineering Department when considering any application different from that described in our technical data sheets and our manuals
SPECIAL APPLICATION: ENCAPSULATION OF ROOF SURFACES MADE UP WITH ASBESTOS FIBRE CEMENT BOARDS
Politerm® Blu
WATERPROOFING MEMBRANE:Bituminous precasted hot membrane; bituminous preca-stedcoldmembrane;liquidbituminousmembrane;synthe-ticprecastedmembrane; liquidsyntheticmembrane(con-tact Edilteco Technical Department)
Galvanized mesh
Politerm® Blu thickness 50 mm over the upper wave
WATERPROOFING MEMBRANE:Bituminousprecastedhotmembrane;bituminousprecastedcoldmembra-ne;liquidbituminousmembrane;syntheticprecastedmembrane;liquidsyntheticmembrane(contact Edilteco Technical Department)
Galvanized mesh Coverage in asbestos
Temporary stabilising with Edilstik F.C.A.
19
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
APPLICATION:lightweightthermalinsulatingscreed,madeusingPoliterm®Blubeads,suppliedinbagsof500Land/or200Llaidbyskilledinstallersusingthe single layer method to create a flat close tolerance surface suitable for the direct laying and adhesion of ceramic tiles, stone tiles and pre-polished marble.
INTENDED USE: internalfloors,externalterraces(withorwithoutfalls).
MINIMUM THICKNESS OF POLITERM® SCREED ON ABSORBENT SURFACES: 50 mm iftherearepipesorconduitspresentontherecei-vingsurfacethenthe50mmminimumappliestothethicknessabovethehighestlevelofthosepipesorconduits.Thisthicknessmustbeincreasedto100mmwherethereareseparatinglayerse.g.dampproofmembranes(dpm),vapourcontrollayers(VCL)orslipsheetsthatdebondthePoliterm®BluorPoliterm®BluFeinscreedfromtheexistingslab.Additionallyitwillbenecessarytopla-ceagalvanizedreinforcingmeshsheets(minimumdimensions:thread2mmdiameter,mesh50x50mm)properlytiedtogetherandappropriatelyspacedwithinthelightweightPoliterm®screed.For advice on thicknesses less than those recommended above please contact the Edilteco Technical Department.
MINIMUM THICKNESS OF POLITERM® SCREED ON NON ABSORBENT SURFACES: the minimum thickness of 50 mm is suitable only for the following surfaces:1) Existing floor finish comprising ceramic tiles, marble or similar having first been treated:a) Surfacecleaningtoremovealldemolitionwaste,wax,dust,particlesandanyothermaterialthatmightpreventagoodbond
betweentheexistingfloorsurfaceandnewscreed.b) Applicationofasuitableadhesionpromoter (like Wingrip Evo)tousefollowingtheproducer’sprovisions(indicativeuseonflat
surface:300g/m2,onlyonecoat).c) Afterthedrying(min24hours),layingofthelightweightthermalinsulatingscreedmadeofPoliterm®BluorPoliterm®BluFein,
withminimumdensityof300kg/m3.
2) Existing bituminous waterproof coating having first been treated:a) Surfacecleaningtoremoveallwax,dust,particlesandanyothermaterialthatmightpreventagoodbondbetweentheexisting
floorsurfaceandnewscreed.b) Applicationofasuitableadhesionpromoter(like Wingrip Evo)tousefollowingtheproducer’sprovisions(indicativeuseonflat
surface:300g/m2,onlyonecoat).Afterthedrying(min24hours),layingofthelightweightbasescreedmadeofPoliterm®BluorPoliterm®BluFein,withmini-mumdensityof300kg/m3,installgalvanizedmeshsheets(minimumdimensions:threadø3mm-mesh50x50mm),tiedtogetherandspacedfromthebase.
Note:Foranyothernonabsorbentsurfacestheminimumthicknessofscreedlayeris100mm.BeforelayingofthelightweightthermalinsulatingscreedmadeofPoliterm®BluorPoliterm®BluFein,installgalvanizedreinforcingmeshsheets(minimumdi-mensions:thread3mmdiameter,mesh50x50mm)tiedtogetherandspacedformthebase. Our technical department is available for any questions.
ITEM SPECIFICATION:CreationofthermalinsulatingbaseslabpreparedwithPoliterm®BlumanufacturedbyEdiltecoS.p.A:superli-ghtaggregateinvirginexpandedpolystyrenebeadswithconstantparticlesize(beadsø3/6mmorø2mm-Politerm®BluFein)andwithcontrolleddensity;premixedpearlbypearlwithE.I.A.®additiveintheproductionphase,whichallowsperfectmixingwithwaterbinder,eliminatesthebeadfloatingphenomenonandguaranteestheirhomogeneousdistributioninthemix.Themixcanbebatchedwithadensityof300to350kg/m³usingPortland32.5CemIoCemII,withoutaddinganysandand/orotheradditives.Therefore,everycubicmetreofmortarwillbepreparedonlywith840LofPoliterm®Blubeads,Portland32.5CemIoCemIIcementinthedosagesprescribedandtherelevantvolumeofwaterrequiredforhydration.
InordertoachievetheflatsurfacerequiredtosuccessfullylayceramictilesormarbleonthescreedmadeofPoliterm®BluorPoli-term®BluFeinitwillbenecessarytoplacescreedrailsbeforemixingbegins.ThesearemadeofPVC,are50mmhighandremaininthescreedonceithascuredanddried.Thescreedrailshavetobesetupontheexistingfloorsurfaceandlevelled,packedupwithmortarasrequiredtoensurethatthetopoftherailisatthedesiredfinishedlevelofthePoliterm®BluorPoliterm®BluFeinscreed.Itisrecommendedthatthedistancebetweenscreedrailsshouldnotexceed2.5metres.Todiscussothersuitablealternatives
FlatSingle Layer Screed
FOR DIRECT ADHESION OF CERAMIC TILES, STONE TILES, PRE-POLISHED MARBLE (INTERNAL AND EXTERNAL)
20
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
pleasecontacttheEdiltecoTechnicalDepartment.
OncethescreedrailsaresetinpositionthescreedmadeofPoliterm®BluorPoliterm®BluFeincanbepouredbetweenthem,spre-adandthenlevelledusingastraightedgebladepulledoverthetopedgeofthescreedrails.
On average, once a period of 72 hours has elapsed since pouring and levelling the screed, the surface preparation for tiling can commence:1. Surfaceabrasion,carriedoutwithappropriateequipmentinordertoremoveanyimperfectionscausedbythestraightedge.2. Onareasofthefloorthatthefloorsandercannotreachi.e.theperimeteritwillbenecessarytopreparethoseareaswitha
scrapingknifeortool.3. Surfacecleaningtoremovedust,particlesandanyothermaterialthatmightpreventagoodbondbetweenthenewfloorscreed
surfaceandnextlayer.4. Checkthefinishedlevelandflatnessofthescreedusingaonemetrestraightedge.5. Additionalpreparationworkthatmaybecarriedoutbythecontractor:meltthesurfacepolystyrenebeadsusinganLPGroofing
gastorch,andtoremoveswirlscreatedasaconsequenceofthepolishing.Noneofthesemethodstobeemployeduntil7daysafterthescreedhasbeenlaid.
IfsodesiredaninitialnominalprotectionofthePoliterm®BluorPoliterm®BluFeinbasecanbeemployedbyusingathin(about2mm)protectivesmoothingmortarpreparedasfollows(suitableforinteriors):
Dosage for a cement mixer:· Tileadhesive: 125kg· Cement: 25kg· Sand: about90-120L(2wheelbarrows)· Hydration: hydratetoasemi-fluidconsistencywithamixturecomprising4partsofcleanwaterto 1partofEdilstik latex.· Application: withasmoothmetaltrowel.
Asanalternative,thesmoothingcoatcanbemadeusingpremixedself-levelledsmoothingmortarAutoliv,afterbeingtreatedwithEdilstiklatex,appliedfreshonfresh.Thiscoatedbasescreedwillbesuitableforsubsequentdirectadhesionofceramic,terracotta,stoneware,clinkerandprepolishedmarblefloorcoverings.
EXTERNAL SURFACES: In case of external surfaces, before the application of the final floor layer make a suitable waterproofing (bitumi-nous Wingrip use is recommended according the producer’s provisions).
The base screed will have the following characteristics:
FORMULA 300 350
Densityafter28dayskg/m3 approx.315 approx.365
ThermalconductivityλD W/mK 0,080 0,103
CompressivestrenghtN/mm2 1,61 1,69
FlexuralstrenghtN/mm2 0,95 0,59
CohesionkPa 127,17 n.a.
Hot-sealedmembraneruptureN/50mm 62 n.a.
Cold-sealedmembraneruptureN/50mm 47 n.a.
ElasticitymoduleN/mm2 551,1 n.a.
Permeabilitytowatervapourμ 7,2 9,2
SpecificheatJ/kgK 1000* 1000*
Shrinkage(NBN)mm/m 0,352 0,270
Acoustic performance ΔLw
26dB** n.a.
ImpactnoiseinsulationL’nT,W
n.a. n.a.
Fire reactivity class A2-s1,d0
*1000J/kgK=0,24kcal/kgK/**Valueobtainedinlaboratorywith7cmofPoliterm®Blu+Fonotech5
21
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
WARNINGS AND PRECAUTIONS:· WhenlayingthePoliterm®Bluscreedanyexistingstructuraljointsand/orexpansionjointsinthereceivingsurfacemustbe
maintainedandextendedupthroughthePoliterm®Bluscreed.· IfacousticmatsorlayersaretobeincorporatedintotheconstructionbeneaththePoliterm®Bluscreedlaidusingthesingle
layermethodthentheseacoustic layersshouldbe installedbeneath,notover,anypipesorconduitstherebyavoidingthepossibilityofcreatingairpocketswhichcouldhavetheeffectsoflesseningtheacousticperformanceandalsothestructuralintegrityofthePoliterm®Bluscreed.
· BeforelayingthePoliterm®Bluscreed,thoroughlycleanthereceivingsurface.· AftercleaningofthescreedsurfaceandbeforelayingthescreedpreparedwithPoliterm®Blu,wetthefloorwellbutwithout
leavingpuddles.Whenlayingonanonporousorwaterproofsurfacelikeplasticsheetingoverinsulationboards,waterprooflayersortiledfloorsdonotwetthesurface.
· Whenrequired,dayjointsinthePoliterm®Bluscreedshouldbecastvertically.· WhencontinuingthepourthedayjointsneedtobetreatedwithEdilstiklatexadhesive,tobeused“freshonfresh”.· Whenadheringfinalfinishsurfaces likeceramictilesorvinyls, ifasmoothing layer isnotappliedthentheconsumptionof
adhesivemaybe20%greaterthannormal.Thisisduetotheopencellsthatremainaftersurfacebeadshavebeenremoved.Thisdoeshoweverprovideastrongermechanicalbondbetweenthelayers.
· Theadhesivesmustbeusedstrictlyinaccordancewiththeinstructionsoftheadhesivemanufacturers.· Installingplasterboardpartitions:beforeinstallingplasterboardpartitionsdirectlyonSinglelayerscreedsmadewithPoliterm®
Blu‐orwithPoliterm®BluFein,firstapplyasmoothingplaster(thickness2mm).Thesmoothingplastermustcoveranareaequaltothewidthofthefloorplatesplus50mmeachside.Subsequently,thefloorplatescanbeinstalledusingspecialdou-ble-sidedadhesivetape.
· AvoidmixingandlayingPoliterm®Bluwhentemperaturesarebelow5°C.AnyantifreezeadditivesthatmaybeusedmustbeiscompatiblewiththephysicalchemicalpropertiesofPoliterm®Blu.Thecontractorshouldhoweverevaluatethecostsandbenefitsofusingantifreezeadditivesonacasebycasebasis.
· WhenmixingPoliterm®Blu,strictlyfollowthedosagesandmethodsindicatedinthetechnicalsheets,theproductpackagingandinthismanual.OnlythencanEdiltecoguaranteetheresultsandperformanceclaimed.
· It is essential that you contact our Engineering Department when considering any application different from that described in our technical data sheets and our manuals.
INTER FLOOR: LIGHTWEIGHT THERMAL INSULATIN SINGLE LAYER FOR CERAMIT FLOOR
MasterPiano zero / Flat
FLOORING FIXED WITH GLUE:ceramic-prepolishedmarble
Politerm® Blu
Sound insulating band
Slab
Water pipes/electric cables
TERRACE AND BALCONY: LIGHTWEIGHT THERMAL INSULATING SINGLE LAYER
MasterPiano zero / Flat
FLOORING:ceramic - marble
Soundinsulating band
Politerm® Blu
WATERPROOFING MEMBRANE SUITABLE FOR THE GLUING OF THE FINISHED FLOOR·liquidmembrane·precastedmembrane
Slab
Water pipes / electric cables
22
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
APPLICATION:lightweightthermalinsulatingscreed,madeusingPoliterm®Blubeads,suppliedinbagsof500Land/or200Llaidbyskilledinstallersusingthe single layer method to create a flat close tolerance surface suitable for the direct laying and adhesion of ceramic tiles, stone tiles and pre-polished marble.
INTENDED USE: Internalfloors,externalterraces(withorwithoutfalls),fillingofvolumes,corrugatedsheetlofts,etc..
MINIMUM THICKNESS OF POLITERM® SCREED ON ABSORBENT SURFACES: 50 mm. Iftherearepipesorconduitspresentontherecei-vingsurfacethenthe50mmminimumappliestothethicknessabovethehighestlevelofthosepipesorconduits.Thisthicknessmustbeincreasedto100mmwherethereareseparatinglayerse.g.dampproofmembranes(dpm),vapourcontrollayers(VCL)orslipsheetsthatdebondthePoliterm®BluorPoliterm®BluFeinscreedfromtheexistingslab.Additionallyitwillbenecessarytoplaceagalvanizedreinforcingmeshsheets(minimumdimensions:thread2mmdiameter,mesh50x50mm)properlytiedtogether,andappropriatelyspacedwithinthelightweightPoliterm®screed.For advice on thicknesses less than those recommended above please contact the Edilteco Technical Department.
MINIMUM THICKNESS OF POLITERM® SCREED ON NON ABSORBENT SURFACES: the minimum thickness of 50 mm is suitable only for the following surfaces:1) Existing floor finish comprising ceramic tiles, marble or similar having first been treated:a) Surfacecleaningtoremoveallwax,dust,particlesandanyothermaterialthatmightpreventagoodbondbetweentheexisting
floorsurfaceandnewscreed.b) Applicationofasuitableadhesionpromoter(like Wingrip Evo)tousefollowingtheproducer’sprovisions(indicativeuseonflat
surface:300g/m2,onlyonecoat).c) WhiletheadhesiveisstilltackypourthelightweightscreedmadeofPoliterm®BluorPoliterm®BluFein,withaminimumden-
sityof300kg/m3,
2) Existing floor coated with a bituminous waterproofing layer:a) Surfacecleaningtoremoveallwax,dust,particlesandanyothermaterialthatmightpreventagoodbondbetweentheexisting
floorsurfaceandnewscreed.b) Applicationofasuitableadhesionpromoter(like Wingrip Evo) tousefollowingtheproducer’sprovisions(indicativeuseonflat
surface:300g/m2,onlyonecoat).Afterthedrying(min24hours),layingofthelightweightbasescreedmadeofPoliterm®BluorPoliterm®BluFein,withmini-mumdensityof300kg/m3,installgalvanizedmeshsheets(minimumdimensions:threadø3mm-mesh50x50mm),tiedtogetherandspacedfromthebase.
Note.Foranyothernonabsorbentsurfacestheminimumthicknessofscreedlayeris100mm.BeforelayingofthelightweightthermalinsulatingscreedmadeofPoliterm®BluorPoliterm®BluFein,installgalvanizedreinforcingmeshsheets(minimumdi-mensions:thread3mmdiameter,mesh50x50mm)tiedtogetherandspacedformthebase.Our technical department is available for any questions.
ITEM SPECIFICATION:“CreationofthermalinsulatingbaseslabpreparedwithPoliterm®BlumanufacturedbyEdiltecoS.p.A:super-lightaggregateinvirginexpandedpolystyrenebeadswithconstantparticlesize(beadsø3/6mmorø2mm-Politerm®BluFein)andwithcontrolleddensity;premixedpearlbypearlwithE.I.A.®additiveintheproductionphase,whichallowsperfectmixingwithwaterbinder,eliminatesthebeadfloatingphenomenonandguaranteestheirhomogeneousdistributioninthemix.Themixcanbebatchedwithadensityof300to350kg/m³usingPortland32.5CemIoCemII,withoutaddinganysandand/orotheradditives.Therefore,everycubicmetreofmortarwillbepreparedonlywith840LofPoliterm®Blubeads,Portland32.5CemIoCemIIcementinthedosagesprescribedandtherelevantvolumeofwaterrequiredforhydration.
BeforethemixingandtheapplicationofthebasesceedmadeofPoliterm®Blu,proceedwiththeapplicationofthespecificPVCthrowawayguides,namedPianoZero(height:50mm).Thescreedrailshavetobesetuponthededucedfloorsurfacelevel,thefinalfloorlayerthickness,therelativeglueandtheirplantplacement,thatwillbemadeaccordingtodimensionsandspace.Itisrecommendedthatthedistancebetweenthescreedrailsshouldnotexceed2,50mt.Todiscussothersuitablealternativesforte
FlatSingle Layer
FOR DIRECT ADHESION OF CERAMIC TILES, STONE TILES, PRE-POLISHED MARBLEon thin-bed cement smoothing mortar
23
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
realizationoflevelstrips,pleasecontacttheEdiltecotechnicaldepartiment.Thescreedrailsmustbesetonthebasewiththetopoftherailssetattherequiredfinishedfloorlevelbutallowingfor:1. Thethicknessofthecementitioussmoothinglayeratlowthickness.2. Thethickessofthefinalfloorfinshlayerandtheadhesivelayerthatsecuresit.
ThesubsequentapplicationofthemortarmadeofPoliterm®Blu,willrequirethematerialspredingthroughthesalt(itisreccomen-dedtheuseofacuttingfloat)followingthePiano Zero guides.
Onaverage,onceaperiodof72hourshaselapsedsincepouringandlevellingthescreed,thesurfacepreparationfortilingcancommence:1. Surfaceabrasion,carriedoutwithappropriateequipmentinordertoremoveanyimperfectionscausedbythestraightedge.2. Onareasofthefloorthatthefloorsandercannotreachi.e.theperimeteritwillbenecessarytopreparethoseareaswitha
scrapingknifeortool.3. Surfacecleaningtoremovedust,particlesandanyothermaterialthatmightpreventagoodbondbetweenthenewfloorscreed
surfaceandnextlayer.4. Checkthefinishedlevelandflatnessofthescreedusingaonemetrestraightedge.5. Additionalpreparationworkthatmaybecarriedoutbythecontractor:meltthesurfacepolystyrenebeadsusinganLPGroofing
gastorch,andtoremoveswirlscreatedasaconsequenceofthepolishing.Noneofthesemethodstobeemployeduntil7daysafterthescreedhasbeenlaid.
6. Thethin-bedcementsmoothingmortar(2mm)maybeappliedusingoneofthetwofollowingmethods:a. Self levellingpremixedmortarAutoliv(seethespecifictechnicaldatasheet),afterthetreatingthesurfaceusing“freshon
fresh”methodwithEdilstik.b. Mortarmixedonsite.
Dosaggio per una betoniera:· Tileadhesive:: 125kg· Cement: 25kg· Sand: about90-120L(2wheelbarrows)· Hydration: hydratetoasemi-fluidconsistencywithamixturecomprising4partsofcleanwaterto 1partofEdilstik latex.· Application: Withasmoothmetaltrowel.
Analternative,thesmoothingcoatcanbemadeusingpremixedself-levelledsmoothingmortarAutoliv.Thiscoatedbasescreedwillbesuitableforsubsequentdirectadhesionofceramic,terracotta,stoneware,clinkerandprepolishedmarblefloorcoverings.Waitatleast7daysfromlayingthebasescreedbeforelayingthefloorcovering.Checkingthatitiscuredanddry.
The base screed will have the following characteristics:
FORMULA 300 350
Densityafter28dayskg/m3 approx.315 approx.365
ThermalconductivityλD W/mK 0,080 0,103
CompressivestrenghtN/mm2 1,61 1,69
FlexuralstrenghtN/mm2 0,95 0,59
CohesionkPa 127,17 n.a.
Hot-sealedmembraneruptureN/50mm 62 n.a.
Cold-sealedmembraneruptureN/50mm 47 n.a.
ElasticitymoduleN/mm2 551,1 n.a.
Permeabilitytowatervapourμ 7,2 9,2
SpecificheatJ/kgK 1000* 1000*
Shrinkage(NBN)mm/m 0,352 0,270
Acoustic performance ΔLw
26dB** n.a.
ImpactnoiseinsulationL’nT,W
n.a. n.a.
Fire reactivity class A2-s1,d0
*1000J/kgK=0,24kcal/kgK/**Valueobtainedinlaboratorywith7cmofPoliterm®Blu+Fonotech5
24
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
WARNINGS AND PRECAUTIONS:· WhenlayingthePoliterm®Bluscreedanyexistingstructuraljointsand/orexpansionjointsinthereceivingsurfacemustbe
maintainedandextendedupthroughthePoliterm®Bluscreed.· IfacousticmatsorlayersaretobeincorporatedintotheconstructionbeneaththePoliterm®Bluscreedlaidusingthesingle
layermethodthentheseacoustic layersshouldbe installedbeneath,notover,anypipesorconduitstherebyavoidingthepossibilityofcreatingairpocketswhichcouldhavetheeffectsoflesseningtheacousticperformanceandalsothestructuralintegrityofthePoliterm®BluscreedBeforelayingthePoliterm®Bluscreed,thoroughlycleanthereceivingsurface.
· AftercleaningofthescreedsurfaceandbeforelayingthescreedpreparedwithPoliterm®Blu,wetthefloorwellbutwithoutleavingpuddles.Whenlayingonanonporousorwaterproofsurfacelikeplasticsheetingoverinsulationboards,waterprooflayersortiledfloorsdonotwetthesurface.
· Whenrequired,dayjointsinthePoliterm®Bluscreedshouldbecastvertically.· WhencontinuingthepourthedayjointsneedtobetreatedwithEdilstiklatexadhesive,tobeused“freshonfresh”.· AvoidmixingandlayingPoliterm®Bluwhentemperaturesarebelow5°C.Anyantifreezeadditivesthatmaybeusedmustbe
iscompatiblewiththephysicalchemicalpropertiesofPoliterm®Blu.Thecontractorshouldhoweverevaluatethecostsandbenefitsofusingantifreezeadditivesonacasebycasebasis.
· WhenmixingPoliterm®Blu,strictlyfollowthedosagesandmethodsindicatedinthetechnicalsheets,theproductpackagingandinthismanual.OnlythencanEdiltecoguaranteetheresultsandperformanceclaimed.
· It is essential that you contact our Engineering Department when considering any application different from that described in our technical data sheets and our manuals.
INTER FLOOR: LIGHTWEIGHT THERMAL INSULATIN SINGLE LAYERWITH PROTECTIVE LOW THICKNESS SMOOTHING
FLOORING: ceramic-marble
Politerm® Blu
Slab
Soundinsulating band
Water pipes / electric cables
MasterPiano zero / Flat
Low thickness smoothing 2 mm made with Autoliv
25
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
FlatSingle Layer Screed
FOR PARQUET FLOORING AND MARBLE TO BE POLISHED ON SITE LAID ON A THIN BED COATING
APPLICATION:lightweightthermalinsulatingscreed,madeusingPoliterm®Blubeads,suppliedinbagsof500Land/or200Llaidbyskilledinstallersusingthe single layer method to create a flat close tolerance surface suitable for the direct laying and adhesion of ceramic tiles, stone tiles and pre-polished marble.
INTENDED USE: internalfloors,externalterraces(withorwithoutfalls).
MINIMUM THICKNESS OF POLITERM® SCREED ON ABSORBENT SURFACES: 55 mm iftherearepipesorconduitspresentontherecei-vingsurfacethenthe50mmminimumappliestothethicknessabovethehighestlevelofthosepipesorconduits.Thisthicknessmustbeincreasedto105mmwherethereareseparatinglayerse.g.dampproofmembranes(dpm),vapourcontrollayers(VCL)orslipsheetsthatdebondthePoliterm®BluorPoliterm®BluFeinscreedfromtheexistingslab.Additionallyitwillbenecessarytopla-ceagalvanizedreinforcingmeshsheets(minimumdimensions:thread2mmdiameter,mesh50x50mm)properlytiedtogether,andappropriatelyspacedwithinthelightweightPoliterm®screed.For advice on thicknesses less than those recommended above please contact the Edilteco Technical Department.
MINIMUM THICKNESS OF POLITERM® SCREED ON NON ABSORBENT SURFACES: the minimum thickness of 55 mm including the thick-ness of the cement section (minimum 5 mm) is suitable only for the following surfaces, is suitable only for the following surfaces:1) Existing floor finish comprising ceramic tiles, marble or similar having first been treated:a) Surfacecleaningtoremoveallwax,dust,particlesandanyothermaterialthatmightpreventagoodbondbetweentheexisting
floorsurfaceandnewscreed.b) Applicationofasuitableadhesionpromoter(like Wingrip Evo)tousefollowingtheproducer’sprovisions(indicativeuseonflat
surface:300g/m2,onlyonecoat).c) Afterthedrying(min24hours),layingofthelightweightthermalinsulatingscreedmadeofPoliterm®BluorPoliterm®BluFein,
withminimumdensityof300kg/m3.
2) Existing bituminous waterproof coating having first been treated: a) Surfacecleaningtoremoveallwax,dust,particlesandanyothermaterialthatmightpreventagoodbondbetweentheexisting
floorsurfaceandnewscreed.b) Applicationofasuitableadhesionpromoter(like Wingrip Evo)tousefollowingtheproducer’sprovisions(indicativeuseonflat
surface:300g/m2,onlyonecoat).Afterthedrying(min24hours),layingofthelightweightbasescreedmadeofPoliterm®BluorPoliterm®BluFein,withmini-mumdensityof300kg/m3,installgalvanizedmeshsheets(minimumdimensions:threadø3mm-mesh50x50mm),tiedtogetherandspacedfromthebase.
Note.Foranyothernonabsorbentsurfacestheminimumthicknessofscreedlayeris100mm.BeforelayingofthelightweightthermalinsulatingscreedmadeofPoliterm®BluorPoliterm®BluFein,installgalvanizedreinforcingmeshsheets(minimumdi-mensions:threadø 3mmdiameter,mesh50x50mm)tiedtogetherandspacedformthebase.Our technical department is available for any questions.
ITEM SPECIFICATION: CreationofthermalinsulatingbaseslabpreparedwithPoliterm®BlumanufacturedbyEdiltecoS.p.A.:super-lightaggregateinvirginexpandedpolystyrenebeadswithconstantparticlesize(beadsø3/6mmorø2mm-Politerm®BluFein)andwithcontrolleddensity;premixedpearlbypearlwithE.I.A.®additiveintheproductionphase,whichallowsperfectmixingwithwaterbinder,eliminatesthebeadfloatingphenomenonandguaranteestheirhomogeneousdistributioninthemix.Themixcanbebatchedwithadensityof300to350kg/m³usingPortland32.5CemIoCemII,withoutaddinganysandand/orotheradditives.Therefore,everycubicmetreofmortarwillbepreparedonlywith840LofPoliterm®Blubeads,Portland32.5CemIoCemIIcementinthedosagesprescribedandtherelevantvolumeofwaterrequiredforhydration.
InordertoachievetheflatsurfacerequiredtosuccessfullylayceramictilesormarbleonthescreedmadeofPoliterm®BluorPoli-term®BluFeinitwillbenecessarytoplacescreedrailsbeforemixingbegins.ThesearemadeofPVC,are50mmhighandremaininthescreedonceithascuredanddried.Thescreedrailshavetobesetupontheexistingfloorsurfaceandlevelled,packedupwithmortarasrequiredtoensurethatthetopoftherailisatthedesiredfinishedlevelofthePoliterm®BluorPoliterm®BluFeinscreed.
26
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
Itisrecommendedthatthedistancebetweenscreedrailsshouldnotexceed2.5metres.To discuss other suitable alternatives please contact the Edilteco Technical Department.The screed rails must be set on the base with the top of the rails set at the required finished floor level but allowing for:1. The thickness of the cementitious coating layer (minimum 5 mm);2. Thethicknessesofthefinalfloorfinishlayer(tiles,marble,engineeredwoodetc.)andtheadhesivelayerthatsecuresit.
OncethescreedrailsaresetinpositionthescreedmadeofPoliterm®BluorPoliterm®BluFeincanbepouredbetweenthem,spre-adandthenlevelledusingastraightedgebladepulledoverthetopedgeofthescreedrails.
On average, once a period of 72 hours has elapsed since pouring and levelling the screed, the surface preparation for tiling can commence: 1. Surfaceabrasion,carriedoutwithappropriateequipmentinordertoremoveanyimperfectionscausedbythestraightedge.2. Onareasofthefloorthatthefloorsandercannotreachi.e.theperimeteritwillbenecessarytopreparethoseareaswitha
scrapingknifeortool.3. Surfacecleaningtoremovedust,particlesandanyothermaterialthatmightpreventagoodbondbetweenthenewfloorscreed
surfaceandnextlayer.4. Checkthefinishedlevelandflatnessofthescreedusingaonemetrestraightedge.5. Additionalpreparationworkthatmaybecarriedoutbythecontractor:MeltthesurfacepolystyrenebeadsusinganLPGroofing
gastorch,andtoremoveswirlscreatedasaconsequenceofthepolishing.None of these methods to be employed until 7 days after the screed has been laid.
6. Thethinbedmortarcanbeprepared,withaminimumthicknessof5mmusingtheselflevellingpremixmortarAutoliv(seethespecifictechnicaldatasheet).Note.TheapplicationofAutolivispossibleonlyonabasewithamoisturecontentnotexceeding2%involume(measuredwithacalciumcarbideinstrument,seealsothetechnicalspecification)andalsoafterthetreatmentofthesurfacewithEdilstikusingthe“freshonfresh”method.
Thisthin-coatedbasescreedwillbesuitableforsubsequentdirectadhesionofceramic,terracotta,stoneware,clinkerandprepo-lishedmarblefloorcoverings.Waitatleast7daysfromlayingthebasescreedbeforelayingthefloorcovering,checkingthatitiscuredanddry.
The base screed will have the following characteristics:
WARNINGS AND PRECAUTIONS:· ScreedsmadewithPoliterm®Bluand“PianoZero”system,arenotcomparabletothetraditionalsand-cementscreeds.Inpar-
ticular,thewaterabsorptionisparticularlyreduced.Becauseofthis,itisnecessarytobeextremelycarefulinselectingadhe-sivesforparquetormarble.Waterbasedadhesivesarenotrecommended,sincesuchwaterwon’tbeabsorbedbythescreedandtheriskofbulgesand/ordelaminationishigh.
· IfacousticmatsorlayersaretobeincorporatedintotheconstructionbeneaththePoliterm®Bluscreedlaidusingthesinglelayermethodthentheseacoustic layersshouldbe installedbeneath,notover,anypipesorconduitstherebyavoidingthepossibilityofcreatingairpocketswhichcouldhavetheeffectsoflesseningtheacousticperformanceandalsothestructuralintegrityofthePoliterm®Bluscreed.
· Whenrequired,dayjointsinthePoliterm®Bluscreedshouldbecastvertically.
FORMULA 300 350
Densityafter28dayskg/m3 approx.315 approx.365
ThermalconductivityλD W/mK 0,080 0,103
CompressivestrenghtN/mm2 1,61 1,69
FlexuralstrenghtN/mm2 0,95 0,59
CohesionkPa 127,17 n.a.
Hot-sealedmembraneruptureN/50mm 62 n.a.
Cold-sealedmembraneruptureN/50mm 47 n.a.
ElasticitymoduleN/mm2 551,1 n.a.
Permeabilitytowatervapourμ 7,2 9,2
SpecificheatJ/kgK 1000* 1000*
Shrinkage(NBN)mm/m 0,352 0,270
Acoustic performance ΔLw
26dB** n.a.
ImpactnoiseinsulationL’nT,W
n.a. n.a.
Fire reactivity class A2-s1,d0
*1000J/kgK=0,24kcal/kgK/**Valueobtainedinlaboratorywith7cmofPoliterm®Blu+Fonotech5
27
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
· WhencontinuingthepourthedayjointsneedtobetreatedwithEdilstiklatexadhesive,tobeused“freshonfresh”.· Thenormallayingofparquetflooringrequiresskillwithgreatcareandattentiontodetail.Itisexactlythesamewhenlaying
parquetflooringonapreparedPoliterm®Bluscreed. Following is a list of important instructions, these are guides and the list is not exhaustive:· Takecaretoconditiontheparquettiles,roombyroom,startingatleast8daysbeforeitsinstallationbegins.· Protecttheroomsandfloorsfromadverseconditions,atleast30daysbeforetheinstallationbegins.· Turnontheheatingsystematleast8daysbeforetheinstallationoftheparquetflooring.· Checkthemoisturecontentofthebasescreedandalsotheinternalenvironmentimmediatelybeforethestartingofthein-
stallation,inordertoestablishtheidealconditionforlayingtheparquetflooring(seealsothe“measurementofthemoisturecontentofalightbasemadewithPoliterm®Blu).
· Waterbasedadhesivesmustnotbeused.· Installtheparquetattheminimumdistanceof8mmfromwallsandanyotherpartswhichmayobstaclethenaturaldeforma-
tionofthewooditself.Allowanexpansiongapof8mmbetweentheparquetfloortilesandwallsanyotherfixedelementthatmayobstructmovement.
Consider what mentioned above, being understood any other precaution due to the rule of art.· WhenlayingthePoliterm®Bluscreedanyexistingstructuraljointsand/orexpansionjointsinthereceivingsurfacemustbe
maintainedandextendedupthroughthePoliterm®Bluscreed.· BeforelayingthePoliterm®Bluscreed,thoroughlycleanthereceivingsurface.· AftercleaningofthescreedsurfaceandbeforelayingthescreedpreparedwithPoliterm®Blu,wetthefloorwellbutwithout
leavingpuddles.Whenlayingonanonporousorwaterproofsurfacelikeplasticsheetingoverinsulationboards,waterprooflayersortiledfloorsdonotwetthesurface.
· Theadhesivesmustbeusedstrictlyinaccordancewiththeinstructionsoftheadhesivemanufacturers.· AvoidmixingandlayingPoliterm®Bluwhentemperaturesarebelow5°C.Anyantifreezeadditivesthatmaybeusedmustbe
compatiblewiththephysical‐chemicalpropertiesofPoliterm®Blu.Thecontractorshouldhoweverevaluatethecostsandbe-nefitsofusingantifreezeadditivesonacasebycasebasis.
· WhenmixingPoliterm®Blu,strictlyfollowthedosagesandmethodsindicatedinthetechnicalsheets,ontheproductpacka-gingandinthismanual.OnlythencanEdiltecoguaranteetheresultsandperformanceclaimed.
· It is essential that you contact our Engineering Department when considering any application different from that described in our technical data sheets and our manuals.
MEASURING THE MOISTURE CONTENT OF LIGHTWEIGHT SCREEDS MADE USING POLITERM® BLU
Inordertoestablishthemoisturecontentofthescreeditwillbenecessarytomeasuretheamountofwaterpresentinaselectedsample.ThemethodemployedistheHOECHSTsystem.Thismethodisbasedontheuseofacalciumcarbidehygrometeronsite.Beforeproceedingwiththemeasurements, it isnecessaryto identifytheareasfromwheretotakesamples.Foreachsampletakenitisnecessarytonotethemeansoftakingthesample(thetypeofinstrumentsusedandthequantityofmaterialtaken)plusanyotherkindofinformationsuchasdatethesamplewastaken,theenvironmentalconditions,temperatureandhumidity.Bycarefullynotingalltheseconditions, itallowsapropercomparisonbetweendifferenttestsconductedatdifferenttimesbydifferentoperators.TheHoechstsystemformeasuringofmoisturecontentusesacalciumcarbidehygrometer,generallysoldasakit,comprising:abottleshapedcontainerwithabuiltingaspressuregauge,aboxwithvialsofcalciumcarbide,steelpulverisingballs,asetofpreci-siontestingscalesforweighingthesampleandotheraccessoriessuchasabrushtocleanthecontainerandchiselsforbreakingoutthesamplefromthescreedsurface.Theprocessissimple:measurethepressureexertedbythegasdevelopedbythereactionbetweencalciumcarbideandthewatercontainedinthesample.Accordingtoaparticularchemicalreactioncalciumcarbide(CaC2)andwaterproduceacertainamountofacetylene(C2H2)whiledevelopingacertainpressuremeasuredbythepressuregaugeinthetopofthecontainer.Basedonthepressureexertedandtheweightofthematerialitispossibletocalculatethepercentageofmoisturecontainedinthesample.Thetooliseasytouseandthemeasurementsobtainedareconsideredreliable.However,themostcriticalissueisthatthesamplingiscarriedoutcarefully.Thesamplescreedmaterialmustbetakenandfinelycrushedusingthemortarsupplied.Thesampleisthenweighedusingtestingscalessupplied,andtheninsertedintothebottletogetherwiththepulverisingsteelballsandthevialofcalciumcarbide.Shakingthecontainer,closedwiththecappressuregauge,thesteelballsbreaktheampouleofcalciumcarbide.Thenthereactionstartswhichendsatthemomentwhenonereadsaconstantpressureonthepressuregauge(usuallyafterabouttenminutes).Becausethereactionoccursinaclosedenvironment,asmoregasisformed,thehigherbecomesthepressurewhichismeasuredwiththepressuregauge.Thereactionofcalciumcarbideincontactwithwaterproducesanexplosivemixtureofair/acetyleneinsidethecylinder.There-fore,allpossiblesourcesofignitionshouldberemovedbeforeemptyingthecylinder.Ifpossiblethecylindershouldbeopenedoutdoors.Theinstrumentusedformeasuringthetemperatureandrelativehumidityoftheenvironmentatthetimeofsamplingandtestingisapsychometricbulb.Theinstrumentmustbeplaced,laidflat,intheareawhereyouwanttodeterminetheafore-mentionedparameters.Thepanatthebasemustbefilledwithdistilledwaterwhichhastobeincontactwithoneofthetwother-mometers(viaasockmadeofabsorbentmaterial).Byreadingthethermometerdryandthenreadingthewetthermometerthedifferencebetweenthetwomeasurementscanbeusedtoobtainavaluefromwhich,usinganappropriategraduatedscalecanbedeterminedtherelativehumidityoftheair.
28
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
ItisimportanttonotethatwhenperformingthesemeasurementsonabasescreedmadefromthelightweightmortarpreparedwithPoliterm®BluorPoliterm®BluFein,orabasescreedmadeusingaproductfromthelightweightpremixedIsolcaprangevalueobtainedbyusingthecalciumcarbidemethodhastobedividedby5or6dependingontheamountofcementbinderusedinthepreparationofthescreed.ThisisbecausethevolumetricmassofthePoliterm®Blueisone-fifthoronesixthofthemassofanormalsand-cementscreed.
Iftheamountofthecementbinderis300kg/m3themeasurementreadonthemanometermustbedividedby6;·Iftheamountofthecementbinderis350kg/m3themeasuringgaugereadingisdividedby5;·Theoptimalmeasureisobtainedwithasampleof20g.
Moisturecontentmeasuredusingthecarbidemethodisvalidonlyifyouareusingaproductmadeexclusivelywithvirginpoly-styrenebeads(whichisthecaseforPoliterm®BluandIsolcap,init’svarioustypes).Conductingthistestonscreedsmadeusinggroundorrecycledpolystyrenegranules,makesthemeasurementunreliablesincewaterremainsinsidegranulesofthemilledpolystyrene,therebydistortingthefinalmeasure.Ifyouapplyotherscreeds(sandandcement,self-leveling,etc...)ontopofthebasepreparedfromPoliterm®BluorPoliterm®BluFein,orabasescreedmadeusingaproductfromthelightweightpremixedIsol-caprangethemeasurementisperformedatthepartbeingthetwomaterialsdifferentincompositionandcharacteristics.
INTER FLOOR: LIGHTWEIGHT THERMAL INSULATIN SINGLE LAYERWITH PROTECTIVE LOW THICKNESS SMOOTHING
FLOORING: ceramic-marble-parquet
Politerm® Blu
Slab
Soundinsulating band
Water pipes / electric cables
Guida Piano Zero
low thickness smoothing 5 mm made with Autoliv
29
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
APPLICATION:lightweightthermalinsulatingscreed,madeusingPoliterm®Blubeads,suppliedinbagsof500Land/or200L,laidbyskil-ledinstallersusingthesinglelayermethodformediumthicknessscreedstocreateaflatclosetolerancesurfacesuitableforthedirectlayingandadhesionofflexibleflooringsuchaslinoleum,PVC,rubber,moquetteetc.
INTENDED USE:internalfloors,externalterraces(withorwithoutfalls).
MINIMUM THICKNESS OF POLITERM® SCREED ON ABSORBENT SURFACES: 70 mm including the thickness of the cement section (mini-mum 20 mm).Iftherearepipesorconduitspresentonthereceivingsurfacethenthe70mmminimumappliestothethicknessabovethehighestlevelofthosepipesorconduits.Thisthicknessmustbeincreasedto120mmincludingthethicknessofthecementsection(minimum20mm) wherethereareseparatinglayerse.g.dampproofmembranes(dpm),vapourcontrollayers(VCL)orslipsheetsthatdebondthePoliterm®BluorPoliterm®BluFeinscreedfromtheexistingslab.Additionallyitwillbenecessarytoplaceagalvanizedrein-forcingmeshsheets(minimumdimensions:thread2mmdiameter,mesh50x50mm)properlytiedtogether,andappropriatelyspacedwithinthe lightweightPoliterm®screed.For advice on thicknesses less than those recommended above please contact the Edilteco Technical Department.
MINIMUM THICKNESS OF POLITERM® SCREED ON NON ABSORBENT SURFACES: the minimum thickness of 70 mm is suitable only for the following surfaces:1) Existing floor finish comprising ceramic tiles, marble or similar having first been treated:a) Surfacecleaningtoremoveallwax,dust,particlesandanyothermaterialthatmightpreventagoodbondbetweentheexistingfloor
surfaceandnewscreed.b) Applicationofasuitableadhesionpromoter(like Wingrip Evo)tousefollowingtheproducer’sprovisions(indicativeuseonflat
surface:300g/m2,onlyonecoat).c) Afterthedrying(min24hours),layingofthelightweightthermalinsulatingscreedmadeofPoliterm®BluorPoliterm®BluFein,with
minimumdensityof300kg/m3.
2) Existing bituminous waterproof coating having first been treated: a) Surfacecleaningtoremoveallwax,dust,particlesandanyothermaterialthatmightpreventagoodbondbetweentheexistingfloor
surfaceandnewscreed.b) Applicationofasuitableadhesionpromoter(like Wingrip Evo)tousefollowingtheproducer’sprovisions(indicativeuseonflat
surface:300g/m2,onlyonecoat).Afterthedrying(min24hours),layingofthelightweightbasescreedmadeofPoliterm®BluorPoliterm®BluFein,withmini-mumdensityof300kg/m3,installgalvanizedmeshsheets(minimumdimensions:threadø3mm-mesh50x50mm),tiedtogetherandspacedfromthebase.
Note.Foranyothernonabsorbentsurfacestheminimumthicknessofscreedlayeris100mm.BeforelayingofthelightweightthermalinsulatingscreedmadeofPoliterm®BluorPoliterm®BluFein,installgalvanizedreinforcingmeshsheets(minimumdimensions:threadø 3mmdiameter,mesh50x50mm)tiedtogetherandspacedformthebase.Our technical department is available for any questions.
ITEM SPECIFICATION:Creationofthermal insulatingbaseslabpreparedwithPoliterm®BlumanufacturedbyEdiltecoS.p.A.:superlightaggregateinvirginexpandedpolystyrenebeadswithconstantparticlesize(beadsø3/6mmorø2mm-Politerm®BluFein)andwithcontrolleddensity;premixedpearlbypearlwithE.I.A.®additiveintheproductionphase,whichallowsperfectmixingwithwaterbinder,eliminatesthebeadfloatingphenomenonandguaranteestheirhomogeneousdistributioninthemix.Themixcanbebatchedwithadensityof300to350kg/m³ofusingPortland32.5CemIoCemII,withoutaddinganysandand/orotheradditives.Therefore,everycubicmetreofmortarwillbepreparedonlywith840LofPoliterm®Blubeads,Portland32.5CemIoCemIIcementinthedosagesprescribedandtherelevantvolumeofwaterrequiredforhydration.
InordertoachievetheflatsurfacerequiredtosuccessfullylayceramictilesormarbleonthescreedmadeofPoliterm®BluorPoliterm®BluFeinitwillbenecessarytoplacescreedrailsbeforemixingbegins.ThesearemadeofPVC,are50mmhighandremaininthescreedonceithascuredanddried.Thescreedrailshavetobesetupontheexistingfloorsurfaceandlevelled,packedupwithmortarasrequiredtoensurethatthetopoftherailisatthedesiredfinishedlevelofthePoliterm®BluorPoliterm®BluFeinscreed.Itisrecommendedthatthe
FlatSingle Layer Screed
FOR LAYING FLEXIBLE FLOOR COVERINGS ON A MEDIUM THICKNESS BASE
30
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
distancebetweenscreedrailsshouldnotexceed2.5metres.To discuss other suitable alternatives please contact the Edilteco Technical Department.Thescreedrailsmustbesetonthebasewiththetopoftherailssetattherequiredfinishedfloorlevelbutallowingfor:1. The thickness of the cementitious coating layer (minimum 20 mm);2. Thethicknessesofthefinalfloorfinishlayer(tiles,marble,engineeredwoodetc.)andtheadhesivelayerthatsecuresit.Oncethescreedrailsareset inpositionthescreedmadeofPoliterm®BluorPoliterm®BluFeincanbepouredbetweenthem,spreadandthenlevelledusingastraightedgebladepulledoverthetopedgeofthescreedrails.OncethescreedmadewithPoliterm®Bluhasattainedamoisturecontentof2%(measuredwithacalciumcarbideinstrument),thetoppinglayercanbeprepared,withaminimumthicknessof20mmusingtheselflevellingpremixmortarAutoliv(seethespecifictechnicaldatasheet).Note. theapplicationofAutolivispossibleonlyonabasewithamoisturecontentnotexceeding2%involume(measuredwithacalciumcarbide instrument,seealsothetechnicalspecification)andalsoafterthetreatmentof thesurfacewithEdilstikusingthe“freshonfresh”method.Thelightweightscreedsurfaceproducedissuitabletoreceivethedirectlayingofflexibleflooringsuchaslinoleum,pvc,rubber,moquetteetc.installingthemdirectlywithadhesive.Theinstallationofthefinalfinishlayerisonlypossibleafteradequatecuringandcorrectmoisturecontentofthebase.
The thus prepared footing will have the following characteristics:
WARNINGS AND PRECAUTIONS:· WhenlayingthePoliterm®Bluscreedanyexistingstructuraljointsand/orexpansionjointsinthereceivingsurfacemustbemaintai-
nedandextendedupthroughthePoliterm®Bluscreed.· IfacousticmatsorlayersaretobeincorporatedintotheconstructionbeneaththePoliterm®Bluscreedlaidusingthesinglelayer
methodthentheseacousticlayersshouldbeinstalledbeneath,notover,anypipesorconduitstherebyavoidingthepossibilityofcreatingairpocketswhichcouldhavetheeffectsoflesseningtheacousticperformanceandalsothestructuralintegrityofthePoli-term®Bluscreed.
· BeforelayingthePoliterm®Bluscreed,thoroughlycleanthereceivingsurface.· Whenrequired,dayjointsinthePoliterm®Bluscreedshouldbecastvertically.· WhencontinuingthepourthedayjointsneedtobetreatedwithEdilstiklatexadhesive,tobeused“freshonfresh”.· Adhesivesmustbeusedstrictlyinaccordancewiththeinstructionsoftheadhesivemanufacturers.· AvoidmixingandlayingPoliterm®Bluwhentemperaturesarebelow5°C.Anyantifreezeadditivesthatmaybeusedmustbecompa-
tiblewiththephysical‐chemicalpropertiesofPoliterm®Blu.Thecontractorshouldhoweverevaluatethecostsandbenefitsofusingantifreezeadditivesonacasebycasebasis.
· WhenmixingPoliterm®Blu,strictlyfollowthedosagesandmethodsindicatedinthetechnicalsheets,theproductpackagingandinthismanual.OnlythencanEdiltecoguaranteetheresultsandperformanceclaimed.
· It is essential that you contact our Engineering Department when considering any application different from that described in our technical data sheets and our manuals.
FORMULA 300 350
Densityafter28dayskg/m3 approx.315 approx.365
ThermalconductivityλD W/mK 0,080 0,103
CompressivestrenghtN/mm2 1,61 1,69
FlexuralstrenghtN/mm2 0,95 0,59
CohesionkPa 127,17 n.a.
Hot-sealedmembraneruptureN/50mm 62 n.a.
Cold-sealedmembraneruptureN/50mm 47 n.a.
ElasticitymoduleN/mm2 551,1 n.a.
Permeabilitytowatervapourμ 7,2 9,2
SpecificheatJ/kgK 1000* 1000*
Shrinkage(NBN)mm/m 0,352 0,270
Acoustic performance ΔLw
26dB** n.a.
ImpactnoiseinsulationL’nT,W
n.a. n.a.
Fire reactivity class A2-s1,d0
*1000J/kgK=0,24kcal/kgK/**Valueobtainedinlaboratorywith7cmofPoliterm®Blu+Fonotech5
31
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
TYPE:constructionoflightweightthermallyinsulatedbasepreparedusingPoliterm®Blu,suppliedinbagsof500Lyieldor200Lyieldeach;laidbyaspecialisedteamusingthe Intermediate Layer method: i.e. suitable for subsequent laying of an asphalt pavement for motor vehicle traffic.
INTENDED USE: spacebetweenfloors-basements(onloosestonefoundationswellconsolidated)etc.
MINIMUM APPLICATION THICKNESS: 100 mm. For advice on thicknesses less than 100 mm please contact the Edilteco Technical Department.
ITEM SPECIFICATION: CreationofthermalinsulatingbaseslabpreparedwithPoliterm®BlumanufacturedbyEdiltecoS.p.A.:super-lightaggregateinvirginexpandedpolystyrenebeadswithconstantparticlesize(beadsø3/6mmorø2mm-Politerm®BluFein)andwithcontrolleddensity;premixedpearlbypearlwithE.I.A.®additiveintheproductionphase,whichallowsperfectmixingwithwaterbinder,eliminatesthebeadfloatingphenomenonandguaranteestheirhomogeneousdistributioninthemix.Themixcanbebatchedwithadensityof300to350kg/m³usingPortland32.5CemIoCemII,withoutaddinganysandand/orotheradditives.Therefore,everycubicmetreofmortarwillbepreparedonlywith840LofPoliterm®Blubeads,Portland32.5CemIoCemIIcementinthedosagesprescribedandtherelevantvolumeofwaterrequiredforhydration.The base is suitable for subsequent laying of:a. Flooringwithwaterproofinglayer:waterproofinglayer+non‐wovenfabriclayer+asphaltlayerwithaminimumthicknessof50
mm.b. Basementflooringwithoutwaterproofing:non‐wovenfabriclayer+asphaltlayerwithaminimumthicknessof50mm.Note:Wheninstallingawaterproofinglayerand/orvapourbarrierbelowaPoliterm®Bluscreed,thelayerhastobecoveredwithareinforcedconcreteslab,withaminimumthicknessof100mm.Types,layingmethodsandcharacteristicsmustbedeterminedbythedesignerresponsibleorthecustomeraccordingtothespecificintendeduses.
The base will have the following characteristics:
IntermediateLayer
BENEATH TRAFFICABLE ASPHALT PAVEMENTS
FORMULA 300 350
Densityafter28dayskg/m3 approx.315 approx.365
ThermalconductivityλD W/mK 0,080 0,103
CompressivestrenghtN/mm2 1,61 1,69
FlexuralstrenghtN/mm2 0,95 0,59
CohesionkPa 127,17 n.a.
Hot-sealedmembraneruptureN/50mm 62 n.a.
Cold-sealedmembraneruptureN/50mm 47 n.a.
ElasticitymoduleN/mm2 551,1 n.a.
Permeabilitytowatervapourμ 7,2 9,2
SpecificheatJ/kgK 1000* 1000*
Shrinkage(NBN)mm/m 0,352 0,270
Acoustic performance ΔLw
26dB** n.a.
ImpactnoiseinsulationL’nT,W
n.a. n.a.
Fire reactivity class A2-s1,d0
*1000J/kgK=0,24kcal/kgK/**Valueobtainedinlaboratorywith7cmofPoliterm®Blu+Fonotech5
32
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
In case of crawl space subbase, concreting, honeycomb... the laying of the screed made with Politerm® Blu, may be done without interpose on the casting a galvanized mesh. In case that the subbase is made by insulating sheets, bituminous and/or synthetic waterproofing mats, ceramic or linoleum pavements, pvc, wood, moquette, corrugated sheet etc. before the laying of the screed made with Politerm® Blu, it is necessary proceeding installing sheets of galvanized mesh (minimum dimension: wire diam. 2 mm, mesh 50 x 50 mm) properly connected and spaced from the subbase.
TECHNICAL EVALUATION: below isanexampleofa loadingcalculationforasubbasemadewithPoliterm®Bluwhenused intheconstructionofcarparksandparkingareasconsideringtheloadsimposedbyamotorvehiclenotexceedingatareweightof3.5tonswhenfullyloaded.
ThesubbasemadewithPoliterm®Bluandbatchedwith350kg/m³ofcement,compressivestrengthofabout1,69N/mm2. If for the purposeofthiscalculationweassignacompressivestrengthtotheasphaltpavementnohigherthanthatofthePoliterm®basebeneathitandalsoignoretheloadspreadaffordedbythe50mmlayerofasphalt,thenweobtainthefollowing:·Max.loadofthemotorvehicle: 3500kg·Footprint(contactarea)ofeachtyre(20x10cm): 200cm2
·For4tyresthetotalloadsupportedwillbe: 800cm2
·ThecompressivestrengthofPoliterm®Blubase(cementdosage350kg/m3=1,69N/mm2=17,24kg/cm2): approx.17,24kg/cm2
·TheloadimposedbythevehicleonthePoliterm®Blubasewillbeequaltocm2800x17,24kg/cm2= 13.792kg
TheabovecalculationshowsthathecompressivestrengthofthePoliterm®baseissignificantlygreaterthanthemaximumloadappliedbyany4‐wheeledvehicle.ThereforenodifficultiesareforeseenwhenusingPoliterm®Bluathisdensityinthisapplication.Politerm®BluhasbeenusedinthisapplicationunderthedirectsupervisionofEdiltecotechnicians,inSpain(undergroundparkingattheNewTheatreofCatalunyainBarcelona-year1995)andinPortugal(municipalparkinginthecityofPorto-year1996andalsoinBraga).
WARNINGS AND PRECAUTIONS:· WhenlayingthePoliterm®Bluscreedanyexistingstructuraljointsand/orexpansionjointsinthereceivingsurfacemustbe
maintainedandextendedupthroughthePoliterm®Bluscreed.· BeforelayingthePoliterm®Bluscreed,thoroughlycleanthereceivingsurface.· AftercleaningofthescreedsurfaceandbeforelayingthescreedpreparedwithPoliterm®Blu,wetthefloorwellbutwithout
leavingpuddles.Whenlayingonanonporousorwaterproofsurfacelikeplasticsheetingoverinsulationboards,waterprooflayersortiledfloorsdonotwetthesurface.
· AvoidmixingandlayingPoliterm®Bluwhentemperaturesarebelow5°C.Anyantifreezeadditivesthatmaybeusedmustbecompatiblewiththephysical‐chemicalpropertiesofPoliterm®Blu.Thecontractorshouldhoweverevaluatethecostsandbe-nefitsofusingantifreezeadditivesonacasebycasebasis.
· WhenmixingPoliterm®Blu,strictlyfollowthedosagesandmethodsindicatedinthetechnicalsheets,ontheproductpacka-gingandinthismanual.OnlythencanEdiltecoguaranteetheresultsandperformanceclaimed.
· It is essential that you contact our Engineering Department when considering any application different from that described in our technical data sheets and our manuals.
SPECIAL APPLICATION: FOUNDATION FOR BITUMINOUS-ASPHALT COAT
Politerm® Blumin. thickness 100 mm
bituminous-asphalt coat, min. 50 mm
Tissue non tissue
Compacted soil
33
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
TYPE: constructionoflightweightthermallyinsulatedbasepreparedusingPoliterm®Blu,suppliedinbagsof500Lyieldor200Lyieldeach;laidbyaspecialisedteamusingthe Intermediate Layer method: i.e. suitable for subsequent laying of a concrete pavement for motor vehicle traffic.
INTENDED USE: spacebetweenfloors-basements(onloosestonefoundationswell‐consolidated)etc.
MINIMUM APPLICATION THICKNESS: 100 mm. For advice on thicknesses less than 100 mm please contact the Edilteco Technical Department.
ITEM SPECIFICATION:CreationofthermalinsulatingbaseslabpreparedwithPoliterm®BlumanufacturedbyEdiltecoS.p.A.:super-lightaggregateinvirginexpandedpolystyrenebeadswithconstantparticlesize(beadsø3/6mmorø2mm-Politerm®BluFein)andwithcontrolleddensity;premixedpearlbypearlwithE.I.A.®additiveintheproductionphase,whichallowsperfectmixingwithwaterbinder,eliminatesthebeadfloatingphenomenonandguaranteestheirhomogeneousdistributioninthemix.Themixcanbebatchedwithadensityof300to350kg/m³usingPortland32.5CemIoCemII,withoutaddinganysandand/orotheradditives.Therefore,everycubicmetreofmortarwillbepreparedonlywith840LofPoliterm®Blubeads,Portland32.5CemIoCemIIcementinthedosagesprescribedandtherelevantvolumeofwaterrequiredforhydration.
Main construction types and build ups are: a. Paving on the floor with underlying waterproofing:waterproofinglayer+non‐wovenfabriclayer+concreteindustrialflooring
designedandconstructedtosuitthespecificintendeduse.b. Basement flooring on waterproofing and/or vapour barrier:waterproofinglayerand/orvapourbarrier+non‐wovenfabriclayer
+concreteindustrialflooringdesignedandconstructedtosuitthespecificintendeduse.c. Basement flooring without waterproofing and/or vapour barrier:non‐wovenfabriclayer+concreteindustrialflooringdesigned
andconstructedtosuitthespecificintendeduse.Note:whenthelayingofthewaterproofingsurfaceand/orwatervaporbarrierisrequiredunderthePoliterm®Blubase-screed,thisonemustbecoveredwithareinforcingconcreteslab,withthicknessof100mm.Typologiesandmethodologies,prescribedbythedesigner,dependontheparticularapplicationfields.
The base will have the following characteristics:
IntermediateLayer
LAYING BENEATH INDUSTRIAL CONCRETE TRAFFICABLE PAVEMENTS AND FLOORS
FORMULA 300 350
Densityafter28dayskg/m3 approx.315 approx.365
ThermalconductivityλD W/mK 0,080 0,103
CompressivestrenghtN/mm2 1,61 1,69
FlexuralstrenghtN/mm2 0,95 0,59
CohesionkPa 127,17 n.a.
Hot-sealedmembraneruptureN/50mm 62 n.a.
Cold-sealedmembraneruptureN/50mm 47 n.a.
ElasticitymoduleN/mm2 551,1 n.a.
Permeabilitytowatervapourμ 7,2 9,2
SpecificheatJ/kgK 1000* 1000*
*1000J/kgK=0,24kcal/kgK/**Valueobtainedinlaboratorywith7cmofPoliterm®Blu+Fonotech5
34
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
In case of crawl space subbase, concreting, honeycomb. the laying of the screed made with Politerm® Blu, may be done without interpose on the casting a galvanized mesh. In case that the subbase is made by insulating sheets, bituminous and/or synthetic waterproofing mats, ceramic or linoleum pavements, pvc, wood, moquette, corrugated sheet etc. before the laying of the screed made with Politerm® Blu, it is necessary proceeding installing sheets of galvanized mesh (minimum dimension: wire diam. 2 mm, mesh 50 x 50 mm) properly connected and spaced from the subbase.
TECHNICAL EVALUATION: below isanexampleofa loadingcalculationforasubbasemadewithPoliterm®Bluwhenused intheconstructionofcarparksandparkingareasconsideringtheloadsimposedbyamotorvehiclenotexceedingatareweightof3.5tonswhenfullyloaded.
ThesubbasemadewithPoliterm®Bluandbatchedwith350kg/m³ofcement,compressivestrengthofabout1,69N/mm2. If for the purposeofthiscalculationweassignacompressivestrengthtotheconcretepavementnohigherthanthatofthePoliterm®basebeneathitandalsoignoretheloadspreadaffordedbythe100mmlayerofconcretethenweobtainthefollowing:·Max.loadofthemotorvehicle: 3500kg·Footprint(contactarea)ofeachtyre(20x10cm): 200cm2
·For4tyresthetotalloadsupportedwillbe: 800cm2
·ThecompressivestrengthofPoliterm®Blubase(cementdosage350kg/m3=1,69N/mm2=17,24kg/cm2)isequalto: Approx.17,24kg/cm2
·TheloadimposedbythevehicleonthePoliterm®Blubasewillbeequaltocm2800x17,24kg/cm2= Approx.13.792kg
TheabovecalculationshowsthatthecompressivestrengthofthePoliterm®baseissignificantlygreaterthanthemaximumloadappliedbyany4‐wheeledvehicle.ThereforenodifficultiesareforeseenwhenusingPoliterm®Bluathisdensityinthisapplication
WARNINGS AND PRECAUTIONS:· WhenlayingthePoliterm®Bluscreedanyexistingstructuraljointsand/orexpansionjointsinthereceivingsurfacemustbe
maintainedandextendedupthroughthePoliterm®Bluscreed.· BeforelayingthePoliterm®Bluscreed,thoroughlycleanthereceivingsurface.· AftercleaningofthescreedsurfaceandbeforelayingthescreedpreparedwithPoliterm®Blu,wetthefloorwellbutwithout
leavingpuddles.Whenlayingonanonporousorwaterproofsurfacelikeplasticsheetingoverinsulationboards,waterprooflayersortiledfloorsdonotwetthesurface.
· AvoidmixingandlayingPoliterm®Bluwhentemperaturesarebelow5°C.Anyantifreezeadditivesthatmaybeusedmustbecompatiblewiththephysical‐chemicalpropertiesofPoliterm®Blu.Thecontractorshouldhoweverevaluatethecostsandbe-nefitsofusingantifreezeadditivesonacasebycasebasis.
· WhenmixingPoliterm®Blu,strictlyfollowthedosagesandmethodsindicatedinthetechnicalsheets,theproductpackagingandinthismanual.OnlythencanEdiltecoguaranteetheresultsandperformanceclaimed.
· It is essential that you contact our Engineering Department when considering any application different from that described in our technical data sheets and our manuals
SPECIAL APPLICATION: LAYER LEVEL INSULATION IN INDUSTRIAL FLOOR
Galvanised mesh
Politerm® Blu
Vapour barrier
Industrial pavement made of concrete, finished with streight edge or with mechanical device
HONEYCOMB
FORMULA 300 350
Shrinkage(NBN)mm/m 0,352 0,270
Acoustic performance ΔLw
26dB** n.a.
ImpactnoiseinsulationL’nT,W
n.a. n.a.
Fire reactivity class A2-s1,d0
*1000J/kgK=0,24kcal/kgK/**Valueobtainedinlaboratorywith7cmofPoliterm®Blu+Fonotech5
35
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
ConcreteBatching Plants
DOSES AND METHODS FOR PREPARATION OF LIGHTWEIGHT THERMAL INSULATING MORTARSMADE WITH POLITERM® BLU READY MIX AND FEIN READY MIX IN TRUCK MIXER
DOSES FOR 1 m³ YIELD OF LIGHTWEIGHT THERMAL INSULATING MORTAR:
ORDER OF INTRODUCTION INTO THE TRUCK MIXER - MIXING AT FULL SPEED:1. Water:asmuchasrequiredforthemix,lessabout20-30litres(seepoint7). NOTE: water-cementratio0,4:0,5accordingtothe
cementcharacteristics;2. Politerm® Blu Ready Mix - Politerm® Blu Fein Ready Mix;3. Mixforabout10minutesattopspeed;4. Cement;5. Sand(ifapplicable);6. Mixforabout10minutesattopspeed;7. Cleantheloadingbowlwithabout20-30litresofwater(thuscompletingdosageofthemixingwater);8. Dependingontheresidualmoistureinthesand,addwater.
WARNINGS AND PRECAUTIONS:· Ifthetruckmixerhasavolumetriccapacityof10m³,preparetheloadfor9m³.· Duringthetripfromthebatchingplanttositethetruckmixerhastorunatmaintenancespeed.Onceonsite,andafterpossibly
addingwater,thelengthoftimespentmixinginthetruckmixeris1minuteforeachm3 of mixture.· Theambienttemperaturecanaffecttheyield.Insummerthisisnotaproblembutinwinterthemixingwatertemperaturemay
dropcloseto“zero”.Itisthereforerecommendedtoincreasethemixingtimeinthetruckmixerby5-8minutesafteraddingsome cement.
· Attemperaturesbelow+5°C,itisrecommendedtoaddliquidantifreezetothedosagesrecommendedbythemanufacturer.Anyantifreezeadditivesthatmaybeusedmustbecompatiblewiththephysical‐chemicalpropertiesofPoliterm®Blu.Thecon-tractorshouldhoweverevaluatethecostsandbenefitsofusingantifreezeadditivesonacasebycasebasis.
· BeforestartingtopumpthemortarmadewithPoliterm®BluReadyMix,itisimportantinitiallytopumpjustwaterorgroutwa-ter/cement,inordertowettheentirepipesection.Then,beforebeginningtopumpthemortarmadewithPoliterm®BluReadyMix,introducethesponge“tubecleaner”.Thislastactionpreventsthepossiblewashingoutofthebeads,causedbystandingwaterinthepipes,andsoavoidsthepossibleformationofplugs.Forcorrectpumping,normallydoneusingpistonpumps,pourthemortarmadewithPoliterm®BluReadyMixintothepumphopperandstartpumpingslowly,untilthemortarflowsoutfromthepumptube.Thencontinuepumpingatthedesiredspeed.
· Checktheamountofresidualmoistureinthesandsoasnottoaddtoomuchwatertothemix.· Ifusingdifferentmixingdevice,pleasecontacttheEdiltecoTechnicalDepartment· Forcorrectoperationandoptimalpumping,itisrecommendedtoruntestswithquantitiesnotlessthan5m³atatime.
FORMULA WATER *(L)
CEMENT PORTLAND32.5R CEM I o CEM II (kg)
POLITERM® BLU READY MIXAND POLITERM® BLU
FEIN READY MIX
SAND 0,4 - 0,6 mm(kg)
200 90 200
840L
-
250 110 250 -
300 140 300 -
350 160 350 -
500 140** 300 160
800 140** 300 680L 450
1200 140** 300 510L 850
*Thewaterdosagehastobeadaptedtothequalityofthelotofcementtobeused.**Adjustaccordingtothesandmoisturecontent.Pleasecontactusforfurtherformulas.
36
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
· Anyrestriction/bottleneckontheholdingmaterialpipecancausethe‘cap’formation.Itisthereforerecommendedtousepipeswiththesamediameteruptothedischargeterminal.
· AlwaysverifythattheheldhoseconnectorareintactavoidinganypossibleairsuctionthatwouldcausethelackofpumpingofthelightweightbasescreedpreparedwithPoliterm®BluReadyMix.
ADVICE FOR THE WASHING OF CONCRETE MIXER: · DischargetheleftovermaterialintocontainerswhichallowthewatertorunoffandthenrecoverthePoliterm®BluReadyMix
beadsandtheaggregate,whichcanthenonlybeusedforoversiteconcrete.· UsingsandinthepreparationofmortarmadewithPoliterm®BluReadyMix,reduceswastageofbeads,butDOESNOTmeanthat
youcandoawaywiththeabovementionedwashingphases.Thefollowingrulemustalsoberespected.
OBLIGATIONS:Whenthetruckmixerhasbeenwashedoutinthisway,thenextmixmustonlybeusedforoversiteconcreteandNOTforpouringindustrialflooring.
SPECIFIC EQUIPMENT (see appendix 3. “Equipments and spare parts”):Ediltecosuggestsusingequipmentspecificallydesignedforbatchingplants,forpreparationandpumpingoflightweightthermalinsulatingmortarspreparedwithPoliterm®BluReadyMix.Usingthisspecificequipmentspeedsuptheloading,preparationandworkingtimeandguaranteesaconstantexcellentresultfromthefinishedproduct.
37
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
Main productsPOLITERM® BLUSuperlight thermal insulating aggregate composed of virgin expanded polystyrene beads withgrainsizeincurve (ø3-6mm)andwithacontrolleddensity.DuringproductionthebeadsaremixedwithaspecialE.I.A.additivewhichallowsperfectmixingwithwaterandbinder,evenatverylowdoses.Thehomogenousdistributionofthebeadsthroughoutthemixandtheeliminationoftheproblemofbeadflotationcreateaproductthatisperfectforpumping.
Packaging/Yield:Bagof170Lforayieldof200L(1/5m3)offinishedmortar;Bagof420Lforayieldof500L(1/2m3)offinishedmortar.
POLITERM® BLU FEINSuperlight thermal insulating aggregate composed of virgin expanded polystyrene beads withfinegrain(ø 2mm),andwithacontrolleddensity.DuringproductionthebeadsaremixedwithaspecialE.I.A.additivewhichallowsperfectmixingwithwaterandbinder,evenatverylowdoses.Thehomogenousdistributionofthebeadsthroughoutthemixandtheeliminationoftheproblemofbeadflotationcreateaproductthatisperfectforpumping.ItisidealforproducingsinglelayerlevelscreedsusingthePianoZerosystemthatoncecuredwillacceptthedirectadhesivefixingoffloorcoveringsandfinishes.There is no need to add sand.
Packaging/Yield:Bagof170Lforayieldof200L(1/5m3)offinishedmortar;Bagof420Lforayieldof500L(1/2m3)offinishedmortar.
POLITERM® BLU FEIN READY MIXSpecific for mix in concrete mixing and cls pump.Superlight and high thermal insulating aggregate composed of fine beads of expanded polystyrenewithconstantgrainsize(ø 3-6mm).andwithacontrolleddensity.Duringproduction,thebeadsaremixedwithaspecialE.I.A.additivewhichallowsperfectmixingwithwaterandbinder,evenatverylowdoses.Thehomogenousdistributionofthebeadsthroughoutthemixandtheeli-minationoftheproblemofbeadflotation.
Packaging/Yield:Bagforayieldof500L(1/2m3)offinishedmortar.
POLITERM® BLU READY MIXSpecific for mix in concrete mixing and cls pump.Superlight and high thermal insulating aggregate composed of fine beads of expanded polystyrene withconstantgrainsize(ø 3-6mm)andwithacontrolleddensity.Duringproduction,thebeadsaremixedwithaspecialE.I.A.additivewhichallowsperfectmixingwithwaterandbinder,evenatverylowdoses.Thehomogenousdistributionofthebeadsthroughoutthemixandtheeli-minationoftheproblemofbeadflotation.
Packaging/Yield:Bagforayieldof500L(1/2m3)offinishedmortar.
38
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
Complementary productsSCREED RAILSPVC profiles usedtofixthefinishedheightofthescreed.Theyareparticularlysuitableforsingle-layerlightweightscreeds.Eachprofileis2mlongand5cmhigh.Thespecialcross-sectiondesignallowsthemtobesecurelyfixedandheldwithinthescreed,highlystablewithexcellentalignment.Theyalsopreventtheformationofthermalbridges.PianoZeroProfilescanalsobeusedintraditionalsandandcementscreeds;inthiscase,theyactasthecontractionorshrinkagejoint.
EDILSTIKSynthetic latex forsurfacepreparationortoimprovethepropertiesofcementscreeds.Foruseinthelayingofsingle-layerlightweightscreeds(PianoZerosystem)topromoteadhesiontothereceivingsurfaceandforthepreparationofverythinsmoothingscreedsforsurfacepro-tection.
Packaging: 1kgcan/5kgcan/20kgcan/Palletised1.000kgtank.Fortheyeld,pleaserefertothetechnicaldatasheet
EDILSTIK F.C.A.Pigmented synthetic latex fortemporarystabilisationofasbestosfibrecementsheets(type“D” certificate). To apply before the encapsulationworkwith lightweight thermal insulatingmortarsforscreedspreparedwithproductsofPoliterm®Blurange.
Packaging:5kgcan/20kgcanorpalletised1.000kgtank.Colour:yellow-orange.Low-pressureapplicationwithspraynozzle(seeEdilstikBlowMachine)orairless.Alsoavailableinthepre-dilutedversion.Fortheyeld,pleaserefertothetechnicaldatasheet
AUTOLIV Smoothing screedReady to use self-levelling mineral screed powder, formanualandmechanical application.SuitableasahighstrengthtopcoatinglayerorforthefinelevellingofPoliterm®BluorIsolcaplightweightscreeds(seeEdilteco’sapplicationmanuals)priortolayingceramictiles,stoneormarblefloorsandparquetflooring.
Packaging/Yield:· Bagof25kg.· Yield:20kg/m2per1cmofthickness.
AUTOLIV SP ScreedCement-based self-levelling screed readytouse.Itiscomposedofspecialcementbinders,cal-careousandsiliceousaggregatesingrainsizecurvewithadditivestoimprovetheworkabilityandlevelling.
Packaging/Yield:· Bagof25kg.· Yield:20kg/m2per1cmofthickness.
39
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
EquipmentPOLITERM® MACHINE 1000 ECOEntirely stainless steel equipment for the preparation (mixture) and pumping of screeds and lightweight screeds composedbyfinegrainedmaterialssuchasvirginexpandedpolystyrenebeads, reclaimedex-pandedpolystyrenebeads,perlite,vermiculiteandcork,alsomixedwithcellularfoamproducedbyspecificequipment(FoamMakertype).Themaximumlengthofthepipeforcarryingthemortarisof100mwithamaximumheightof30m.
Electrical power supply: 400V-50Hz.Also available with diesel fuel:homologateddieselengineinaccordancewithregulationofnoisepollution.Available with tank:·from1m3
POLITERM® PUMP WITH OR WITHOUT HOPPERMixing machine with pumping system for lightweight screeds consisting of virtual aggregates likevirginexpandedpolystyrenebeads,recycledexpandedpolystyrenebeads,perlite,vermicu-liteandcork,evenwhenmixedwithcellularfoam.Pumpingcapacityupto120minlengthandupto30minheight.
Available in the following types:·Electricalpowersupply400V.·Withhydraulicengineprovidedbyexternalsupply(e.g.trucks).
Customized fittings available on request.
* It is also available in the following version:
POLITERM® MACHINE 1000 H2OEquipped with automatic water dosage system.For the setting up, please consult the technical sheet.
ISOLCAP MACHINE 400 V H2OEntirely stainless steel equipment for the preparation (mixing) and pumping of screeds and lightweight screeds (inparticularthereadytouseonesoftheIsolcaprange)composedoffinegrainedmaterialslikevirginexpandedpolystyrenebeads,reclaimedexpandedpolystyrenebe-ads,perlite,vermiculite,corkandself-levellingscreeds(concreteandanidrihite).
Weight:320kg.Capacity tank: approx.220LElectrical power supply: 2,2kw.400V.Maximum length of the pipe for carrying the mortar:30mwithamaximumheightof15m.Equippedwithautomaticwaterdosagesystem.
** It is also available in the following version:
ISOLCAP MACHINE 230 V H2O
Edilteco S.p.A. Via dell’Industria, 710 . 41038 San Felice sul Panaro (MO) ItalyPh. +39 0535 82161 . Fax +39 0535 82970 . www.edilteco.com I [email protected]
EquipmentPOLITERM® MACHINE SCREWEquipment for the mechanical addition ofcementintothePoliterm®machinetank.Electrical power supply: 400V.
Customized fittings available on request.
LEVELLING TOOLAluminium straight edge rail withhandleforthespreadingoflightweightscreeds.
EDILSTIK BLOW MACHINEEquipment for atomizing latex.Electricalpowersupply:230V/50Hz.
HIGH RESISTANCE RIGID METAL PIPEThisaccessoryimprovestheflowingofthemortarandavoidstherisksofbreakingandburstingthepipeswhileworking.Essentialforpumpingtoheightsgreaterthan10m.3mlongpipeswithflangesandringsforfixingtoscaffolding.
METAL ELBOWFOR PIPESAvailablewith45°and90°elbow.
STEEL REINFORCEDRUBBER PIPE Pipes for pumping lightweightscreedswithPoliterm®Machine.10 m long pipes complete withflanges.
LIGHT PLASTICPIPEPipes forpumping lightweightscreeds(end length) with Politerm® Machine.10mlongpipescompletewithflanges.
PartnersEdilteco Group
LEGEND
Distributors
Edilteco is associated with:
EDILTECO, ANINTERNATIONALSUCCESSitaly . france . benelux . sudamericana
350
- GB
Rev.
05
- 201
7©
Cop
yrig
ht E
DILT
ECO
S.p.
A. -
Non
auth
oriz
ed re
prod
uctio
n is
forb
idde
n.
Consult our technical and application videos on the Edilteco YouTube Channel . www.youtube.com/user/EDILTECOvideo
Edilteco S.p.A.Viadell’Industria,710.41038SanFelicesulPanaro(MO)Italy.Ph.+39053582161.Fax+39053582970www.edilteco.com I [email protected]
360° Insulation