Project Management

By:- Kumar Ratnesh

Page 2: DocumentPM

CHAPTER-1

2

Page 3: DocumentPM

Concept of Project

A project is a temporary endeavor undertaken to create a unique product or service. It implies– a specific timeframe– a budget– unique specifications – working across organizational boundaries

Page 4: DocumentPM

Project Management

Project management is about creating an environment conducive to

getting critical projects done!

Project management is about changing people’s behavior

Page 5: DocumentPM

Why Project Management?

• Today’s complex environments require ongoing implementations

• Project management is a method and mindset…a disciplined approach to managing chaos

• Project management provides a framework for working amidst persistent change

Page 6: DocumentPM

Why Projects Fail

• Failure to align project with organizational objectives • Poor scope• Unrealistic expectations• Lack of executive sponsorship• Lack of project management• Inability to move beyond individual and personality

conflicts• Politics

Page 7: DocumentPM

Why Projects Succeed!

• Project Sponsorship at executive level• Good project charter• Strong project management• The right mix of team players• Good decision making structure• Good communication• Team members are working toward common

goals

Page 8: DocumentPM

Why this matters to YOU• Most of us get to where we are by some technical or

specific set of skills• If you want to get things done, you need a good

blend of– Business knowledge– People management – Knowledge of organizational politics– AND an area of technical expertise

Those are the people that make things happen!

Page 9: DocumentPM

What is Project ? • Objective • Activities Outputs ⇒• Duration • Budget ( Input)• Resources (Input)

An undertaking for the purpose of achieving established objectives, within a given budget and time period.

Page 10: DocumentPM

CONCEPT

►The dictionary meaning of project is speculative meaning .

►It deal with three dimensions :-innovation , risk , and vision.

►Gilliner:- defines “it as the whole complex of activities involved in using recourses to gain benefits”.

Page 11: DocumentPM

CHARACTERISTICS OF A PROJECT

►Investment pattern

►Expected result

►Time limit

►Location

Page 12: DocumentPM

PROJECT MANAGEMENT

►Project management is the modern context is a highly sophisticated and fast developing concept and practice.

►It has been defined as “The process of planning directing a project from its inception to its completion in a given cost to generate a given results”.

Page 13: DocumentPM

PHASES OF PROJECT MANAGEMENT

►Identification

►Formulation

►Appraisal

►Selection

► Implementation

►Management

Page 14: DocumentPM

ROJECT CLASSIFICATION

►Quantitative & non-quantitative project

►Sectoral project

►Techno- Economic project

►Financial institution classification

Page 15: DocumentPM

CHAPTER-2

15

Page 16: DocumentPM

PROJECT IDENTIFICATION

►It is concerned with the collection, completion and analysis of economic data for the eventual purpose of locating possible opportunity for investment and with the development of the characteristics of such opportunity.

Page 17: DocumentPM

CONSTRAINTS IN PROJECT IDENTIFICATION

►Internal constraints

►External constraints

Page 18: DocumentPM

TECHNIQUES OF PROJECT IDENTIFICATION

►Desk research

►Techno-Economic survey

Page 19: DocumentPM

CRITERIA FOR PROJECT SELECTION

►Investment size

►Location

►Technology

►Equipment

►Marketing

Page 20: DocumentPM

STAGES OF PROJECT FORMULATION

►Feasibility Analysis

►Techno-economic analysis

►Project design and network analysis

►Input analysis

►Financial analysis

►Pre-investment analysis

Page 21: DocumentPM

PROJECT FEASIBILITY

►The methods are as follows:-

►Economic analysis

►Financial analysis

►Market analysis

►Technical assessment

►Managerial competence

Page 22: DocumentPM

TOOLS OF PROJECT APPRAISAL

►Financial appraisal

► Economic appraisal

►Technological appraisal

►Socio-economic appraisal

►Managerial appraisal

Page 23: DocumentPM

What is Project Cycle ?

• Project identification• Project formation• Appraisal• Implementation• Monitoring• Plan revision• Evaluation• Feedback

Page 24: DocumentPM

Project Cycle Management

    Planning

Implementation

Evaluation

PDM

Page 25: DocumentPM

Plan

DoSee

Do See

Plan

See

Plan

Do

We are in this stage.

Page 26: DocumentPM

Project Design Matrix ( PDM )Narrative Summary

Objectively Verifiable Indicators

Means of Verification

Important

Assumptions

Overall Goal

Project Purpose

Outputs

Activities Inputs

Pre-conditions

Page 27: DocumentPM

PDM Vertical Logic • Project Purpose  

Objectives that the project should achieve within the project duration

• Overall Goal Direction that the project should take next

• OutputsStrategies for achieving the Project Purpose

• Activities Specific actions taken to produce Outputs

• Important Assumptions Conditions important for project success, but that cannot be controlled by the projects. Whether these conditions develop or not is uncertain.

Page 28: DocumentPM

PDM Horizontal Logic • Objectively Verifiable Indicators

Standards for measuring project achievement.

• Means of VerificationData sources from which indicators are derived.

• Inputs Personnel, materials, equipments, facilities and funds required by the project.

• Preconditions Conditions that must be fulfilled before a project gets underway

Page 29: DocumentPM

Characteristics of PCM

Participatory Approach

Logicality

Consistency Transparency

Problem-Solving

Page 30: DocumentPM

Development of PCM Method

• Late 1960s Logical Framework (USAID) ➢ International Agencies introduce the

Logframe

• Early 1980s ZOOP (GTZ) Objectives-Oriented

Project Planning ➢ European countries adapt the ZOPP

• Early 1990s PCM(FASID) ➢ JICA begins full-scale introduction of the PCM

Page 31: DocumentPM

Participants in the Workshop

Moderator

Resident of the community

Personnel of the donor agency

Expert in a related issue

Other organization

Recipient country governmental agency

Recipient country implementing agency

Page 32: DocumentPM

PCM Workshop

Working as a team

Visualizing ideas

Analyzing step by step Cards

&Board

Consensus

Brainstorming

Moderator

Page 33: DocumentPM

8 Rules 1. Write down your own statement on a card.2. Write only one idea on a card.3. Make your statement specific.4. Express your statement in a concise sentence. 5. Stick to the facts and avoid abstractions and

generalizations.6. Make it a rule to write cards before beginning

discussions.7. Do not remove a card from the board before a

consensus is obtained. 8. Do not ask who wrote a particular card.

Page 34: DocumentPM

7 Steps in PP

Stakeholders Analysis

Problems Analysis

Objectives Analysis

Project Selection

PDM Plan of Operation

Analysis Stage

Planning Stage

Appraisal

We are practicing by this stage.

Page 35: DocumentPM

STEP1 Stakeholders Analysis

Identify the issues, problems, and current conditions of the target area through analyzing the area and local residents targeted for assistance, related groups, related organizations and agencies.

Focus on people and organization.

Tentatively select a target group.

Page 36: DocumentPM

STEP2 Problems Analysis

Problems Analysis visually represents the causes and effects of existing problems in the project area, in the form of a Problem Tree. It clarifies the relationships among the identified problems.

Page 37: DocumentPM

STEP3 Objectives Analysis

Objective Analysis clarifies the means-ends relationship between the desirable situation that would be attained one problems have been solved and the solution for attaining it. This stage also requires an Objective Tree.

Page 38: DocumentPM

STEP4 Project Selection

Project Selection is a process in which specific project strategies are selected from among the objectives and means raised in Objectives Analysis, based upon selection criteria.

Page 39: DocumentPM

STEP5 Formation of the PDM

The project design Matrix (PDM) is formed through elaborating the major project components and plans based on the approach selected. The format of PDM is similar to that of the Logical Framework, and therefore can be commonly used worldwide.

Page 40: DocumentPM

STEP6 PDM Appraisal

The PDM Appraisal is conducted by an aid agency to ensure the project plan. It is composed of the following stage:

(1) Examination of the details of the PDM elements; (2) review of the PDM formation process; (3) examination from the perspective of the five evaluation criteria.

Page 41: DocumentPM

STEP7 Plan of Operations

The Plan of Operation is prepared by the project implementers, based on the PDM and other information. It is an effective tool for project implementation and management, and provides important data for monitoring and evaluation of the project.

Page 42: DocumentPM

Rules for Writing Problems

1. Write in a Sentence. Make Clear “Subject and Object”. 2. Avoid “No Solution”.3. Avoid Generalization.– Be Specific.4. Don’t Write a Cause and Effect in One Card. 5. Be Specific Whose problem.

Page 43: DocumentPM

Example: Format of Plan of Operation

Activities Expected Results

Schedule Person in Charge

Implementer Materials and Equipment

Cost Remarks

1-1

1-1-1

1-1-2

2-1

2-1-1

2-1-2

Page 44: DocumentPM

Monitoring and Evaluation

The Five Evaluation Criteria

1. Efficiency 2. Effectiveness

3. Impact 4. Relevance

5. Sustainability

Page 45: DocumentPM

• Efficiency The productivity in project implementation. The degree to which Inputs have

been converted into Outputs.

• Effectiveness The degree to which the Project Purpose has been achieved by the project

Outputs.

• ImpactPositive and negative changes produced, directly or indirectly, as a result of the Implementation of the project.

• Relevance The validity of the Overall Goal and Project Purpose at the evaluation stage.

• Sustainability The durability of the benefits an and development effects produced by the

project after its completion.

Page 46: DocumentPM

Laws of Project Management

• No major project is ever installed on time, within budget, or with the same staff that started it. Yours will not be the first.

• Projects progress quickly until they become 90% complete, then they remain at 90% complete forever.

• When things are going well, something will go wrong.

• When things just cannot get any worse, they will.

Page 47: DocumentPM

• When things appear to be going better, you have overlooked something.

• No system is ever completely debugged. Attempts to debug a system inevitably introduce new bugs that are even harder to find.

• A carelessly planned project will take three times longer to complete than expected

• A carefully planned project will take only twice as long.

• Project teams detest progress reporting because it vividly manifests their lack of progress.

Page 48: DocumentPM

Core Project Management Tools

• Project Charter• Work Breakdown Structure (WBS)• Project Schedule• Project Budget

Page 49: DocumentPM

Project Charter• What must be done?

– What are the required resources?– What are the constraints?– What are the short and long term implications?

• Why do it?• When must it be done?• Where must it be done?• Who does what?

– Who is behind the project?– Who is funding the project?– Who is performing the work of the project?

Page 50: DocumentPM

Project Charter

• Project Goal & Objective

• Sponsor• Stakeholders• Timeline• Resources required• Deliverables

• Decision making• Assumptions• Risks• Business process

changes• Project manager• Project team• Budget• Signatures

Page 51: DocumentPM

Assumptions

• Opportunity to put it all out there– Challenges facing the project– Implications– Organizational history– Political implications– Impact to traditional power– Requirements of decision-making

• Write down what cannot be said– Keep it objective

Page 52: DocumentPM

Project Schedule Tools• Many tools available

– Microsoft Project– Many more specialized softwar– Excel

• Most important– Monitor tasks– Gantt views of project

• one page views for executives• rollout and more complex views for work teams

– Critical Paths– Inputs from multiple teams that roll up to project manager– Dependencies– Resources assigned to tasks

Page 53: DocumentPM

Project Budget

• Direct Costs• Indirect Costs• Ongoing costs

Page 54: DocumentPM

Project Budget• Direct Costs

– Hardware– Software– Contractor fees

• Estimated hours• Hourly Rates per

contractor• Various contractor

rates

– Training– Fanfare– Other

TOTALS

• Indirect Costs– Your people’s time

and effort• Estimated time on

project• Estimated cost

based on hourly rate

– Other’s time and effort

– Opportunity cost• What projects or

tasks are NOT going to get done in order to get this project done?

Year 1 Year 2 Year 3

Page 55: DocumentPM

Managing the Project

• Triple Constraint• Five Stages• Project Manager Role• Decision Making Structure• Communication Plan• Meeting Management• Team Development• Navigating Organizational Politics

Page 56: DocumentPM

Five Stages of Project Management

Project Management (in our industry) is divided into five parts:

1.Project charter development2.RFP Development and Process 3.Planning & Design

• Project team creation• Project kick-off• Planning (WBS, schedule)• Budget

4.Implementation/construction5.Project termination, hand-off to operations mgt.

Page 57: DocumentPM

Project Manager’s Role

Lead

Define Plan Monitor Complete

Re-Plan

Communicate

Communicate

Page 58: DocumentPM

Project Manager’s Role

• Leadership• Organization• Communication• Finance• Technical savvy• Politicking• Team building• Praising• Punishing

Page 59: DocumentPM

Traditional OrganizationPresident

VP Academics VP Student Affairs VP Finance VP Development

Page 60: DocumentPM

Project Management is Change

• Project methodology is really about managing change– Change in current practices– Developing new practices– Getting people to change their behaviors

• How they do their work• How they work together• How they get the work of the project done• Avoidance of paving the cowpaths

• PM is a mindset, a discipline, that can help your organization increase effectiveness and put order to chaos

Page 61: DocumentPM

Limitations of Project Management

• PM works when there is buy-in for the methods and process

• It does not work when – buy-in is lacking or there is not support for the methods by

executives– ‘end arounds’ are tolerated– influential players operate project business outside the

project– decisions made by project teams are not supported– charters, schedules and other work products of the team are

not supported

Page 62: DocumentPM

Project Portfolio Management

• More common in disciplined IT organizations• Manages projects that are

– Proposed– Approved– In progress

• Requires organizational buy-in

Page 63: DocumentPM

Project Finance

Page 64: DocumentPM

How is most corporate investment organized?

• In corporations– Debt is usually recourse to entire organization’s

assets– Leverage is usually modest (obvious exceptions)

Page 65: DocumentPM

What is project finance?• Refers to a wide range of financing structures. These financing

structures usually have one thing in common --- the financing is not primarily dependent on the credit support (credit quality) of the sponsors or the value of the assets involved. Instead, debtholders (banks, public lenders) place a substantial degree of reliance on the performance (I.e., cash flows) of the project itself…

• Non-recourse (or at least limited resource) financing• Project finance is both a financial structure and a corporate

governance structure aimed at resolving capital market imperfections and efficiently allocating risk.

Page 66: DocumentPM

What types of projects?

• Somewhat arbitrary, but– Single purpose capital investment– Stand alone entity– Finite and long life– Large in size

Page 67: DocumentPM

Project finance versus conventional financing

• Modigliani Miller still holds if its assumptions are true– if there were no taxes or transactions costs– no costs of financial distress– no agency conflicts– no information costs– THEN PROJECT FINANCE WOULD ADD NO VALUE

RELATIVE TO CONV. FIN.

Page 68: DocumentPM

Project finance is very costly

• Transactions costs very large• Contracts: very complex organizational

structure, not much flexibility• Long negotiations, long time to close• Fees (0.6% of deal size, similar to M&A)• DISADVANTAGE RELATIVE TO CONVENTIONAL

FINANCE

Page 69: DocumentPM

Costs of distress/bankruptcy

• Risk of default and allocation of this risk very different than conventional debt

• Less risk contamination with other parts of firm

• Less co-insurance benefit• Rearranges “states” in which default occurs• Trade-off, clearly

Page 70: DocumentPM

Agency costs

• High leverage, dedicated cash flows, very specific contractual terms for repayment and contingencies– May limit opportunities for risk shifting– May limit cross subsidization incentives– May replace managerial incentives of a public-

sector project with a for-profit venture, contracts used to enhance incentives

Page 71: DocumentPM

May improve economics

• MM theorem assumes the investment is fixed

– It may be that the investment itself is improved by the structure

• Walt Disney got huge tax and governmental relief by setting up EuroDisney as a project structure rather than owning outright

– Tax, gov’t. reg.’s may be reduced

Page 72: DocumentPM

Outside guarantees

• Project finance is usually high leverage and non recourse to project sponsors– even with its possible benefits, this usually leads to high

risk debt, which is often illiquid, costly and sometimes simply not available

• Often a guarantee or credit support is offered by– Governments/international agency (IFC/World

Bank)/Sponsors/etc.

Page 73: DocumentPM

Different contractual relationships

• Contracts needed:– Management/shareholder agency relationship– Intercorporate agency relationship– Government/corporate agency relationship– Bondholder stockholder relationship

• Definition of the organization (corporation) is a nexus of these contracts

Page 74: DocumentPM

CHAPTER-3

74

Page 75: DocumentPM

75

PROJECT APPRAISALINTRODUCTION PROJECT APPRAISAL:

1. Technique to analyse if the project is feasible or not.2. It helps in recognizing needs and problems, and their

early analysis3. A tool for decision making4. Identifying input, output parameters and criteria for

evaluating systems.5. Evaluating feasibility in terms of technical, financial

and economic practicability.6. Developing and implementation of system so designed

in terms of - Engg. Calculations

Page 76: DocumentPM

76

- Specification of finalization- Production, manufacturing Installation and commissioning

SALIENT ASPECTS OF PROJECT APPRAISAL

a. Need - New or improvedb. Realisability - Cost/benefit termsc. Practicability - Technically, Financially economically

viable.d. Optimality: Project to be best alternativee. Uncertainty : Probability of risk and cost of information

to achieve greater certaintyf. Controllability - Needs a feed back loop to review

update and keep system on rough track.

Page 77: DocumentPM

77

Feasibility Study:

It involved creating, identifying, brain storming feasibility of ideas and then selecting to prove further one or more feasible solutions.

- Then prilimary design, optimal design (best alternatives)- Detailed design (a complete description of projects for its

implimentation.- Lastly planning for production:

Page 78: DocumentPM

78

Feasibility Study: A Schematic Diagram

Yes No

Initial Screening

Is the Idea Prima Facie Promising ?

Plan Feasibility Analysis

Generation of Ideas

Conduct Market AnalysisConduct Technical Analysis

Basic and functional feasibliity

Terminate

Conduct Financial AnalysisRisk./ Return

Pre

limin

ary

Pra

cti

cal

An

aly

sis

Page 79: DocumentPM

79

Yes NO

Is the Project Worthwhile?

Prepare Funding Proposal

Including optimality and controllability

Conduct Economic and Ecological AnalysisSocial & Political Realisability

Terminate

Page 80: DocumentPM

80

Key issues in Project AnalysisPotential Market

Market Analysis Market Share Technical ViabilityTechnical Analysis Sensible Choices RiskFinancial Analysis Return Benefits and Costs in Shadow PricesEconomic Analysis Other Impacts Environmental DamageEcological Analysis Restoration Measure

Page 81: DocumentPM

81

Feasibility Study has following sequence of events (Parts)

Need Analysis: Define objectives of the projects. New or improves.

Project Identification: Quantifies input, output, design parameters.

a. Project Inputs: (i) Purposeful – Controllable - Uncontrollable Controllable: Man hours, Capital Inflow, Activity Analysis: Uncontrollable: Cost of Raw Material, Reliability of Technology, Availability of Power, Govt. & Political Interference.

Page 82: DocumentPM

82

(ii) Environment (Business) Interest, Insurance,

Legal, Regulatory, Pollution.

b. Project Output (i) Desired (ii) Undesired (i) Desired: Desired could involved physical quantities of

products how much, how many, could also involve value judgment status, comfort, Aesthetic Appeal (Keeping user in view undesired)

(ii) Undesired: Undesired Pollution, Waste material, Waste Energy, Danger (Bhopal Gas Tragedy, Nuclear Explosion). Discomfort to people living in vicinity.

c. Design Parameters: Like features attributes that

would affect behavior and performance. Most common are physical size, weight, etc.

Page 83: DocumentPM

83

d. Constraint Specification: on input, output, design parameters which could be essential to evaluate the alternative solutions. Measure of the values indicate range of acceptable values.

e. Evaluation Criteria: Total revenue operating cost gross/ net profit, ROI/ EOI etc.

3. Practicability Analysis: Idea to eliminate the concepts that are not feasible. Are these operational financeable, Economical, Physically realizable, Politically acceptable ,

Physically Realizable which alternatives needs

the solutions within the specified parameters.

Financial Realizability: (i) Will the money required come as per time frame.

Page 84: DocumentPM

84

(ii) Sources of Capital Inflow who where from: 4. Economic Practicality : (i) Even a financially feasible may not be

economically practical. (ii) Economic Feasibility Study of alternative

solutions by constraints operating cost, Maintenance and Spare part expenditure.

(iii) Total revenue that would accrue over the operational life of systems, (i.e. what is the break even point or optimum point of economic operations of the project)

We will consider those alternative solutions to be

economically feasible that meet the specified rates of return on investment.

Page 85: DocumentPM

85

5. Social and Political Realizeability : The project may be physically, Financially, Economically feasible, but may encounter social at political obstacles.

Normally in case of large projects, there are additional considerations of health (Polio Campaign, Malaria, TB, CNG Buses) education (private and foreign universities) Welfare (METRO RAIL, Realignment over the range area, Civil Nuclear Technology).

Page 86: DocumentPM

86

Technical Appraisal By technical appraisal of project, we mean an assessment

of its basic technical and functional feasibility of project (Road – under/over bridge)

Besides costs and schedules, the project performance depends on how well the project is meeting the technical requirements of the end project (connect village to stadium)

- THREE STAGES OF TECH APPRAISAL

(i) Detailed technical Appraisal Which include describing the details of the

assignment and the key property.

Page 87: DocumentPM

87

It also includes describing the deficiencies of particular acclamation.

The detailed technical appraisal method helps in commenting on the reviewer’s action, analysis and conclusions.

(ii) Exceptional Technical Appraisal appraisal reviews records only significant and

exceptional findings and action take by the reviewer. The exceptional review is often used for high – level

reviews within an organization when the first level review is a narrative report.

(iii)Form Technical Appraisal In form review, further abbreviates the documentation

associated with reviewing an appraisal report. Forms are developed for specific institutional or

agency needs and the Standard Appraisal Review

Page 88: DocumentPM

88

Report from is becoming more widely accepted by many users.

Factors Effecting Technical Appraisal

(i) Layout:- Layout of the project includes description of the project in terms of what they represent and when they occur, who has authorized it, number of people who will handle. It also states where quality control will be

exercised. A description and explanation of the methods of

that will be used to monitor progress e.g. bar charts could be used.

For Example – Weekly progress meeting to exercise control over the

project.

Page 89: DocumentPM

89

(ii) Location:- The nine key factors that influence location of a project are: (keep NANO Car Project – In Mind)

- Costs- Infrastructure around the location- Labour Characteristics - Wage rates- Motivation of workers- Telecommunication systems- Government stability and industrial relations laws- Protection of patents A availability of management resources and specific

skills and system and integration costs. These factors have an impact on management

decisions and governments policies.

Page 90: DocumentPM

90

Government policies: Regulatory barriers may preclude the use of innovative technologies e.g. some reservation for SME Sector (Now only 3s items)

Types of equipment or processes: Equipments are basically of two types – temporary and permanent equipments. (Olympic stadium in China)

The availability and quality of equipments affect the technical appraisal.

Appropriateness of Local Conditions: The project should be adaptable to local technical and environmental conditions, such as voltage, dust, temperature, humidity, etc.

The appropriate supply of material and equipments for keeping the project working should be available in proximity.

Page 91: DocumentPM

91

Impact of Environment: The potential impact of the project on the human and physical environment is examined to make sure that nay adverse effects can be controlled or minimized e.g. pollution.

Approach Followed: Procedures for obtaining engineering, architectural, or other professional services are examined.

Risk Factor: It is necessary to identify the risks associated with the project and estimate the scale of risk. There should also be contingency plans in place to minimize the risk of project failure or of a major gap between what’s promised and what’s delivered.

Cost Estimated: Technical appraisal is a review of the cost estimates of the engineering and maintaining the project.

Cost estimates also determine whether technical appraisal is accurate within an acceptable margin.

Page 92: DocumentPM

92

Environmental Appraisal

A systems approach is a holistic approach to problem solving that involves formal considerations of the following parameters:

1. The total objectives of the project and, ore specifically, the performance measures of the whole project.

2. The project’s environment or the fixed constraints.3. The resources or inputs to the projects.4. The components of the project, their activities, goals,

and measures of performance.5. The management of the project, or the organization or

various components and their interactions. The next aspect to consider in the system approach is

the project’s environment.

Page 93: DocumentPM

93

This can be viewed as whatever lies ‘outside’ the project, but that which can affect and be affected by the operations of the project.

In project parlance the environment means much more than just the weather.

For example, for automobile environment, we can consider the roads and highways; petrol pumps and servicing stations, etc. need to be included in our definition of the automobile system.

When we say that something lies ‘outside’ the project, and hence constitutes its environment, we mean that the project can do relatively little about its environment’s characteristics or behaviour.

Identification of the environment depends on the answers to the following two questions.

1. Can I do anything about it?

Page 94: DocumentPM

94

2. Does it affect my situation or objectives’? If the answer to the first is ‘No’, and that do the

second is ‘Yes’, then ‘it’ is the environment.

Characteristics of the Environment

The environment provide, ‘given’ or ‘fixed’ inputs to the project.

It is also affected, directly or indirectly, by the outputs from the project;

Hence, it has a ‘dynamic’ influence on the project or by the project.

However, less attention is paid on environment because of two reasons

(a) Firstly : The environment is ‘outside’ the project and hence of little direct interest to us.

Page 95: DocumentPM

95

(b). Secondly, by definition, the environment is something that we cannot control, and hence it is ‘fixed’.

Of course we could consider the effects of the output of a project on its environment. (METRO – NO Pollution – Less Noise, Dev of Area)

This is what is referred to as Environmental Impact Assessment (EIA), which would be a part of the feasibility study for most projects, especially for large industrial projects. (e.g. Refinery , Chemical plant, Nuclear plant)

Page 96: DocumentPM

96

Managerial Appraisal

One of the main preoccupations of management in any organization and in project organization is the allocation of scarce resources.

These resources include manpower, materials, facilities, and financial resources.

For every project being planned, the project manager must ask the following two questions:

- Are the resources required for the given project available ?

- Is this the best use to which these resources can be put ?

Most project are subjected to an evaluation before they are given the go-ahead.

An essential part of his evaluation is the financial

Page 97: DocumentPM

97

appraisal.

Traditionally, this has been aimed at deciding whether or not a project will be profitable and selecting the one project out of several competing projects that appears the most profitable. The project manager should understand the processes so that he can benefit from them. (Difference between private – public Social Benefit projects).

It is with this intention that we present the various techniques of managerial evaluation, which consist of the technical, economic, financial, social and political appraisal and assessment of a project.

Page 98: DocumentPM

Project Selection

• Project selection is the process of evaluating individual projects or groups of projects, and then choosing to implement some set of them so that the objectives of the parent organization will be achieved

• Managers often use decision-aiding models to extract the relevant issues of a problem from the details in which the problem is embedded

• Models represent the problem’s structure and can be useful in selecting and evaluating projects

Chapter 2-1

Page 99: DocumentPM

Criteria for Project Selection Models

• Realism - reality of manager’s decision

• Capability- able to simulate different scenarios and optimize the decision

• Flexibility - provide valid results within the range of conditions

• Ease of Use - reasonably convenient, easy execution, and easily understood

• Cost - Data gathering and modeling costs should be low relative to the cost of the project

• Easy Computerization - must be easy and convenient to gather, store and manipulate data in the model

Chapter 2-2

Page 100: DocumentPM

Risk Versus Uncertainty

• Analysis Under Uncertainty - The Management of Risk– The difference between risk and uncertainty

• Risk - when the decision maker knows the probability of each and every state of nature and thus each and every outcome. An expected value of each alternative action can be determined

• Uncertainty - when a decision maker has information that is not complete and therefore cannot determine the expected value of each alternative

Chapter 2-7

Page 101: DocumentPM

Risk Analysis

• Principal contribution of risk analysis is to focus the attention on understanding the nature and extent of the uncertainty associated with some variables used in a decision making process

• Usually understood to use financial measures in determining the desirability of an investment project

Chapter 2-8

Page 102: DocumentPM

Risk Analysis

• Probability distributions are determined or subjectively estimated for each of the “uncertain” variables

• The probability distribution for the rate of return (or net present value) is then found by simulation

• Both the expectation and its variability are important criteria in the evaluation of a project

Chapter 2-9

Page 103: DocumentPM

Risk Analysis

Chapter 2-10

Page 104: DocumentPM

Information Base for Selections

• Accounting Data• Measurements

– Subjective vs. Objective– Quantitative vs. Qualitative– Reliable vs. Unreliable– Valid vs. Invalid

• Technological Shock

Chapter 2-11

Page 105: DocumentPM

CHAPTER-4

105

Page 106: DocumentPM

In Nut Shell ! Project Scheduling

• Project Scheduling– Understanding Project plan

• Scheduling activities• Managing time

– Essential methodologies

• Overcoming time constraint• Effective project scheduling

Page 107: DocumentPM

Project Scheduling

• Project planning and Project Scheduling • Project scheduling involves,

– Estimated start time – Required completion time– WBS (Work Breakdown Structure)– Scheduling the activities – Allocating owners and resources

Page 108: DocumentPM

Scheduling Activities

• Activity duration– An estimate

• Influence – Estimated start time – Required completion time

Activity Description

Activity Number Duration Estimate

Owners

Page 109: DocumentPM

• Key concepts – Earliest start time (ES)– Earliest finish time (EF)

EF = ES + Duration – Latest finish time (LF)– Latest start time (LS)

LS = LF - Duration

Time

Earliest start

Estimated Duration

Earliest Finish

Latest start

Latest Finish Total Slack

Activity NumberActivity Description

Page 110: DocumentPM

Falling behind ?

• Activities and entire Project• Total slack (Float)

– Difference • All activities EF and Project required completion time

– Positive result• Activity can be delayed without any hassle

– Negative result• Activity work needs to be accelerated

• Free slack ??

Page 111: DocumentPM

Critical Path Analysis

• What is critical path analysis?– Understanding it’s Effect

• Calculating,– Critical path – Noncritical path– Most critical path

• Using calculated information– Advantages

Page 112: DocumentPM

• Scheduling in Information System– A random process

• Figures need to be realistic– Identifying requirements– allocating resources

• Project scheduling software – an advantage • Perfection comes with practice and

experience

Scheduling – a challenge

Page 113: DocumentPM

Project Scheduling Models

Project Scheduling Models

113

Page 114: DocumentPM

5.1 Introduction

• A project is a collection of tasks that must be completed in minimum time or at minimal cost.

• Objectives of Project Scheduling– Completing the project as early as possible by

determining the earliest start and finish of each activity.

– Calculating the likelihood a project will be completed within a certain time period.

– Finding the minimum cost schedule needed to complete the project by a certain date.

114

Page 115: DocumentPM

5.1 Introduction

• A project is a collection of tasks that must be completed in minimum time or at minimal cost.

• Objectives of Project Scheduling

115

– Investigating the results of possible delays in Investigating the results of possible delays in activity’s completion time.activity’s completion time.

– Progress control.Progress control.– Smoothing out resource allocation over the Smoothing out resource allocation over the

duration of the project.duration of the project.

Page 116: DocumentPM

Task Designate

• Tasks are called “activities.” – Estimated completion time (and sometimes costs) are associated with each activity.– Activity completion time is related to the amount of resources committed to it. – The degree of activity details depends on the

application and the level of specificity of data.

116

Page 117: DocumentPM

5.2 Identifying the Activities of a Project

• To determine optimal schedules we need to– Identify all the project’s activities.– Determine the precedence relations among activities.

• Based on this information we can develop managerial tools for project control.

117

Page 118: DocumentPM

5.3 The PERT/CPM Approach for Project Scheduling

• The PERT/CPM approach to project scheduling uses network presentation of the project to– Reflect activity precedence relations– Activity completion time

• PERT/CPM is used for scheduling activities such that the project’s completion time is minimized.

118

Page 119: DocumentPM

Earliest Start Time / Earliest Finish Time

• Make a forward pass through the network as follows:

– Evaluate all the activities which have no immediate predecessors.

• The earliest start for such an activity is zero ES = 0.• The earliest finish is the activity duration EF = Activity duration.

– Evaluate the ES of all the nodes for which EF of all the immediate predecessor has been determined.

• ES = Max EF of all its immediate predecessors. • EF = ES + Activity duration.

– Repeat this process until all nodes have been evaluated• EF of the finish node is the earliest finish time of the project. 119

Page 120: DocumentPM

Earliest Start / Earliest Finish – Forward Pass

120

A90

B15

C5

F25

I30

G14

D20

E21

H28

J45

90,105

90,115

90,120

105,110

110,124115,129 129,149

149,170

149,177

120,165149,194

170

194

A

0,90

B

I

F

C

G D

E

H

J

177

194

EARLIEST FINISH

Page 121: DocumentPM

Latest start time / Latest finish time• Make a backward pass through the network as

follows:

– Evaluate all the activities that immediately precede the finish node.

• The latest finish for such an activity is LF = minimal project completion time.

• The latest start for such an activity is LS = LF - activity duration.– Evaluate the LF of all the nodes for which LS of all the

immediate successors has been determined. • LF = Min LS of all its immediate successors. • LS = LF - Activity duration.

– Repeat this process backward until all nodes have been evaluated.

121

Page 122: DocumentPM

Latest Start / Latest Finish – Backward Pass

122

B

F

C

A

I

E

DG HH28

166,194

JJ45

149,194

E21

173,19490,105

90,115

90,120

105,110

115,129 129,149

149,170

149,177

149,194

153,173

146,166194

129,149

0,90

129,149

D20

129,149129,149

129,149129,149129,149

129,149129,149

G14

115,129

I30

119,149

29,119

C5

110,115B1595,110

5,95F25

90, 115

0,90A90

Page 123: DocumentPM

Slack Times

• Activity start time and completion time may be delayed by planned reasons as well as by unforeseen reasons.

• Some of these delays may affect the overall completion date.

• To learn about the effects of these delays, we calculate the slack time, and form the critical path.

123

Page 124: DocumentPM

Slack Times

– Slack time is the amount of time an activity can be delayed without delaying the project completion date, assuming no other delays are taking place in the project.

124

Slack Time = LS - ES = LF - EF

Page 125: DocumentPM

125

Critical activities

must be rigidly

scheduled

Critical activities

must be rigidly

scheduled

Activity LS - ES SlackA 0 -0 0B 95 - 90 5C 110 - 105 5D 119 - 119 0E 173 - 149 24F 90 - 90 0G 115 - 115 0H 166 - 149 17I 119 - 90 29J 149 - 149 0

Slack time in the Klonepalm 2000 Project

Page 126: DocumentPM

The Critical Path

• The critical path is a set of activities that have no slack,connecting the START node with the FINISH node.

• The critical activities (activities with 0 slack) form at least one critical path in the network.

• A critical path is the longest path in the network.

• The sum of the completion times for the activities on the critical path is the minimal completion time of the project.

126

Page 127: DocumentPM

The Critical Path

127

B

F

C

A

I

E

DG HH28

166,194

JJ45

149,194

E21

173,19490,105

90,115

90,120

105,110

115,129 129,149

149,170

149,177

149,194

D20

0,90129,149

G14

115,129

I30

119,149

A90

C5

110,115B15

95,110

F25

90, 1150,90

Page 128: DocumentPM

Possible Delays

• We observe two different types of delays:

– Single delays.

– Multiple delays.

• Under certain conditions the overall project completion time will be delayed.

• The conditions that specify each case are presented next.

128

Page 129: DocumentPM

Single delays

• A delay of a certain amount in a critical activity, causes the entire project to be delayed by the same amount.

• A delay of a certain amount in a non-critical activity will delay the project by the amount the delay exceeds the slack time. When the delay is less than the slack, the entire project is not delayed.

129

Page 130: DocumentPM

Multiple delays of non critical activities: Case 1: Activities on different paths

130LS =119

A90

J45

H28

E21

D20

I30

G14

F25

C5

B15

ES=149

LS=173 DELAYED START=149+15=164

ES=90DELAYED START=90+15 =105

Activity E and I are each delayed 15 days.

THE PROJECT COMPLETION TIME IS NOT THE PROJECT COMPLETION TIME IS NOT DELAYEDDELAYED

FIN

ISH

Page 131: DocumentPM

131

AA9090

90

BB

1515

Gantt chart demonstration of the (no) effects on the project completion time when delayingactivity “I” and “E” by 15 days.

Activity I

FF2525

II

3030

105

CC

55

115

GG1414

129

DD

2020149

EE2121

HH

2828

JJ

4545

194

194

Activity E

Page 132: DocumentPM

Multiple delays of non critical activities:Case 2: Activities are on the same path,

separated by critical activities.

132

A90

B15

C5

F25

I30

G14

D20

E21

H28

J45

FIN

ISH

ES=149

LS =173 DELAYED START=149+15 =164

ES=90DELAYED START =94

LS =95

THE PROJECT COMPLETION TIME IS NOT DELAYEDTHE PROJECT COMPLETION TIME IS NOT DELAYED

Activity B is delayed 4 days, activity E is delayed 15 days

Page 133: DocumentPM

Multiple delays of non critical activities:Case 2: Activities are on the same path,

no critical activities separating them.

Activity B is delayed 4 days; Activity C is delayed 4 days.

133

A90

B15

C5

F25

I30

G14

D20

E21

H28

J45

FIN

ISH

DELAYED START= 109 + 4 =113;

ES= 90

DELAYED START =94

DELAYED FINISH =94+15=109

LS =110

3 DAYS DELAYIN THE ENTIRE

PROJECT

THE PROJECT COMPLETION TIME IS DELAYED 3 DAYSTHE PROJECT COMPLETION TIME IS DELAYED 3 DAYS

Page 134: DocumentPM

5.6 Gantt Charts

• Gantt charts are used as a tool to monitor and control the project progress.

• A Gantt Chart is a graphical presentation that displays activities as follows:– Time is measured on the horizontal axis. A horizontal bar is

drawn proportionately to an activity’ s expected completion time.– Each activity is listed on the vertical axis.

• In an earliest time Gantt chart each bar begins and ends at the earliest startfinish the activity can take place.

134

Page 135: DocumentPM

Here‘s how we build an Earliest Time Gantt Chart for KLONEPALM 2000

135

Page 136: DocumentPM

136

Immediate EstimatedActivity Predecessor Completion Time

A None 90B A 15C B 5D G 20E D 21F A 25G C,F 14H D 28I A 30J D,I 45

AA9090

90

BB

1515

FF2525

II

3030

105

CC

55

115

GG1414

129

DD

2020

149

EE2121

HH

2828

JJ

4545

194

194

Page 137: DocumentPM

Gantt Charts- Monitoring Project Progress

• Gantt chart can be used as a visual aid for tracking the progress of project activities.

• Appropriate percentage of a bar is shaded to document the completed work.

• The manager can easily see if the project is progressing on schedule (with respect to the earliest possible completion times).

137

Page 138: DocumentPM

Monitoring Project Progress

138

AA9090

BB

1515

FF2525

II

3030

CC

55

GG1414

DD

2020

EE2121

HH

2828

JJ

4545

194

194

135

The shaded bars representcompleted work BY DAY 135.

Do not conclude that the project is behind schedule.

Activity “I” has a slack and therefore can be delayed!!!

Page 139: DocumentPM

Gantt Charts – Advantages and Disadvantages

• Advantages. – Easy to construct– Gives earliest completion date.– Provides a schedule of earliest possible start and finish times

of activities.

• Disadvantages– Gives only one possible schedule (earliest).– Does not show whether the project is behind schedule.– Does not demonstrate the effects of delays in any one activity

on thestart of another activity, thus on the project completion time.

139

Page 140: DocumentPM

5.7 Resource Leveling and Resource Allocation

• It is desired that resources are evenly spread out throughout the life of the project.

• Resource leveling methods (usually heuristics) are designed to: – Control resource requirements– Generate relatively similar usage of resources

over time.

140

Page 141: DocumentPM

Resource Leveling – A Heuristic

• A heuristic approach to “level” expenditures– Assumptions

• Once an activity has started it is worked on continuously until it is completed.

• Costs can be allocated equally throughout an activity duration.

141

Step 1: Consider the schedule that begins each activity at its ES.

Step 2: Determine which activity has slack at periods of peak

spending.

Step 3: Attempt to reschedule the non-critical activities performed

during these peak periods to periods of less spending, but

within the time period between their ES and LF.

Page 142: DocumentPM

5.8 The Probability Approach to Project Scheduling

• Activity completion times are seldom known with 100% accuracy.

• PERT is a technique that treats activity completion times as random variables.

• Completion time estimates are obtained by theThree Time Estimate approach

142

Page 143: DocumentPM

The Probability Approach – Three Time Estimates

143

• The TThe Three Time Estimatehree Time Estimate approachapproach provides completion time estimate for provides completion time estimate for each activity.each activity.

• We use the notation:We use the notation:

a = an optimistic time to perform the a = an optimistic time to perform the activity.activity.

m = the most likely time to perform the m = the most likely time to perform the activity.activity.

b = a pessimistic time to perform the b = a pessimistic time to perform the activity.activity.

Page 144: DocumentPM

144

= the mean completion time =a + 4m + b

6= the standard deviation =

b - a6

Approximations for the mean and Approximations for the mean and the standard deviation of activity the standard deviation of activity completion time are based on the completion time are based on the BetaBeta distribution. distribution.

The Distribution, Mean, and The Distribution, Mean, and Standard Deviation of an Standard Deviation of an

ActivityActivity

Page 145: DocumentPM

The Project Completion Time Distribution - Assumptions

145

To calculate the mean and standard deviation of the project completion time we make some simplifying assumptions.

Page 146: DocumentPM

The Project Completion Time Distribution - Assumptions

• Assumption 2– The time to complete one activity is independent of

the time to complete any other activity.• Assumption 3

– There are enough activities on the critical path so that the distribution of the overall project completion time can be approximated by the normal distribution.

146

• Assumption 1Assumption 1– A critical path can be determined by using the A critical path can be determined by using the

mean completion times for the activities. mean completion times for the activities. – The project mean completion time is determined The project mean completion time is determined

solely by the completion time of the activities on solely by the completion time of the activities on the critical path.the critical path.

Page 147: DocumentPM

The Project Completion Time Distribution

The three assumptions imply that the overall project

completion time is normally distributed, the

following parameters:

147

Mean = Sum of mean completion times

along the critical path.

Variance = Sum of completion time

variances along the critical

path.

Standard deviation = Variance

Page 148: DocumentPM

5.10 Cost Analyses Using The Critical Path Method (CPM)

• The critical path method (CPM) is a deterministic approach to project planning.

• Completion time depends only on the amount of money allocated to activities.

• Reducing an activity’s completion time is called “crashing.”

148

Page 149: DocumentPM

Crash timeCrash cost

• There are two crucial completion times to consider for each activity.– Normal completion time (TN).

– Crash completion time (TC), the minimum possible completion time.

149

• The cost spent on an activity varies between– Normal cost (CN). The activity is completed in

TN.

– Crash cost (CC). The activity is completed in TC.

Page 150: DocumentPM

Crash timeCrash cost – The Linearity Assumption

• The maximum crashing of activity completion time is TC – TN.

• This can be achieved when spending CN – CC.

• Any percentage of the maximum extra cost (CN – CC) spent to crash an activity, yields the same percentage reduction of the maximum time savings (TC – TN).

150

Page 151: DocumentPM

Crash time/ Crash cost -The Linearity Assumption

151

Marginal Cost =Additional Cost to get Max. Time Reduction

Maximum Time reduction

= (4400 - 2000)/(20 - 12) = $300 per day

M = M = E

R

Page 152: DocumentPM

Crashing activities – Meeting a Deadline at Minimum Cost

• If the deadline to complete a project cannot be met using normal times, additional resources must be spent on crashing activities.

• The objective is to meet the deadline at minimal additional cost.

152

Page 153: DocumentPM

7.11 PERT/COST

• PERT/Cost helps management gauge progress against scheduled time and cost estimates.

• PERT/Cost is based on analyzing a segmented project. Each segment is a collection of work packages.

153

PROJECTPROJECT

Work Package 1Activity 1Activity 2

Work Package 2Activity 3Activity 5

Work Package 3Activity 4Activity 6

Page 154: DocumentPM

Work Package - Assumptions

– Once started, a work package is performed continuously until it is finished. – The costs associated with a work package are

spread evenly throughout its duration.

154

Page 155: DocumentPM

Monitoring Project progress

• For each work package determine:– Work Package Forecasted Weekly cost =

Budgeted Total Cost for Work Package Expected Completion Time for Work Package (weeks)

– Value of Work to date = p(Budget for the work package)where p is the estimated percentage of the work package completed.

– Expected remaining completion time = (1 – p)(Original Expected Completion Time)

155

Page 156: DocumentPM

Monitoring Project progress

156

• Completion Time AnalysisCompletion Time AnalysisUse the expected remaining completion time Use the expected remaining completion time estimates, estimates,

to revise the project completion time.to revise the project completion time.• Cost OverrunCost Overrun//Underrun AnalysisUnderrun Analysis

For each work package (completed or in progress) For each work package (completed or in progress) calculatecalculate

Cost overrun =Cost overrun = [Actual Expenditures to Date] - [Value of [Actual Expenditures to Date] - [Value of

Work to Date].Work to Date].

Page 157: DocumentPM

Monitoring Project Progress – Corrective Actions

• A project may be found to be behind schedule, and or experiencing cost overruns.

• Management seeks out causes such as:

– Mistaken project completion time and cost estimates.

– Mistaken work package completion times estimates and

cost estimates.

– Problematic departments or contractors that cause delays.

157

Page 158: DocumentPM

Monitoring Project Progress – Corrective Actions

• Possible Corrective actions, to be taken whenever needed.

– Focus on uncompleted activities.

– Determine whether crashing activities is desirable.

– In the case of cost underrun, channel more resources to

problem activities.

– Reduce resource allocation to non-critical activities.158