PM Lessons Learned (May 7, 2013)
2
PM Lessons Learned (May 7, 2013)
• Badging rules kept changing (changing again; COMSEC)
• Facilities worked well. (move to D-1)
• ESPO support; be sure everyone knows to come to ESPO for issues.
• Schedule:Last science day is not the last day of deployment.GH crew down days will float; no all crew or science down days.
3
PM Lessons Learned (May 7, 2013)
• Communication:Separation of GH and Science (changed in D-1)PI hand over went betterNew personnel training was betterMore info in POD (GH agrees; plus pictures)Too many independent computer scan requests
(weekly)
• Need to stick with proven procedures:Start up and failure procedures went well. Kept things standard during shift changes and provided info (ie times) when trouble shooting.