97
PMP exam Workshop – Winter 2008 PMP exam Workshop – Winter 2008 Time Management Timothy J. Krikau, MBA, PMP

PMP Exam Prep - Time Management

  • Upload
    tkrikau

  • View
    8.433

  • Download
    2

Embed Size (px)

DESCRIPTION

This is a presentation I gave at Walsh College to help project managers prepare for the PMP certification exam. It is based on PMBoK 3rd Version.

Citation preview

Page 1: PMP Exam Prep - Time Management

PMP exam Workshop – Winter 2008PMP exam Workshop – Winter 2008

Time Management

Timothy J. Krikau, MBA, PMP

Page 2: PMP Exam Prep - Time Management

TIME MANAGEMENTTIME MANAGEMENT

The PMBOK states that Project Time The PMBOK states that Project Time Management is the Knowledge Area Management is the Knowledge Area

that “includes the processes required that “includes the processes required to accomplish timely completion of to accomplish timely completion of

the project.”the project.”

This is NOT Franklin/Covey stuff…! This is NOT Franklin/Covey stuff…!

Page 3: PMP Exam Prep - Time Management

Warning!!!Warning!!!

The PMP Examination does not The PMP Examination does not recognize PM software!!recognize PM software!!

You must know the “manual” method You must know the “manual” method of time management!of time management!

TIME MANAGEMENTTIME MANAGEMENT

Page 4: PMP Exam Prep - Time Management

TIME MANAGEMENTTIME MANAGEMENT

• 6.1 – Activity Definition 6.1 – Activity Definition

• 6.2 – Activity Sequencing 6.2 – Activity Sequencing

• 6.3 – Activity Resource Estimating6.3 – Activity Resource Estimating

• 6.4 – Activity Duration Estimating 6.4 – Activity Duration Estimating

• 6.5 – Schedule Development 6.5 – Schedule Development

• 6.6 – Schedule Control 6.6 – Schedule Control

Page 5: PMP Exam Prep - Time Management

6.1 Activity Definition • Involves identifying and documenting the work Involves identifying and documenting the work

that is planned to be performedthat is planned to be performed• This process identifies the deliverables at the This process identifies the deliverables at the

lowest level of the work breakdown structure lowest level of the work breakdown structure (WBS), called the (WBS), called the work packagework package

• The work package is then broken down into The work package is then broken down into smaller components called schedule activitiessmaller components called schedule activities– These provide a basis for estimating, scheduling, These provide a basis for estimating, scheduling,

executing, and monitoring and controlling the project executing, and monitoring and controlling the project workwork

TIME MANAGEMENTTIME MANAGEMENT

Page 6: PMP Exam Prep - Time Management

TIME MANAGEMENTTIME MANAGEMENTInputs

1. Enterprise Environmental Factors

2. Organizational Process Assets

3. Project Scope Statement

4. Work Breakdown Structure (WBS)

5. WBS Dictionary

6. Project Management Plan

Tools & Techniques

1. Decomposition

2. Templates

3. Rolling Wave Planning

4. Expert Judgment

5. Planning Component

Outputs

1. Activity List

2. Activity Attributes

3. Milestone List

4. Requested Changes

Page 7: PMP Exam Prep - Time Management

InputsInputs

The Project Management Plan contains the The Project Management Plan contains the schedule management plan, which schedule management plan, which

provides guidance on the development provides guidance on the development and planning of schedule activities.and planning of schedule activities.

TIME MANAGEMENTTIME MANAGEMENT

Page 8: PMP Exam Prep - Time Management

Tools and TechniquesTools and Techniques

• Decomposition:Decomposition: The process of subdividing the project The process of subdividing the project work packages into smaller, more manageable work packages into smaller, more manageable components called schedule activities. components called schedule activities.

• Templates:Templates: A standard activity list or a portion of an A standard activity list or a portion of an activity list from a previous project can often be used as a activity list from a previous project can often be used as a template. template.

TIME MANAGEMENTTIME MANAGEMENT

Page 9: PMP Exam Prep - Time Management

Tools and TechniquesTools and Techniques

• Rolling Wave Planning: Rolling Wave Planning: A form of progressive elaboration planning where the work to be accomplished at the near term is planned in detail at a low level of the WBS, while the work far in the future is planned at relatively high levels of the WBS

• Expert Judgment:Expert Judgment: Use your team members – they’re your Use your team members – they’re your SMEs and best source of information. SMEs and best source of information.

TIME MANAGEMENTTIME MANAGEMENT

Page 10: PMP Exam Prep - Time Management

Tools and TechniquesTools and Techniques

• Planning Component: Planning Component: When insufficient definition of the project scope is When insufficient definition of the project scope is available to decompose a branch of the WBS down to the work package available to decompose a branch of the WBS down to the work package level, the last component in that branch can be used to develop a high level level, the last component in that branch can be used to develop a high level project schedule for that component. There are planning components that project schedule for that component. There are planning components that are summary activities that aren’t detailed enough to support estimating, are summary activities that aren’t detailed enough to support estimating, scheduling, executing, monitoring, or controlling the project work. scheduling, executing, monitoring, or controlling the project work.

– Control Account: Management control point where scope, budget, actual cost, and schedule are integrated and compared to earned value for performance measurement.

– Planning Package: Planning Package: A WBS component below the control account with known A WBS component below the control account with known work content but without detailed schedule activities. work content but without detailed schedule activities.

TIME MANAGEMENTTIME MANAGEMENT

Page 11: PMP Exam Prep - Time Management

OutputsOutputs

• Activity List: Activity List: A comprehensive list including all schedule A comprehensive list including all schedule activities that are planned to be performed on the project. activities that are planned to be performed on the project. No activities should be included that are not in the project No activities should be included that are not in the project scope. scope.

• Activity Attributes: Activity Attributes: Support details like the activity Support details like the activity description, predecessor activities, successor activities, description, predecessor activities, successor activities, etc. etc.

TIME MANAGEMENTTIME MANAGEMENT

Page 12: PMP Exam Prep - Time Management

OutputsOutputs

• Milestone List: Milestone List: This is pretty self-explanatory. This is pretty self-explanatory.

• Requested Changes: Requested Changes: Any changes discovered during Any changes discovered during activity definition that can affect the project scope activity definition that can affect the project scope statement and the WBS should be processed through the statement and the WBS should be processed through the Integrated Control ProcessIntegrated Control Process

TIME MANAGEMENTTIME MANAGEMENT

Page 13: PMP Exam Prep - Time Management

6.2 Activity Sequencing

• Involves identifying and documenting the logical Involves identifying and documenting the logical relationships among schedule activities. relationships among schedule activities.

• Schedule activities can be logically sequenced with Schedule activities can be logically sequenced with precedence relationships as well as leads and lags in order precedence relationships as well as leads and lags in order develop a realistic and achievable project schedule.develop a realistic and achievable project schedule.

• Can be done via PM software, manual techniques, or both. Can be done via PM software, manual techniques, or both.

– Remember that the exam doesn’t recognize PM softwareRemember that the exam doesn’t recognize PM software. . Know the manual techniques. Know the manual techniques.

TIME MANAGEMENTTIME MANAGEMENT

Page 14: PMP Exam Prep - Time Management

TIME MANAGEMENTTIME MANAGEMENTInputs

1. Project Scope Statement

2. Activity List

3. Activity Attributes

4. Milestone List

5. Approved Change Requests

Tools & Techniques

1. Precedence Diagramming Method (PDM)

2. Arrow Diagramming Method (ADM)

3. Schedule network templates

4. Dependency Determination

5. Applying leads and lags

Outputs

1. Project schedule network diagrams

2. Activity list (updates)

3. Activity attributes (updates)

4. Requested Changes

Page 15: PMP Exam Prep - Time Management

InputsInputsProject Scope StatementProject Scope Statement

– The project scope statement contains the product scope description, which includes product characteristics that often can affect activity sequencing, such as the physical layout of a plant to be constructed or subsystem interfaces on a software project

– While these effects are often apparent in the activity list, the product scope description is generally reviewed to ensure accuracy

TIME MANAGEMENTTIME MANAGEMENT

Page 16: PMP Exam Prep - Time Management

Tools and TechniquesTools and Techniques

Precedence Diagramming Method:Precedence Diagramming Method: PDM is a method of constructing a project schedule network PDM is a method of constructing a project schedule network

that uses boxes or rectangles, referred to as nodes, to that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that represent activities and connects them with arrows that show the dependencies. It’s also known as Activity-On-show the dependencies. It’s also known as Activity-On-

Node (AON).Node (AON).

TIME MANAGEMENTTIME MANAGEMENT

B

C

E

D

F

Finish

A

Start

Page 17: PMP Exam Prep - Time Management

Tools and TechniquesTools and Techniques

TIME MANAGEMENTTIME MANAGEMENT

PDM Includes four types of dependencies or PDM Includes four types of dependencies or precedence relationships:precedence relationships:

•Finish-to-start – most commonFinish-to-start – most common•Finish-to-finishFinish-to-finish•Start-to-startStart-to-start•Start-to-finishStart-to-finish – rarely used (I don’t see how this is possible!)

Page 18: PMP Exam Prep - Time Management

Tools and TechniquesTools and Techniques

TIME MANAGEMENTTIME MANAGEMENT

Start-to-Finish (SF)

when activity A starts

B can finish

Start-to-Start (SS)

when activity A starts

B can also start

Finish-to-Start (FS)

Activity A must finish

before B can start

Finish-to-Finish (FF)

Activity A must finish

before B can finish

BBAA

AA BB

AA BB

AA BB

Page 19: PMP Exam Prep - Time Management

Tools and TechniquesTools and Techniques

TIME MANAGEMENTTIME MANAGEMENT

Arrow Diagramming Method (ADM) Arrow Diagramming Method (ADM)

• Method for constructing a project schedule network diagram using arrows to represent activities.

• Nodes are used to designate dependencies. • Also known as Arrow-On-Arrow (AOA) • Uses only Finish-To-Start dependencies• Use “dummy” relationships.

• Arrows are dashed and have no time duration.

• Used to establish logical relationships correctly.

Page 20: PMP Exam Prep - Time Management

Tools and TechniquesTools and Techniques

TIME MANAGEMENTTIME MANAGEMENT

Arrow Diagramming Method (ADM) Arrow Diagramming Method (ADM)

The dashed linerepresents a dummy activity

AB

C

D

E

F

Finish

Start 1

4

32

5

6

Page 21: PMP Exam Prep - Time Management

Tools and TechniquesTools and Techniques

TIME MANAGEMENTTIME MANAGEMENT

POP QUIZ!!!!POP QUIZ!!!!

Can a “dummy” activity have dependencies?

YES! Dummies are used to establish dependencies

between activities but do not have time or work requirements.

Page 22: PMP Exam Prep - Time Management

Tools and TechniquesTools and Techniques

TIME MANAGEMENTTIME MANAGEMENT

Schedule Network TemplatesSchedule Network Templates

• Standardized project schedule network diagram Standardized project schedule network diagram templates can be used to expedite the preparation of templates can be used to expedite the preparation of networks of project schedule activities. networks of project schedule activities. • Floor plansFloor plans• Clinical trials on pharmaceuticalsClinical trials on pharmaceuticals• Start-up phase on development projects. Start-up phase on development projects.

Page 23: PMP Exam Prep - Time Management

Tools and TechniquesTools and Techniques

TIME MANAGEMENTTIME MANAGEMENT

Dependency DeterminationDependency Determination

• Three type of dependencies used to define activity Three type of dependencies used to define activity sequencing.sequencing.• Mandatory Dependencies (Hard Logic)Mandatory Dependencies (Hard Logic) – inherent in – inherent in

the nature of the work being done. the nature of the work being done. • In order to build a deck, you must have the tools.In order to build a deck, you must have the tools.

• Discretionary Dependencies (Preferred, Preferential, Discretionary Dependencies (Preferred, Preferential, or Soft Logic)or Soft Logic) – generally determined by “best – generally determined by “best practices”practices”• Which tools to use…Which tools to use…

• External DependencyExternal Dependency – Based on needs/desires of – Based on needs/desires of parties outside of the project. parties outside of the project. • Building codes regulations and compliance Building codes regulations and compliance

Page 24: PMP Exam Prep - Time Management

Tools and TechniquesTools and Techniques

TIME MANAGEMENTTIME MANAGEMENT

Applying Leads and LagsApplying Leads and Lags

• Lead – allows an acceleration of the successor activity. Lead – allows an acceleration of the successor activity. • Example: Coding may be able to start five days Example: Coding may be able to start five days

before the design is finished. before the design is finished.

• Lag – allows a delay in the successor activity Lag – allows a delay in the successor activity • Example: Pouring concrete – the task may be Example: Pouring concrete – the task may be

finished, but it takes time for the concrete to cure. finished, but it takes time for the concrete to cure. The time taken to cure is the The time taken to cure is the lag.lag.

Page 25: PMP Exam Prep - Time Management

OutputsOutputs

TIME MANAGEMENTTIME MANAGEMENT

Project Schedule Network DiagramsProject Schedule Network Diagrams

• The project schedule network diagram can include full project details, or have one or more summary activities

• A summary narrative accompanies the diagram and describes the basic approach used to sequence the activities. Any unusual activity sequences within the network are fully described within the narrative

Page 26: PMP Exam Prep - Time Management

OutputsOutputs

TIME MANAGEMENTTIME MANAGEMENT

Activity List (updates) Activity List (updates)

• Approved change requests resulting from the Activity Sequencing Process will reflect in the updated Activity List.

Activity Attributes (updates) Activity Attributes (updates)

• Updated to include defined logical relationships plus any leads Updated to include defined logical relationships plus any leads and/or lags. and/or lags.

• Any changes in the Activity List will result in changes in the Any changes in the Activity List will result in changes in the Activity Attributes. Activity Attributes.

Page 27: PMP Exam Prep - Time Management

OutputsOutputs

TIME MANAGEMENTTIME MANAGEMENT

Requested Changes Requested Changes

• Preparation of logical relationships, lead, and lags in a project might reveal a need for a change.

Page 28: PMP Exam Prep - Time Management

6.3 Activity Resource Estimating

• Involves determining what resources (persons, equipment, Involves determining what resources (persons, equipment, materiel) and what quantities of each resource will be used.materiel) and what quantities of each resource will be used.

• This activity is closely coordinated with the Cost Estimating This activity is closely coordinated with the Cost Estimating process.process.

• Resources must be planned and coordinated in order to Resources must be planned and coordinated in order to avoid common problems such as lack of resources and avoid common problems such as lack of resources and resources being taken away from the project.resources being taken away from the project.

TIME MANAGEMENTTIME MANAGEMENT

Page 29: PMP Exam Prep - Time Management

TIME MANAGEMENTTIME MANAGEMENTInputs

1. Enterprise environmental factors

2. Organizational process assets

3. Activity list

4. Activity attributes

5. Resource availability

6. Project management plan

Tools & Techniques

1. Expert judgment

2. Alternatives analysis

3. Published estimating data

4. Project management software

5. Bottom-up estimating

Outputs

1. Activity resource requirements

2. Activity attributes (updates)

3. Resource Breakdown Structure (RBS)

4. Resource calendar (updates)

5. Requested Changes

Page 30: PMP Exam Prep - Time Management

InputsInputs

Resource AvailabilityResource Availability • Information on which resources (such as people, Information on which resources (such as people,

equipment, and materiel) are potentially available is used equipment, and materiel) are potentially available is used for estimating the resource types. Can include: for estimating the resource types. Can include: – Geographical considerationsGeographical considerations– Resource pool experience and needs. Resource pool experience and needs.

• Project might need a large number of engineers at both the junior Project might need a large number of engineers at both the junior and senior levels, but may be pared down to engineers with project and senior levels, but may be pared down to engineers with project knowledge in later phases. knowledge in later phases.

TIME MANAGEMENTTIME MANAGEMENT

Page 31: PMP Exam Prep - Time Management

Tools and TechniquesTools and Techniques

TIME MANAGEMENTTIME MANAGEMENT

Alternatives AnalysisAlternatives Analysis

• Many schedule activities have alternative methods of Many schedule activities have alternative methods of accomplishment. accomplishment. • Various levels of capabilities and skillsVarious levels of capabilities and skills• Types and sizes of machinery Types and sizes of machinery • Different types of tools (manual or automated) Different types of tools (manual or automated) • Make-or-buy decisions. Make-or-buy decisions.

Page 32: PMP Exam Prep - Time Management

Tools and TechniquesTools and Techniques

TIME MANAGEMENTTIME MANAGEMENT

Published Estimating DataPublished Estimating Data

• Several companies routinely publish updated production Several companies routinely publish updated production rates and unit costs of resources for an extensive array rates and unit costs of resources for an extensive array of labor trades, materiel, and equipment based on of labor trades, materiel, and equipment based on geography. geography.

Page 33: PMP Exam Prep - Time Management

Tools and TechniquesTools and Techniques

TIME MANAGEMENTTIME MANAGEMENT

Project Management SoftwareProject Management Software

• Has the capability to help plan, organize, and manage Has the capability to help plan, organize, and manage resource pools and develop resources. resource pools and develop resources. • Depending of the sophistication of the software, a Depending of the sophistication of the software, a

project manager can define rates, availabilities, and project manager can define rates, availabilities, and calendars for the required resources. calendars for the required resources.

• These programs are great, but are only as good as These programs are great, but are only as good as the PM using them. the PM using them.

Page 34: PMP Exam Prep - Time Management

Tools and TechniquesTools and Techniques

TIME MANAGEMENTTIME MANAGEMENT

Bottom-Up EstimatingBottom-Up Estimating

• When a schedule activity cannot be estimated with a When a schedule activity cannot be estimated with a reasonable degree of confidence, the work within the reasonable degree of confidence, the work within the schedule activity is decomposed into more detail schedule activity is decomposed into more detail • The resources needs of each lower, more detailed The resources needs of each lower, more detailed

piece of work are estimated. piece of work are estimated. • Then they are aggregated into a total quantity for Then they are aggregated into a total quantity for

each of the activity’s resources. each of the activity’s resources.

Page 35: PMP Exam Prep - Time Management

OutputsOutputs

TIME MANAGEMENTTIME MANAGEMENT

Activity Resource RequirementsActivity Resource Requirements

• Identification and description of the types and quantities Identification and description of the types and quantities of resources required for each schedule activity in a of resources required for each schedule activity in a work packagework package

• The requirements can then be aggregated to determine The requirements can then be aggregated to determine the estimated resources for each work package. the estimated resources for each work package.

Page 36: PMP Exam Prep - Time Management

OutputsOutputs

TIME MANAGEMENTTIME MANAGEMENT

Resource Breakdown StructureResource Breakdown Structure

• An RBS is a hierarchical structure of the identified An RBS is a hierarchical structure of the identified resources by category and type. resources by category and type.

Resource Calendar (Updates) Resource Calendar (Updates) • A composite resource calendar for the project A composite resource calendar for the project

documents working days and non-working days that documents working days and non-working days that determine those dates on which a specific resource, determine those dates on which a specific resource, whether person or materiel, can be active or idle. whether person or materiel, can be active or idle.

Page 37: PMP Exam Prep - Time Management

6.4 Activity Resource Estimating

• The process of estimating schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities

• The inputs for the estimates of schedule activity duration originate from the person or group on the project team who is most familiar with the nature of the work content in the specific schedule activity

• The duration estimate is progressively elaborated, and the process considers the quality and availability of the input data

• All data and assumptions that support duration estimating are documented for each activity duration estimate

TIME MANAGEMENTTIME MANAGEMENT

Page 38: PMP Exam Prep - Time Management

TIME MANAGEMENTTIME MANAGEMENTInputs

1. Enterprise environmental factors

2. Organizational process assets

3. Project scope statement

4. Activity list

5. Activity attributes

6. Activity resource requirements

7. Resource calendar

8. Project management plan

1. Risk register

2. Activity cost estimates

Tools & Techniques

1. Expert judgment

2. Analogous estimating

3. Parametric estimating

4. Three-point estimates

5. Reserve analysis

Outputs

1. Activity duration estimates

2. Activity attributes (updates)

Page 39: PMP Exam Prep - Time Management

InputsInputsProject Scope Statement Project Scope Statement

The constraints and assumptions from the project scope statement are considered when estimating

the schedule activity durations

TIME MANAGEMENTTIME MANAGEMENT

Page 40: PMP Exam Prep - Time Management

InputsInputsActivity Resource RequirementsActivity Resource Requirements

The estimated activity resource requirements will have an effect on the duration of the schedule activity, since the

resources assigned to the schedule activity, and the availability of those resources, will significantly influence

the duration of most activities

TIME MANAGEMENTTIME MANAGEMENT

Page 41: PMP Exam Prep - Time Management

InputsInputsResource CalendarResource Calendar

The composite resource calendar, developed as part of the Activity Resource Estimating process, includes the availability, capabilities, and skills of human resources.

The type, quantity, availability, and capability, when applicable, of both equipment and materiel resources that could significantly influence the duration of schedule activities are also considered.

For example, if a senior and junior staff member are assigned full time, a senior staff member can generally be expected to complete a given schedule activity in less time than a junior staff member

TIME MANAGEMENTTIME MANAGEMENT

Page 42: PMP Exam Prep - Time Management

InputsInputsProject Management Plan – Risk RegisterProject Management Plan – Risk Register

• The risk register has information on identified project risks that the project team considers when producing estimates of activity durations and adjusting those durations for risks

• The project team considers the extent to which the effects of risks are included in the baseline duration estimate for each schedule activity, in particular those risks with ratings of high probability or high impact

TIME MANAGEMENTTIME MANAGEMENT

Page 43: PMP Exam Prep - Time Management

InputsInputsProject Management Plan – Activity Cost EstimatesProject Management Plan – Activity Cost Estimates

• The project activity cost estimates, if already completed, can be developed in sufficient detail to provide estimated resource quantities for each schedule activity in the project activity list

TIME MANAGEMENTTIME MANAGEMENT

Page 44: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesAnalogous Estimating Analogous Estimating

• Analogous duration estimating means using the actual duration of a previous, similar schedule activity.

• Frequently used to estimate project duration when there is a limited amount of detailed information about the project.

• Early stages of a project is a good example.

• Most reliable when the previous activities are similar in fact, not just in appearance and when the team members have the needed expertise.

TIME MANAGEMENTTIME MANAGEMENT

Page 45: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesParametric Estimating Parametric Estimating

• Estimating the basis for activity durations can be quantitatively deterined by multiplying the quantity of work to be performed by the productivity rate.

• For example, productivity rates can be estimated on a design project by the number of drawings times labor hours per drawing, or a cable installation in meters of cable times labor hours per meter

• The total resource quantities are multiplied by the labor hours per work period or the production capability per work period, and divided by the number of those resources being applied to determine activity duration in work periods

TIME MANAGEMENTTIME MANAGEMENT

Page 46: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesThree Point EstimatesThree Point Estimates

• Estimating the basis for activity durations can be quantitatively determined by multiplying the quantity of work to be performed by the productivity rate.

• For example, productivity rates can be estimated on a design project by the number of drawings times labor hours per drawing, or a cable installation in meters of cable times labor hours per meter

• The total resource quantities are multiplied by the labor hours per work period or the production capability per work period, and divided by the number of those resources being applied to determine activity duration in work periods

TIME MANAGEMENTTIME MANAGEMENT

Page 47: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesThree Point EstimatesThree Point Estimates

Three-point estimates are based on determining three types of estimates:

• Most likely. The duration of the schedule activity, given the resources likely to be assigned, their productivity, realistic expectations of availability for the schedule activity, dependencies on other participants, and interruptions

• Optimistic. The activity duration is based on a best-case scenario of what is described in the most likely estimate

TIME MANAGEMENTTIME MANAGEMENT

Page 48: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesThree Point EstimatesThree Point Estimates

Three-point estimates are based on determining three types of estimates:

• Pessimistic. The activity duration is based on a worst-case scenario of what is described in the most likely estimate

• An activity duration estimate can be constructed by using an average of the three estimated durations

• That average will often provide a more accurate activity duration estimate than the single point, most-likely estimate

TIME MANAGEMENTTIME MANAGEMENT

Page 49: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesReserve Analysis Reserve Analysis

• Project teams can choose to incorporate additional time referred to as contingency reserves, time reserves or buffers, into the overall project schedule as recognition of schedule risk

• The contingency reserve can be a percentage of the estimated activity duration, a fixed number of work periods, or developed by quantitative schedule risk analysis

TIME MANAGEMENTTIME MANAGEMENT

Page 50: PMP Exam Prep - Time Management

OutputsOutputsActivity duration estimates Activity duration estimates

• These quantitative assessments of the likely number work periods that will be required to complete a schedule activity.

– Example: 2 weeks ± 2 days – indicating that the schedule activity will take at least 8 days but no more than 12. • Remember to measure days based on the hours of

operation. 2 weeks is 10 days if closed on weekends.

TIME MANAGEMENTTIME MANAGEMENT

Page 51: PMP Exam Prep - Time Management

TIME MANAGEMENTTIME MANAGEMENT

6.5 Schedule Development

• Project schedule development, an iterative process, determines planned start and finish dates for project activities

• Schedule development can require that duration estimates and resource estimates are reviewed and revised to create an approved project schedule that can serve as a baseline against which progress can be tracked

• Schedule development continues throughout the project as work progresses, the project management plan changes, and anticipated risk events occur or disappear as new risks are identified

Page 52: PMP Exam Prep - Time Management

TIME MANAGEMENTTIME MANAGEMENTInputs

1. Organizational process assets

2. Project scope statement

3. Activity list

4. Activity attributes

5. Project schedule network diagrams

6. Activity resource requirements

7. Resource calendars

8. Activity duration estimates

9. Project management plan

1. Risk register

Tools & Techniques

1. Schedule network analysis

2. Critical path method

3. Schedule compression

4. What-if scenario analysis

5. Resource leveling

6. Critical chain method

7. Project management software

8. Applying calendars

9. Adjusting leads and lags

10.Schedule model

Outputs

1. Project schedule

2. Schedule model data

3. Schedule baseline

4. Resource requirements (updates)

5. Activity Attributes (updates)

6. Project Calendar (updates)

7. Requested changes

8. Project management plan (updates)

1. Schedule management plan (updates)

Page 53: PMP Exam Prep - Time Management

InputsInputs• Organizational Process AssetsOrganizational Process Assets – may have some resources like a – may have some resources like a

project calendar to indicate resource availability. project calendar to indicate resource availability.

• Project Scope StatementProject Scope Statement – contains assumptions and constraints – contains assumptions and constraints that can impact schedule development.that can impact schedule development.

TIME MANAGEMENTTIME MANAGEMENT

Page 54: PMP Exam Prep - Time Management

InputsInputs• Project Management PlanProject Management Plan – contains the schedule management – contains the schedule management

plan, the cost management plan, project scope plan, and risk plan, the cost management plan, project scope plan, and risk management plan. These plan help guide the schedule management plan. These plan help guide the schedule development. development. – Risk RegisterRisk Register – contains risks and risk response plans needed to – contains risks and risk response plans needed to

support the Schedule Development process. support the Schedule Development process.

TIME MANAGEMENTTIME MANAGEMENT

Page 55: PMP Exam Prep - Time Management

InputsInputs• Project Management PlanProject Management Plan – contains the Schedule management – contains the Schedule management

plan, the cost management plan plan, the cost management plan

• Project Scope StatementProject Scope Statement – contains assumptions and constraints – contains assumptions and constraints that can impact schedule development.that can impact schedule development.

TIME MANAGEMENTTIME MANAGEMENT

Page 56: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesSchedule Network AnalysisSchedule Network Analysis

• Schedule network analysis is a technique that generates the project schedule

• It employs a schedule model and various analytical techniques, such as critical path method, critical chain method, what-if analysis, and resource leveling to calculate the early and late start and finish dates, and scheduled start and finish dates for the uncompleted portions of project schedule activities

TIME MANAGEMENTTIME MANAGEMENT

Page 57: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesSchedule Network AnalysisSchedule Network Analysis

• If the schedule network diagram used in the model has any network loops or network open ends, then those loops and open ends are adjusted before one of the analytical techniques is applied

• Some network paths may have points of path convergence or path divergence that can be identified and used in schedule compression analysis or other analyses

TIME MANAGEMENTTIME MANAGEMENT

Page 58: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesCritical Path MethodCritical Path Method

• The critical path method is a schedule network analysis technique that is performed using the schedule model

• The critical path method calculates the theoretical early start and finish dates, and late start and finish dates, for all schedule activities without regard for any resource limitations, by performing a forward pass analysis and a backward pass analysis through the project schedule network paths

TIME MANAGEMENTTIME MANAGEMENT

Page 59: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesCritical Path MethodCritical Path Method

• Critical paths have either a zero or negative total float, and schedule activities on a critical path are called "critical activities"

• Adjustments to activity durations, logical relationships, leads and lags, or other schedule constraints may be necessary to produce network paths with a zero or positive total float

• Once the total float for a network path is zero or positive, then the free float - the amount of time that a schedule activity can be delayed without delaying the early start date of any immediate successor activity within the network path - can also be determined

TIME MANAGEMENTTIME MANAGEMENT

Page 60: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesSchedule Compression Schedule Compression

• This method shortens the project schedule without changing the project scope to schedule constraints, imposed dates, or other schedule objectives.

• Methods include: • Crashing – cost and schedule tradeoffs are analyzed to determine how to

obtain the greatest amount of compression for the least incremental cost. • Does not always work and many times can only end up increasing cost.

• Fast Tracking – activities that are normally done in sequence are performed in parallel. • Increases risk as tasks are required to be performed without complete

information. • Both of these methods run the risk of increased time and cost due to

rework.

TIME MANAGEMENTTIME MANAGEMENT

Page 61: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesWhat-If Scenario AnalysisWhat-If Scenario Analysis

• This is an analysis of the question "What if the situation represented by scenario 'X' happens?"

• A schedule network analysis is performed using the schedule model to compute the different scenarios, such as delaying a major component delivery, extending specific engineering durations, or introducing external factors, such as a strike or a change in the permitting process

TIME MANAGEMENTTIME MANAGEMENT

Page 62: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesWhat-If Scenario AnalysisWhat-If Scenario Analysis

• The outcome of the what-if scenario analysis can be used to assess the feasibility of the project schedule under adverse conditions, and in preparing contingency and response plans to overcome or mitigate the impact of unexpected situations

• Simulation involves calculating multiple project durations with different sets of activity assumptions

• Most common technique is the Monte Carlo Analysis • A distribution of possible activity durations is defined for each schedule activity

used to calculate a distribution of possible outcomes for a total project.

TIME MANAGEMENTTIME MANAGEMENT

Page 63: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesResource Leveling Resource Leveling

• A schedule network analysis technique applied to a schedule model that has already been analyzed by the critical path method.

• Primarily used when shared or critical required resources are only available at limited times or in limited quantities.

• Resource leveling can cause the critical path to change.

TIME MANAGEMENTTIME MANAGEMENT

Page 64: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesCritical Chain MethodCritical Chain Method

• Critical chain is another schedule network analysis technique that modifies the project schedule to account for limited resources

• Critical chain combines deterministic and probabilistic approaches. Initially, the project schedule network diagram is built using non-conservative estimates for activity durations within the schedule model, with required dependencies and defined constraints as inputs

• After the critical path is calculated resource availability is entered and the resource-limited schedule result is determined

• The resulting schedule often has an altered critical path

TIME MANAGEMENTTIME MANAGEMENT

Page 65: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesProject Management SoftwareProject Management Software

• Project management scheduling software is widely used to assist with schedule development

• Other software might be capable of interacting directly or indirectly with project management software to carry out the requirements of other Knowledge Areas, such as cost estimating by time period and schedule simulation in quantitative risk analysis

• Remember that the software is only good as the user and does not manage the project for you!

TIME MANAGEMENTTIME MANAGEMENT

Page 66: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesProject Management SoftwareProject Management Software

• These products automate the calculation of the mathematical forward pass and backward pass critical path analysis and resource leveling, and, thus, allow for rapid consideration of many schedule alternatives

• They are also widely used to print or display the outputs

of developed schedules

TIME MANAGEMENTTIME MANAGEMENT

Page 67: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesApplying CalendarsApplying Calendars

• Project calendars and resource calendars identify periods when work is allowed

• Project calendars affect all activities

• For example, it may not be possible to work on the site during certain periods of the year because of weather

• Resource calendars reflect how some resources work only during normal business hours, while others work three full shifts, or a project team member might be unavailable, such as on vacation or in a training program, or a labor contract can limit certain workers to certain days of the week

TIME MANAGEMENTTIME MANAGEMENT

Page 68: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesApplying Leads and LagsApplying Leads and Lags

• Since the improper use of leads or lags can distort the project schedule, the leads or lags are adjusted during schedule network analysis to develop a viable project schedule

TIME MANAGEMENTTIME MANAGEMENT

Page 69: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesSchedule ModelSchedule Model

• Schedule data and information are compiled into the schedule model for the project

• The schedule model tool and the supporting schedule model data are used in conjunction with manual methods or project management software to perform schedule network analysis to generate the project schedule

TIME MANAGEMENTTIME MANAGEMENT

Page 70: PMP Exam Prep - Time Management

OutputsOutputsProject ScheduleProject Schedule

• The project schedule includes at least a planned start date and planned finish date for each schedule activity

• If resource planning is done at an early stage, then the project schedule would remain preliminary until resource assignments have been confirmed, and scheduled start dates and finish dates are established

• This process usually happens no later than completion of the project management plan.

TIME MANAGEMENTTIME MANAGEMENT

Page 71: PMP Exam Prep - Time Management

OutputsOutputsProject ScheduleProject Schedule

• A project target schedule may also be developed with defined target start dates and target finish dates for each schedule activity

• The project schedule can be presented in summary form, sometimes referred to as the master schedule or milestone schedule, or presented in detail

TIME MANAGEMENTTIME MANAGEMENT

Page 72: PMP Exam Prep - Time Management

OutputsOutputsProject ScheduleProject Schedule

• Can be shown in one more or more of the following formats.

– Project Schedule Network Diagrams– Bar Charts– Milestone Charts

TIME MANAGEMENTTIME MANAGEMENT

Page 73: PMP Exam Prep - Time Management

OutputsOutputsProject ScheduleProject Schedule

• Project Schedule Network Diagrams – Used to primarily show dependencies.

• Bar Charts– Progress reporting the project team.

• Milestone Charts– Reporting to Senior Management.

TIME MANAGEMENTTIME MANAGEMENT

Page 74: PMP Exam Prep - Time Management

OutputsOutputsSchedule Model DataSchedule Model Data

• Supporting data for the project schedule includes at least the milestones, schedule activities, activity attributes, and documentation of all identified assumptions and constraints.

• The amount data used varies by application area.

TIME MANAGEMENTTIME MANAGEMENT

Page 75: PMP Exam Prep - Time Management

OutputsOutputsSchedule Model DataSchedule Model Data

• Supporting includes, but is not limited to: – Resource requirements by time period

• Usually in the form of a histogram

– Alternative schedules• Best-case vs. Worst-case• Resource Leveled vs. Not Resource Leveled.• With or without imposed dates.

– Schedule contingency reserves

TIME MANAGEMENTTIME MANAGEMENT

Page 76: PMP Exam Prep - Time Management

OutputsOutputsSchedule BaselineSchedule Baseline

TIME MANAGEMENTTIME MANAGEMENT

•A schedule baseline is a specific version of the project schedule developed from the schedule network analysis of the schedule model

•It is accepted and approved by the project management team as the schedule baseline with baseline start dates and baseline finish dates

Page 77: PMP Exam Prep - Time Management

OutputsOutputsResource Requirements (updates)Resource Requirements (updates)

• Resource leveling can have a significant effect on preliminary estimates of the types and quantities of resources required

• If the resource-leveling analysis changes the project resource requirements, then the resource requirements are updated

TIME MANAGEMENTTIME MANAGEMENT

Page 78: PMP Exam Prep - Time Management

OutputsOutputsProject Calendar (updates)Project Calendar (updates)

• A project calendar is a calendar of working days or shifts that establishes those dates on which schedule activities are worked

• It also establishes nonworking days that determine dates on which schedule activities are idle, such as holidays, weekends, and non-shift hours

• The calendar for each project may use different calendar units as the basis for scheduling the project

TIME MANAGEMENTTIME MANAGEMENT

Page 79: PMP Exam Prep - Time Management

OutputsOutputsProject Management Plan (Updates)Project Management Plan (Updates)

• The project management plan (Section 4.3) is updated to reflect any approved changes in how the project schedule will be managed

– Schedule Management Plan - Updates• If approved change requests result from the Project Time

Management processes, then the schedule management plan component of the project management plan may need to be updated to include those approved changes

TIME MANAGEMENTTIME MANAGEMENT

Page 80: PMP Exam Prep - Time Management

TIME MANAGEMENTTIME MANAGEMENT

6.6 Schedule Control

• Determining the current status of the project schedule.Determining the current status of the project schedule.• Influencing the factors that create schedule changesInfluencing the factors that create schedule changes• Determining that the project schedule has changedDetermining that the project schedule has changed• Managing the actual changes as they occur. Managing the actual changes as they occur.

Note that this section is not in the Planning Group, but in the Note that this section is not in the Planning Group, but in the Monitoring and Controlling Group. Monitoring and Controlling Group.

The previous sections in Time Management should be The previous sections in Time Management should be completed before launching the project. This section is completed before launching the project. This section is

done during while executing the project. done during while executing the project.

Page 81: PMP Exam Prep - Time Management

TIME MANAGEMENTTIME MANAGEMENTInputs

1. Schedule management plan

2. Schedule baseline

3. Performance reports

4. Approved change requests

5. Project schedule network diagrams

Tools & Techniques

1. Progress reporting

2. Schedule change control system

3. Performance measurement

4. Project management software

5. Variance analysis

6. Schedule comparison bar charts

Outputs

1. Schedule model data (updates)

2. Schedule baseline (updates)

3. Performance measurements

4. Requested changes

5. Recommended corrective actions

6. Organizational process assets (updates)

7. Activity list (updates)

8. Activity attributes (updates)

9. Project management plan (updates)

Page 82: PMP Exam Prep - Time Management

InputsInputsPerformance ReportsPerformance Reports

• Performance reports provide information on schedule performance, such as which planned dates have been met and which have not

• Performance reports may also alert the project team to issues that may cause schedule performance problems in the future

TIME MANAGEMENTTIME MANAGEMENT

Page 83: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesProgress Reporting Progress Reporting

• Includes information such as actual start and finish dates, Includes information such as actual start and finish dates, and the remaining durations for unfinished schedule and the remaining durations for unfinished schedule activities. activities.

• If progress measurement such as earned value is also used, then the percent complete of in-progress schedule activities can also be included

• To facilitate the periodic reporting of project progress, a template created for consistent use across various project organizational components can be used throughout the project life cycle

TIME MANAGEMENTTIME MANAGEMENT

Page 84: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesSchedule Change Control SystemSchedule Change Control System

• The schedule change control system defines the procedures by which the project schedule can be changed

• It includes the paperwork, tracking systems, and approval levels necessary for authorizing changes

• The schedule change control system is operated as part of the Integrated Change Control process

TIME MANAGEMENTTIME MANAGEMENT

Page 85: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesPerformance MeasurementPerformance Measurement

• Performance measurement techniques produce the Schedule Variance (SV)) and Schedule Performance Index (SPI), which are used to assess the magnitude of any project schedule variations that do occur

• Schedule Variance (SV) = Earned Value (EV) – Planned Value (PV) • Schedule Performance Index (SPI) = EV/PV

• An important part of schedule control is to decide if the schedule variation requires corrective action.

• For example, a major delay on any schedule activity not on the critical path may have little effect on the overall project schedule, while a much shorter delay on a critical or near-critical activity may require immediate action

TIME MANAGEMENTTIME MANAGEMENT

Page 86: PMP Exam Prep - Time Management

POP QUIZ!!!!POP QUIZ!!!!

Which of the following is correct?Which of the following is correct?A.A. A critical path can run over a dummy. A critical path can run over a dummy. B.B. There can only be one critical path.There can only be one critical path.C.C. The network path will change every time every The network path will change every time every

time the end date changes. time the end date changes.

D.D. A project can never have negative float.A project can never have negative float.

TIME MANAGEMENTTIME MANAGEMENT

Page 87: PMP Exam Prep - Time Management

POP QUIZ!!!!POP QUIZ!!!!

Use the process of elimination for exam questions. Use the process of elimination for exam questions. There can be more than one critical path.There can be more than one critical path.

The network path may change or may not, depending on The network path may change or may not, depending on

schedule reserve amounts and the reason for the change. schedule reserve amounts and the reason for the change. Note the question used a definitive verb, “will” Note the question used a definitive verb, “will”

You can have negative float if the project is behind scheduleYou can have negative float if the project is behind schedule

TIME MANAGEMENTTIME MANAGEMENT

Page 88: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesVariance AnalysisVariance Analysis

• Performing the schedule variance analysis during the schedule monitoring process is a key function of schedule control

• Comparing target schedule dates with the actual/forecast start and finish dates provides useful information for the detection of deviations, and for the implementation of corrective actions in case of delays

• The total float variance is also an essential planning component to evaluate project time performance

TIME MANAGEMENTTIME MANAGEMENT

Page 89: PMP Exam Prep - Time Management

Tools and TechniquesTools and TechniquesSchedule Comparison Bar ChartsSchedule Comparison Bar Charts

• To facilitate analysis of schedule progress, it is convenient to use a comparison bar chart, which displays two bars for each schedule activity

• One bar shows the current actual status and the other shows the status of the approved project schedule baseline

• This shows graphically where the schedule has progressed as planned or where slippage has occurred

TIME MANAGEMENTTIME MANAGEMENT

Page 90: PMP Exam Prep - Time Management

OutputsOutputsSchedule Model Data (updates)Schedule Model Data (updates)

• A project schedule update is any modification to the project schedule model information that is used to manage the project

• Appropriate stakeholders are notified of significant modifications as they occur

TIME MANAGEMENTTIME MANAGEMENT

Page 91: PMP Exam Prep - Time Management

OutputsOutputsSchedule Model Data (updates)Schedule Model Data (updates)

• New project schedule network diagrams are developed to display approved remaining durations and modifications to the work plan

• In some cases, project schedule delays can be so severe that development of a new target schedule with revised target start and finish dates is needed to provide realistic data for directing the work, and for measuring performance and progress

TIME MANAGEMENTTIME MANAGEMENT

Page 92: PMP Exam Prep - Time Management

OutputsOutputsSchedule Baseline (updates)Schedule Baseline (updates)

• Schedule revisions are a special category of project schedule updates. Revisions are changes to the schedule's start and finish dates in the approved schedule baseline

• These changes are generally incorporated in response to approved change requests (Section 4.4.1.4) related to project scope changes or changes to estimates

• Development of a revised schedule baseline can only occur as a result of approved changes

The original schedule baseline is saved and archived before creating the new baseline to retain historical data. You never know…, the original baseline could work better on a future project.

TIME MANAGEMENTTIME MANAGEMENT

Page 93: PMP Exam Prep - Time Management

OutputsOutputsPerformance MeasurementsPerformance Measurements

• The calculated schedule variance (SV) and schedule performance index (SPI) values for WBS components, in particular the work packages and control accounts, are documented and communicated to stakeholders

TIME MANAGEMENTTIME MANAGEMENT

Page 94: PMP Exam Prep - Time Management

OutputsOutputsRecommended Corrective ActionsRecommended Corrective Actions

• A corrective action is anything done to bring expected future project schedule performance in line with the approved project schedule baseline

• Corrective action in the area of time management often involves expediting, which includes special actions taken to ensure completion of a schedule activity on time or with the least possible delay

• Corrective action frequently requires root cause analysis to identify the cause of the variation

• The analysis may address schedule activities other than the schedule activity actually causing the deviation; therefore, schedule recovery from the variance can be planned and executed using schedule activities delineated later in the project schedule

TIME MANAGEMENTTIME MANAGEMENT

Page 95: PMP Exam Prep - Time Management

OutputsOutputsOrganizational Process Organizational Process

AssetsAssets

• Lessons Learned! • Lessons Learned! • Lessons Learned!

TIME MANAGEMENTTIME MANAGEMENT

Page 96: PMP Exam Prep - Time Management

OutputsOutputsProject Management Plan (Updates)Project Management Plan (Updates)

• Any change made in the schedule management plan will Any change made in the schedule management plan will result in a change in the overall planresult in a change in the overall plan

TIME MANAGEMENTTIME MANAGEMENT

Page 97: PMP Exam Prep - Time Management

TIME MANAGEMENTTIME MANAGEMENT