# Activities Completion Date
Signoff1 PM
OrientationOrientation Completed: On boarding of Project On boarding for Initiative specific projects Communicate with existing resources (both State Farm
and IGS) CAS Orientation QA Process
2 Project Initialization
Create/Validate need for Work Order Assignment of Work Order tracking Number Review questions for initiative lead and/or project lead Review supporting documentation Initiate meeting with Initiative Sponsor
3 Project Initialization
Define/Refine project objectives, scope and stakeholders Complete Project Charter Gain approval from Initiative Sponsor on Project
Charter Submit initial State Farm resource request (PARS) Submit initial IGS resource request CAS will assist in Pre-MAW Development
4 Project Initialization
Conduct Method Adoption Workshop (MAW) Schedule Method Adoption Workshop Create Work products list Create/Refine IGS and/or State Farm resource request Complete project definition document Create preliminary project plan Obtain State Farm and IGS agreement of initial project
definition agreement Review milestones/deliverables identified in the Project
Definition5 Project
InitializationCreate/Review detailed project plan, risk, and refine resources plans Create project communication plan Refine deliverables definitions Create/Revise State Farm Resources request (PARS) Create/Revise IGS resources team request Create detailed project plan Create resource estimating worksheets Perform risk assessment and determine any risk
mitigation plans needing to be incorporated into plan Review with State Farm and IGS project dependencies Create preliminary IGS team availability schedules
6 Project Initialization
Create/Review work order Extract current work order template from the AC
Collaboration Database.document.doc 4/11/231 of 4
# Activities Completion Date
Signoff Validate plan with IGS and State Farm work order
activities, Work Order dependencies, State Farm resource request, and IGS Resource Estimating Spreadsheet
Complete draft Work order using agreed project definition, identified dependencies, assumptions and IGS and State Farm responsibilities, estimated schedule and State Farm resource requirements
Review draft Work Order with initiative QA lead Review draft Work Order after revisions with State
Farm sponsor Create Work Order Quality Assurance and Pricing
package Send documents to Initiative QA Lead
7 Project Startup
Conduct Kickoff Confirm PAR approvals Agenda for meeting distributed Supporting documentation entered in SFW phase for
release Initialize Control Books (Financial and Project) Post control books and supporting documentation to
team rooms8 Project
TrackingKey Project Management Tasks Review changes in processes (State Farm and IBM)
that may impact project completion. Validate initial work order (open PCRs, open Issues,
Risk assessment) Review AC Project changes and impact to overall
project Validate project resource changes Manage changes or dependencies that may impact
project schedules Monitor State Farm and IGS team dynamics
9 Project Tracking
Weekly Communication Regular Scheduled Project Team Meetings Distribute project tasks to IGS and State Farm
resources on Friday of each week (Project Tasks list for team members should include tasks that are to be started and/or finished during that reporting period)
Validate that all team members have sent project status updates by tasks
Post weekly status reports in SFW Phase
10 Project Tracking
IBM Internal Project Management Tasks
document.doc 4/11/232 of 4
# Activities Completion Date
Signoff Update project plans with actual hours (Information
from IGS team resources) Update financials with expenses Validate actual hours with hours reported to CLAIM Validate project critical path and any variances in
project schedule impacting deliverables or milestone
11 Project Tracking
State Farm Project Management Tasks Update project tasks that are assigned to State with %
Complete (information from State Farm Resources) Validate project State Farm resources with State Farm
Resource sheet Validate Planview with resource task assigned to State
Farm resources
12 Project Control
AC Project ReportingWeekly IGS and SF team tasks reporting State Farm Detailed View Reporting State Farm Hours by Task Reporting (State Farm
Resources Only) State Farm Variance Reporting Weekly Status Report Review project checklist (Critical path changes,
variance in project tasks, changes in resource availability, changes in cross dependency schedules)
13 Project Control
AC Project ReportingBi-Weekly Prepare Executive Status Reports supporting
information14 Project
ControlAC Project ReportingMonthly Update SPP Monthly status Validate PlanView report for resources and total hours
15 Project Control
Perform Ongoing IBM Internal Project Management Tasks. Work with Quality Assurance Manager to schedule
Project Management Reviews (PMRs) Develop a schedule at the beginning of the project to
ensure that time is planned. Prepare PMR materials for distribution at least one
week prior to PMR.
16 Project Perform Ongoing IBM/State Farm Project Management
document.doc 4/11/233 of 4
# Activities Completion Date
SignoffControl Tasks
Plan Monitoring and Controlling Review open issues and assign responsibilities and
resolution dates Update project plan to reflect any mitigation plans. Ensure that your communication plan is working and all
project stakeholders are informed of project status. Plan, prepare and conduct deliverables review
17 Project Closure
Perform Project Closeout Activities Obtain final client approval and deliverable signoff Review and complete the project closeout checklist that
Raleigh’s contract specialist provides Submit all deliverables to Raleigh for contract file Submit work products and deliverables to ICM Reconcile financial performance and determine final
Gross Profit Prepare lessons learned document and discuss with
Quality Assurance Manager Ensure that Customer Satisfaction Survey is completed
18 Project Closure
Review Project Management Assets Review documentation on AC PMO team rooms Review documentation on SFW Phase