    Introduction [Project Management Framework]

    A project is a temporary endeavor undertaken to create a unique product, service, or result

    Example: Building a road is an example of a project. The process of building a road takes a finite amount of

    time, and produces a unique product Second Definition:

    A project is a complex, nonroutine, one time effort limited by time, budget resources, and

    performance specifications designed to meet customer needs.

    What is Not a Project?

    Projects should not be confused with everyday work. A project is not routine, repetitive work. Ordinary daily

    work typically requires doing the same or similar work over and over, while a project is done only once; a

    new service or a new product exists when the project is completed.

    Routine, Repetitive Work[Operations] Projects

    Taking class Notes

    daily entering sales receipts into the

    accounting ledger

    Responding to a supply-chain request

    Practicing scales on the piano

    Routine manufacture of an Apple iPod

    Writing a term paper Setting up a sales kiosk for a professional accounting

    meting

    Developing a supply chain information system Writing a new piano piece Designing an iPod that is approximately 2*4 inches,

    interfaces with PD and stores 10,000 songs

    They share many of the following characteristics

    Performed by people Constrained by limited resources Planned, executed, and controlled

    Projects and operations differ primarily in that operations are ongoing and repetitive, while

    projects are temporary and unique

    Project Objectives

    Project objectives are contained in the preliminary Project Scope Statement and Project ScopeStatement.

    Projects are considered complete when the objectives have been met A reason for terminating a project before completion is that the project objectives cannot be met A more complete understanding of the objectives is achieved over the length of the project. It is the project manager's role to accomplish the project objectives. Objectives should be clear and achievable. The Reason for quality activities is to make sure that project meets its objectives.

  • 7/29/2019 PMP Resumen (Por RDCL)

    2/64

    The Reason for the risk process group is to enhance opportunities and reduce threats to the projectobjectives.

    Things that could negatively impact the project objectives, such as risk and stakeholders' influenceshould be watched and tracked.

    Projects often require tradeoffs between the project requirements and the projects objectives. Project objectives are determined in the initiating process group and refined in the planning process

    group.

    One of the purposes of the develop project management plan process is to determine how work willbe accomplished to meet project objectives.

    A Project management is the application of knowledge, skills, tools and techniques to project activities to

    meet project requirements

    Managing a project includes

    Identifying requirements Establishing clear and achievable objectives Balancing the competing demands for quality, scope, time and cost Adapting the specifications, plans, and approach to the different concern and expectations of the

    various stakeholders.

    A Program is a group of related projects managed in a coordinated way to obtain benefits and control not

    available from managing them individually. Programs may include elements of related work outside of the

    scope of the discrete projects in the program

    Triple Constraints - A Balance Project

    The triple constraints are cost, time, scope of work, quality and customer satisfaction.

    These are so intertwined that a change in one will most often cause a change in at least

    one of the others , For example:

    If time is extended, the cost of the project will increase. If time extended with the same cost then quality of the product will reduce. If scope is extended then cost and time will also extend. Changes to any of these lesgs sets off a series of activities that are needed to integrate the change

    across the project.

    Progressive Elaboration

    Progressively means proceeding in steps; continuing steadily by increments, while elaborated means

    worked out with care and detail; developed thoroughly

  • 7/29/2019 PMP Resumen (Por RDCL)

    3/64

    International and political environment

    Some team members may need to be familiar with applicable international, national, regional, and local laws

    and customs, as well as the political climate that could affect the project. Other international factors to

    consider are time-zone differences, national and regional holidays, travel requirements for face-to-face

    meetings, and the logistics of teleconferencing.

    Cultural and social environment

    The team needs to understand how the project affects people and how people affect the project. This

    Includes

    understanding of aspects of the economic, demographic, educational, ethical, ethnic, religious, And other characteristics of the people whom the project affects or who may have an interest in the

    project.

    The project manager should also examine the organizational culture and determine whether project

    management is recognized as a valid role with accountability and authority for managing the project

    Physical environment

    If the project will affect its physical surroundings, some team members should be knowledgeable about the

    local ecology and physical geography that could affect the project or be affected by the project

    Interpersonal Skills (PMBOK Appendix G)

    Leadership. Developing a vision and strategy, and motivating people to achieve that vision and strategy

    Team Building. Helping a group of individuals bound by a commonsense of purpose to work

    interdependently with each other.

    Motivation. Energizing people to achieve high levels of performance and to overcome barriers to change

    Communication The exchange of information

    Influencing the organization. The ability to 'get things done'.

    Decision Making. The combination of problem definition, alternatives identification and analysis, and

    solution action and evaluation.

    Political and Cultural Awareness. Getting to know political and cultural environment.

    Negotiation and conflict management. Conferring with others to come to terms with them or to reach an

    agreement

  • 7/29/2019 PMP Resumen (Por RDCL)

    4/64

    A standard is a 'document established by consensus and approved by a recognized body that provides, for

    common and repeated use, rules, guidelines or characteristics for activities or their results, aimed at the

    achievement of the optimum degree of order in a given context.' Some examples of standards are computer

    disk sizes and the thermal stability specifications of hydraulic fluids

    A regulation is a government-imposed requirement, which specifies product, process or service

    characteristics, including the applicable administrative provisions, with which compliance is mandatory.

    Building codes are an example of regulations

    Project Management Office [PMO]

    A project management office (PMO) is an organizational unit to centralize and coordinate the management of

    projects under its domain

    Portfolio

    Collection of Projects, Programs and other work grouped together to facilitate effective management to meet

    strategic objectives.

    Project Expeditor

    Staff Assistant and Communication coordinator. No Power to make decisions

    Project Coordinator

    Some authority, power and reports to higher-level manager

  • 7/29/2019 PMP Resumen (Por RDCL)

    5/64

    Project Life Cycle and Organization

    Project life cycle - Organizations performing projects will usually divide each project into several project

    phases to improve management control. Collectively, the project phases are known as the project life cycle.

    Usually they are sequential.

    Project Life Cycle Define

    What technical work to do in each phase When the deliverables are to be generated, how they are reviewed, verified & validated. Who is involved in each phase How to control and approve each phase

    Project Phase

    Each project phase is marked by completion of one or more deliverables. A deliverable is a tangible,

    verifiable work product. The conclusion of a project phase is generally marked by a review of both keydeliverables and project performance to date, to a) determine if the project should continue into its next

    phase and b) detect and correct errors cost effectively. These phase-end reviews are often called phase

    exits, stage gates, or kill points. Practice of overlapping phases is often called fast tracking.

    Cost and staffing

    levels are low at the start, higher towards end, and drop rapidly as the project draws to a conclusion.

    Completion

    The probability of successful completion generally gets progressively higher as the project continues.

    Stakeholder Influence

    On the final characteristics of the projects product and the final cost of the project is highest at the start and

    gets progressively lower as the project continues.Risk

    Uncertainty and hence risk of failing is high at the beginning and get progressively lesser/better as project

    continues

    Key stakeholders

    pm, customer (buy/use), org, team & sponsor (pays), Project Management team, PMO Differences - In

    general, differences between or among stakeholders should be resolved in favor of the customer.

    Managing

    is primarily concerned with consistently producing key results expected by stakeholders,Leading

    Establishing direction vision of the future and strategies, Aligning people to vision, Motivating and inspiring.

    Problem definition

    Requires distinguishing between causes and symptoms. Problems may be internal (a key employee is

    reassigned to another project) or external (a permit required to begin work is delayed). Problems may be

    technical (differences of opinion about the best way to design a product), managerial (a functional group is

  • 7/29/2019 PMP Resumen (Por RDCL)

    6/64

    not producing according to plan), or interpersonal (personality or style clashes).

    Organizational Structure Influence on Projects

    Functional Weak Matrix Balanced Matrix Strong Matrix Projectized

    PM authority Little or None Limited Low to Moderate Moderate to High High to Total

    Resource Availability Little or None Limited Low to Moderate Moderate to High High to Total

    Project Budget Functional Mngr Functional Mngr Mixed PM PM

    PM Role Part Time Part Time Full Time Full Time Full Time

    Administrative Staff Part Time Part Time Full Time Full Time Full Time

    PMO

    Can exist in any kind of organization including the functional organization

    Planning

    Planning is the only PM Process group that has a specific order of activities

    Release Resources

    Is the Last activity in the closing process group.

    Iterations

    Start after Risk management because only after this final cost and schedule can be determined

    Functional Organization

    Advantages Disadvantages

    Easier management of specialists People place more emphasis on their functionalspecialty to the detriment of project

    Team members report to only one supervisor No career path in project management

    Similar resources are centralized PM has little/no authorityProjectized Organization

    Advantages Disadvantages

    Efficient project organization No home when project is completed

    Loyalty to the project Lack or professionalism in disciplines

    More effective communications than functional Duplication of facilities and job functions

    Less efficient use or resources

    Matrix Organization

    Advantages Disadvantages

    Highly visible project objectives Extra administration required

    Improved PM control over resources More than one boss for project teams

    More support from functional areas More complex to monitor and control

    Maximum utilization of scarce resources Tougher problems with resource allocation

    Better coordination Need extensive policies and procedures

    Better horizontal and vertical dissemination ofinformation

    Functional managers may have different prioritiesthan project managers

    Team members maintain a home Higher potential for conflict

  • 7/29/2019 PMP Resumen (Por RDCL)

    7/64

    Project MANAGEMENT Processes for a project

    Pick Process

    Project Manager along with team is responsible for picking what processes are appropriate

    Concept of interaction among PM processes

    (By Shewhart & Deming) PLAN DO CHECK ACT

    Monitoring & Control

    Group not only monitors and controls the work being done within a process group but also monitors andcontrols the entire project effort

    Process

    is a series of actions bringing about a result

    Process Group

    Are not project phases. Process groups are usually repeated for each phase/sub project.

    Initiating Process

    Are often done external to the projects scope of control

    Project Charter

    Approval and funding are handled external to the project boundaries. Charter is primarily concerned withauthorizing the project /phase. It links project to the ongoing work of the organization.

    Rolling Wave Planning

    Progressive detailing of the project management plan is called rolling wave planning, indicating plan is aninteractive and ongoing process.

    Executing Process Group

    Majority of the project budget will be spent in performing Executing process group.

    Integrated Change Control

    Is performed throughout the project, from project initiation thru Project closure.

    Core processes

    Are Performed in same order & may be iterated several times during any one phase

    Facilitating processes

    Performed intermittently and as needed during project planning, they are not Optional.

  • 7/29/2019 PMP Resumen (Por RDCL)

    8/64

    Project INTEGRATION Management

    Knowledge

    Areas

    Major Processes

    desc.Primary Inputs

    Tools &

    TechniquesPrimary Outputs

    Integration

    Develop Project

    Charter

    Developing the project

    charter that formally

    authorizes a project or

    a project phase

    1. Project Statement

    of Work

    2. Business Case

    3. Contract

    4. Enterprise

    environmental factors

    5. Organizational

    Process Assets

    1. Expert

    Judgment

    1. Project Charter

    Develop Project

    Management

    Plan

    Documenting the

    actions necessary to

    define, prepare,

    integrate and

    coordinate all

    subsidiary plans into a

    project management

    plan.

    1. Project Charter

    2. Outputs from

    planning process

    3. Enterprise

    Environmental Factors

    4. Organizational

    Process Assets

    1. Expert

    Judgment

    1. Project

    Management Plan

    Direct and

    Manage Project

    Execution

    Performing the work

    defined in the project

    management plan to

    achieve the projects

    objectives.

    1. Project

    Management Plan

    2. Approved Change

    Requests

    3. Enterprise

    Environmental Factors

    4. Organizational

    Process Assets

    1. Expert

    Judgment

    2. PMIS

    1. Deliverables

    2. Work Performance

    Information

    3. Change Requests

    4. Project

    management plan

    updates

    5. Project document

    updates

  • 7/29/2019 PMP Resumen (Por RDCL)

    9/64

    Monitor and

    Control Project

    Work

    Tracking, reviewing and

    regulating the progress

    to meet the

    performance objectives

    defined in the project

    management plan

    1. Project

    Management Plan

    2. Performance

    reports

    3. Enterprise

    Environmental Factors

    4. Organizational

    Process Assets

    1. Expert

    Judgment

    1. Change Requests

    2. Project

    Management Plan

    Updates

    3. Project Document

    Updates

    Perform

    Integrated

    Change Control

    Reviewing all change

    requests, approving

    changes, and managing

    changes to the

    deliverables,

    organizational process

    assets, project

    documents and the

    project management

    plan.

    1. Project

    Management Plan

    2. Work Performance

    Information

    3. Change Requests

    4. Enterprise

    Environmental Factors

    5. Organizational

    Process Assets

    1. Expert

    Judgment

    2. Change

    Control Meetings

    1. Change Request

    status updates

    2. Project

    Management Plan

    updates

    3. Project Document

    updates

    Close Project

    or Phase

    Finalizing all activities

    across all of the Project

    Management Process

    Groups to formally

    close the project or a

    project phase.

    1. Project

    Management Plan

    2. Accepted

    Deliverables

    3. Organizational

    Process Assets

    1. Expert

    Judgment1. Final Product,

    Service or result

    4. Organizational

    Process Assets

    updates

    Integration Management

    Identification, Definition, Combination, Unification, and Coordination of the various processes and project

    management activities within the Project Management Processes Groups. Integration is about making

    choices, about where to concentrate resources and effort. It also involves making tradeoffs among competing

    objectives and alternatives. PM and team must address every process and level of implementation for

    process

    Project Deliverables

    Need to be integrated with ongoing operations.

    Reasons to start projects

    1. Problems 2. Market Opportunity 3.Business Requirements

    Project Charter

    1. Authorize project

  • 7/29/2019 PMP Resumen (Por RDCL)

    10/64

    2. Gives Project Manager Authority

    3. Issued by initiator or sponsor external to project organization who has the authority to fund.

    4. It is broad enough that it does not have to change as the project changes

    Project Charter Contain

    1. Requirements that specify Customer/Sponsor Needs, wants and expectations

    2.Business Needs

    3.Project purpose or justification

    4. Assigned PM authority 5.Stakeholder influence

    6.Functional organization participation

    7.Assumptions & Constraints

    8.Business case and return on investment

    9.Summary Budget

    Enterprise Environmental Factors

    Company Culture & Structure, Government or industry standards, infrastructure, existing human resources,

    personal administration (Hire, Fire, performance), work authorization, Marketplace condition, Stakeholder

    risk tolerance, Commercial database, PMIS (existing sysetms) that the project will have to deal with or can

    use of.

    Organizational Process Assets

    Existing Process, Standards, Policies, Standard Product and Project Life Cycles, Quality policies & procedure,

    performance measurement criteria, Templates, Communication requirements, Project Closure Guidelines,

    Risk Control procedure, Issue and Defect Management Procedure, Change Control Procedure, Procedure for

    Approving & issuing work authorization. It also include Process Measurement database, project files,

    Historical information & Lessons learned, Configuration management database, financial database containing

    labor hours, costs & budgets

    Project Selection Methods

    1.Benefit Measurement Methods (Comparative Approach)

    1. Scoring Models

  • 7/29/2019 PMP Resumen (Por RDCL)

    11/64

    2. Benefit Contributions

    3. Murder board Panel of people who try to shoot down a new project idea.

    4. Peer Review

    5. Economic Models

    1. Benefit Cost Ratio

    2. Cash Flow

    3.Internal Return Rate

    4. Preset Value (PV) and net present value (NPV)

    5.Opportunity Cost

    6. Discounted Cash Flow

    7. Return On Investment

    2.Constrained Optimization Methods (Mathematical Models)

    1. Linear 2. Nonlinear 3. Dynamic 4. Integer 5. Multiple Objective Programming

    Project Management Plan

    It defines how project is executed, monitored and controlled and Closed. PMP can be either summary level or

    detailed and can be composed of one or more subsidiary plans and other components. It contains following

    management plans 1. Change, 2. Communications, 3. Configuration, 4. Cost, 5. Cost Performance

    Baseline, 6.Human resources, 7. Process Improvement, 8. Procurement, 9. Quality, 10.

    Requirements, 11. Risk, 12. Schedule Baseline, 13. Schedule, 14.Scope Baseline, 15. Scope.

    Configuration Management

    It is a sub system of overall project management information system. It is a means of monitoring and

    controlling emerging project scope against the scope baseline; its purpose is to manage control changes

    to the deliverables and the resulting documentation, including which organizational tools will be

    used. It is any documented procedures used to apply technical and administrative direction and surveillance

    to audit the items and system to verify conformance requirements. . It documents the physical

    characteristics of formal project documents and steps required to control changes to them (e.g. would be

  • 7/29/2019 PMP Resumen (Por RDCL)

    12/64

    used by a customer who wishes to expand the project scope after the performance measurement baseline

    has been established). When more than one individual has sign a Charter, you have to be concerned with

    competing needs and requirements impacting your efforts on configuration management

    Configuration Management Activities

    1.Configuration Identification 2.Configuration Status Accounting 3.Configuration Verification and auditing

    Change Control System

    It is a collection of formal documented procedures that define how project deliverables and documentation

    are controlled, changed and approved. It is a subsystem of configuration management. It must also include

    procedures to handle changes that may be approved without prior review (e.g. result of an emergency)

    Integrated Change Control

    It is performed from project inception through completion, it includes

    Influencing the factors about change control so that only approved changes are implemented Reviewing, analyzing and approving change requests promptly. Managing approved changes as and when they occur and regulating them Maintain integrity of baseline Review and approve all recommended corrective and preventive actions Coordinating changes across the entire project Documenting the complete impact of requested changes

    Process for Making Changes

    1. Prevent the root causes of changes (proactively eliminate need of changes)2. Identify change (coming from measuring from performance baseline, sponsor, team, management,

    customer, etc.). PM should be looking for changes proactively).

    3. Look for the Impact of the change to the project4. Create a change request (to product scope, project management plan, baseline, etc.)5. Perform Integrated Change control ( a) Assess the change, b) look for options, c) change is

    approved or rejected, d)Update status of the change in change control system ).

    6. Adjust project management plan, project documents, and baselines.7.

    Manage stakeholders expectations communicating changes to stakeholders affected

    8. Manage the project to the revised project management plan and project documentsIntegrated change Control

    Occurs during all the project management processes.

    Project Baseline

    Should be changed for all implemented changes. Sometimes, certain classification of changes gets automatic

    approval on a project and do not need Change Control Board approval.

  • 7/29/2019 PMP Resumen (Por RDCL)

    13/64

    Project Plan

    as an input to team development, the project plan describes the technical context within which the team

    operates

    Project Execution

    Although the products, services or results of the project are frequently in the form of tangible deliverablessuch as building, road or software, intangible deliverables such as training is also provided.

    Schedule Change Control System

    Can include the paper, systems and approvals for authorizing changes. The project manager is normally not

    the approval authority, and not all the changes approved

    Organization Process Assets

    Includes an index & location of project documentation

    Formal Acceptance Documentation Project Files Closure Documents Historical information

    Difference between Configuration Management and Change Management systems

    Both the Configuration Management and Change Management systems are sub systems of the ICC.

    They are to be understood as: Configuration Management System - Relates to maintaining the changes to

    the product of the project. Change Control System - Relates to maintaing the changes to the Project itself.

    Take a small example. Your project is to design a latest design washing machine. You have 2 things here. 1-

    is a Project whose objective is to design the washing machine 2- is a Product of the project - which is the

    washing machine itself. All the characteristics of the Washing Machie viz., height, capacity, drum diameter,

    motor speed, color etc are called configuration of the product. This is maintained in the Configuration

    Management Database. Any change to this configuration will be managed through the Configuration

    Management System.(CMS) On the other hand, there will be plans for controlling scope, cost , time and

    quality in the project. Any change in these constraints would be managed through the Change Control

    System (CCS). Hope this helps.

    Process Improvement Plan

    Is an effort made by PM to improve processes attached to a project, which results in completing the work

    faster, cheaper and with higher quality.

  • 7/29/2019 PMP Resumen (Por RDCL)

    14/64

    Project SCOPE Management

    Knowledge AreasMajor Processes

    desc.Primary Inputs Tools & Techniques Primary Outputs

    SCOPE

    Collect

    Requirements

    Defining and

    documenting

    stakeholders needs

    to meet the project

    objectives.1. Project charter

    2.Stakeholder

    Register

    1. Interviews

    2. focus Groups

    3. Facilitated

    workshops

    4. Group creativity

    techniques

    5. Group decision

    making techniques

    6. Questionnaires

    and surveys

    7. Observations

    8. Prototypes

    1. Requirements

    Documentation

    2. Requirements

    Management Plan

    3. Requirements

    Traceability Matrix

    Define Scope

    Developing a detailed

    description of the

    project and product.

    1. Project charter

    2. Requirements

    Documentation

    3. Organizational

    Process Assets

    1. Expert Judgment

    2. Product analysis

    3. Alternatives

    Identification

    4. Facilitated

    workshops

    1. Project Scope

    Statement

    2. Project Document

    Updates

    Create WBS

    Subdividing project

    deliverables and

    project work into

    smaller more

    manageable

    components

    1. Project Scope

    Statement

    2. Requirements

    documentation

    3. Organizational

    Process Assets

    1. Decomposition1. Work Breakdown

    Structure (WBS)

    2. Scope baseline

    3. WBS dictionary

    4. Project Document

    Updates

    Verify Scope

    Formalizingacceptance of thecompleted projectdeliverables.

    1. ProjectManagement Plan2. RequirementsDocumentation3. RequirementsTraceability Matrix4. ValidatedDeliverables

    1. Inspection1. Accepteddeliverables2. Change requests3. Project Documentupdates

    Monitoring the status 1. Project 1. Variance analysis 1. Work Performance

  • 7/29/2019 PMP Resumen (Por RDCL)

    15/64

    Control Scopeof the project and

    product scope and

    managing changes to

    the scope baseline

    management plan

    2. Work Performance

    information

    3. Requirements

    Documentation

    4. Requirements

    Traceability Matrix

    5. Organizational

    Process Assets

    Measurements

    2. Organizational

    process assets updates

    3. Change requests

    4. Project

    management plan

    updates

    5. Project document

    updates

    Scope Management Plan Project Scope

    Provides guidance on how project scope will be defined, documented, verified, managed and controlled. This

    planning effort is part of the Develop Project Management Plan, in the Integration process group.

    Project Scope: the work that must be done in order to deliver a product; completion is measured against theproject plan. It includes meetings, reports, analysis and all the other parts of PM.

    Product Scope: features and functions that are to be included in a product; completion is measured against

    the Product requirements. It can be supplied as a result of a previous project to determine the requirements

    Scope Management Process

    1. Determine Requirements, making sure all of them support the business need as described on the charter.

    2. Sort thru and balance needs of the stakeholders to determine product scope and project scope.

    3. Create a WBS to break scope down to smaller more manageable pieces.

    4. Verify that the scope of work planned is actually being done

    5. Measure scope performance, and adjust as needed.

    Requirements Documentation

    How requirements meet business needs:

    (Non)Functional reqs, Quality reqs, Acceptance criteria, Assumptions, Organizational Areas Impacted.

    Signed by stakeholders.

    Requirements Management Plan: Documents how requirements will be analyzed, documented, andmanaged throughout the project. Main parts are:

    How reqs activities will be planned, tracked and reported Configuration management activities (how changes to product/service/result will be initiated, analyzed

    for impacts, tracked, and reported, and authorization levels to approve changes) Reqs prioritization process Product metrics Traceability structure

    Requirements Traceability Matrix: PM uses the RTM to keep track of all information and to analyzerequirements proposed. It takes a form of table with information like:

    Identification numbers Source of each requirement

  • 7/29/2019 PMP Resumen (Por RDCL)

    16/64

    Who is assigned to manage the requirement (similar to risk owners) Status of requirement (including if its finished)

    Rolling Wave Planning

    The Project Management team usually waits until the deliverable or subproject is clarified so the details of theWBS can be developed. This is referred as rolling wave planning. So Work to be performed in the near futureis planned to the low level of the WBS, whereas work to be performed far into the future can be planned atthe relatively high level of the WBS.

    WBS Dictionary

    For each WBS Component, WBS dictionary includes a Code of Account Identifier, a description of work,

    responsible organization, and a list of schedule milestones. Other information can be Contract information,

    Quality requirements, acceptance criteria, and technical reference, among others.

    Scope Baseline

    Includes:

    Approved project Scope statement WBS WBS dictionary

    Verify Scope

    Is the process of formalizing acceptance of the completed project deliverables. Includes reviewing deliverables

    with the customer or sponsor to ensure that theyre completed satisfactory and obtaining formal acceptance of

    deliverables. Differs from Quality Control in that Scope is concerned with acceptance of deliverables, while

    Quality Control is concerned with correctness od the deliverables meeting quality requirements specified for

    the deliverables.

    Inspection

    Are called Reviews, Product Reviews, Audits and Walkthroughs.Scope Creep

    Uncontrolled changes are often referred as project scope creep

    Variance Analysis

    Project performance is measurements are used to assess the magnitude of variation. It includes finding the

    cause of variation relative to the scope baseline.

    Constraints

    A constraint is an applicable restriction that will affect the performance of the project. For example, a

    predefined budget is a constraint

    Assumptions

    Assumptions are factors that, for planning purposes, are considered to be true, real, or certain.

    Decomposition

    (1st level Project phases, 2nd level Deliverables (Break down till cost estimates can be done, verify

    decomposition correctness) ) lowest level of the WBS may be referred to as work packages. Work not in the

    WBS is outside the scope of the project.

  • 7/29/2019 PMP Resumen (Por RDCL)

    17/64

    Decomposing

    subdividing project work packages into smaller, more manageable components (activities/action steps). The

    heuristic (rule of thumb) used in project decomposition is 80 hours.

    Stakeholder Management

    the project manager must identify the stakeholders, determine their needs and expectations, then manageand influence expectations to ensure project success. Project success depends primarily on customer

    satisfaction.

    WBS

    subdividing project deliverables into smaller, more manageable components. It is a deliverable-oriented

    grouping of project elements that organizes and defines the total scope of the project. It is a communication

    tool and it describes what needs to be done and what skills are required. Anything missing in the WBS should

    be added. The 1st level should be the project life-cycle (not product). The WBS is created by the team (helps

    to get buy-in) and it is used to make certain that all the work is covered. It provides a basis for estimating the

    project and helps to organize the work. Its purpose is to include the total project scope of all the work that

    must be done to complete the project. Defines the projects scope baseline.

    WBS Dictionary

    Defines each item in the WBS, including description of the work packages and other planning info such as

    schedule dates, cost budgets and staff assignments. It helps reduce Scope Creep and increases

    understanding. WBS dictionary can be used as a part of Work Authorization system to inform team members

    of when their work package is going to start, schedule milestones and other info.

    Scope Statement

    Define and record Requirements. A documented description of the objectives, work content, deliverables, and

    end product; it includes a description of project assumptions and constraints. Provides stakeholders with a

    common understanding of the scope of the project and is a source of reference for making future project

    decisions

    Statement of Work

    a narrative description of products or services to be supplied under contract.

    Work Package

    deliverable at the lowest level of WBS. They are control points in the WBS and are used for assignments to

    work centers. They are used to pass a group of work for further breakdown in the executive organization.

    Control Account

    one level above the Work Package.

    Assumptions

    factors that, for planning purposes, are considered to be true, real or certain The principal sources of project

    failure are organizational factors, poorly identified customer needs, inadequate specified project requirements,

  • 7/29/2019 PMP Resumen (Por RDCL)

    18/64

    and poor planning and control.

  • 7/29/2019 PMP Resumen (Por RDCL)

    19/64

  • 7/29/2019 PMP Resumen (Por RDCL)

    20/64

    6. Enterprise

    environmental factors

    7. Organizational

    Process Assets

    5. Reserve Analysis

    Develop

    Schedule

    Analyzing activitysequences, durations,

    resource

    requirements, and

    schedule constraints

    to create the project

    schedule.

    1. Activity list2. Activity Attributes

    3. Project Schedule

    network diagrams

    4. Activity Resource

    requirements

    5. Resource Calendars

    6. Activity duration

    estimates

    7. Project Scope

    Statement

    8. Enterprise

    environmental factors

    9. Organizational

    process assets

    1. ScheduleNetwork analysis

    2. Critical path

    method

    3. Critical chain

    method

    4. Resource

    leveling

    5. What-if scenario

    analysis

    6. Appling leads

    and lags

    7. Schedule

    Compression

    8. Scheduling tool

    1. Project schedule

    2. Schedule

    baseline

    3. Schedule data

    4. project

    document updates

    Control

    Schedule

    Monitoring the status

    of the project to

    update project

    progress and manage

    changes to schedule

    baseline

    1. Project management

    plan

    2. Project schedule

    3. Work performance

    information

    4. Organizational

    process assets

    1. Performance

    reviews

    2. Variance analysis

    3. Project

    management

    software

    4. Resource

    leveling

    5. What-if scenario

    analysis

    6. Adjusting leads

    and lags

    7. Schedule

    compression

    8. scheduling tool

    1. Work

    performance

    measurements

    2. Organizational

    process assets

    updates

    3. Change requests

    4.Project

    management plan

    updates

    5. Project

    document updates

  • 7/29/2019 PMP Resumen (Por RDCL)

    21/64

    Project Time Management

    processes required to ensure timely completion of the project

    Activity Definition

    defines activities that must take place to produce project deliverables

    Activity

    consumes time (eg testing

    Events (or Milestones)

    specified accomplishment / does not consume time (eg tested)

    Time Management

    In small projects Activity Definition, Sequencing, Resource Estimation, Duration Estimation and Schedule

    development are so tightly linked that they are viewed as single process.

    Schedule Management Plan

    Is part of Develop Project Management Plan Process. SMP is a subsidiary plan of PMP and may formal or

    informal, highly detailed or broadly framed depending on the project. Includes: 1) Scheduling methodology,

    2)schedule baseline, 3)Identification of performance measures, 4) planning schedule variances management,

    5)Identification of schedule change control procedures.

    Decomposition(Tools and Techniques used in Activity Definition)

    Involves sub dividing the Work Packages into smaller components called activities. Activity Definition output is

    schedule activities not Deliverables (Create WBS output is Deliverables) Activity list, WBS and WBS dictionary

    can be developed either sequentially or concurrently. Performed by team members responsible for the work

    package.

    Control Account

    From management Perspective a control line is drawn in the WBS Hierarchy levels. All the Planning

    components above this line belong to what is called the Control Account. All efforts performed within a control

    account are documented in a control account plan.

    Planning Package

    It is a WBS Component below the control account but above the work package.

    Activity List

    Does not include any schedule activity that is not required as part of the project scope It includes a activity

    identifier and scope of work description for each schedule activity in sufficient detail. It is used in schedule

    model and is part of PMP(Project Management Plan) Discrete components of Project Schedule but are not

    components of the WBS.

    Activity Attributes

    Contain Activity identifier, activity Code, Activity Description, Predecessor Activities, Successor activities,

    logical relationships, leads and lags, resource requirements, imposed dates, constraints and assumptions.

    Milestone

    Can be mandatory or optional, it a component of PMP, included in SS and WBSD and used in schedule model.

    PM can impose additional milestones.

  • 7/29/2019 PMP Resumen (Por RDCL)

    22/64

    Fragment Network

    Portions of project schedule network diagram are often referred to as a Sub network or Fragment Network.

    Sub Network templates are useful when project has several identical or nearly identical deliverables.

    Lead and Lag

    Lead allows acceleration of the successor activity, A lag direct a delay in Successor activity

    Bottom Up Estimation

    Estimation is done for lower level items and then aggregated.

    Activity Resource Estimation

    Identifies type and quantities of resources required for a schedule activity. These are aggregated to determine

    the estimated resources for each work package

    RBS (Resource Break Down Structure)

    Output of Activity Resource Estimation process, it is a hierarchical structure of resources by category & type.

    Tools and Techniques for Estimate Activity Duration

    One Point Estimate One estimator submits one estimate per activity. It can made based on theexpert judgment.

    Analogous Estimation Using actual duration of previous similar schedule activity. It is projectlevel, given to PM from Management or Sponsor; it is a form of Expert Judgment.

    Parametric Estimation Quantity of Work * Productivity Rate - 1.Regression Analysis (ScatterDiagram) 2.Learning Curve. Results of Parametric Estimation can become heuristics.

    Three Point Estimates Most Likely, Optimistic, Pessimistic. Reserve Analysis Reserve Analysis to have a reserve for accommodate the risks that remain in the project. These

    reserves can be reduced after completion of Plan Risk Responses process. There are two types of

    reserves: 1)Contingency (or buffers) for covering the Plan Risk Responses 2) Management Reserves

    (to cover unforeseen risks).

    Imposed Dates

    Imposed dates in Scope Statement (I/P to Schedule Development Process) restrict the start or finish date.

    Schedule Network Analysis (Tools abd Techniques for Schedule Development)

    Critical Path Method Calculate Project Duration, Critical path length and Float. Critical path canhave 0 or negative total float.

    Schedule Compression Crashing (Additional Resources) and Fast Tracking (Parallel) What-if Scenario Monte Carlo Analysis Resource Leveling Applied after Critical Path Method,

    Keep resource usage at constant level

    Critical Chain Method Uses Pessimistic resource availability, Adds duration buffers that are non

  • 7/29/2019 PMP Resumen (Por RDCL)

    23/64

  • 7/29/2019 PMP Resumen (Por RDCL)

    24/64

    Finish-to-Start logical relationship Time estimates appear on arrow

    Critical Path Method

    (CPM)

    Emphasis on controlling cost and leaving the schedule flexible One time estimate per activity Activity oriented; uses dummy; activity on arrow Time estimates appear on arrow

    Precedence Diagram

    Method (PDM)

    Represents improvement to PERT and CPM by adding lag relationships toactivities

    [Start to Start; Start to Finish; Finish to Start; Finish to Finish] Work is done during activity. Arrow indicates dependancy Activity on node; no dummy finish-to-start is the most commonly used type of logical

    relationship. Start-to-finish relationships are rarely used

    GERTA network diagram drawing method that allows loops between tasks. It is a method of

    sequencing (e.g. a project requires redesign after completion of testing)

    Dependencies

    Mandatory or HardOften involve physical or technological limitations (based on the nature of work being

    done)

    Discretionary

    may also be called preferred logic, preferential logic, or soft logic. Soft: desirable and customary (based on experience) Preferential: preferred or mandated by a customer (also, need of the project

    sponsor)

    Defined by PM Team

    External Input needed from another project or source

    Critical chain is a technique that modifies the project schedule to account for limited resources.

    Monte Carlo Analysis

    Computer simulation of project outcomes using PERT estimates; result represented in S curve. Provides the

    ability to compute the probability of completing a project on a specific day. Can also be used to assess

    feasibility of schedule under adverse conditions (eg when a schedule constraint is identified)

    Heuristics - rules of thumb

    Critical Path longest path (almost always have no float)

    Near Critical Path Path is close in duration to critical path, the close it is the more RISK project has.

  • 7/29/2019 PMP Resumen (Por RDCL)

    25/64

    Variance - Plan minus Actual

    Float / Slack

    1.Free 2. Total 3. Project Float. Time an activity may be delayed from its early start without delaying the

    project finish date. Difference between the required end date and the expected project completion date. A

    negative slack on the critical path means that the project is behind schedule.

    Free Float

    Amount of time a task can be delayed without delaying the early start of its successor

    Total Float

    amount of time that an activity may be delayed from early start without delaying the project finish date

    Lag waiting time between two tasks (negative lead)

    Schedule Baseline

    The original, approved project schedule; should never be changed without proper review and approval. Any

    approved change should be documented in writing. Should be created at the beginning of the project and

    used during the project to gauge (measure) overall project performance, not just schedule. The project

    Performance Measurement Baseline should generally change only in response to a scope or deliverable

    change. The project performance measurement baselines should generally change only in response to a scope

    or deliverable change

    Corrective action - in project time management primarily concerns expediting to ensure that activities

    remain on schedule. Is anything done to bring expected future schedule performance in line with the project

    plan.

    Revisions are changes to the scheduled start and finish dates in the approved project schedule; generally

    revised only in response to scope changes. Rebaselining may be needed to provide realistic data to measure

    performance. Scheduling and allocating resources to multiple projects may affect schedule slippage and in-

    process inventory.

    Duration Compression Methods occurs after activity duration estimating and before finalizing the

    schedule. Include crashing, fast track,

    Crashing when you are worried about time, not so much about costs.

    Fast Track resources in parallel, involve increase rework. Should fast track tasks on the critical path (float

    = 0) in order to save time.

    Resource Leveling often results in a project duration that is longer than the preliminary schedule.

    Resource reallocation from non-critical to critical path activities is a common way to bring the schedule

    back, or as close as possible, to the originally intended overall duration. So 1. Schedule Can Slip 2. Cost

    increase

  • 7/29/2019 PMP Resumen (Por RDCL)

    26/64

    Finish to Finish - activities must finish on a specific sequence

    Start no earlier than & Finish no later than Respectively #1 and #2 most popular date constraint in

    project management software

    Root Cause Analysis used to identify the cause of the variation

    Variance analysis key element to time control. Float variance is an essential planning component for

    evaluating project time performance

    Revision category of schedule update that result in change to the projects scheduled start or finish dates.

    New target schedule should be the usual mode of schedule revision.

    Schedule Management Plan -defines how schedule changes will be managed; may be formal or informal.

    Schedule Change Control System-defines procedures for changing the project schedule and includes the

    documentation, tracking systems, and approval levels required for authorizing schedule changes.

    Resource Planning Tools

    Responsibility Matrix Identify who does what at what time/phase of the project

    Resource SpreadsheetQuantifies how much work is needed from each resource during each time

    period

    Resource Gantt ChartIdentify the periods of time (e.g. calendar date) when a particular resource

    is working on a particular task

    Resource Histogram (Resource

    Loading Chart)

    Vertical bar chart showing the total number of resources needed during

    each time period

    Scheduling Tools

    Networks (PERT, CPM, PDM) Interdependencies; how related

    Barchart (Gantt)Effective progress reporting tool; no logical relationships shown between

    activities

    Milestone Chart Significant events; good for communicating status (used to track success)

    Bar Chart (Grant Chart) 1. Weak Planning Tools 2. Good reporting tools 3. No Dependency Shown 4. No

    Resources shown

    Progress Report 50/50, 20/80, 0/100 An Activity is considered X percent complete when it begins

    and gets credit of the last 100-X percent only when it is completed.

  • 7/29/2019 PMP Resumen (Por RDCL)

    27/64

    Project COST Management

    Knowledge AreasMajor Processes

    desc.Primary Inputs Tools & Techniques

    Primary

    Outputs

    Cost

    Estimate

    Costs

    Developing an

    approximation of the

    monetary resources

    needed to complete

    project activities

    1. Scope Baseline

    2. Project Schedule

    3. Human resource

    Plan

    4. Risk Register

    5. Enterprise

    environmental factors

    6. Organizational

    Process Assets

    1. Expert Judgment

    2. Analogous estimating

    3. Parametric estimating

    4. Bottom-up estimating

    5. Three-point estimates

    6. Reserve Analysis

    7. Cost of quality

    8. Project Management

    Estimating Software

    9. Vendor bid analysis

    1. Activity

    Cost estimates

    2. Basis of

    estimates

    3. Project

    Document

    updates

    Determine

    Budget

    Aggregating the

    estimated costs of

    individual activities or

    work packages to

    establish a cost

    baseline (excludes

    management

    reserves).

    1. Activity Cost

    estimates

    2. Basis of estimates

    3. Scope baseline

    4. Project Schedule

    5. Resource Calendars

    6. Contracts

    7.Organizational

    Process Assets

    1. Cost aggregation

    2. Reserve Analysis

    3. Expert Judgment

    4. Historical relationships

    5. Funding Limit

    reconciliation

    1. Cost

    performance

    baseline

    2. Project

    funding

    requirements

    3. Project

    Document

    updates

    Control

    Costs

    Monitoring the status

    of the project to

    update the project

    budget and managing

    changes to the cost

    baseline. (influencing

    the factors that create

    changes to the

    authorized cost

    baseline)

    1. Project management

    plan

    2. Project funding

    requirements

    3. Work performance

    information

    5. Organizational

    process assets

    1. Earned Value

    Management

    2. Forecasting

    3. To-complete

    performance index

    4. Performance Reviews

    5. Variance Analysis

    6. Project Management

    software

    1. Work

    performance

    measurements

    2. Budget

    forecasts

    3.

    Organizational

    process assets

    updates

    4. Change

    requests

    5. Project

    management

  • 7/29/2019 PMP Resumen (Por RDCL)

    28/64

    Plan updates

    6. Project

    Document

    Updates

    Estimate Costs

    Developing and approximation (estimate) of the costs of the resources needed to complete project activities.Determine Budgeting

    Allocating the overall cost estimate to individual work activities.

    Control Cost

    Controlling changes to the project budget.

    Life Cycle Costing

    Broader view of Project Cost Management, which includes cost of resources needed to complete schedule

    activities along with effect of decisions on cost of using, maintaining & supporting the product, service or

    result of the project.

    Cost Management Plan

    It is created as part of the Develop Project Management Plan process. It can establish:

    1)Specifications for how estimates should be stated 2)Level of accuracy for estimates 3)Reporting formats 4) Rules for measuring cost performance 4)Whether costs will include both direct costs and indirect costs 5) Control thresholds.

    Accuracy of Estimates

    ROM (Rough Order of Magnitude): Accuracy of project estimate, done at initiating process.Project at initial stages can have ROM in the range of+/50% from actual later it will narrow to a

    range of10 to +15%.

    Budget Estimate: Usually made during the planning phase, in the range of -10 to +25 % fromactual.

    Definitive Estimate:Estimate will become more refined later on the project. Its used whether +/-10%, or -5 to +10%.

    Contingency Reserve

    1.Project (known Unknowns) Part of Cost Baseline 2.Management (Unknown Unknowns) Part of Cost

    Budget

    Chart of Accounts

    A chart of accounts describes the coding structure used by the performing organization to report financial

    information in its general ledger

    Analogous estimating

    also called top-down estimating, means using the actual cost of a previous, similar project Parametric

    modeling - mathematical model to predict project costs - per square foot of living space

  • 7/29/2019 PMP Resumen (Por RDCL)

    29/64

    Parametric Estimation

    It uses statistical relationship between historical data and other variables to calculate cost estimate. It can

    produce higher levels of accuracy depending on sophistication, resource quantity and cost data.

    Bottom-up estimating

    the cost of individual activities or work packages rolled up to get the estimate for whole component.

    Determine Budget

    Cost baseline: Is a time-phased budget that will be used to measure and monitor cost performance on the

    project. It is shown as an S curve.

    Control Account: Represent the basic level at which project performance is measured and reported. The

    purpose of cost accounts is to monitor and report on project performance.

    Contingency Reserves: Address the cost impacts of the risks remaining during risk response planning.

    Management Reserves: Extra funds to be set aside to cover unforeseen risks or changes to the project.

    Funding Limit Reconciliation

    Customer will set limits on disbursement of funds for the project. Funding Limit Reconciliation (TT of Cost

    Budgeting) will necessitate the scheduling of work to be adjusted to smooth or regulate those expenditures.

    It is accomplished by placing imposed date constraints for some work packages.

    Project Performance Reviews (Tools and Techniques of Cost Control)

    1.Variance Analysis 2.Trend Analysis 3.Earned Value Technique

  • 7/29/2019 PMP Resumen (Por RDCL)

    30/64

    Progress Reporting: Rules of:

    50/50: Activity is considered 50% complete when it begins, and gets 50% only when its completed

    20/80: Activity is considered 20% complete when it begins, and gets 80% only when its completed

    0/100: Activity gets no credit for partial completion. It only gets credit only when its full completed

    EAC

    Original estimating assumptions were fundamentally flawed, or that they are no longer relevant to a change

    in conditions. Formula: EAC = AC + ETC. Current variances are seen as atypical and the project management

    team expectations are that similar variances will not occur in the future. Formula: EAC = AC + BAC EV.

    When current variances are seen as typical of future variances. Formula: EAC = AC + ((BAC EV)/CPI)

    Project Cost ManagementProcesses required to ensure that the project is

    completed within the approved budget.

    Benefit Cost Ratio

    Expected Revenues / Expected Costs. Measure benefits

    (payback) to costs; not just profits. The higher the better(if rating over 1, the benefits are greater than the costs)

    Internal Rate of ReturnInterest Rate which makes the PV of costs equal to PV of

    benefits

    Payback Period

    Number of time periods up to the point where cumulative

    revenues exceeds cumulative costs. Weakness in this

    approach is the lack of emphasis on the magnitude of the

    profitability. Does not account for time value of money

    nor consider value benefits after payback.

    Opportunity Cost

    Cost of choosing one alternative and therefore giving up

    the potential benefits of another alternative: it is the

    value of the project not selected (lost opportunity).

    Sunk CostExpended costs which should be ignored when making

    decisions about whether to continue investing in a project

    Law of Diminishing Returns Straight Line

    Depreciation

    The point beyond which the marginal addition of

    resources does not provide a proportional amount of

    utility. Same amount each time period (e.g. 10 10

    10). Types 1. Straight Line 2. Accelerated (1. Double

    Declining Balance 2. Sum of Years Digits)

    Contingency Reserve

    Separate quantity of time/money for known unknowns.

    Designed to cover specific risk events previously identified

    and measured in the Risk Management Process.

    Management Reserve Separate quantity of time/money for unknown unknowns

  • 7/29/2019 PMP Resumen (Por RDCL)

    31/64

    Working Capital Current Assets - Current Liabilities

    Value Analysis

    Cost reduction tool that considers whether function is

    really necessary and whether it can be provided at a

    lower cost without degrading performance or quality.

    Finding the least expensive way to do the scope of work.

    Value Estimating Part of Cost Control

    Value Engineering ToolTool for analyzing a design, determining its function, and

    assessing how to provide those functions cost effectively.

    50-50 RuleAt beginning, charge 50% of its BCWS to the account.

    Charge remaining at completion.

    Analogous Estimating

    Top down; based on similar projects. Represents a form

    of expert judgment. Gives project team an understanding

    of managements expectations (part of cost budgetingand cost estimating)

    Bottom-up EstimatingDetailed cost estimates of work packages are aggregated.

    Would provide best overall quality of the estimate.

    Parametric Estimating

    Relies on knowledge of mathematical relationships;

    measured in $/unit (scalable, quantifiable). It does not

    make use of team estimate. (part of cost budgeting and

    cost estimating). Using a mathematical model to predict

    the duration of a task (e.g. taking the average duration of

    all past tasks)

    Regression AnalysisStatistical technique graphically represented on scatter

    diagram

    Learning Curve

    Mathematically models the intuitive notion that the more

    times we do something, the faster we will be able to

    perform

    Variable Costs Costs rise directly with the size and scope of the project

    Fixed CostsCosts do not change; non-recurring (e.g. project setup

    costs)

    Direct Costs

    Incurred directly by a specific project. The PMI want the

    team to participate in the cost estimates to get their buy-

    in.

    Indirect CostsPart of the overall organization's cost of doing business

    and are shared by all projects. Usually computed as a

  • 7/29/2019 PMP Resumen (Por RDCL)

    32/64

    percentage of the direct costs.

    Control Account

    Represent the basic level at which project performance is

    measured and reported. The purpose of cost accounts is

    to monitor and report on project performance.

    Cost Change Control Systems Includes the documentation, tracking systems, andapproval levels needed to authorize a change.

    Budget updatesShould be the next steps after an approved cost baseline

    has changed because of a major change on a project.

    Operating profitAmount of money earned: Revenue (direct + indirect

    costs)

    Discounted cash-flow approach

    Present value method determines the net present value of

    all cash flow by discounting it by the required rate of

    return.

    Parametric modelingInvolves using project characteristics (parameters) in a

    mathematical model to predict project costs.

    Life-Cycle CostProvide a picture of the total cost for the product (project,

    operations and maintenance).

    Project Closeout(output to cost control) Process and procedures

    developed for the closing or canceling of projects

  • 7/29/2019 PMP Resumen (Por RDCL)

    33/64

    Project QUALITY Management

    Knowledge AreasMajor Processes

    desc.Primary Inputs Tools & Techniques Primary Outputs

    Quality

    Plan

    Quality

    Identifying quality

    requirements and/or

    standards for the

    project and product,

    and documenting how

    the project will

    demonstrate

    compliance.

    1. Scope baseline

    2. Stakeholder

    register

    3. Cost performance

    baseline

    4.Schedule baseline

    5. Risk register

    6. Enterprise

    environmental

    factors

    7. Organizational

    Process Assets

    1. Cost-Benefit

    analysis

    2. Cost of quality

    3. Control Charts

    4.Benchmarking

    5. Design of

    experiments

    6. Statistical sampling

    7. Flowcharting

    8. Proprietary quality

    management

    methodologies

    9. Additional quality

    Planning Tools

    1. Quality

    management plan

    2. Quality Metrics

    3. Quality Checklists

    4. Process

    Improvement Plan

    5. Quality Baseline

    6. Project

    Management Plan

    (updates)

    Perform

    Quality

    Assurance

    Auditing the quality

    requirements and the

    results from quality

    control

    measurements to

    ensure appropriate

    quality standards and

    operational definitions

    are used

    1. Project

    management plan

    2. Quality metrics

    3. Work

    performance

    information

    4. Quality control

    measurements

    1. Plan quality and

    perform quality control

    tools and techniques

    2. Quality audits

    3. Process analysis

    1. Organizational

    process assets

    updates

    2. Change requests

    3. Project

    management plan

    updates

    4. Project document

    updates

    Perform

    Quality

    Control

    Monitoring and

    recording results of

    executing the quality

    activities to assess

    performance and

    recommend necessary

    changes

    1. Project

    management plan

    2. Quality Metrics

    3. Quality Checklists

    4. Work

    performance

    measurements

    5. Approved Change

    Requests

    1. Cause and effect

    diagram

    2. Control charts

    3. Flow-charting

    4. Histogram

    5. Pareto chart

    6. Run Chart

    7. Scatter diagram

    8. Statistical sampling

    1. Quality Control

    Measurements

    2. Validated

    Changes

    3. Validated

    deliverables

    4. Organizational

    process assets

    updates

  • 7/29/2019 PMP Resumen (Por RDCL)

    34/64

    6. Deliverables

    7. Organization

    process assets

    9. Inspection

    10. Approved change

    requests review

    5. Change requests

    6. Project

    management plan

    updates

    7. Project document

    updates

    Quality: Degree to which the project fulfills requirements.

    Grade: Category assigned to products or services having the same functional use but different

    characteristics.

    Low grade (a limited number of features) - low quality (many bugs)

    Precision Consistency that the value of repeated measurements have little scatter. Precise measurementsmay not be accurate

    Accurate It correctness of measured value, accurate measurements may not be precise.

    Joseph Juran Quality - Fitness of Use Edward Deming Quality Improvement Plan, Do, Check and Act Philip Crosby Quality Conformance to requirements, Advocated Prevention over inspection and

    Zero defects

    Quality ManagementCreating and following policies and procedures to ensure that a project meets thedefined needs it was intended to meet from the customers perspective.

    Cost of quality - All work to ensure conformance to requirements + nonconformance to requirements.

    Cost of conformance: (quality training, studies, surveys, efforts to ensure everyone knows the processesto use to complete their work).

    Cost of non conformance: (Rework, scrap, inventory costs, warranty costs, lost business).Costs of nonconformance should be lower than the costs of nonconformance.

    Continuous Improvement (or Kaizen):Kaizen: (Kai: means to alter, Zen: Make better or improve).Continuous Improvement: quality movement.

    Marginal Analysis Optimal Quality is reached at the point where the increased revenue fromimprovement equal incremental cost to secure it

    Quality Management Plan Provides input to the overall project management plan and must addressQuality Control, Quality Assurance and continues process improvement for the project. Peer review may notinclude individuals that worked on the material being reviewed.

    Gold Plating Giving Customers extras, it is not recommended

    Quality Matrix Defines what something is and how to measure it.

    Process improvement Plan Subsidiary of PMP, it details the steps for analyzing processes that will

    facilitate the identification of waste and non-value added activity, it includes

    1. Process boundaries

    2.Process configuration

    3.Process matrix

    4.Targets for improved performance.

    Quality Control Measurements Results of QC activities that are fed back to QA to reevaluate and

  • 7/29/2019 PMP Resumen (Por RDCL)

    35/64

    analyze the quality standards and processes for performing organization.

    Seven Basic Tools of Quality

    1.Cause and Effect Diagram

    2.Control Charts

    3.Flowcharting

    4.Histogram

    5.Pareto Chart

    6.Run Chart

    7.Scatter Diagram

    Design of experiments - is a statistical method that helps identify which factors might influence specific

    variables

    Prevention: keeping errors out of the process

    Inspection: keeping errors out of the hands of the customerTolerances - (the result is acceptable if it falls within the range specified by the tolerance) and control limits(the process is in control if the result falls within the control limits).

    Inspections - are variously called reviews, product reviews, audits, and walkthroughs; The process may be

    changed to provide improvements, but it should not be adjusted when it is in control.

    Pareto Diagram Histogram, ordered freq of occurrence, take corrective action & 80 prob/20 causes

    Statistical sampling - Statistical sampling involves choosing part of a population of interest for inspection

    Trend analysis involves using mathematical techniques to forecast future outcomes based on historical

    results.

    Project Quality Management processes required to ensure that the project will satisfy the needs forwhich it was undertaken.

    Quality is the conformance to requirements/specifications and to fitness of use.

    Quality function deployment provide better product definition and product development. Its main feature

    are to capture the customers requirements, ensure cross functional teamwork, and link the main phases of

    product development

    Rework action taken to bring a non-conforming item into compliance. Rework is a frequent cause of

    project overruns

  • 7/29/2019 PMP Resumen (Por RDCL)

    36/64

    Quality Variable A quality characteristic that is measurable

    Quality AttributeA quality characteristic that is classified as either conforming or

    nonconforming

    Benchmarking

    Comparing practices of other projects. Provides a standard to

    measure performance (time consuming). (e.g. investigatingquality standards that other companies are using)

    Statistical Analysis Involves determining the probability of an occurrence

    Trend Analysis

    Uses mathematical techniques to forecast future outcomes based

    on historical results; used to measure technical, cost, and

    schedule performance

    Quality Audit

    Structured review of other quality management activities

    erformed to identify lessons learned (used for process

    improvement) Part of Quality Assurance. Provide managementconfidence that the project will satisfy relevant quality standards.

    InspectionPrevent errors from reaching the customer before delivery to the

    customer. Can be done throughout product development.

    Design of Experiments

    A technique to identify which variables have the most influence

    on overall outcomes (part of Quality Planning) (e.g. analyze the

    color/size combination that will contribute most to the

    functionality of the new product). Can be applied to cost and

    schedule tradeoffs.

    Flow chart Help analyze how problems occurs

    Attribute Sampling Measures whether or not the results conforms to specifications

    Variable Sampling

    Are characteristic you want to measure (size, shape, weight,

    etc). An attribute is what you are measuring. The result is rated

    on a continuous scale that measures the degree of conformity.

    Assignable Causes Data point on a control chart that requires investigation

    Specification Limit Shows customers expectations for quality (on a control chart)

    Control Chart

    Help newly assigned project manager determine whether theroject is out of control (in order to verify quality level). Can be

    used to monitor project management processes such as coscard,

    schedule variance, volume and frequency of scope changes, and

    errors in project documents.

    Statistical Control ChartAre used to monitor process variations overtime. Help people

    understand and control their process work.

  • 7/29/2019 PMP Resumen (Por RDCL)

    37/64

    Out of Control1. A data point falls outside of the upper or lower control limit.

    2. Non-random points that are still within the upper and lower

    control limit.

    Upper and Lower Control Limit on a Control

    Chart

    Acceptable range of variation of a process. [These limits are set

    based on the companys quality standards. The control limits are

    determined from data obtained from the process itself.]

    Specification Limit Fixed by the customer

    Pareto DiagramUsed to show how results were generated, by type or category of

    identified cause

    IshikawaMade popular Pareto Chart, Cause-and-Effect Diagram and

    Control Chart

    Taguchi Method

    Is used to estimate the loss associated with controlling or failing

    to control process variability. If you select good designarameters, you can produce products that are more forgiving

    and tolerant. The tool helps determine the value or break-even

    oint of improving a process to reduce variability.

    ISO 9000Provides a basic set of requirements for a quality system, without

    specifying the particulars for implementation.

    ChecklistsUsed to verify that a set of required steps has been performed in

    quality control process

    Statistically IndependentDetermine if problems are related before planning what to do

    about them

    Mutually Exclusive If two events cannot both occur in a single trial (?)

    Random Cause Normal process variation

    Cause and Effect Diagram (Fishbone)

    (1) Creative way to look at actual causes and potential causes of

    a problem

    (2) Process of constructing helps stimulate thinking about an

    issue; helps to organize thoughts; generates discussion

    (3) Used to explore a wide variety of topics

    (4) Also known as Ishikawa or Fishbone diagram

    Quality Planning

    Refers to potential problems. Although it usually occurs during

    Planning Phase, it can occur during execution if there is a

    change.

    Quality ControlRefers to specific performance of a task (measuring quality and

    comparing results to the quality plan). Its done throughout the

  • 7/29/2019 PMP Resumen (Por RDCL)

    38/64

    project

    Quality Assurance

    Refers to overall quality requirements (standards) (e.g.

    evaluating overall project performance regularly). Mostly done

    during project executing.

    Impact of Poor Quality

    Increased cost Decreased productivity Increased risk and uncertainty Increased costs in monitoring

  • 7/29/2019 PMP Resumen (Por RDCL)

    39/64

    Goal of the cost of quality program should be 3 - 5% of total value.

    Cost of non-quality is estimated to be 12 - 20% of sales.

    Cost of Quality Includes Prevention Costs (training), Appraisals Costs (inspection/testing) and Internal

    (scrap, rework)/External (warranty) Failure costs

    Management is 85% responsible for quality. The team member is ultimately responsible for qualitymanagement. The project manager is primarily responsible for quality management.

    Two components ofproduct availability are reliabilityand maintainability.

    To effectively use statistical quality control, the project team should know the differences between special

    causes and random causes.

    Sampling and probability are the most important topics to understand in statistical process control. Top

    management should direct continuous improvement

    Quality control measurement are records of quality control testing and measurement in a format for

    comparison and analysis (input to quality assurance).

    Documentation Quality Management Plan describes method for implementing quality policy project

    quality system and organizational structures, responsibilities, procedures, processes and resources needed to

    implement project quality management

    TQM Total Quality Management Philosophy encourages companies and their employees to focus on finding

    ways to continuously improve quality of their business practices and products.

    Process Analysis Lessons learned in first few cases is used to improve the process on the remaining ones.

    Standard Deviation From 3 point Estimates = (P O)/6

    Six Sigma Level of Quality, which is percentage of occurrences to fall between the two control limits.

    +/- 1 Sigma = 68.26%

    +/- 2 Sigma = 95.46%

    +/- 3 Sigma = 99.73%

    +/- 6 Sigma = 99.9995%

    Rule of Seven Based on Heuristics, seven random data points grouped together in a series with in control

    limit. It represents that they are not random and should be investigated.

  • 7/29/2019 PMP Resumen (Por RDCL)

    40/64

    Project HUMAN RESOURCE Management

    Knowledge AreasMajor Processes

    desc.Primary Inputs Tools & Techniques Primary Outputs

    Human Resource

    Management

    Develop

    Human

    Resource Plan

    Identifying and

    documenting project

    roles, responsibilities

    and required skills,

    reporting relationships

    and creating the

    staffing management

    plan

    1. Activity resource

    requirements

    2. Enterprise

    Environmental

    Factors

    3. Organizational

    Process Assets

    1. Organization charts

    and position

    descriptions

    2. Networking

    3. Organizational

    theory.

    1. Human

    Resource Plan

    Acquire

    Project Team

    Confirming human

    resource availability

    and obtaining the

    team necessary to

    complete project

    assignments.

    1. Project

    Management Plan

    2. Enterprise

    Environmental

    Factors

    3. Organizational

    Process Assets

    1. Pre-assignment

    2. Negotiation

    3. Acquisition

    4. Virtual teams

    1. Project Staff

    Assignments

    2. Resource

    Calendars

    3. Project

    Management plan

    updates

    Develop

    Project Team

    Improving the

    competencies, team

    interaction and overall

    team environment to

    enhance project

    performance.

    1. Project Staff

    Assignments

    2. Project

    Management Plan

    3. Resource

    Calendars

    1. Interpersonal skills

    2. Training

    3. Team-building

    activities

    4. Ground rules

    5. Co-location

    6. Recognition and

    rewards

    1. Team

    Performance

    assessments

    2. Enterprise

    environmental

    factors updates.

    Manage

    Project Team

    Tracking team

    member performance,providing feedback,

    resolving issues, and

    managing changes to

    enhance project

    performance

    1. Project Staff

    Assignments2. Project

    Management Plan

    3. Team

    Performance

    Assessments

    4. Performance

    1. Observation and

    conversation2. Project performance

    appraisals

    3. Conflict

    management

    4. Issue log

    5. Interpersonal Skills

    1. Enterprise

    environmentalfactors updates

    2. Organizational

    process assets

    updates

    3. Change

    requests

  • 7/29/2019 PMP Resumen (Por RDCL)

    41/64

    Reports

    5. Organizational

    Process Assets

    4. Project

    management plan

    updates

    Constraints Organizational Structure, Collective bargaining agreements, Economic Conditions

    Organizational Charts Hierarchical, Matrix based and Text Oriented

    RBS Resource Break Down Structureis a hierarchical chart which shows break down of project by resourcetypes. RBS is helpful in tracking project costs, aligned with organizations accounting system, can containcategories other than human resources.

    RAMResponsibility Assignment Matrix, can be developed at various levels. RACI (Responsible,Accountable, Consult and Inform)

    Halo Effect Tendency to rate high or low on all the factors due to the impression of a high or low rating onsome specific factor

    Organizational Theory Provides information regarding the ways that people, teams and organizational

    units behave.

    Roles and Responsibilities (O/P of HR planning) Role, Authority, Responsibility and competency

    SPONSORThe one who provides the financial resources for the project. If project is beingdone for an outside customer, it becomes the sponsor.

    TEAMGroup of people who will complete work on the project. Team members canchange throughout the project as people are added and removed from theproject.

    STAKEHOLDERS

    Anyone who can positively or negatively influence the project, as well asincluding within the organization (customer users, project manager, team,sponsor, program and portfolio managers, PMO, functional and operationsmanagers) as external sellers that provide services or material for the project

    FUNCTIONALMANAGER

    Manages and "owns" the resources in a specific department, such as IT,engineering, public relations, or marketing, and generally directs the technicalwork of individuals from the functional area working on the project

    PROJECTMANAGER

    Responsible for managing the project to meet project objectives

    PORTFOLIOMANAGER

    Responsible for governance at an executive level of the projects or programsthat make up a portfolio

    PROGRAMMANAGER

    Responsible for managing a group of related projects. Projects are combinedinto a program to provide coordinated control, support, and guidance

    Staffing Management Plan (part of the Human Resources Plan) Describes when and how humanresource requirements will be met. SMP can be updated because of promotions, retirements, illness,performance issues and changing workloads. SMP contents:

    1 Staff acquisition internal or external or contract, same location or different etc.2 Resource Calendars When are people available?, when will they used.3 Staff Release Plan When will resources be released and no longer be charged to the project?.

    4 Staff Training Needs - What are the needs of training for the resources?5 Recognition and rewards What are they?, What are the criteria for their use?6 Compliance With Government regulations7.Safety What policiesprotect the resources?

    Five Stages of Team Building Activities Forming, Storming, Norming, Performing and Adjourning(Tuckman Ladder)

    Forming Team meets and learns about the project and roles and responsibilities.

    StormingBegins to address project work, technical decisions, and project managementapproach. (disagreements as people learn to work together)

    NormingTeam members begin to work together and adjust work habits and behaviors thatsupport the team. Team begins to trust each other.

  • 7/29/2019 PMP Resumen (Por RDCL)

    42/64

    PerformingTeam becomes efficient and works effectively together. In this point Projectmanager pay most attention to developing team members.

    Adjourning Team completes the work and moves on from the project.

    Ground Rules: establish clear expectations regarding acceptable behavior by project team members.

    Kickoff Meeting Indirect Method to start team development. It should answer 1.Why am I here? 2. Whoare you and your expectations of me? 3. What is this team going to do? 4. How is the team going to do thiswork? 5. How do I fit into all this?

    Lessons Learned from Manage Project Team

    Project organization charts, positions and SMP Ground rules, conflict management techniques and recognitions Procedures for Virtual teams, co-location, training and team building Special skills and competencies by team members discovered Issues and solutions

    Project Human Resource Management - process required to make the most effective use of the peopleinvolved with the project

    Responsibility Assignment Matrix (RAM) Show who does what (x=person, y=phase). The most

    important feature of the RAM is the participatory development process involving all stakeholders. Show who

    is participant, who is accountable, who handles reviews, who provides input and who must sign off on

    specific work packages or project phases.

    Linear Responsibility Chart (LRC) identifying responsibility, assignments by work packages and action

    required. Also referred to as RAM.

    Organizational Breakdown Structure (OBS) - A depiction of the project organization arranged so as to

    relate work packages to organization units.

    Resources Histogram often part of Staffing Management Plan; shows resource usage (eg staff hours) pertime period (eg wk, mth) of a specific job function.

    Rewards and Recognition Systems -- to be effective, must make the link between performance and

    reward clear, explicit and achievable.

    Types of Power

    Legitimate(Formal)

    Derived from formal position

    Coercive Predicated on fear

    Reward

    Involves positive reinforcement and ability to award something of value Project often

    needs their own rewards system to affect employee performance. Used correctly, bring

    the teams goals and objectives in line with each other and with the project.

    Expert Held in esteem because of special knowledge or skill (requires time)

    Referent Ability to influence others through charisma, personality, etc.

    The best forms of power are generally Reward and Expert

  • 7/29/2019 PMP Resumen (Por RDCL)

    43/64

    Conflict Management

    Avoidance

    /Withdrawal

    (Ignoring)

    At least one party withdraws from conflict. Cool off period, could be lose/lose

    Retreating from actual or potential disagreement; delaying (e.g. Just document the

    problem)

    Competition/Forcing

    Exerting ones viewpoint; a last resort [win/lose] (e.g. Call the customer and demandthat you receive the approval today.

    Compromising

    Bargaining and searching for solutions; neither party wins but each gain some

    satisfaction [win-lose/win-lose] this is very rarely a good way to resolve technical

    issues.

    AccommodationOpposite of Competition. One party meets other party need at expense of his own.

    Lose/Win

    Collaborating

    Involves incorporating multiple ideas and viewpoints from people with different

    perspectives and offers a good opportunity to learn from others (good when project istoo important to be compromised) Win/Win Best Strategy

    Smoothing

    De-emphasize differences and emphasize commonalities; friendly but avoids solving

    root causes; delaying (eg. Manager says an issue is valid but doesnt think it will be a

    big problem later)

    Problem Solving

    / ConfrontationAddress conflict directly in problem solving mode [win/win]

    6 steps of problem solving:

    1. Define what is the real/root problem

    2. Analyze the problem

    3. Identify solutions

    4. Pick a solution

    5. Implement a solution

    6. Review the solution and confirm that the solution solved the problem

    Motivational Theory: Content & Process Theories

    Content: What energizes, directs behavior

    1. Maslows Hierarchy of Needs Theory (1. Physiological, 2. Safety, 3. Social/Belonging, 4. Esteem, 5.

    Self-Actualization)

    2. Hertzbergs Motivator/Hygiene Theories (Motivator: Responsibility, Self-Actualization, Esteem,

    Professional Growth, Recognition. Hygiene: Working Conditions, Salary, Relationship at Work, Social, Safety,

    Physiological)

  • 7/29/2019 PMP Resumen (Por RDCL)

    44/64

    Process: How personal factors influence behavior

    1. McGregors Theory X and Theory Y (X: Assumes people lack ambition, dislike responsibility, are

    inherently self-centered and are not very bright; motivate by reward and punishment. Y: Assumes people

    become lazy w/o recognition, will accept responsibility, can become self-motivated and exercise self-control;

    motivate by removing obstacles and providing self-directed environment.)

    2.Ouchis Theory Z/Japanese Theory ( focus on team, company; usually lifetime employment, collective

    decision making )

    Other Motivational Theories

    Behaviorism people behavior can be modified through manipulation of rewards and punishments

    Expectancy Theory Motivation is explained in terms of expectations that people have about

    (1) their ability to perform effectively on the job,

    (2) the rewards they might obtain if they do perform effectively and

    (3) the value or degree of satisfaction they anticipate from those rewards.

    MBO More support to team, not more power (remain to PM)

    Leadership Theories:

    McGregor Theory X (employee lack ambition) and Theory Y (org