Upload
harsha-reddy
View
214
Download
0
Embed Size (px)
Citation preview
8/3/2019 PM0015-set-2
1/8
Master of Business Administration-MBA Semester 4
Project Management PM0015Assignment Set - 2
Q.1 Explain Relationship between PERT & CPM. Also describe the framework required for PERT & CPMAns: PERT and CPM are the project management techniques created for the need of the Western andMilitary Establishments to plan, schedule and control the complex projects. CPM/PERT developed along twoparallel streams one industrial and the other military.
CPM was first introduced by M. R. Walker and J. E. Kelly. This computation was designed for the UNIVAC-Icomputer. The first test was made in 1958, when CPM was applied in the construction of a new chemicalplant. In March 1959, the CPM was applied in the planned shutdown at the Du Pont works in Louisville,Kentucky. The introduction of CPM greatly reduced the unproductive time from the 125 hours to the 93 hours.
PERT was introduced first for the POLARIS missile program by the Program Evaluation Branch of the Special
Projects office of the U.S. Navy. The calculations were so arranged so that they could be performed in the
IBM Naval Ordinance Research Computer (NORC) at Dahlgren, Virginia. Rather than giving technical
benefits, it is found that PERT/CPM provides a focus around which managers could brain-storm and can put
their ideas. PERT/CPM is a great communication medium by which thinkers and planners at one level can
communicate their ideas, their doubts and fears for another level. Another important feature of the PERT/CPM
is that it is a useful tool for evaluating the performance of the individuals and the teams. There are many
variations of CPM/PERT which have been useful in planning costs, scheduling manpower and machine time.
CPM/PERT can answer following important questions
How long will the entire project take to be completed? What are the risks involved in this?
Which are the critical activities or tasks in the project which could delay the entire project if they were notcompleted on time?Is the project on schedule, behind schedule or ahead of schedule?
If the project has to be finished earlier than the planned, what is the best way to do this at the least cost?
The Framework for PERT and CPM
There are six steps which are common to both the techniques. The procedure is as follows
1. Define the Project and all of its significant activities or tasks. The project (made up of several tasks)should have only a single start activity and a single finish activity.
2. Develop the relationships among the activities. Decide which activities must precede and which mustfollow others.
3. Draw the Network connecting all the activities. Each activity should have unique event numbers.Dummy arrows are used where required to avoid giving the same numbering to two activities.
4. Assign time and/or estimates to each activity.
5. Compute the longest time path through the network. This is called the critical path.
6. Use the network to help plan, schedule, monitor and control the project.
The key concept used by both in PERT as well as CPM is that a small set of activities, which make up the
longest path through the activity network control the entire project. If these critical activities could beidentified and assigned to the responsible persons, management resources could be optimally used by
concentrating on the few activities which determine the fate of the entire project. The non-critical activities canbe re-planned, rescheduled and resources for them can be reallocated flexibly, without affecting the whole
project. The five important questions that should be asked before the preparation of an activity network arethe following
Is this a Start Activity?
Is this a Finish Activity? What activity precedes this?
What activity follows this?
What activity is concurrent with this?
8/3/2019 PM0015-set-2
2/8
Q.2 Describe Time-Cost optimization Algorithm.
Ans: Time-Cost Optimization Algorithm
The process of shortening a project is called crashing and is usually achieved by adding extra resources to anactivity. The steps involved in the project crashing are the following
Step 1 Schedule a project with all its activities at their normal duration as well as identify the critical path andcritical activities
Step 2 Calculate the cost slope for the different activities and rank the activities in the ascending order of thecost slope
Step 3 Crash the activities on the critical path as per the ranking, i.e., activity having lower cost slope wouldbe crashed first to the maximum extent possible
Step 4 As the critical path duration is reduced by crashing in Step 3, other paths may also become critical,i.e., we get parallel critical paths. This means that the project duration can be reduced duly by simultaneouscrashing of activities in the parallel critical paths
Step 5 Crashing as per Steps 3 and 4, one reaches a point when further crashing is either not possible ordoes not result in the reduction of crashing of project duration
Step 6 Compute the total project cost by adding corresponding fixed cost to the direct cost, which isobtained by adding the crashing cost cumulatively to the normal cost
Q.3 Explain the importance of business forecasting. List & explain the steps in the PERT planningprocess.
Ans: Because of the variation of the economic and business conditions over time, managers must find ways
to keep abreast of the effects that such changes will have on their organizations. One technique which is very
much useful in planning for the future needs is the forecasting. Although numerous forecasting methods have
been devised, they all have one common goal to make predictions of the future events so that the
projections can then be incorporated into the planning and strategy process. The need for forecasting
encompasses the modern society. Forecasting is highly essential in our modern society to take necessary
precautionary action. For example, officials in government must be able to forecast such things as
unemployment, inflation, industrial production, and expected revenues from personal and corporate income
taxes in order to formulate policies. Marketing executives of a large retailing corporation must be able to
forecast product demand, sales revenues, consumer preferences, inventory and so on, in order to make
timely decisions regarding current and future operations and to assist in strategic planning activities. The
directors of an airline must be able to fill equipment and personnel needs based on forecasts of the number ofpassengers and revenues. Administrators of a college or university must make forecasts of student
enrolments and consider the trends in curricula that are based on technological developments in order to plan
for the construction of dormitories and other academic facilities, plan for student and faculty recruitment, and
make assessments of other needs. There are two common approaches to forecasting qualitative and
quantitative. Qualitative forecasting methods are especially important when historical data are unavailable.
Qualitative forecasting methods are considered to be highly subjective and judgmental.
Quantitative forecasting methods make use of historical data. The goal of these methods is to study what has
happened in the past in order to better understand the underlying structure of the data and thereby provide a
way of predicting future values. Quantitative forecasting methods can be subdivided into two types time-
series and casual. Time-series forecasting methods involve the projection of future values of a variable basedentirely on the past and present observations of that variable. For example, the daily closing prices of a
particular stock on the New York Stock Exchange constitute a time series. Other examples of economic or
business time series are the monthly publication of the Consumer Price Index, the quarterly statements of
gross domestic product (GDP), and the annually recorded total sales revenues of a particular company.
Casual forecasting methods involve the determination of factors that relate to the variable to be predicted.These include multiple regression analysis with lagged variables, econometric modelling, leading indicatoranalysis, diffusion indexes, and other economic barometers.
Steps in the PERT Planning Process
PERT planning involves the following steps
1. Identification of the specific activities and the milestones
Page 3 of 7
8/3/2019 PM0015-set-2
3/8
2. Determination of the proper sequence of the activities
3. Construction of a network diagram
4. Estimation of the time required for each activity
5. Determination of the critical path
6. Updating of the PERT chart as the project progresses
1. Identification of the Specific Activities and Milestones
The activities are the tasks that are required to be completed in the project. The milestones include the eventsmarking the beginning and the end of one or more activities. It is helpful to list the tasks in a table that in latersteps can be expanded to include information on the sequence and duration.
2. Determination of the Activity Sequence
This step may be combined with the activity in the identification step since the activity sequence is evident forsome tasks. Other tasks may require more analysis in order to determine the exact order in which they mustbe performed.
3. Construction of the Network Diagram
Using the activity sequence information, a network diagram can be drawn showing the sequence of the serialand parallel activities. For the original activity-on-arc model, the activities are depicted by arrowed lines andmilestones are depicted by circles of bubbles. Manual drawings may require several drafts for correctportrayal of the relationships among the activities. Software packages simplify the step by automaticallyconverting the tabular information into a network diagram.
4. Estimation of the Activity Times
Weeks or days are commonly used unit of time for activity completion, but any consistent unit of time can beused. A distinguishing feature of PERT is its ability to deal with uncertainty in activity completion times. Foreach activity, the model usually includes three time estimates
Optimistic time Generally optimistic time represents the shortest time in which the activity can be completed.It is the common practice to specify optimistic times to be three standard deviations from the mean so thatthere is approximately a 1% chance that the activity will be completed within the optimistic time.
Most likely time Most likely time is the completion time having the highest probability. This time is differentfrom the expected time.
Pessimistic time The pessimistic time is the longest time that an activity might require. Three standarddeviations from the mean are commonly used for the pessimistic time.
PERT assumes a beta probability distribution for the time estimates. For the beta distribution, the expected
time for each activity can be approximated using the following weighted average Expected time =(Optimistic + 4 X Most likely + Pessimistic) / 6
This expected time may be displayed on the network diagram.
To calculate the variance for each activity completion time, if three standard deviation times were selected forthe optimistic and pessimistic times, then there are six standard deviations between them, so the variance isgiven by [(Pessimistic Optimistic)/6]2.
5. Determination of the Critical Path
The critical path is determined by adding the times for the activities in each sequence and determining thelongest path in the project. The critical path determines the total calendar time required for the project. Ifactivities outside the critical path speed up or slow down (within limits), the total project time does not change.The amount of time that a non-critical path activity can be delayed without delaying the project is referred toas slack time.
If the critical path is not immediately obvious, it may be helpful to determine the following four quantities foreach activity
ES Earliest Start Time EF Earliest Finish Time LS Latest Start Time LF Latest Finish Time
These times are calculated using the expected time for the relevant activities. The earliest start and finish
times of each activity are determined by working forward through the network and determining the earliest
time at which an activity can start and finish considering its predecessor activities. The latest start and finish
times are the latest times that an activity can start and finish without delaying the project. LS and LF are found
by working backward through the network. The difference in the latest and earliest finish of each activitys
slack. The critical path then is the path through the network in which none of the activities have slack. The
variance in the project completion time can be calculated by summing the variances in the completion times of
the activities in the critical path. Given this variance, one can calculate the probability that the project
Page 4 of 7
8/3/2019 PM0015-set-2
4/8
will be completed by a certain date assuming a normal probability distribution for the critical path. The normaldistribution assumption holds if the number of activities in the path is large enough for the central limit theoryto be applied.
Since the critical path determines the completion date of the project, the project can be accelerated by addingthe resources required to decrease the time for the activities in the critical path. Such a shortening of theproject sometimes is referred to as project crashing.
6. Updating of the PERT chart as the Project Progresses
Adjustments in the PERT chart are to be made as the project progresses. As the project unfolds, theestimated times can be replaced with the actual times. In cases where there are delays, additional resourcesmay be needed to stay on schedule and the PERT chart may be modified to reflect the new situation.
Q.4 What do you understand by a decision tree. Write a short note on project crashing using networkanalysis.
Ans: A Decision tree (or tree diagram) is a decision support tool that uses a tree-like graph or model ofdecisions and their possible consequences, including chance event outcomes, resource costs and utility.Decision trees have vast applications in operations research and decision analysis for identifying a strategymost likely to reach a specific goal. It is widely used for project policy decision making. Another use ofdecision tree is as a descriptive means for calculating conditional probabilities.
A decision tree analysis is a specific technique in which a diagram (decision tree) is used for the purposes ofassisting the project leader and the project team in making a difficult decision. The decision tree is a diagram
that presents the decision under consideration and, along different branches, the implications that may arisefrom choosing one path or another. The decision tree analysis is often conducted when a number of future
outcomes of scenarios remains uncertain, and is a form of brainstorming which, when decision making, canhelp to assure all factors are given proper consideration.
A decision tree is a logical model represented as a binary (two-way split) tree that shows how the value of atarget variable can be predicted by using the values of a set of predictor variables. It can be described as analgorithm or a formal step-wise process used in coming to a conclusion or making a judgment. An example ofthe decision tree is shown below
Figure 1: Decision Tree on choosing between two products
Figure 1 describes a decision tree for choosing between two products X and Y. A company has to decide
upon development of two products X and Y. They can develop only one product at a time. For developing the
product X, they have to make an initial investment of INR 2 Lakh, whereas for developing the product Y, they
have to make an initial investment of INR 3 Lakh. Now as per the decision tree, in case of opting the product
X, there is probability of 0.7 that the return in one year will be INR 1 Lakh and there is probability of 0.3 that
the return will be INR 3 Lakh. Now, if the product Y is opted, there is probability of 0.4 that the return will be
INR 2 Lakh after a year and there is probability of 0.6 that the return will be INR 3 Lakh after a year. Now, after
analyzing the decision tree, it is possible to get an insight of the future prospects (expected returns) of both
the products and accordingly it is possible for the company to choose the most profitable product for
development.
Project Crashing as in question 6 of assignment set 1
8/3/2019 PM0015-set-2
5/8
Page 5 of 7
8/3/2019 PM0015-set-2
6/8
Q.5 Describe in brief the various pages of the task information form in the MS Project software.
Ans: Task entry is the main activity in setting up a new project. The tasks which have been identified at the
Design Stage must be entered in this stage. The system will hold task information in a task database, which
we cannot access directly but is used by the system whenever we view task data. This is one of the two
databases the system uses and the other is the resource database. It is important to understand that the
system checks the data that it holds and where the data does not cross check then the system will generally
update the database to make it right. It is important to keep an eye on this process; this will be discussed in a
later section. As each entry is made, the system will update the appropriate data and views to reflect the
entries. The order of entry should be in the logical progression but this is not essential as it can be changed.
Normal Task entry will be by using the standard Task Sheet. The Gantt View shows the Gantt Chart in the
right part of the window with the Task Sheet in the left part.
Figure 2: Task Information Box / Task Sheet (General Section)
The Task sheet is a view of the selected task with information shown in the columns as follows:
ID: The Task Identification number.Name: The Name of the Task.
Duration: The time the Task will take including the time units.
Start Date: This is the current Scheduled Start date for the Task. Not the Planned or Actual Start.
Finish Date: The Scheduled Finish date.
Predecessors: The ID numbers for the preceding Tasks that are linked to this Task.
Resources: The names of the resources performing or used in the Task.
Table 1: Information in the Task Sheet
Figure 3: Task Information Sheet (Predecessors Section)
Page 6 of 7
8/3/2019 PM0015-set-2
7/8
Task Entry Form
One can select the Task Entry view to see the Gantt Chart in the upper pane and the Task Form in the lowerpane. To do this, you have to choose View, More Views, Task Entry.From the Task Sheet the following entries can be made.
ID: The Task Identification number.
Task Name: The Name of the Task.
Duration: The time the Task will take including the time units.
As the entries are made, the Gantt Chart will automatically be updated to display the tasks.
If someone is using the Task Form, it is possible for him/her to enter and/or view the following:
Name: The name of the task
Duration: The length of time the task will take and the units of time.
Fixed: A check box to specify the start date to be fixed.
Start: The scheduled start date, if this is not entered the system will calculate it from the
data entered and the relationships defined.
Finish: The scheduled finish date, entered or calculated as above.
% Complete: A measure of the completion of the Task if it has been started.
Tables and Descriptions
Resource Table
ID: The identification number of the Resource
Resource Name: The name of the resource.
Units The number of units available for the resource.Work The amount of work currently assigned to the resource.
Predecessor Table
ID The identification number of the Predecessor.
Predecessor Name: The name of the Predecessor. If this is not entered the system will look it up
using the ID number.
Type: The relationship with the current Task which will be FS, or SS, or FF.
Lag The time delay between the end of the Predecessor the start of the Successor.
Completion of all the fields at entry time is not necessary as more information is added so the system willupdate the boxes. It is only necessary to enter the data that has been determined in the design stage.
In order to enter task descriptions and durations one cell at a time:
In the Task Name column, select the first available cell and type the name of the task.
Press TAB
In the Duration column, type the value of the duration. If the duration is anything other thandays, type m for minutes, h for hours, orw for weeks.
Press ENTER
Press LEFT ARROW to return to the Task Name column and repeat steps 1 through 4 asrequired.
Entering task descriptions and durations by selecting a range:
Select the first cell (the numbered cell) of the desired range.
Drag the mouse through the range of cells you want to include.
In the first cell, type the desired information. Press TAB
In the Duration column, type the appropriate information.
Repeat steps 4 and 5 as required.
It is possible to move to the previous cell without deselecting the range through pressing SHIFT+TAB.Clicking the mouse inside or outside the range will deselect the range.
Q.6. Describe how you can change the duration of a project task.Ans:Changing DurationThe default duration is 1day. To change this one can simply overtype with the new value.
Change the durations for each Module to 2d.
When the Wizard appears READ THE INFORMATION then click on the OK button.
Select all the remaining tasks. Open the Task information box.
Set the duration to 1.5d
8/3/2019 PM0015-set-2
8/8
2011 Page 7 of 7