20
PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

Embed Size (px)

DESCRIPTION

PNW Regional Summary 226 RTUs Serviced/Measured! Avista = 6 pairs to be metered Bonneville Power Administration RTU Pilot = 150 metered + 11 from Avista Energy Trust of Oregon = 15 metered/94 total Idaho Power = 9 metered Puget Sound Energy = 41 metered

Citation preview

Page 1: PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

PNW RoofTop Unit Working Group - RTUG –

RTU Savings Research ProjectPhase 3

December 15, 2009

Page 2: PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

RTUG Agenda 12/15/09• 9:30-9:45am - Presentation on expected RTU savings and potential from

the NW Power and Conservation Council’s 6th Power Plan- NW Energy efficiency Alliance Service Assistant Project Update

• 9:45-10:45 Results: Bonneville RTU Savings Research

>> 10:45-11:00 Break

• 11:00-12:00pm Discussion: Bonneville Results

• 12:00-12:15pm Results: Idaho Power RTU Savings Research

>> 12:15-1:15pm Lunch Break - WEB shows agenda; telcomm off line

• 1:15-1:30pm Results: Energy Trust of Oregon RTU Pilot Savings

• 1:30-1:45pm Results: Puget Sound Energy RTU Savings Evaluation

• 1:45-2:00pm Results: AirCare Plus℠ in California

• 2:00-3:30pm Discussion: Next Steps- Use of the data for additional analysesOptions for Assessing Expected Value SavingsRecommendations to the RTF - January 5, 2010

Page 3: PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

PNW Regional Summary 226 RTUs Serviced/Measured!

• Avista = 6 pairs to be metered

• Bonneville Power Administration RTU Pilot = 150 metered + 11 from Avista - 2008

• Energy Trust of Oregon = 15 metered/94 total

• Idaho Power = 9 metered

• Puget Sound Energy = 41 metered

Page 4: PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

Idaho Power RTU

• 3 sites, 3 units per site, 12 months all units (Sept. 09 – Sept. 10)

• Level 1 monitoring 2 per siteLevel 2 monitoring 1 per site

• Heating signal at 1 unit per site• Heavy equipment supply/repair; title

insurance company; wholesale beverage

Page 5: PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

Idaho Power RTU Summary Results

Summary weather compressor Savings Pre Post Pre

site ID RTU ID size tons data Stages kWh/yr kWh/yr kWh/yr

t'stat stages Econo?

Bigelow #1 5 BOISE 1 -2,145 8,193 10,339 Yes Bigelow #2 7 BOISE 2 0 6,236 6,236 Yes Bigelow #3 10 BOISE 2 6,479 38,710 32,231 Yes Cesco #1 7 BOISE 1 86 14,351 14,265 yes Cesco #2 7 BOISE 1 0 12,072 12,072 no Cesco #3 6 BOISE 1 -7,905 7,827 15,733 yes Nampa #1 5.5 BOISE 1 -180 7,162 7,342 yes Nampa #2 7 BOISE 1 -7,227 2,853 10,080 yes Nampa #3 5.5 BOISE 1 6,161 10,652 4,490 yes

Page 6: PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

Interpretation of Results - Idaho

• 2 units fan power increase due to filter cleaning

• 1 unit incomplete economizer damper opening

• 2 units fan schedule increase to 24 hours, major losses

• 1 unit fan schedule reduction, major savings

• 1 unit properly operating in pre-retrofit

• 2 units failure to set back schedule

Page 7: PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

Take Away Results - Idaho

• Net savings all RTUs: - 4,700 kWh/yr• Savings target for refined settings: 23,000 kWh

dependent on schedule settings

Page 8: PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

Favorable Schedule Change - Idaho

Time Series

0

2

4

6

8

10

12

2016

6

2064

6

2112

621

606

2208

6

2256

6

2304

6

2352

6

2400

6

2448

6

2496

6

2544

6

2592

6

2640

6

2688

6

2736

6

2784

6

2832

6

2880

6

2928

6

2976

6

3024

6

3072

6

3120

6

3168

6

3216

6

3264

6

3312

6

3360

6

3408

6

3456

6

3504

6

3552

6

3600

6

3648

6

3696

6

3744

6

3792

6

3840

6

3888

6

3936

6

3984

6

4032

6

4080

6

4128

6

Hour of Day

Pow

er k

W kW #3OSA/10max

Page 9: PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

A Puzzle - IdahoEnergy Signature

0

20

40

60

80

100

120

140

160

180

200

220

40 45 50 55 60 65 70 75 80 85 90 95 100

Mean Month Temperature

Ener

gy, k

Wh/

day

mod postmod predata predata post

This unit had a significant economizer improvement.

Why did slope increase?

Page 10: PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

Maximum Power Signatures - Idaho

• Fan power decreased from ~1.5 kW to 1.4 kW due to filter replacement because flow increased

• Post-retrofit power increased for both stages due to flow increase, more cooling delivered

• Increased cooling doesn’t reduce cooling energy because thermostat setting not achieved

Compressor Usage

0

2

4

6

8

10

12

14

40.0 45.0 50.0 55.0 60.0 65.0 70.0 75.0 80.0 85.0 90.0 95.0 100.0

Average Hourly Temperature, deg F

Com

pres

sor k

Wh

or M

ax k

W

pre comppost comppre maxpost max

Page 11: PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

Next Steps - Idaho

• Properly set schedules• Monitor winter operation –consider morning

warm up• Next summer establish improved post-retrofit

performance and savings

Page 12: PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

California RTU Monitoring

• About 300 RTU new replacements instrumented for post-retrofit air-side output and electrical input

• No pre-retrofit measurement – “empirical pre-retrofit baseline drawn from selected samples”

• Monitored for 1-2 summer months

• Differ from NW monitoring by inclusion of return RH and Supply Air Temp with hourly data structure not average daily structure

• Results are normalized to performance efficiency

• Reconciliation with DEER modeling

Page 13: PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

California Results Example 1Analytic Target: Monitored performance as EER vs. Temperature

EER Performance Model

0.002.004.006.008.00

10.0012.0014.0016.0018.0020.00

70.00 80.00 90.00 100.00 110.00

Hourly Temperature, deg F

EER

model

hi

mxt

lo

Page 14: PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

California Results Example 2Monitored performance Compared to DEER

EER Performance

0.00

2.00

4.006.00

8.00

10.00

12.00

14.0016.00

18.00

20.00

70.00 80.00 90.00

Hourly Temperature, Deg F

EER

observed SEER 10 ref SEER 13 ref

Page 15: PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

Summary Results - CA

• Results to be published 12/21/09• Observed performance generally lower than

modeled expectation

Page 16: PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

Regional Results Database• Results from all programs will be entered• Primary structure a directory tree with each

program results as a separate directory• Each directory: unit raw data/template +

results summary for each units + site/unit characteristics & service measures

• Uniform format not being designed• Summary data will include selected site/unit

characteristics

Page 17: PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

Database Summary View

Site Summary• Site ID• RTU ID• Weather data• Annual kWh pre• Annual kWh post• Compressor stages• Compressor max duty (frac of

full load)• Economizer (y/n)• Monitoring level

Pre- and Post- Service Summary• Fan kW• Fan duty (frac of full load)• Baseload kWh/day• Balance point temp• Slope kWh/day/degF• Demand @ 80 deg F, Stage

1&2 kW• Compressor trigger degF

Page 18: PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

Database Format Refinements

• The format will change to accommodate the economizer analysis made possible by the Y1 signal most recently being monitored

• The format will change to accommodate more detailed descriptions of measures applied

• The summary row proceeds from the current template. Other analysis approaches and revised templates may have different summary row formats

Page 19: PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

Use of Regional RTU Data

• Data to be available through NPCC site• Getting 8760 results/analysis/EER vs Temp• EUI per conditioned sf• Sensitivity analysis on methodology• IPMVP Method B analysis: 2 week data only• Correlating data to building characteristics -

partial data available• Annual savings methodology using signatures

Page 20: PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009

RTUG Next Steps

• Prepare presentation to RTF• Discuss with NPCC staff, RTU database implementation

+ integration with other regional buildings-related database(s)

• Further development of ‘Expected Value Savings’ [aka Deemed Savings]

• Continue communications with California organizations