  • Power Management System(Testing Check List)

    REV 5M2012 1

    PMS Site Name / RegionPMS IP Address / GSM Number

    1- System Checking:This part of document underlines the Pre-Test system checking to insure systemfinalization and ready for testing.

    Checking PMC UnitTask Checked Result

    LCD fixed on PMC Board3 x Push buttons fixed8 x Indicator LEDsPower Connector1 x Y28M19 PIN1 x Y28M16 PIN1 x Y28M3 PIN for temperature sensors2 x Y28M4 PIN for Fuel and Flow levelsensors4 Ports Ethernet SwitchGSM modemGrounding

    Checking PMP UnitTask Checked Result

    All Electrical components are fixed incabinet referring to list in:PMP Commissioning DocumentREV4J2011Grounding

    Checking CablingTask Checked Result

    Y28M19 cable PMC to PMPY28M16 cable PMC to PMPY28M3 cable with 2 Temperaturesensors2xY28M4 cable with fuel level and flowsensorsPower Cable for PMCEthernet CableUSB to Serial cable ( optional for GSMmodem)

  • Power Management System(Testing Check List)

    REV 5M2012 2

    Checking If all sensors are connected to PMPTask Checked Result

    Battery Current sensorFire alarm sensorDoor Intrusion sensorWind Speed sensorATS for GeneratorsContactor for BTS reset

    Checking If all other PMP Junctions are connectedTask Checked Result

    Generators and Com. PowerInverterRectifierAC1 and AC2Site LightingDC power from batteriesWind Turbine Voltage measurementDisable/Enable Gen manual switch fromPMPBTS Alarm connection when MetallicBypassBattery Low Voltage & Gen Failure Alarmconnected to BTS Dry contact alarms.Exhaust

    Checking If all sensors are connected to PMCTask Checked Result

    2 x Temperature Sensors1 x Fuel Level Sensor2 x Flow Meter Sensor

    Checking for Power Sources available for testingCommercial PowerGenerators PowerInverter powerRectifier power

  • Power Management System(Testing Check List)

    REV 5M2012 3

    2- System Testing:This part of document underlines testing actions applied on full system features andfunctions.

    Installation and Commissioning TestTest Objective Process Expected result Pass or fail

    Connect the PMC/PMP ground to thegeneral site ground

    MC should begrounded

    Connect PMC to PMP Y28M Connectionsshould be connectedproperly

    ConnectTemperature/FuelLevel/Flow metersensors cables to PMC

    sensors cables shouldbe connected properly

    Connect the PC toPMC with RJ45Straight cableconnection

    RJ45 cable should beconnected properly

    Connect Managedcomponents andpower sources to PMP

    All components andpower sources shouldbe connected to PMPjunctions properly

    Connect 48V power tothe PMC power input

    Power Cable should beplugged properly toPMC

    Commissioning allsystem partstogetherPMC,PMP,Software

    Configuringnetworking betweenrs485 to Ethernetconverter and PC

    Put your PC NC IP assame subnet ofconverter IP and try toaccess the convertervia web interface tochange and configurenew IP. (PMC IP will bethe IP of converter)

    Turn On PMC LCD should Turn Onthen PMC is OnPMC functionality

    test Turn Off PMC LCD should Turn Offthen PMC is Off

    Push Buttons test Scroll LC pages Pages should scroll

  • Power Management System(Testing Check List)

    REV 5M2012 4

    Connection TestingTest Objective Process Expected result Pass or fail

    Test EthernetConnection toPMC

    Connect the Ethernetcross cable betweenPMC Ethernet BackSwitch and PC. Put PCIP address in samerange of PMC IPaddress. Try toconnect from PMCEMS software to PMC

    Connection SucceededSoftware should logonproperly to PMC UNIT

    Test GSM Datacall RemoteConnection toPMC

    Insert SIM-Card withData call activatedinto external GSMmodem. Connect themodem to PC by serialor USB to Serialconnector. Dial PMCmodem from PMCEMS software.

    Connection succeeded.Software should logonproperly to PMC unit

    Software TestTest Objective Process Expected result Pass or fail

    Double click onSoftware icon

    Software should open

    Login On Software Software should loginand open access onconfiguration bar

    Logout from Software Software should logoutand close access onconfiguration bar

    Click exit or closeSoftware

    Software should close

    Access onSoftware Test

    Connecting to PMCvia TCP/IP.

    Software will show(Online) on its Top bar.System page shouldshow all System statusmeasurement etc

  • Power Management System(Testing Check List)

    REV 5M2012 5

    Full Features TestTesting Monitoring, Configuration and functionality between Software and systemfeaturesTest Objective Process Expected result Pass or fail

    Room-SettingsEnable/DisableAC1/AC2manually fromsoftware

    System Enable--->Enable/DisableAC1/AC2

    Status will be shownbeside each AC on systemsoftware page(Enabled/Disabled).Statuswill be shown on LCDpage 10-11

    With RoomTemperature sensormake temperaturemore than Coolingtemp set point 1

    AC1 should Turn On.Status will be monitoredon system software andLCD page 1

    With RoomTemperature sensormake temperaturemore than SecondCooling temp setpoint

    AC2 should Turn On withAC1. Status will bemonitored on systemsoftware and LCD page 1

    With RoomTemperature sensormake temperatureless than SecondCooling temp setpoint

    AC2 should Turn Off.Status will be monitoredon system software andLCD page 1

    RoomTemperature SetPoints

    With RoomTemperature sensormake temperatureless than Coolingtemp set point 1

    AC1 should Turn Off.Status will be monitoredon system software andLCD page 1

  • Power Management System(Testing Check List)

    REV 5M2012 6

    With AmbientTemperature sensormake temperatureless than Coolingtemp Low set point.With RoomTemperature sensormake temperaturemore than Coolingtemp set point 1

    Exhaust should Turn Ontrying to cool the roomfrom outside.AC1/AC2 should still Off.Status will be monitoredon system software andLCD page 1-2

    With AmbientTemperature sensormake temperatureless than Coolingtemp Low set point.With RoomTemperature sensormake temperaturemore than SecondCooling temp s.point

    Exhaust should Turn OffAC1/AC2 should Turn On.Status will be monitoredon system software andLCD page 1-2

    Current Setting Monitoring currentconsumption ofrunning AC onsoftware and LCD

    During running time ofAC1 and AC2 monitorcurrent consumptionvalues on softwareSystem page and LCDpage 3

    Switch betweenpower sources ex:from Inverter powerto Com. Power whenAC are On

    AC should turn off andwait the Start up delaytime before turning Onagain. Status shown onLCD page 1Delay Timer

    Set compressor Maxrunning time

    ACs should switchrunning time betweenthem and if 1 AC isneeded to cool the roomthe AC with less runningtime will be automaticallyselected.

    With RoomTemperature sensormake temperature

    Alarm with buzzer shouldbe activated on software.SMS sent with alarm

  • Power Management System(Testing Check List)

    REV 5M2012 7

    more than High limitalarm

    statusRoom TempAlarm Limit With Room

    Temperature sensormake temperatureless than High limitalarm

    Alarm with buzzer shouldbe activated on software.SMS sent with alarmstatus

    Test Objective Process Expected result Pass or failGenerators-Settings

    Enable/DisableGen1/Gen2/Com. Powermanually fromsoftware & fromPMP Switch.

    System Enable--->Enable/DisableGen1/Gen2/ Com.Power

    Status will be shownbeside each Gen or Com.Power on systemsoftware page(Enabled/Disabled).Statuswill be shown on LCDpage 12-13-14

    Put GeneratorMaximum runningtime

    Generators should autoswitch running timebetween them

    Generator Timers

    Put Generator OilChange Hours

    When Generator totalrunning hours will beequal Generator OilChange hours Oil Changealarm should appear forGenerator on systemsoftware page + Buzzer+SMS

    Generator Fuel

    Change the distanceup or down ofobstacle front of Fuelsensor.

    Fuel meter shows the Fullspace in cm not theEmpty space referring tocalibration. ex: if Fuelcalibration is 300cm andmeasure on system pageis 256cm means Fuelsensor is measuring (300-256 = 44cm). what isshown on systemsoftware page and onLCD page 7 is 256cm fullspace

  • Power Management System(Testing Check List)

    REV 5M2012 8

    Put a flow on flowmeter input

    Flow in L/h should bemeasured on systemsoftware page and LCDpage 7.

    Make fuel level lessthan Low Fuel LevelAlarm value

    Low fuel Level Alarmshould be activated onsystem software page+buzzer+ SMS+ LCD alarmpage 7

    Make flow levelmore than flowlevel max Alarmvalue

    High flow Alarm shouldbe activated on systemsoftware page+ buzzer+SMS+ LCD alarm page 7

    Turn On Gen 1 for 3hours and Gen 2 for2 hours for example.

    General should showthe total time running ofeach generator.Generator with less totalrunning time should beselected the first to runwhen Generator power isneeded

    Generator HourMeter

    After several runningtime of Generators

    Oil Change shouldmeasure and show thetotal time running for Oilchange

    Voltage andCurrent Settings

    Monitoring VoltageOutput ofGenerators and Com.Power

    Voltages should bemeasured and monitoredon system software pageand LCD page 4. in caseof any of these sourceswill be selected to beOn and no Voltageoutput. system will autoswitch to other powersource a Fault alarmshould be activated onsystem software page+buzzer + SMS + LCDalarm page 6

    Monitoring CurrentOutput ofGenerators and Com.Power

    Current load should bemeasured and monitoredon system software pageand LC page 5

  • Power Management System(Testing Check List)

    REV 5M2012 9

    Test Objective Process Expected result Pass or failWind Turbine-Settings

    Wind TurbineVoltage

    Connect an ACpower source 1phase to WindTurbine voltagejunction of PMP

    Power Voltage should beshown on systemsoftware page + LCD page8

    Test Objective Process Expected result Pass or failBattery-Settings

    Set Low LimitAlarm of BatteryVoltage

    When battery Voltagelevel attend the limit analarm should be activatedon system software page+ buzzer + SMS + LCDalarm page 9Voltage and

    Current Settings Set High LimitAlarm of BatteryCurrent and monitorCurrentmeasurement onSystem page

    When battery Currentlevel attend the limit analarm should be activatedon system software page+ buzzer + SMS + LCDalarm page 9

    DIS/EN Inverterfrom software

    Disable/EnableInverter from BatterySettings

    Status will be shownbeside Inverter on systemsoftware page(Enabled/Disabled).Statuswill be shown on LCD

    Voltage Set Point Set Empty Voltageof Voltage Set Point

    Battery Voltage low thanVoltage Set point. Systemshould auto run to Com.Power. If com. Power Off.Auto switch toGenerators to chargebatteries

    Test Objective Process Expected result Pass or failDigital Sensors Test

    Fire sensor Make short circuit onfire alarm junctionon PMP simulatingfire sensor

    Fire Alarm should beactivated on systemsoftware page + buzzer +SMS

  • Power Management System(Testing Check List)

    REV 5M2012 10

    Wind Speedsensor

    Put Anemometer inWind

    Wind Speed should bemeasured and monitoredon system software page+ LCD page 8

    BTS reset Push BTS buttonon System softwarepage

    BTS reset Relay on PMPshould close for 30s thenOpen

    Door Intrusion Click Door intrusionsensor

    Intrusion Alarm should beactivated on systemsoftware page + buzzer +SMS

    Metallic Bypass Power Off the PMC System should:1- Start Generator2- Provide Power to

    rectifier3- Generate bypass

    alarm on BTS

    Test Objective Process Expected result Pass or failAlarms SMS & Reset Alarms

    Alarms SMS Set mobile Numbersthat should receiveSMS in case of anyalarm

    Alarm status should besent by SMS for specifieddestination Number

    Reset Alarms Try to reset anyactivated Alarm formsystem softwarepage or LCD

    Alarm should be Reset

    Test Objective Process Expected result Pass or failAuto Switching between Power Sources

    Battery VoltageLow.Com. Power On

    System should turn offInverter. Switch to Com.Power for chargingBatteries

    Cases

    Battery Voltage Low.Com. Power Off

    System should turn offInverter. Turn OnGenerator with less totalrunning time. If generatorfault, auto switch toGenerator 2.

  • Power Management System(Testing Check List)

    REV 5M2012 11

    Battery Voltage Low.Generator was Onand Com. Powerbecome On

    System should turn OffGenerator and switch toCom. Power to continuecharging batteries

    Generator Oncharging batteriesand batteriesbecome fullycharged

    System should turn OffGenerator and switch toInverter. (N.B: if batteriesbecome full beforeGenerator min runningtime = 1h) system keepsgenerator running untilmin running time.

    Generator On andbecome fault

    Auto switch to Generator2

    Batteries full Inverter selected

    Test Objective Process Expected result Pass or failReport Test

    Archive Period Set Archive period tosave data

    System should savevalues and alarmsreferring to archiveperiod ex: each 20 min.

    Upload data fromsystem

    Upload data fromsystem

    Report Data should beuploaded to system andsaved on PC

    Text Report Select Report--->Text Report onsoftware. Set Dateand time Selection(From/To). Selectmaximum 6 itemsfrom Report list.

    Text report should begenerated showing Itemvalues and measurementthat you selectedreferring to time intervalselected (From/To)

    TREND Report Select Report--->TREND Report onsoftware. Set Dateand time Selection(From/To). Selectmaximum 6 itemsfrom Report list.

    Trend report with graphvariation should begenerated showing Itemvalues and measurementthat you selectedreferring to time intervalselected (From/To)

  • Power Management System(Testing Check List)

    REV 5M2012 12

    BAR GRAPHReport

    Select Report--->BAR GRAPH Reporton software. SetDate and timeSelection(From/To). SelectFUEL Level OR Flowfrom Report list.

    Bar graph report shouldbe generated showingmonthly measurementthat you selectedreferring to time intervalselected (From/To).Double click on monthlyBAR, Daily BAR graph byhours should be shown.

    TOTALIZATIONReport

    Select Report--->TOTALIZATIONReport on software.Set Date and timeSelection(From/To). SelectInverter OR/AndMain Power.

    Bar graph report shouldbe generated showingmonthly running time forinverter/main powersources that you selectedreferring to time intervalselected (From/To). Withpercentage running timeof each source.

    3- System approval:This document should be signed after full system checking and full features testingby comnet power and customer team.

    Signing this document proves that customer agree on system functionality referringto his requirements.

    Comnet Power Engineer Testing EngineerSignature SignatureName NameDesignation DesignationDate Date