Introduction [Project Management Framework]
A project is a temporary endeavor undertaken to create a unique product, service, or result
Example: Building a road is an example of a project. The process of building a road takes a finite amount of
time, and produces a unique product Second Definition:
A project is a complex, nonroutine, one time effort limited by time, budget resources, and
performance specifications designed to meet customer needs.
What is Not a Project?
Projects should not be confused with everyday work. A project is not routine, repetitive work. Ordinary daily
work typically requires doing the same or similar work over and over, while a project is done only once; a
new service or a new product exists when the project is completed.
Routine, Repetitive Work[Operations] Projects
Taking class Notes
daily entering sales receipts into the
accounting ledger
Responding to a supply-chain request
Practicing scales on the piano
Routine manufacture of an Apple iPod
Writing a term paper Setting up a sales kiosk for a professional accounting
meting
Developing a supply chain information system Writing a new piano piece Designing an iPod that is approximately 2*4 inches,
interfaces with PD and stores 10,000 songs
They share many of the following characteristics
Performed by people Constrained by limited resources Planned, executed, and controlled
Projects and operations differ primarily in that operations are ongoing and repetitive, while
projects are temporary and unique
Project Objectives
Project objectives are contained in the preliminary Project Scope Statement and Project ScopeStatement.
Projects are considered complete when the objectives have been met A reason for terminating a project before completion is that the project objectives cannot be met A more complete understanding of the objectives is achieved over the length of the project. It is the project manager's role to accomplish the project objectives. Objectives should be clear and achievable. The Reason for quality activities is to make sure that project meets its objectives.
7/29/2019 PMP Resumen (Por RDCL)
2/64
The Reason for the risk process group is to enhance opportunities and reduce threats to the projectobjectives.
Things that could negatively impact the project objectives, such as risk and stakeholders' influenceshould be watched and tracked.
Projects often require tradeoffs between the project requirements and the projects objectives. Project objectives are determined in the initiating process group and refined in the planning process
group.
One of the purposes of the develop project management plan process is to determine how work willbe accomplished to meet project objectives.
A Project management is the application of knowledge, skills, tools and techniques to project activities to
meet project requirements
Managing a project includes
Identifying requirements Establishing clear and achievable objectives Balancing the competing demands for quality, scope, time and cost Adapting the specifications, plans, and approach to the different concern and expectations of the
various stakeholders.
A Program is a group of related projects managed in a coordinated way to obtain benefits and control not
available from managing them individually. Programs may include elements of related work outside of the
scope of the discrete projects in the program
Triple Constraints - A Balance Project
The triple constraints are cost, time, scope of work, quality and customer satisfaction.
These are so intertwined that a change in one will most often cause a change in at least
one of the others , For example:
If time is extended, the cost of the project will increase. If time extended with the same cost then quality of the product will reduce. If scope is extended then cost and time will also extend. Changes to any of these lesgs sets off a series of activities that are needed to integrate the change
across the project.
Progressive Elaboration
Progressively means proceeding in steps; continuing steadily by increments, while elaborated means
worked out with care and detail; developed thoroughly
7/29/2019 PMP Resumen (Por RDCL)
3/64
International and political environment
Some team members may need to be familiar with applicable international, national, regional, and local laws
and customs, as well as the political climate that could affect the project. Other international factors to
consider are time-zone differences, national and regional holidays, travel requirements for face-to-face
meetings, and the logistics of teleconferencing.
Cultural and social environment
The team needs to understand how the project affects people and how people affect the project. This
Includes
understanding of aspects of the economic, demographic, educational, ethical, ethnic, religious, And other characteristics of the people whom the project affects or who may have an interest in the
project.
The project manager should also examine the organizational culture and determine whether project
management is recognized as a valid role with accountability and authority for managing the project
Physical environment
If the project will affect its physical surroundings, some team members should be knowledgeable about the
local ecology and physical geography that could affect the project or be affected by the project
Interpersonal Skills (PMBOK Appendix G)
Leadership. Developing a vision and strategy, and motivating people to achieve that vision and strategy
Team Building. Helping a group of individuals bound by a commonsense of purpose to work
interdependently with each other.
Motivation. Energizing people to achieve high levels of performance and to overcome barriers to change
Communication The exchange of information
Influencing the organization. The ability to 'get things done'.
Decision Making. The combination of problem definition, alternatives identification and analysis, and
solution action and evaluation.
Political and Cultural Awareness. Getting to know political and cultural environment.
Negotiation and conflict management. Conferring with others to come to terms with them or to reach an
agreement
7/29/2019 PMP Resumen (Por RDCL)
4/64
A standard is a 'document established by consensus and approved by a recognized body that provides, for
common and repeated use, rules, guidelines or characteristics for activities or their results, aimed at the
achievement of the optimum degree of order in a given context.' Some examples of standards are computer
disk sizes and the thermal stability specifications of hydraulic fluids
A regulation is a government-imposed requirement, which specifies product, process or service
characteristics, including the applicable administrative provisions, with which compliance is mandatory.
Building codes are an example of regulations
Project Management Office [PMO]
A project management office (PMO) is an organizational unit to centralize and coordinate the management of
projects under its domain
Portfolio
Collection of Projects, Programs and other work grouped together to facilitate effective management to meet
strategic objectives.
Project Expeditor
Staff Assistant and Communication coordinator. No Power to make decisions
Project Coordinator
Some authority, power and reports to higher-level manager
7/29/2019 PMP Resumen (Por RDCL)
5/64
Project Life Cycle and Organization
Project life cycle - Organizations performing projects will usually divide each project into several project
phases to improve management control. Collectively, the project phases are known as the project life cycle.
Usually they are sequential.
Project Life Cycle Define
What technical work to do in each phase When the deliverables are to be generated, how they are reviewed, verified & validated. Who is involved in each phase How to control and approve each phase
Project Phase
Each project phase is marked by completion of one or more deliverables. A deliverable is a tangible,
verifiable work product. The conclusion of a project phase is generally marked by a review of both keydeliverables and project performance to date, to a) determine if the project should continue into its next
phase and b) detect and correct errors cost effectively. These phase-end reviews are often called phase
exits, stage gates, or kill points. Practice of overlapping phases is often called fast tracking.
Cost and staffing
levels are low at the start, higher towards end, and drop rapidly as the project draws to a conclusion.
Completion
The probability of successful completion generally gets progressively higher as the project continues.
Stakeholder Influence
On the final characteristics of the projects product and the final cost of the project is highest at the start and
gets progressively lower as the project continues.Risk
Uncertainty and hence risk of failing is high at the beginning and get progressively lesser/better as project
continues
Key stakeholders
pm, customer (buy/use), org, team & sponsor (pays), Project Management team, PMO Differences - In
general, differences between or among stakeholders should be resolved in favor of the customer.
Managing
is primarily concerned with consistently producing key results expected by stakeholders,Leading
Establishing direction vision of the future and strategies, Aligning people to vision, Motivating and inspiring.
Problem definition
Requires distinguishing between causes and symptoms. Problems may be internal (a key employee is
reassigned to another project) or external (a permit required to begin work is delayed). Problems may be
technical (differences of opinion about the best way to design a product), managerial (a functional group is
7/29/2019 PMP Resumen (Por RDCL)
6/64
not producing according to plan), or interpersonal (personality or style clashes).
Organizational Structure Influence on Projects
Functional Weak Matrix Balanced Matrix Strong Matrix Projectized
PM authority Little or None Limited Low to Moderate Moderate to High High to Total
Resource Availability Little or None Limited Low to Moderate Moderate to High High to Total
Project Budget Functional Mngr Functional Mngr Mixed PM PM
PM Role Part Time Part Time Full Time Full Time Full Time
Administrative Staff Part Time Part Time Full Time Full Time Full Time
PMO
Can exist in any kind of organization including the functional organization
Planning
Planning is the only PM Process group that has a specific order of activities
Release Resources
Is the Last activity in the closing process group.
Iterations
Start after Risk management because only after this final cost and schedule can be determined
Functional Organization
Advantages Disadvantages
Easier management of specialists People place more emphasis on their functionalspecialty to the detriment of project
Team members report to only one supervisor No career path in project management
Similar resources are centralized PM has little/no authorityProjectized Organization
Advantages Disadvantages
Efficient project organization No home when project is completed
Loyalty to the project Lack or professionalism in disciplines
More effective communications than functional Duplication of facilities and job functions
Less efficient use or resources
Matrix Organization
Advantages Disadvantages
Highly visible project objectives Extra administration required
Improved PM control over resources More than one boss for project teams
More support from functional areas More complex to monitor and control
Maximum utilization of scarce resources Tougher problems with resource allocation
Better coordination Need extensive policies and procedures
Better horizontal and vertical dissemination ofinformation
Functional managers may have different prioritiesthan project managers
Team members maintain a home Higher potential for conflict
7/29/2019 PMP Resumen (Por RDCL)
7/64
Project MANAGEMENT Processes for a project
Pick Process
Project Manager along with team is responsible for picking what processes are appropriate
Concept of interaction among PM processes
(By Shewhart & Deming) PLAN DO CHECK ACT
Monitoring & Control
Group not only monitors and controls the work being done within a process group but also monitors andcontrols the entire project effort
Process
is a series of actions bringing about a result
Process Group
Are not project phases. Process groups are usually repeated for each phase/sub project.
Initiating Process
Are often done external to the projects scope of control
Project Charter
Approval and funding are handled external to the project boundaries. Charter is primarily concerned withauthorizing the project /phase. It links project to the ongoing work of the organization.
Rolling Wave Planning
Progressive detailing of the project management plan is called rolling wave planning, indicating plan is aninteractive and ongoing process.
Executing Process Group
Majority of the project budget will be spent in performing Executing process group.
Integrated Change Control
Is performed throughout the project, from project initiation thru Project closure.
Core processes
Are Performed in same order & may be iterated several times during any one phase
Facilitating processes
Performed intermittently and as needed during project planning, they are not Optional.
7/29/2019 PMP Resumen (Por RDCL)
8/64
Project INTEGRATION Management
Knowledge
Areas
Major Processes
desc.Primary Inputs
Tools &
TechniquesPrimary Outputs
Integration
Develop Project
Charter
Developing the project
charter that formally
authorizes a project or
a project phase
1. Project Statement
of Work
2. Business Case
3. Contract
4. Enterprise
environmental factors
5. Organizational
Process Assets
1. Expert
Judgment
1. Project Charter
Develop Project
Management
Plan
Documenting the
actions necessary to
define, prepare,
integrate and
coordinate all
subsidiary plans into a
project management
plan.
1. Project Charter
2. Outputs from
planning process
3. Enterprise
Environmental Factors
4. Organizational
Process Assets
1. Expert
Judgment
1. Project
Management Plan
Direct and
Manage Project
Execution
Performing the work
defined in the project
management plan to
achieve the projects
objectives.
1. Project
Management Plan
2. Approved Change
Requests
3. Enterprise
Environmental Factors
4. Organizational
Process Assets
1. Expert
Judgment
2. PMIS
1. Deliverables
2. Work Performance
Information
3. Change Requests
4. Project
management plan
updates
5. Project document
updates
7/29/2019 PMP Resumen (Por RDCL)
9/64
Monitor and
Control Project
Work
Tracking, reviewing and
regulating the progress
to meet the
performance objectives
defined in the project
management plan
1. Project
Management Plan
2. Performance
reports
3. Enterprise
Environmental Factors
4. Organizational
Process Assets
1. Expert
Judgment
1. Change Requests
2. Project
Management Plan
Updates
3. Project Document
Updates
Perform
Integrated
Change Control
Reviewing all change
requests, approving
changes, and managing
changes to the
deliverables,
organizational process
assets, project
documents and the
project management
plan.
1. Project
Management Plan
2. Work Performance
Information
3. Change Requests
4. Enterprise
Environmental Factors
5. Organizational
Process Assets
1. Expert
Judgment
2. Change
Control Meetings
1. Change Request
status updates
2. Project
Management Plan
updates
3. Project Document
updates
Close Project
or Phase
Finalizing all activities
across all of the Project
Management Process
Groups to formally
close the project or a
project phase.
1. Project
Management Plan
2. Accepted
Deliverables
3. Organizational
Process Assets
1. Expert
Judgment1. Final Product,
Service or result
4. Organizational
Process Assets
updates
Integration Management
Identification, Definition, Combination, Unification, and Coordination of the various processes and project
management activities within the Project Management Processes Groups. Integration is about making
choices, about where to concentrate resources and effort. It also involves making tradeoffs among competing
objectives and alternatives. PM and team must address every process and level of implementation for
process
Project Deliverables
Need to be integrated with ongoing operations.
Reasons to start projects
1. Problems 2. Market Opportunity 3.Business Requirements
Project Charter
1. Authorize project
7/29/2019 PMP Resumen (Por RDCL)
10/64
2. Gives Project Manager Authority
3. Issued by initiator or sponsor external to project organization who has the authority to fund.
4. It is broad enough that it does not have to change as the project changes
Project Charter Contain
1. Requirements that specify Customer/Sponsor Needs, wants and expectations
2.Business Needs
3.Project purpose or justification
4. Assigned PM authority 5.Stakeholder influence
6.Functional organization participation
7.Assumptions & Constraints
8.Business case and return on investment
9.Summary Budget
Enterprise Environmental Factors
Company Culture & Structure, Government or industry standards, infrastructure, existing human resources,
personal administration (Hire, Fire, performance), work authorization, Marketplace condition, Stakeholder
risk tolerance, Commercial database, PMIS (existing sysetms) that the project will have to deal with or can
use of.
Organizational Process Assets
Existing Process, Standards, Policies, Standard Product and Project Life Cycles, Quality policies & procedure,
performance measurement criteria, Templates, Communication requirements, Project Closure Guidelines,
Risk Control procedure, Issue and Defect Management Procedure, Change Control Procedure, Procedure for
Approving & issuing work authorization. It also include Process Measurement database, project files,
Historical information & Lessons learned, Configuration management database, financial database containing
labor hours, costs & budgets
Project Selection Methods
1.Benefit Measurement Methods (Comparative Approach)
1. Scoring Models
7/29/2019 PMP Resumen (Por RDCL)
11/64
2. Benefit Contributions
3. Murder board Panel of people who try to shoot down a new project idea.
4. Peer Review
5. Economic Models
1. Benefit Cost Ratio
2. Cash Flow
3.Internal Return Rate
4. Preset Value (PV) and net present value (NPV)
5.Opportunity Cost
6. Discounted Cash Flow
7. Return On Investment
2.Constrained Optimization Methods (Mathematical Models)
1. Linear 2. Nonlinear 3. Dynamic 4. Integer 5. Multiple Objective Programming
Project Management Plan
It defines how project is executed, monitored and controlled and Closed. PMP can be either summary level or
detailed and can be composed of one or more subsidiary plans and other components. It contains following
management plans 1. Change, 2. Communications, 3. Configuration, 4. Cost, 5. Cost Performance
Baseline, 6.Human resources, 7. Process Improvement, 8. Procurement, 9. Quality, 10.
Requirements, 11. Risk, 12. Schedule Baseline, 13. Schedule, 14.Scope Baseline, 15. Scope.
Configuration Management
It is a sub system of overall project management information system. It is a means of monitoring and
controlling emerging project scope against the scope baseline; its purpose is to manage control changes
to the deliverables and the resulting documentation, including which organizational tools will be
used. It is any documented procedures used to apply technical and administrative direction and surveillance
to audit the items and system to verify conformance requirements. . It documents the physical
characteristics of formal project documents and steps required to control changes to them (e.g. would be
7/29/2019 PMP Resumen (Por RDCL)
12/64
used by a customer who wishes to expand the project scope after the performance measurement baseline
has been established). When more than one individual has sign a Charter, you have to be concerned with
competing needs and requirements impacting your efforts on configuration management
Configuration Management Activities
1.Configuration Identification 2.Configuration Status Accounting 3.Configuration Verification and auditing
Change Control System
It is a collection of formal documented procedures that define how project deliverables and documentation
are controlled, changed and approved. It is a subsystem of configuration management. It must also include
procedures to handle changes that may be approved without prior review (e.g. result of an emergency)
Integrated Change Control
It is performed from project inception through completion, it includes
Influencing the factors about change control so that only approved changes are implemented Reviewing, analyzing and approving change requests promptly. Managing approved changes as and when they occur and regulating them Maintain integrity of baseline Review and approve all recommended corrective and preventive actions Coordinating changes across the entire project Documenting the complete impact of requested changes
Process for Making Changes
1. Prevent the root causes of changes (proactively eliminate need of changes)2. Identify change (coming from measuring from performance baseline, sponsor, team, management,
customer, etc.). PM should be looking for changes proactively).
3. Look for the Impact of the change to the project4. Create a change request (to product scope, project management plan, baseline, etc.)5. Perform Integrated Change control ( a) Assess the change, b) look for options, c) change is
approved or rejected, d)Update status of the change in change control system ).
6. Adjust project management plan, project documents, and baselines.7.
Manage stakeholders expectations communicating changes to stakeholders affected
8. Manage the project to the revised project management plan and project documentsIntegrated change Control
Occurs during all the project management processes.
Project Baseline
Should be changed for all implemented changes. Sometimes, certain classification of changes gets automatic
approval on a project and do not need Change Control Board approval.
7/29/2019 PMP Resumen (Por RDCL)
13/64
Project Plan
as an input to team development, the project plan describes the technical context within which the team
operates
Project Execution
Although the products, services or results of the project are frequently in the form of tangible deliverablessuch as building, road or software, intangible deliverables such as training is also provided.
Schedule Change Control System
Can include the paper, systems and approvals for authorizing changes. The project manager is normally not
the approval authority, and not all the changes approved
Organization Process Assets
Includes an index & location of project documentation
Formal Acceptance Documentation Project Files Closure Documents Historical information
Difference between Configuration Management and Change Management systems
Both the Configuration Management and Change Management systems are sub systems of the ICC.
They are to be understood as: Configuration Management System - Relates to maintaining the changes to
the product of the project. Change Control System - Relates to maintaing the changes to the Project itself.
Take a small example. Your project is to design a latest design washing machine. You have 2 things here. 1-
is a Project whose objective is to design the washing machine 2- is a Product of the project - which is the
washing machine itself. All the characteristics of the Washing Machie viz., height, capacity, drum diameter,
motor speed, color etc are called configuration of the product. This is maintained in the Configuration
Management Database. Any change to this configuration will be managed through the Configuration
Management System.(CMS) On the other hand, there will be plans for controlling scope, cost , time and
quality in the project. Any change in these constraints would be managed through the Change Control
System (CCS). Hope this helps.
Process Improvement Plan
Is an effort made by PM to improve processes attached to a project, which results in completing the work
faster, cheaper and with higher quality.
7/29/2019 PMP Resumen (Por RDCL)
14/64
Project SCOPE Management
Knowledge AreasMajor Processes
desc.Primary Inputs Tools & Techniques Primary Outputs
SCOPE
Collect
Requirements
Defining and
documenting
stakeholders needs
to meet the project
objectives.1. Project charter
2.Stakeholder
Register
1. Interviews
2. focus Groups
3. Facilitated
workshops
4. Group creativity
techniques
5. Group decision
making techniques
6. Questionnaires
and surveys
7. Observations
8. Prototypes
1. Requirements
Documentation
2. Requirements
Management Plan
3. Requirements
Traceability Matrix
Define Scope
Developing a detailed
description of the
project and product.
1. Project charter
2. Requirements
Documentation
3. Organizational
Process Assets
1. Expert Judgment
2. Product analysis
3. Alternatives
Identification
4. Facilitated
workshops
1. Project Scope
Statement
2. Project Document
Updates
Create WBS
Subdividing project
deliverables and
project work into
smaller more
manageable
components
1. Project Scope
Statement
2. Requirements
documentation
3. Organizational
Process Assets
1. Decomposition1. Work Breakdown
Structure (WBS)
2. Scope baseline
3. WBS dictionary
4. Project Document
Updates
Verify Scope
Formalizingacceptance of thecompleted projectdeliverables.
1. ProjectManagement Plan2. RequirementsDocumentation3. RequirementsTraceability Matrix4. ValidatedDeliverables
1. Inspection1. Accepteddeliverables2. Change requests3. Project Documentupdates
Monitoring the status 1. Project 1. Variance analysis 1. Work Performance
7/29/2019 PMP Resumen (Por RDCL)
15/64
Control Scopeof the project and
product scope and
managing changes to
the scope baseline
management plan
2. Work Performance
information
3. Requirements
Documentation
4. Requirements
Traceability Matrix
5. Organizational
Process Assets
Measurements
2. Organizational
process assets updates
3. Change requests
4. Project
management plan
updates
5. Project document
updates
Scope Management Plan Project Scope
Provides guidance on how project scope will be defined, documented, verified, managed and controlled. This
planning effort is part of the Develop Project Management Plan, in the Integration process group.
Project Scope: the work that must be done in order to deliver a product; completion is measured against theproject plan. It includes meetings, reports, analysis and all the other parts of PM.
Product Scope: features and functions that are to be included in a product; completion is measured against
the Product requirements. It can be supplied as a result of a previous project to determine the requirements
Scope Management Process
1. Determine Requirements, making sure all of them support the business need as described on the charter.
2. Sort thru and balance needs of the stakeholders to determine product scope and project scope.
3. Create a WBS to break scope down to smaller more manageable pieces.
4. Verify that the scope of work planned is actually being done
5. Measure scope performance, and adjust as needed.
Requirements Documentation
How requirements meet business needs:
(Non)Functional reqs, Quality reqs, Acceptance criteria, Assumptions, Organizational Areas Impacted.
Signed by stakeholders.
Requirements Management Plan: Documents how requirements will be analyzed, documented, andmanaged throughout the project. Main parts are:
How reqs activities will be planned, tracked and reported Configuration management activities (how changes to product/service/result will be initiated, analyzed
for impacts, tracked, and reported, and authorization levels to approve changes) Reqs prioritization process Product metrics Traceability structure
Requirements Traceability Matrix: PM uses the RTM to keep track of all information and to analyzerequirements proposed. It takes a form of table with information like:
Identification numbers Source of each requirement
7/29/2019 PMP Resumen (Por RDCL)
16/64
Who is assigned to manage the requirement (similar to risk owners) Status of requirement (including if its finished)
Rolling Wave Planning
The Project Management team usually waits until the deliverable or subproject is clarified so the details of theWBS can be developed. This is referred as rolling wave planning. So Work to be performed in the near futureis planned to the low level of the WBS, whereas work to be performed far into the future can be planned atthe relatively high level of the WBS.
WBS Dictionary
For each WBS Component, WBS dictionary includes a Code of Account Identifier, a description of work,
responsible organization, and a list of schedule milestones. Other information can be Contract information,
Quality requirements, acceptance criteria, and technical reference, among others.
Scope Baseline
Includes:
Approved project Scope statement WBS WBS dictionary
Verify Scope
Is the process of formalizing acceptance of the completed project deliverables. Includes reviewing deliverables
with the customer or sponsor to ensure that theyre completed satisfactory and obtaining formal acceptance of
deliverables. Differs from Quality Control in that Scope is concerned with acceptance of deliverables, while
Quality Control is concerned with correctness od the deliverables meeting quality requirements specified for
the deliverables.
Inspection
Are called Reviews, Product Reviews, Audits and Walkthroughs.Scope Creep
Uncontrolled changes are often referred as project scope creep
Variance Analysis
Project performance is measurements are used to assess the magnitude of variation. It includes finding the
cause of variation relative to the scope baseline.
Constraints
A constraint is an applicable restriction that will affect the performance of the project. For example, a
predefined budget is a constraint
Assumptions
Assumptions are factors that, for planning purposes, are considered to be true, real, or certain.
Decomposition
(1st level Project phases, 2nd level Deliverables (Break down till cost estimates can be done, verify
decomposition correctness) ) lowest level of the WBS may be referred to as work packages. Work not in the
WBS is outside the scope of the project.
7/29/2019 PMP Resumen (Por RDCL)
17/64
Decomposing
subdividing project work packages into smaller, more manageable components (activities/action steps). The
heuristic (rule of thumb) used in project decomposition is 80 hours.
Stakeholder Management
the project manager must identify the stakeholders, determine their needs and expectations, then manageand influence expectations to ensure project success. Project success depends primarily on customer
satisfaction.
WBS
subdividing project deliverables into smaller, more manageable components. It is a deliverable-oriented
grouping of project elements that organizes and defines the total scope of the project. It is a communication
tool and it describes what needs to be done and what skills are required. Anything missing in the WBS should
be added. The 1st level should be the project life-cycle (not product). The WBS is created by the team (helps
to get buy-in) and it is used to make certain that all the work is covered. It provides a basis for estimating the
project and helps to organize the work. Its purpose is to include the total project scope of all the work that
must be done to complete the project. Defines the projects scope baseline.
WBS Dictionary
Defines each item in the WBS, including description of the work packages and other planning info such as
schedule dates, cost budgets and staff assignments. It helps reduce Scope Creep and increases
understanding. WBS dictionary can be used as a part of Work Authorization system to inform team members
of when their work package is going to start, schedule milestones and other info.
Scope Statement
Define and record Requirements. A documented description of the objectives, work content, deliverables, and
end product; it includes a description of project assumptions and constraints. Provides stakeholders with a
common understanding of the scope of the project and is a source of reference for making future project
decisions
Statement of Work
a narrative description of products or services to be supplied under contract.
Work Package
deliverable at the lowest level of WBS. They are control points in the WBS and are used for assignments to
work centers. They are used to pass a group of work for further breakdown in the executive organization.
Control Account
one level above the Work Package.
Assumptions
factors that, for planning purposes, are considered to be true, real or certain The principal sources of project
failure are organizational factors, poorly identified customer needs, inadequate specified project requirements,
7/29/2019 PMP Resumen (Por RDCL)
18/64
and poor planning and control.
7/29/2019 PMP Resumen (Por RDCL)
19/64
7/29/2019 PMP Resumen (Por RDCL)
20/64
6. Enterprise
environmental factors
7. Organizational
Process Assets
5. Reserve Analysis
Develop
Schedule
Analyzing activitysequences, durations,
resource
requirements, and
schedule constraints
to create the project
schedule.
1. Activity list2. Activity Attributes
3. Project Schedule
network diagrams
4. Activity Resource
requirements
5. Resource Calendars
6. Activity duration
estimates
7. Project Scope
Statement
8. Enterprise
environmental factors
9. Organizational
process assets
1. ScheduleNetwork analysis
2. Critical path
method
3. Critical chain
method
4. Resource
leveling
5. What-if scenario
analysis
6. Appling leads
and lags
7. Schedule
Compression
8. Scheduling tool
1. Project schedule
2. Schedule
baseline
3. Schedule data
4. project
document updates
Control
Schedule
Monitoring the status
of the project to
update project
progress and manage
changes to schedule
baseline
1. Project management
plan
2. Project schedule
3. Work performance
information
4. Organizational
process assets
1. Performance
reviews
2. Variance analysis
3. Project
management
software
4. Resource
leveling
5. What-if scenario
analysis
6. Adjusting leads
and lags
7. Schedule
compression
8. scheduling tool
1. Work
performance
measurements
2. Organizational
process assets
updates
3. Change requests
4.Project
management plan
updates
5. Project
document updates
7/29/2019 PMP Resumen (Por RDCL)
21/64
Project Time Management
processes required to ensure timely completion of the project
Activity Definition
defines activities that must take place to produce project deliverables
Activity
consumes time (eg testing
Events (or Milestones)
specified accomplishment / does not consume time (eg tested)
Time Management
In small projects Activity Definition, Sequencing, Resource Estimation, Duration Estimation and Schedule
development are so tightly linked that they are viewed as single process.
Schedule Management Plan
Is part of Develop Project Management Plan Process. SMP is a subsidiary plan of PMP and may formal or
informal, highly detailed or broadly framed depending on the project. Includes: 1) Scheduling methodology,
2)schedule baseline, 3)Identification of performance measures, 4) planning schedule variances management,
5)Identification of schedule change control procedures.
Decomposition(Tools and Techniques used in Activity Definition)
Involves sub dividing the Work Packages into smaller components called activities. Activity Definition output is
schedule activities not Deliverables (Create WBS output is Deliverables) Activity list, WBS and WBS dictionary
can be developed either sequentially or concurrently. Performed by team members responsible for the work
package.
Control Account
From management Perspective a control line is drawn in the WBS Hierarchy levels. All the Planning
components above this line belong to what is called the Control Account. All efforts performed within a control
account are documented in a control account plan.
Planning Package
It is a WBS Component below the control account but above the work package.
Activity List
Does not include any schedule activity that is not required as part of the project scope It includes a activity
identifier and scope of work description for each schedule activity in sufficient detail. It is used in schedule
model and is part of PMP(Project Management Plan) Discrete components of Project Schedule but are not
components of the WBS.
Activity Attributes
Contain Activity identifier, activity Code, Activity Description, Predecessor Activities, Successor activities,
logical relationships, leads and lags, resource requirements, imposed dates, constraints and assumptions.
Milestone
Can be mandatory or optional, it a component of PMP, included in SS and WBSD and used in schedule model.
PM can impose additional milestones.
7/29/2019 PMP Resumen (Por RDCL)
22/64
Fragment Network
Portions of project schedule network diagram are often referred to as a Sub network or Fragment Network.
Sub Network templates are useful when project has several identical or nearly identical deliverables.
Lead and Lag
Lead allows acceleration of the successor activity, A lag direct a delay in Successor activity
Bottom Up Estimation
Estimation is done for lower level items and then aggregated.
Activity Resource Estimation
Identifies type and quantities of resources required for a schedule activity. These are aggregated to determine
the estimated resources for each work package
RBS (Resource Break Down Structure)
Output of Activity Resource Estimation process, it is a hierarchical structure of resources by category & type.
Tools and Techniques for Estimate Activity Duration
One Point Estimate One estimator submits one estimate per activity. It can made based on theexpert judgment.
Analogous Estimation Using actual duration of previous similar schedule activity. It is projectlevel, given to PM from Management or Sponsor; it is a form of Expert Judgment.
Parametric Estimation Quantity of Work * Productivity Rate - 1.Regression Analysis (ScatterDiagram) 2.Learning Curve. Results of Parametric Estimation can become heuristics.
Three Point Estimates Most Likely, Optimistic, Pessimistic. Reserve Analysis Reserve Analysis to have a reserve for accommodate the risks that remain in the project. These
reserves can be reduced after completion of Plan Risk Responses process. There are two types of
reserves: 1)Contingency (or buffers) for covering the Plan Risk Responses 2) Management Reserves
(to cover unforeseen risks).
Imposed Dates
Imposed dates in Scope Statement (I/P to Schedule Development Process) restrict the start or finish date.
Schedule Network Analysis (Tools abd Techniques for Schedule Development)
Critical Path Method Calculate Project Duration, Critical path length and Float. Critical path canhave 0 or negative total float.
Schedule Compression Crashing (Additional Resources) and Fast Tracking (Parallel) What-if Scenario Monte Carlo Analysis Resource Leveling Applied after Critical Path Method,
Keep resource usage at constant level
Critical Chain Method Uses Pessimistic resource availability, Adds duration buffers that are non
7/29/2019 PMP Resumen (Por RDCL)
23/64
7/29/2019 PMP Resumen (Por RDCL)
24/64
Finish-to-Start logical relationship Time estimates appear on arrow
Critical Path Method
(CPM)
Emphasis on controlling cost and leaving the schedule flexible One time estimate per activity Activity oriented; uses dummy; activity on arrow Time estimates appear on arrow
Precedence Diagram
Method (PDM)
Represents improvement to PERT and CPM by adding lag relationships toactivities
[Start to Start; Start to Finish; Finish to Start; Finish to Finish] Work is done during activity. Arrow indicates dependancy Activity on node; no dummy finish-to-start is the most commonly used type of logical
relationship. Start-to-finish relationships are rarely used
GERTA network diagram drawing method that allows loops between tasks. It is a method of
sequencing (e.g. a project requires redesign after completion of testing)
Dependencies
Mandatory or HardOften involve physical or technological limitations (based on the nature of work being
done)
Discretionary
may also be called preferred logic, preferential logic, or soft logic. Soft: desirable and customary (based on experience) Preferential: preferred or mandated by a customer (also, need of the project
sponsor)
Defined by PM Team
External Input needed from another project or source
Critical chain is a technique that modifies the project schedule to account for limited resources.
Monte Carlo Analysis
Computer simulation of project outcomes using PERT estimates; result represented in S curve. Provides the
ability to compute the probability of completing a project on a specific day. Can also be used to assess
feasibility of schedule under adverse conditions (eg when a schedule constraint is identified)
Heuristics - rules of thumb
Critical Path longest path (almost always have no float)
Near Critical Path Path is close in duration to critical path, the close it is the more RISK project has.
7/29/2019 PMP Resumen (Por RDCL)
25/64
Variance - Plan minus Actual
Float / Slack
1.Free 2. Total 3. Project Float. Time an activity may be delayed from its early start without delaying the
project finish date. Difference between the required end date and the expected project completion date. A
negative slack on the critical path means that the project is behind schedule.
Free Float
Amount of time a task can be delayed without delaying the early start of its successor
Total Float
amount of time that an activity may be delayed from early start without delaying the project finish date
Lag waiting time between two tasks (negative lead)
Schedule Baseline
The original, approved project schedule; should never be changed without proper review and approval. Any
approved change should be documented in writing. Should be created at the beginning of the project and
used during the project to gauge (measure) overall project performance, not just schedule. The project
Performance Measurement Baseline should generally change only in response to a scope or deliverable
change. The project performance measurement baselines should generally change only in response to a scope
or deliverable change
Corrective action - in project time management primarily concerns expediting to ensure that activities
remain on schedule. Is anything done to bring expected future schedule performance in line with the project
plan.
Revisions are changes to the scheduled start and finish dates in the approved project schedule; generally
revised only in response to scope changes. Rebaselining may be needed to provide realistic data to measure
performance. Scheduling and allocating resources to multiple projects may affect schedule slippage and in-
process inventory.
Duration Compression Methods occurs after activity duration estimating and before finalizing the
schedule. Include crashing, fast track,
Crashing when you are worried about time, not so much about costs.
Fast Track resources in parallel, involve increase rework. Should fast track tasks on the critical path (float
= 0) in order to save time.
Resource Leveling often results in a project duration that is longer than the preliminary schedule.
Resource reallocation from non-critical to critical path activities is a common way to bring the schedule
back, or as close as possible, to the originally intended overall duration. So 1. Schedule Can Slip 2. Cost
increase
7/29/2019 PMP Resumen (Por RDCL)
26/64
Finish to Finish - activities must finish on a specific sequence
Start no earlier than & Finish no later than Respectively #1 and #2 most popular date constraint in
project management software
Root Cause Analysis used to identify the cause of the variation
Variance analysis key element to time control. Float variance is an essential planning component for
evaluating project time performance
Revision category of schedule update that result in change to the projects scheduled start or finish dates.
New target schedule should be the usual mode of schedule revision.
Schedule Management Plan -defines how schedule changes will be managed; may be formal or informal.
Schedule Change Control System-defines procedures for changing the project schedule and includes the
documentation, tracking systems, and approval levels required for authorizing schedule changes.
Resource Planning Tools
Responsibility Matrix Identify who does what at what time/phase of the project
Resource SpreadsheetQuantifies how much work is needed from each resource during each time
period
Resource Gantt ChartIdentify the periods of time (e.g. calendar date) when a particular resource
is working on a particular task
Resource Histogram (Resource
Loading Chart)
Vertical bar chart showing the total number of resources needed during
each time period
Scheduling Tools
Networks (PERT, CPM, PDM) Interdependencies; how related
Barchart (Gantt)Effective progress reporting tool; no logical relationships shown between
activities
Milestone Chart Significant events; good for communicating status (used to track success)
Bar Chart (Grant Chart) 1. Weak Planning Tools 2. Good reporting tools 3. No Dependency Shown 4. No
Resources shown
Progress Report 50/50, 20/80, 0/100 An Activity is considered X percent complete when it begins
and gets credit of the last 100-X percent only when it is completed.
7/29/2019 PMP Resumen (Por RDCL)
27/64
Project COST Management
Knowledge AreasMajor Processes
desc.Primary Inputs Tools & Techniques
Primary
Outputs
Cost
Estimate
Costs
Developing an
approximation of the
monetary resources
needed to complete
project activities
1. Scope Baseline
2. Project Schedule
3. Human resource
Plan
4. Risk Register
5. Enterprise
environmental factors
6. Organizational
Process Assets
1. Expert Judgment
2. Analogous estimating
3. Parametric estimating
4. Bottom-up estimating
5. Three-point estimates
6. Reserve Analysis
7. Cost of quality
8. Project Management
Estimating Software
9. Vendor bid analysis
1. Activity
Cost estimates
2. Basis of
estimates
3. Project
Document
updates
Determine
Budget
Aggregating the
estimated costs of
individual activities or
work packages to
establish a cost
baseline (excludes
management
reserves).
1. Activity Cost
estimates
2. Basis of estimates
3. Scope baseline
4. Project Schedule
5. Resource Calendars
6. Contracts
7.Organizational
Process Assets
1. Cost aggregation
2. Reserve Analysis
3. Expert Judgment
4. Historical relationships
5. Funding Limit
reconciliation
1. Cost
performance
baseline
2. Project
funding
requirements
3. Project
Document
updates
Control
Costs
Monitoring the status
of the project to
update the project
budget and managing
changes to the cost
baseline. (influencing
the factors that create
changes to the
authorized cost
baseline)
1. Project management
plan
2. Project funding
requirements
3. Work performance
information
5. Organizational
process assets
1. Earned Value
Management
2. Forecasting
3. To-complete
performance index
4. Performance Reviews
5. Variance Analysis
6. Project Management
software
1. Work
performance
measurements
2. Budget
forecasts
3.
Organizational
process assets
updates
4. Change
requests
5. Project
management
7/29/2019 PMP Resumen (Por RDCL)
28/64
Plan updates
6. Project
Document
Updates
Estimate Costs
Developing and approximation (estimate) of the costs of the resources needed to complete project activities.Determine Budgeting
Allocating the overall cost estimate to individual work activities.
Control Cost
Controlling changes to the project budget.
Life Cycle Costing
Broader view of Project Cost Management, which includes cost of resources needed to complete schedule
activities along with effect of decisions on cost of using, maintaining & supporting the product, service or
result of the project.
Cost Management Plan
It is created as part of the Develop Project Management Plan process. It can establish:
1)Specifications for how estimates should be stated 2)Level of accuracy for estimates 3)Reporting formats 4) Rules for measuring cost performance 4)Whether costs will include both direct costs and indirect costs 5) Control thresholds.
Accuracy of Estimates
ROM (Rough Order of Magnitude): Accuracy of project estimate, done at initiating process.Project at initial stages can have ROM in the range of+/50% from actual later it will narrow to a
range of10 to +15%.
Budget Estimate: Usually made during the planning phase, in the range of -10 to +25 % fromactual.
Definitive Estimate:Estimate will become more refined later on the project. Its used whether +/-10%, or -5 to +10%.
Contingency Reserve
1.Project (known Unknowns) Part of Cost Baseline 2.Management (Unknown Unknowns) Part of Cost
Budget
Chart of Accounts
A chart of accounts describes the coding structure used by the performing organization to report financial
information in its general ledger
Analogous estimating
also called top-down estimating, means using the actual cost of a previous, similar project Parametric
modeling - mathematical model to predict project costs - per square foot of living space
7/29/2019 PMP Resumen (Por RDCL)
29/64
Parametric Estimation
It uses statistical relationship between historical data and other variables to calculate cost estimate. It can
produce higher levels of accuracy depending on sophistication, resource quantity and cost data.
Bottom-up estimating
the cost of individual activities or work packages rolled up to get the estimate for whole component.
Determine Budget
Cost baseline: Is a time-phased budget that will be used to measure and monitor cost performance on the
project. It is shown as an S curve.
Control Account: Represent the basic level at which project performance is measured and reported. The
purpose of cost accounts is to monitor and report on project performance.
Contingency Reserves: Address the cost impacts of the risks remaining during risk response planning.
Management Reserves: Extra funds to be set aside to cover unforeseen risks or changes to the project.
Funding Limit Reconciliation
Customer will set limits on disbursement of funds for the project. Funding Limit Reconciliation (TT of Cost
Budgeting) will necessitate the scheduling of work to be adjusted to smooth or regulate those expenditures.
It is accomplished by placing imposed date constraints for some work packages.
Project Performance Reviews (Tools and Techniques of Cost Control)
1.Variance Analysis 2.Trend Analysis 3.Earned Value Technique
7/29/2019 PMP Resumen (Por RDCL)
30/64
Progress Reporting: Rules of:
50/50: Activity is considered 50% complete when it begins, and gets 50% only when its completed
20/80: Activity is considered 20% complete when it begins, and gets 80% only when its completed
0/100: Activity gets no credit for partial completion. It only gets credit only when its full completed
EAC
Original estimating assumptions were fundamentally flawed, or that they are no longer relevant to a change
in conditions. Formula: EAC = AC + ETC. Current variances are seen as atypical and the project management
team expectations are that similar variances will not occur in the future. Formula: EAC = AC + BAC EV.
When current variances are seen as typical of future variances. Formula: EAC = AC + ((BAC EV)/CPI)
Project Cost ManagementProcesses required to ensure that the project is
completed within the approved budget.
Benefit Cost Ratio
Expected Revenues / Expected Costs. Measure benefits
(payback) to costs; not just profits. The higher the better(if rating over 1, the benefits are greater than the costs)
Internal Rate of ReturnInterest Rate which makes the PV of costs equal to PV of
benefits
Payback Period
Number of time periods up to the point where cumulative
revenues exceeds cumulative costs. Weakness in this
approach is the lack of emphasis on the magnitude of the
profitability. Does not account for time value of money
nor consider value benefits after payback.
Opportunity Cost
Cost of choosing one alternative and therefore giving up
the potential benefits of another alternative: it is the
value of the project not selected (lost opportunity).
Sunk CostExpended costs which should be ignored when making
decisions about whether to continue investing in a project
Law of Diminishing Returns Straight Line
Depreciation
The point beyond which the marginal addition of
resources does not provide a proportional amount of
utility. Same amount each time period (e.g. 10 10
10). Types 1. Straight Line 2. Accelerated (1. Double
Declining Balance 2. Sum of Years Digits)
Contingency Reserve
Separate quantity of time/money for known unknowns.
Designed to cover specific risk events previously identified
and measured in the Risk Management Process.
Management Reserve Separate quantity of time/money for unknown unknowns
7/29/2019 PMP Resumen (Por RDCL)
31/64
Working Capital Current Assets - Current Liabilities
Value Analysis
Cost reduction tool that considers whether function is
really necessary and whether it can be provided at a
lower cost without degrading performance or quality.
Finding the least expensive way to do the scope of work.
Value Estimating Part of Cost Control
Value Engineering ToolTool for analyzing a design, determining its function, and
assessing how to provide those functions cost effectively.
50-50 RuleAt beginning, charge 50% of its BCWS to the account.
Charge remaining at completion.
Analogous Estimating
Top down; based on similar projects. Represents a form
of expert judgment. Gives project team an understanding
of managements expectations (part of cost budgetingand cost estimating)
Bottom-up EstimatingDetailed cost estimates of work packages are aggregated.
Would provide best overall quality of the estimate.
Parametric Estimating
Relies on knowledge of mathematical relationships;
measured in $/unit (scalable, quantifiable). It does not
make use of team estimate. (part of cost budgeting and
cost estimating). Using a mathematical model to predict
the duration of a task (e.g. taking the average duration of
all past tasks)
Regression AnalysisStatistical technique graphically represented on scatter
diagram
Learning Curve
Mathematically models the intuitive notion that the more
times we do something, the faster we will be able to
perform
Variable Costs Costs rise directly with the size and scope of the project
Fixed CostsCosts do not change; non-recurring (e.g. project setup
costs)
Direct Costs
Incurred directly by a specific project. The PMI want the
team to participate in the cost estimates to get their buy-
in.
Indirect CostsPart of the overall organization's cost of doing business
and are shared by all projects. Usually computed as a
7/29/2019 PMP Resumen (Por RDCL)
32/64
percentage of the direct costs.
Control Account
Represent the basic level at which project performance is
measured and reported. The purpose of cost accounts is
to monitor and report on project performance.
Cost Change Control Systems Includes the documentation, tracking systems, andapproval levels needed to authorize a change.
Budget updatesShould be the next steps after an approved cost baseline
has changed because of a major change on a project.
Operating profitAmount of money earned: Revenue (direct + indirect
costs)
Discounted cash-flow approach
Present value method determines the net present value of
all cash flow by discounting it by the required rate of
return.
Parametric modelingInvolves using project characteristics (parameters) in a
mathematical model to predict project costs.
Life-Cycle CostProvide a picture of the total cost for the product (project,
operations and maintenance).
Project Closeout(output to cost control) Process and procedures
developed for the closing or canceling of projects
7/29/2019 PMP Resumen (Por RDCL)
33/64
Project QUALITY Management
Knowledge AreasMajor Processes
desc.Primary Inputs Tools & Techniques Primary Outputs
Quality
Plan
Quality
Identifying quality
requirements and/or
standards for the
project and product,
and documenting how
the project will
demonstrate
compliance.
1. Scope baseline
2. Stakeholder
register
3. Cost performance
baseline
4.Schedule baseline
5. Risk register
6. Enterprise
environmental
factors
7. Organizational
Process Assets
1. Cost-Benefit
analysis
2. Cost of quality
3. Control Charts
4.Benchmarking
5. Design of
experiments
6. Statistical sampling
7. Flowcharting
8. Proprietary quality
management
methodologies
9. Additional quality
Planning Tools
1. Quality
management plan
2. Quality Metrics
3. Quality Checklists
4. Process
Improvement Plan
5. Quality Baseline
6. Project
Management Plan
(updates)
Perform
Quality
Assurance
Auditing the quality
requirements and the
results from quality
control
measurements to
ensure appropriate
quality standards and
operational definitions
are used
1. Project
management plan
2. Quality metrics
3. Work
performance
information
4. Quality control
measurements
1. Plan quality and
perform quality control
tools and techniques
2. Quality audits
3. Process analysis
1. Organizational
process assets
updates
2. Change requests
3. Project
management plan
updates
4. Project document
updates
Perform
Quality
Control
Monitoring and
recording results of
executing the quality
activities to assess
performance and
recommend necessary
changes
1. Project
management plan
2. Quality Metrics
3. Quality Checklists
4. Work
performance
measurements
5. Approved Change
Requests
1. Cause and effect
diagram
2. Control charts
3. Flow-charting
4. Histogram
5. Pareto chart
6. Run Chart
7. Scatter diagram
8. Statistical sampling
1. Quality Control
Measurements
2. Validated
Changes
3. Validated
deliverables
4. Organizational
process assets
updates
7/29/2019 PMP Resumen (Por RDCL)
34/64
6. Deliverables
7. Organization
process assets
9. Inspection
10. Approved change
requests review
5. Change requests
6. Project
management plan
updates
7. Project document
updates
Quality: Degree to which the project fulfills requirements.
Grade: Category assigned to products or services having the same functional use but different
characteristics.
Low grade (a limited number of features) - low quality (many bugs)
Precision Consistency that the value of repeated measurements have little scatter. Precise measurementsmay not be accurate
Accurate It correctness of measured value, accurate measurements may not be precise.
Joseph Juran Quality - Fitness of Use Edward Deming Quality Improvement Plan, Do, Check and Act Philip Crosby Quality Conformance to requirements, Advocated Prevention over inspection and
Zero defects
Quality ManagementCreating and following policies and procedures to ensure that a project meets thedefined needs it was intended to meet from the customers perspective.
Cost of quality - All work to ensure conformance to requirements + nonconformance to requirements.
Cost of conformance: (quality training, studies, surveys, efforts to ensure everyone knows the processesto use to complete their work).
Cost of non conformance: (Rework, scrap, inventory costs, warranty costs, lost business).Costs of nonconformance should be lower than the costs of nonconformance.
Continuous Improvement (or Kaizen):Kaizen: (Kai: means to alter, Zen: Make better or improve).Continuous Improvement: quality movement.
Marginal Analysis Optimal Quality is reached at the point where the increased revenue fromimprovement equal incremental cost to secure it
Quality Management Plan Provides input to the overall project management plan and must addressQuality Control, Quality Assurance and continues process improvement for the project. Peer review may notinclude individuals that worked on the material being reviewed.
Gold Plating Giving Customers extras, it is not recommended
Quality Matrix Defines what something is and how to measure it.
Process improvement Plan Subsidiary of PMP, it details the steps for analyzing processes that will
facilitate the identification of waste and non-value added activity, it includes
1. Process boundaries
2.Process configuration
3.Process matrix
4.Targets for improved performance.
Quality Control Measurements Results of QC activities that are fed back to QA to reevaluate and
7/29/2019 PMP Resumen (Por RDCL)
35/64
analyze the quality standards and processes for performing organization.
Seven Basic Tools of Quality
1.Cause and Effect Diagram
2.Control Charts
3.Flowcharting
4.Histogram
5.Pareto Chart
6.Run Chart
7.Scatter Diagram
Design of experiments - is a statistical method that helps identify which factors might influence specific
variables
Prevention: keeping errors out of the process
Inspection: keeping errors out of the hands of the customerTolerances - (the result is acceptable if it falls within the range specified by the tolerance) and control limits(the process is in control if the result falls within the control limits).
Inspections - are variously called reviews, product reviews, audits, and walkthroughs; The process may be
changed to provide improvements, but it should not be adjusted when it is in control.
Pareto Diagram Histogram, ordered freq of occurrence, take corrective action & 80 prob/20 causes
Statistical sampling - Statistical sampling involves choosing part of a population of interest for inspection
Trend analysis involves using mathematical techniques to forecast future outcomes based on historical
results.
Project Quality Management processes required to ensure that the project will satisfy the needs forwhich it was undertaken.
Quality is the conformance to requirements/specifications and to fitness of use.
Quality function deployment provide better product definition and product development. Its main feature
are to capture the customers requirements, ensure cross functional teamwork, and link the main phases of
product development
Rework action taken to bring a non-conforming item into compliance. Rework is a frequent cause of
project overruns
7/29/2019 PMP Resumen (Por RDCL)
36/64
Quality Variable A quality characteristic that is measurable
Quality AttributeA quality characteristic that is classified as either conforming or
nonconforming
Benchmarking
Comparing practices of other projects. Provides a standard to
measure performance (time consuming). (e.g. investigatingquality standards that other companies are using)
Statistical Analysis Involves determining the probability of an occurrence
Trend Analysis
Uses mathematical techniques to forecast future outcomes based
on historical results; used to measure technical, cost, and
schedule performance
Quality Audit
Structured review of other quality management activities
erformed to identify lessons learned (used for process
improvement) Part of Quality Assurance. Provide managementconfidence that the project will satisfy relevant quality standards.
InspectionPrevent errors from reaching the customer before delivery to the
customer. Can be done throughout product development.
Design of Experiments
A technique to identify which variables have the most influence
on overall outcomes (part of Quality Planning) (e.g. analyze the
color/size combination that will contribute most to the
functionality of the new product). Can be applied to cost and
schedule tradeoffs.
Flow chart Help analyze how problems occurs
Attribute Sampling Measures whether or not the results conforms to specifications
Variable Sampling
Are characteristic you want to measure (size, shape, weight,
etc). An attribute is what you are measuring. The result is rated
on a continuous scale that measures the degree of conformity.
Assignable Causes Data point on a control chart that requires investigation
Specification Limit Shows customers expectations for quality (on a control chart)
Control Chart
Help newly assigned project manager determine whether theroject is out of control (in order to verify quality level). Can be
used to monitor project management processes such as coscard,
schedule variance, volume and frequency of scope changes, and
errors in project documents.
Statistical Control ChartAre used to monitor process variations overtime. Help people
understand and control their process work.
7/29/2019 PMP Resumen (Por RDCL)
37/64
Out of Control1. A data point falls outside of the upper or lower control limit.
2. Non-random points that are still within the upper and lower
control limit.
Upper and Lower Control Limit on a Control
Chart
Acceptable range of variation of a process. [These limits are set
based on the companys quality standards. The control limits are
determined from data obtained from the process itself.]
Specification Limit Fixed by the customer
Pareto DiagramUsed to show how results were generated, by type or category of
identified cause
IshikawaMade popular Pareto Chart, Cause-and-Effect Diagram and
Control Chart
Taguchi Method
Is used to estimate the loss associated with controlling or failing
to control process variability. If you select good designarameters, you can produce products that are more forgiving
and tolerant. The tool helps determine the value or break-even
oint of improving a process to reduce variability.
ISO 9000Provides a basic set of requirements for a quality system, without
specifying the particulars for implementation.
ChecklistsUsed to verify that a set of required steps has been performed in
quality control process
Statistically IndependentDetermine if problems are related before planning what to do
about them
Mutually Exclusive If two events cannot both occur in a single trial (?)
Random Cause Normal process variation
Cause and Effect Diagram (Fishbone)
(1) Creative way to look at actual causes and potential causes of
a problem
(2) Process of constructing helps stimulate thinking about an
issue; helps to organize thoughts; generates discussion
(3) Used to explore a wide variety of topics
(4) Also known as Ishikawa or Fishbone diagram
Quality Planning
Refers to potential problems. Although it usually occurs during
Planning Phase, it can occur during execution if there is a
change.
Quality ControlRefers to specific performance of a task (measuring quality and
comparing results to the quality plan). Its done throughout the
7/29/2019 PMP Resumen (Por RDCL)
38/64
project
Quality Assurance
Refers to overall quality requirements (standards) (e.g.
evaluating overall project performance regularly). Mostly done
during project executing.
Impact of Poor Quality
Increased cost Decreased productivity Increased risk and uncertainty Increased costs in monitoring
7/29/2019 PMP Resumen (Por RDCL)
39/64
Goal of the cost of quality program should be 3 - 5% of total value.
Cost of non-quality is estimated to be 12 - 20% of sales.
Cost of Quality Includes Prevention Costs (training), Appraisals Costs (inspection/testing) and Internal
(scrap, rework)/External (warranty) Failure costs
Management is 85% responsible for quality. The team member is ultimately responsible for qualitymanagement. The project manager is primarily responsible for quality management.
Two components ofproduct availability are reliabilityand maintainability.
To effectively use statistical quality control, the project team should know the differences between special
causes and random causes.
Sampling and probability are the most important topics to understand in statistical process control. Top
management should direct continuous improvement
Quality control measurement are records of quality control testing and measurement in a format for
comparison and analysis (input to quality assurance).
Documentation Quality Management Plan describes method for implementing quality policy project
quality system and organizational structures, responsibilities, procedures, processes and resources needed to
implement project quality management
TQM Total Quality Management Philosophy encourages companies and their employees to focus on finding
ways to continuously improve quality of their business practices and products.
Process Analysis Lessons learned in first few cases is used to improve the process on the remaining ones.
Standard Deviation From 3 point Estimates = (P O)/6
Six Sigma Level of Quality, which is percentage of occurrences to fall between the two control limits.
+/- 1 Sigma = 68.26%
+/- 2 Sigma = 95.46%
+/- 3 Sigma = 99.73%
+/- 6 Sigma = 99.9995%
Rule of Seven Based on Heuristics, seven random data points grouped together in a series with in control
limit. It represents that they are not random and should be investigated.
7/29/2019 PMP Resumen (Por RDCL)
40/64
Project HUMAN RESOURCE Management
Knowledge AreasMajor Processes
desc.Primary Inputs Tools & Techniques Primary Outputs
Human Resource
Management
Develop
Human
Resource Plan
Identifying and
documenting project
roles, responsibilities
and required skills,
reporting relationships
and creating the
staffing management
plan
1. Activity resource
requirements
2. Enterprise
Environmental
Factors
3. Organizational
Process Assets
1. Organization charts
and position
descriptions
2. Networking
3. Organizational
theory.
1. Human
Resource Plan
Acquire
Project Team
Confirming human
resource availability
and obtaining the
team necessary to
complete project
assignments.
1. Project
Management Plan
2. Enterprise
Environmental
Factors
3. Organizational
Process Assets
1. Pre-assignment
2. Negotiation
3. Acquisition
4. Virtual teams
1. Project Staff
Assignments
2. Resource
Calendars
3. Project
Management plan
updates
Develop
Project Team
Improving the
competencies, team
interaction and overall
team environment to
enhance project
performance.
1. Project Staff
Assignments
2. Project
Management Plan
3. Resource
Calendars
1. Interpersonal skills
2. Training
3. Team-building
activities
4. Ground rules
5. Co-location
6. Recognition and
rewards
1. Team
Performance
assessments
2. Enterprise
environmental
factors updates.
Manage
Project Team
Tracking team
member performance,providing feedback,
resolving issues, and
managing changes to
enhance project
performance
1. Project Staff
Assignments2. Project
Management Plan
3. Team
Performance
Assessments
4. Performance
1. Observation and
conversation2. Project performance
appraisals
3. Conflict
management
4. Issue log
5. Interpersonal Skills
1. Enterprise
environmentalfactors updates
2. Organizational
process assets
updates
3. Change
requests
7/29/2019 PMP Resumen (Por RDCL)
41/64
Reports
5. Organizational
Process Assets
4. Project
management plan
updates
Constraints Organizational Structure, Collective bargaining agreements, Economic Conditions
Organizational Charts Hierarchical, Matrix based and Text Oriented
RBS Resource Break Down Structureis a hierarchical chart which shows break down of project by resourcetypes. RBS is helpful in tracking project costs, aligned with organizations accounting system, can containcategories other than human resources.
RAMResponsibility Assignment Matrix, can be developed at various levels. RACI (Responsible,Accountable, Consult and Inform)
Halo Effect Tendency to rate high or low on all the factors due to the impression of a high or low rating onsome specific factor
Organizational Theory Provides information regarding the ways that people, teams and organizational
units behave.
Roles and Responsibilities (O/P of HR planning) Role, Authority, Responsibility and competency
SPONSORThe one who provides the financial resources for the project. If project is beingdone for an outside customer, it becomes the sponsor.
TEAMGroup of people who will complete work on the project. Team members canchange throughout the project as people are added and removed from theproject.
STAKEHOLDERS
Anyone who can positively or negatively influence the project, as well asincluding within the organization (customer users, project manager, team,sponsor, program and portfolio managers, PMO, functional and operationsmanagers) as external sellers that provide services or material for the project
FUNCTIONALMANAGER
Manages and "owns" the resources in a specific department, such as IT,engineering, public relations, or marketing, and generally directs the technicalwork of individuals from the functional area working on the project
PROJECTMANAGER
Responsible for managing the project to meet project objectives
PORTFOLIOMANAGER
Responsible for governance at an executive level of the projects or programsthat make up a portfolio
PROGRAMMANAGER
Responsible for managing a group of related projects. Projects are combinedinto a program to provide coordinated control, support, and guidance
Staffing Management Plan (part of the Human Resources Plan) Describes when and how humanresource requirements will be met. SMP can be updated because of promotions, retirements, illness,performance issues and changing workloads. SMP contents:
1 Staff acquisition internal or external or contract, same location or different etc.2 Resource Calendars When are people available?, when will they used.3 Staff Release Plan When will resources be released and no longer be charged to the project?.
4 Staff Training Needs - What are the needs of training for the resources?5 Recognition and rewards What are they?, What are the criteria for their use?6 Compliance With Government regulations7.Safety What policiesprotect the resources?
Five Stages of Team Building Activities Forming, Storming, Norming, Performing and Adjourning(Tuckman Ladder)
Forming Team meets and learns about the project and roles and responsibilities.
StormingBegins to address project work, technical decisions, and project managementapproach. (disagreements as people learn to work together)
NormingTeam members begin to work together and adjust work habits and behaviors thatsupport the team. Team begins to trust each other.
7/29/2019 PMP Resumen (Por RDCL)
42/64
PerformingTeam becomes efficient and works effectively together. In this point Projectmanager pay most attention to developing team members.
Adjourning Team completes the work and moves on from the project.
Ground Rules: establish clear expectations regarding acceptable behavior by project team members.
Kickoff Meeting Indirect Method to start team development. It should answer 1.Why am I here? 2. Whoare you and your expectations of me? 3. What is this team going to do? 4. How is the team going to do thiswork? 5. How do I fit into all this?
Lessons Learned from Manage Project Team
Project organization charts, positions and SMP Ground rules, conflict management techniques and recognitions Procedures for Virtual teams, co-location, training and team building Special skills and competencies by team members discovered Issues and solutions
Project Human Resource Management - process required to make the most effective use of the peopleinvolved with the project
Responsibility Assignment Matrix (RAM) Show who does what (x=person, y=phase). The most
important feature of the RAM is the participatory development process involving all stakeholders. Show who
is participant, who is accountable, who handles reviews, who provides input and who must sign off on
specific work packages or project phases.
Linear Responsibility Chart (LRC) identifying responsibility, assignments by work packages and action
required. Also referred to as RAM.
Organizational Breakdown Structure (OBS) - A depiction of the project organization arranged so as to
relate work packages to organization units.
Resources Histogram often part of Staffing Management Plan; shows resource usage (eg staff hours) pertime period (eg wk, mth) of a specific job function.
Rewards and Recognition Systems -- to be effective, must make the link between performance and
reward clear, explicit and achievable.
Types of Power
Legitimate(Formal)
Derived from formal position
Coercive Predicated on fear
Reward
Involves positive reinforcement and ability to award something of value Project often
needs their own rewards system to affect employee performance. Used correctly, bring
the teams goals and objectives in line with each other and with the project.
Expert Held in esteem because of special knowledge or skill (requires time)
Referent Ability to influence others through charisma, personality, etc.
The best forms of power are generally Reward and Expert
7/29/2019 PMP Resumen (Por RDCL)
43/64
Conflict Management
Avoidance
/Withdrawal
(Ignoring)
At least one party withdraws from conflict. Cool off period, could be lose/lose
Retreating from actual or potential disagreement; delaying (e.g. Just document the
problem)
Competition/Forcing
Exerting ones viewpoint; a last resort [win/lose] (e.g. Call the customer and demandthat you receive the approval today.
Compromising
Bargaining and searching for solutions; neither party wins but each gain some
satisfaction [win-lose/win-lose] this is very rarely a good way to resolve technical
issues.
AccommodationOpposite of Competition. One party meets other party need at expense of his own.
Lose/Win
Collaborating
Involves incorporating multiple ideas and viewpoints from people with different
perspectives and offers a good opportunity to learn from others (good when project istoo important to be compromised) Win/Win Best Strategy
Smoothing
De-emphasize differences and emphasize commonalities; friendly but avoids solving
root causes; delaying (eg. Manager says an issue is valid but doesnt think it will be a
big problem later)
Problem Solving
/ ConfrontationAddress conflict directly in problem solving mode [win/win]
6 steps of problem solving:
1. Define what is the real/root problem
2. Analyze the problem
3. Identify solutions
4. Pick a solution
5. Implement a solution
6. Review the solution and confirm that the solution solved the problem
Motivational Theory: Content & Process Theories
Content: What energizes, directs behavior
1. Maslows Hierarchy of Needs Theory (1. Physiological, 2. Safety, 3. Social/Belonging, 4. Esteem, 5.
Self-Actualization)
2. Hertzbergs Motivator/Hygiene Theories (Motivator: Responsibility, Self-Actualization, Esteem,
Professional Growth, Recognition. Hygiene: Working Conditions, Salary, Relationship at Work, Social, Safety,
Physiological)
7/29/2019 PMP Resumen (Por RDCL)
44/64
Process: How personal factors influence behavior
1. McGregors Theory X and Theory Y (X: Assumes people lack ambition, dislike responsibility, are
inherently self-centered and are not very bright; motivate by reward and punishment. Y: Assumes people
become lazy w/o recognition, will accept responsibility, can become self-motivated and exercise self-control;
motivate by removing obstacles and providing self-directed environment.)
2.Ouchis Theory Z/Japanese Theory ( focus on team, company; usually lifetime employment, collective
decision making )
Other Motivational Theories
Behaviorism people behavior can be modified through manipulation of rewards and punishments
Expectancy Theory Motivation is explained in terms of expectations that people have about
(1) their ability to perform effectively on the job,
(2) the rewards they might obtain if they do perform effectively and
(3) the value or degree of satisfaction they anticipate from those rewards.
MBO More support to team, not more power (remain to PM)
Leadership Theories:
McGregor Theory X (employee lack ambition) and Theory Y (org