plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

Embed Size (px)

Citation preview

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    1/249

    SUPERVISORY HYBRID CONTROL OF A WIND ENERGY CONVERSION AND

    BATTERY STORAGE SYSTEM

    by

    Muhammad Shahid Khan

    A dissertation submitted in conformity with the requirements

    for the degree of Doctor of Philosophy

    Graduate Department of Electrical and Computer Engineering

    University of Toronto

    Copyright by Muhammad Shahid Khan, 2008

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    2/249

    ii

    SUPERVISORY HYBRID CONTROL OF A WIND ENERGY CONVERSION AND

    BATTERY STORAGE SYSTEM

    Doctor of Philosophy

    2008

    Muhammad Shahid Khan

    Graduate Department of Electrical and Computer Engineering

    University of Toronto

    ABSTRACT

    This thesis presents a supervisory hybrid controller for the automatic operation and control of a

    wind energy conversion and battery storage system. The supervisory hybrid control scheme is

    based on a radically different approach of modeling and control design, proposed for the subject

    wind energy conversion and battery storage system.

    The wind energy conversion unit is composed of a 360kW horizontal axis wind turbine

    mechanically coupled to an induction generator through a gearbox. The assembly is electrically

    interfaced to the dc bus through a thyristor-controlled rectifier to enable variable speed operation

    of the unit. Static capacitor banks have been used to meet reactive power requirements of the

    unit. A battery storage device is connected to the dc bus through a dc-dc converter to support

    operation of the wind energy conversion unit during islanded conditions. Islanding is assumed to

    occur when the tiebreaker to the utility feeder is in open position. The wind energy conversion

    unit and battery storage system is interfaced to the utility grid at the point of common coupling

    through a 25km long, 13.8kV feeder using a voltage-sourced converter unit. A bank of static

    (constant impedance) and dynamic (induction motor) loads is connected to the point of common

    coupling through a step down transformer.

    A finite hybrid-automata based model of the wind energy conversion and storage system has

    been proposed that captures the different operating regimes of the system during grid-connected

    and in islanded operating modes. The hybrid model of the subject system defines allowable

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    3/249

    iii

    operating states and predefines the transition paths between these operating states. A modular

    control design approach has been adapted in which the wind energy conversion and storage

    system has been partitioned along the dc bus into three independent system modules. Traditional

    control schemes using linear proportional-plus-integral compensators have been used for each

    system module with suitable modifications where necessary in order to achieve the required

    steady state and transient performance objectives. A supervisory control layer has been used to

    combine and configure control schemes of the three system modules to suite the requirements of

    system operation during any one operating state depicted by the hybrid model of the system.

    Transition management strategies have been devised and implemented through the supervisory

    control layer to ensure smooth inter-state transitions and bumpless switching among controllers.It has been concluded based on frequency domain linear analysis and time domain

    electromagnetic transient simulations that the proposed supervisory hybrid controller is capable

    of operating the wind energy conversion and storage system in both grid-connected and in

    islanded modes under changing operating conditions including temporary faults on the utility

    grid.

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    4/249

    iv

    Dedicated to my mother who passed away during the course of this work.

    May Allah rest her gentle soul in eternal peace.

    Aameen.

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    5/249

    v

    ACKNOWLEDGEMENTS

    I would like to express my gratitude to Prof. M.R. Iravani for his guidance and support in

    bringing this work to completion. Thanks are also due to those friends and faculty support staff

    who made my stay at the University of Toronto more comfortable and pleasant. Financial

    support from Prof. M. R. Iravani and from the School of Graduate Studies in the form of research

    grants, open fellowship awards and Roger fellowship awards are gratefully acknowledged.

    Continuous encouragement and support from my parents and other family members has been

    instrumental in completing this work.

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    6/249

    vi

    TABLE OF CONTENTS

    ABSTRACT ................................................................................................................................................. iiACKNOWLEDGEMENTS.......................................................................................................................... v

    TABLE OF CONTENTS............................................................................................................................. vi

    LIST OF TABLES....................................................................................................................................... ix

    LIST OF FIGURES ...................................................................................................................................... x

    NOMENCLATURE................................................................................................................................xviii

    ABBREVIATIONS................................................................................................................................... xix

    1. INTRODUCTION ................................................................................................................................. 1

    1.1 BACKGROUND...................................................................................................................... 1

    1.2 PROBLEM STATEMENT ...................................................................................................... 21.3 STUDY SYSTEM.................................................................................................................... 31.4 RESEARCH OBJECTIVES..................................................................................................... 71.5 LIMITATIONS........................................................................................................................ 91.6 THESIS OUTLINE................................................................................................................ 10

    2. OPERATION AND CONTROL ......................................................................................................... 12

    2.1 OPERATION OF THE STUDY SYSTEM ........................................................................... 122.1.1 Power Management ......................................................................................................... 13

    2.1.1.1 Steady State Power Management ....................................................................................... 132.1.1.2 Transient Power Management ............................................................................................14

    2.1.2 Load Management ........................................................................................................... 14

    2.2 STATE TRANSITION DIAGRAM....................................................................................... 152.3 CONTROL DESIGN .............................................................................................................17

    2.3.1 Modular Design Philosophy ............................................................................................ 19

    2.3.2 Supervisory Control......................................................................................................... 21

    2.4 PERFORMANCE SPECIFICATIONS.................................................................................. 232.4.1 Steady State Specifications.............................................................................................. 23

    2.4.2 Transient Specifications................................................................................................... 23

    2.5 METHODOLOGY................................................................................................................. 242.6 SUMMARY ........................................................................................................................... 25

    3. MODELING AND CONTROL OF SYSTEM MODULES................................................................ 26

    3.1 MODULE: WIND ENERGY CONVERSION UNIT............................................................ 263.1.1 Modeling and Control...................................................................................................... 26

    3.1.1.1 Control Structure................................................................................................................ 273.1.2 Sensitivity Analysis ......................................................................................................... 29

    3.1.2.1 Operating Point Sensitivity.............. ........... .......... ........... ........... .......... ........... .......... ......... 293.1.2.2 Parametric Sensitivity.............. .......... ........... .......... ........... .......... ........... .......... ........... ....... 32

    3.1.3 Simulation Studies........................................................................................................... 38

    3.1.3.1 Response to Step Changes..................................................................................................38

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    7/249

    vii

    3.1.3.2 Performance under Dynamic Wind Conditions........ .......... ........... ........... .......... ........... ..... 413.2 MODULE: VSC-UTILITY GRID ......................................................................................... 43

    3.2.1 Control Structure .............................................................................................................43

    3.2.2 Sensitivity Analysis ......................................................................................................... 463.2.2.1 Operating Point Sensitivity.............. ........... .......... ........... ........... .......... ........... .......... ......... 463.2.2.2 Parametric Sensitivity.............. .......... ........... .......... ........... .......... ........... .......... ........... ....... 48

    3.2.3 Simulation Studies........................................................................................................... 55

    3.2.3.1 Steady State Performance...................................................................................................553.2.3.2 Dynamic Performance ........................................................................................................55

    3.3 MODULE: BATTERY STORAGE AND DC-DC CONVERTER....................................... 593.3.1 Modeling and Control...................................................................................................... 59

    3.3.2 Sensitivity Analysis ......................................................................................................... 60

    3.3.2.1 Operating Point Sensitivity.............. ........... .......... ........... ........... .......... ........... .......... ......... 603.3.2.2 Parametric Sensitivity.............. .......... ........... .......... ........... .......... ........... .......... ........... ....... 63

    3.3.3 Simulation Studies........................................................................................................... 673.4 SUMMARY AND CONCLUSIONS..................................................................................... 69

    3.4.1 Module: Wind Energy Conversion Unit.......................................................................... 69

    3.4.2 Module: VSC-Utility Grid............................................................................................... 71

    3.4.3 Module: Battery Storage and DC-DC Converter............................................................. 72

    4. SUPERVISORY HYBRID CONTROL .............................................................................................. 74

    4.1 HYBRID CONTROL SYSTEMS.......................................................................................... 744.2 HYBRID MODEL OF THE STUDY SYTEM...................................................................... 75

    4.2.1 Finite Hybrid Automata................................................................................................... 76

    4.3 SUPERVISORY HYBRID CONTROL OF THE STUDY SYSTEM................................... 79

    4.3.1 Supervisory Control Requirements.................................................................................. 79

    4.3.2 Supervisory Hybrid Control Philosophy.......................................................................... 80

    4.3.3 Hybrid Control of VSC: Valve Switching Control.......................................................... 82

    4.3.4 Control Transition Management...................................................................................... 87

    4.3.4.1 State Initialization.................. .......... ........... .......... ........... ........... .......... ........... .......... ......... 884.3.4.2 Parameter Scheduling.........................................................................................................90

    4.3.5 Mode Transition Management......................................................................................... 90

    4.3.5.1 Synchronization..................................................................................................................914.3.5.1.1 Signal Transfer .................................................................................................... 92

    4.3.5.2 On-grid to Off-grid Transition........... ........... .......... ........... .......... ........... .......... ........... ....... 924.4 FLOW CHART...................................................................................................................... 934.5 SUMMARY ........................................................................................................................... 94

    5. SYSTEM OPERATION UNDER NORMAL CONDITIONS............................................................ 95

    5.1 STUDY CASES ..................................................................................................................... 955.2 WIND ENERGY CONVERSION UNIT-UTILITY GRID................................................... 96

    5.2.1 Control Scheme ............................................................................................................... 96

    5.2.2 Simulation Studies........................................................................................................... 98

    5.2.2.1 Steady State Performance...................................................................................................99

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    8/249

    viii

    5.2.2.2 Dynamic Performance ........................................................................................................995.3 WIND ENERGY CONVERSION UNIT-STORAGE......................................................... 108

    5.3.1 Control Scheme ............................................................................................................. 108

    5.3.2 Simulation Studies......................................................................................................... 110

    5.4 STORAGE-UTILITY GRID................................................................................................ 1115.4.1 Control Structure ........................................................................................................... 111

    5.4.2 Simulation Studies......................................................................................................... 113

    5.5 STORAGE-VSC-LOAD...................................................................................................... 1175.5.1 Control Structure ........................................................................................................... 117

    5.5.2 Simulation Studies......................................................................................................... 120

    5.6 WIND ENERGY CONVERSION UNIT-STORAGE-UTILITY GRID ............................. 1235.6.1 Control Structure ........................................................................................................... 123

    5.6.2 Simulation Studies......................................................................................................... 126

    5.7 SUMMARY AND CONCLUSIONS................................................................................... 130

    6. SYSTEM OPERATION INVOLVING STATE TRANSITIONS .................................................... 132

    6.1 STUDY CASES ................................................................................................................... 1336.2 SYSTEM STARTUP AND STANDBY.............................................................................. 1356.3 STATE TRANSITIONS ...................................................................................................... 137

    6.3.1 Off-Grid Mode of Operation ......................................................................................... 137

    6.3.2 On-Grid Mode of Operation.......................................................................................... 141

    6.3.2.1 State Transitions during Normal Operation.......... ........... ........... .......... ........... .......... ....... 1416.3.2.2 State Transitions during Temporary Fault Conditions ........... ........... .......... ........... .......... 145

    6.4 MODE TRANSITIONS....................................................................................................... 149

    6.4.1 Pre-planned Transitions................................................................................................. 1496.4.1.1 Synchronization................................................................................................................1496.4.1.2 On-Grid to Off-Grid Transitions ...................................................................................... 153

    6.5 SUMMARY AND CONCLUSIONS................................................................................... 159

    7. CONCLUSIONS................................................................................................................................ 161

    7.1 OVERVIEW......................................................................................................................... 1617.2 CONCLUSIONS.................................................................................................................. 1637.3 CONTRIBUTIONS.............................................................................................................. 1647.4 FUTURE WORK ................................................................................................................. 165

    APPENDIX A........................................................................................................................................... 166

    APPENDIX B........................................................................................................................................... 170APPENDIX C........................................................................................................................................... 175

    APPENDIX D........................................................................................................................................... 189

    APPENDIX E ........................................................................................................................................... 206

    REFERENCES ......................................................................................................................................... 223

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    9/249

    ix

    LIST OF TABLES

    TABLE Page

    Table 3.1-1: WECU; Steady state operating points.................................................................... 29

    Table 3.1-2: WECU; Eigenvalues corresponding to the steady state operating conditions in

    Table 3.1-1. .......................................................................................................... 30

    Table 3.1-3: WECU; Mode association of state variables and participation factors for case 232

    Table 3.2-1: VSC-Utility Grid; Steady state operating points.................................................... 46

    Table 3.2-2: VSC-Utility Grid; Eigenvalues corresponding to the steady state operating points

    identified in Table 3.2-1....................................................................................... 47

    Table 3.2-3: VSC-Utility Grid; Eigenvalues and mode association for case 2........................ 49

    Table 3.2-4: VSC-Utility Grid; Dominant modes, mode association of state variables and

    participation factors for case 2 .......................................................................... 49

    Table 3.3-1: Battery Storage and dc-dc converter (Boost mode of operation); Poles and RHP

    zeros at different steady state operating points .................................................... 61

    Table 3.3-2: Battery Storage and DC-DC Converter (Buck mode of operation); Eigenvalues at

    different steady state operating points ................................................................. 62

    Table 5.1-1: Study Cases and Objectives of the Performance Investigation; System Operation

    Under Normal Conditions.................................................................................... 95

    Table 6.1-1: Study Cases; System Operation Involving State Transitions............................... 133

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    10/249

    x

    LIST OF FIGURES

    FIGURE Page

    Figure 1.3-1: Wind energy conversion and battery storage system.............................................. 6

    Figure 2.2-1: State Transition Diagram (STD) of the wind energy conversion and storage

    system .................................................................................................................. 17

    Figure 2.3-1: Supervisory hybrid control structure..................................................................... 18

    Figure 2.3-2: Schematic diagram of system module Wind Energy Conversion Unit.............. 21

    Figure 2.3-3: Schematic diagram of system module VSC-Utility Grid................................... 21

    Figure 2.3-4: Schematic diagram of system module Storage and dc-dc converter.................. 21

    Figure 3.1-1: WECU; Proposed current-controlled speed regulation scheme............................ 28

    Figure 3.1-2: WECU; Root loci corresponding to different steady state operating points......... 31

    Figure 3.1-3: WECU; Close-up of the root loci near to the origin; sensitivity with respect to the

    steady state operating point.................................................................................. 31

    Figure 3.1-4: WECU; Root locus of mode 1 for variations in the values of the control

    parameters between 0 and 2 per unit in steps of 0.1 per unit [0: .1: 2] ................ 33

    Figure 3.1-5: WECU; Root locus for mode 2 for variations in the values of the control

    parameters between 0 and 2 per unit in steps of 0.1 per unit [0: .1: 2] ................ 34

    Figure 3.1-6: WECU; Root locus for mode 3 for variations in the values of the control

    parameters between 0 and 2 per unit in steps of 0.1 per unit [0: .1: 2] ................ 35

    Figure 3.1-7: WECU; Root locus of mode 4 for variations in the values of the control

    parameters between 0 and 2 per unit in steps of 0.1 per unit [0: .1: 2] ................ 36

    Figure 3.1-8: WECU; Sensitivity of mode 1 and 4 with respect to the LPF time constant iw

    (from 3.0ms to 75.0ms in steps of 3.0ms)............................................................ 37

    Figure 3.1-9: WECU; Response to step changes in wind speed, 1) wind speed 2) dc output

    current and rectifier current limitation 3) optimum, reference and actual speed of

    the generator......................................................................................................... 39

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    11/249

    xi

    Figure 3.1-10: WECU; Response to step changes in wind speed, 1) generator reactive power

    consumption and excitation capacitor bank switching event 2) generator output

    power 3) angular displacement between the generator and the turbine rotors.... 39

    Figure 3.1-11: WECU; Response to step changes in the dc bus voltage, 1) dc bus voltage 2)

    rectifier output current 3) angular displacement of the generator with respect to

    the wind turbine ................................................................................................... 40

    Figure 3.1-12: WECU; Operation during dynamic wind speed conditions, 1) wind speed 2)

    optimum, reference and actual speed of the generator and capacitor bank

    switching events 3) Reference and actual output dc current............................... 42

    Figure 3.2-1: VSC-Utility Grid; Single line schematic and control structure ............................ 45Figure 3.2-2: VSC-Utility Grid; Plot of the eigenvalues (32, 33) corresponding to operating

    conditions from full load in rectifier mode ( dI = -1.0 p.u.) to full load in inverter

    mode ( dI = 1.0 p.u.) ............................................................................................ 48

    Figure 3.2-3: VSC-Utility Grid; Loci of the eigenvalues corresponding to mode 1 for variations

    in pdK and idK of the outer dc regulator ............................................................ 50

    Figure 3.2-4: VSC-Utility Grid; Loci of mode 1 for variations in piK and iiK of the inner

    current regulators ................................................................................................. 51

    Figure 3.2-5: VSC-Utility Grid; Plot of the positive eigenvalues corresponding to Mode 2 for

    variations in the parameters of the current and dc voltage regulators ................. 52

    Figure 3.2-6: VSC-Utility Grid; Plot of the eigenvalue of mode 2 for variations in the

    parameters vfb and ivK ....................................................................................... 53

    Figure 3.2-7: VSC-Utility Grid; Traces of the eigenvalue of mode 2 for variations in piK and

    iiK of the inner current regulators....................................................................... 53

    Figure 3.2-8: VSC-Utility Grid; Trace of the eigenvalue associated with mode 3..................... 54

    Figure 3.2-9: VSC-Utility Grid; Response to load switchings and step changes in reference

    voltages of the dc bus and the load bus, 1) dc current (disturbance) 2) & 3)

    active and reactive terminal currents of the VSC........................................... 57

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    12/249

    xii

    Figure 3.2-10: VSC-Utility Grid; Response to load switchings and step changes in reference

    voltages of the dc bus and the load bus, 1) reference and actual three phase rms

    voltage at the load bus 2) reference and actual dc bus voltage........................... 58

    Figure 3.3-1: Battery Storage and DC-DC Converter; Control structure and schematic diagram

    .............................................................................................................................. 60

    Figure 3.3-2: Battery Storage and DC-DC Converter; Loci of the eigenvalues 2 and 3,4

    corresponding to the steady state operating points given in Table 3.3-2............. 62

    Figure 3.3-3: Battery Storage and DC-DC Converter (Boost Mode); Eigenvalue trace with

    respect to the proportional gain pdcK .................................................................. 63

    Figure 3.3-4: Battery Storage and DC-DC Converter (Boost Mode); Eigenvalue trace with

    respect to the integral gain idcK .......................................................................... 64

    Figure 3.3-5: Battery Storage and DC-DC Converter (Buck Mode); Root loci with respect to the

    proportional constant pdcK ................................................................................. 65

    Figure 3.3-6: Battery Storage and DC-DC Converter (Buck Mode); Root locus with respect to

    the integral constant idcK .................................................................................... 66

    Figure 3.3-7: Battery Storage and DC-DC Converter (Boost Mode), 1) dc output and inductor

    current 2) dc bus voltage..................................................................................... 67

    Figure 3.3-8: Battery Storage and DC-DC Converter (Buck Mode), 1) injected at the dc bus

    and inductor current 2) dc bus voltage................................................................ 68

    Figure 3.3-9: Battery Storage and DC-DC Converter, 1) reference and actual dc bus voltage in

    boost mode 2) reference and actual dc bus voltage in buck mode...................... 69

    Figure 4.2-1: Finite Hybrid Automata (FHA) of the wind energy conversion and storage system

    .............................................................................................................................. 78

    Figure 4.3-1: Hybrid switching control of the VSC ................................................................... 84

    Figure 4.3-2: Operation of the VSC with only SPWM and with hybrid valve switching control,

    1) a phase voltage at the PCC, instantaneous value and amplitude 2) fault current

    3) reference and actual phase a converter current............................................. 86

    Figure 4.3-3: Operation of the VSC under hybrid valve switching control, 1) cycle-to-cycle

    based instantaneous duty ratio and the average duty ratio over a power cycle 2)

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    13/249

    xiii

    instantaneous switching frequency and the average frequency over a power cycle

    .............................................................................................................................. 87

    Figure 4.3-4: Re-initialization of inner current regulators for smooth transition from HSVM to

    SPWM based valve-switching control................................................................. 89

    Figure 4.3-5: Re-initialization of inner current regulators, 1) duration of the OCC operation and

    orthogonal components of the converter terminal voltage for resetting of inner

    current regulators 2) duration of the OCC operation and the orthogonal

    components of the terminal current of the converter........................................... 90

    Figure 4.3-6: Frequency control during synchronization ........................................................... 91

    Figure 4.4-1: Simplified flow chart for software implementation of the supervisory hybridcontrol scheme ..................................................................................................... 93

    Figure 5.2-1: Single line schematic and control structure of the study system in the operating

    state #7 consisting of the two system modules i) WECU and ii) VSC Utility

    Grid ...................................................................................................................... 97

    Figure 5.2-2: Operating State # 7; System Dynamic Performance for Step Changes in Wind

    Speed, 1) wind speed 2) rotor optimal, reference and actual speed................. 101

    Figure 5.2-3: Operating State # 7; System response to step changes in wind speed, 1) rectifier

    output current and active current output of the VSC 2) VSC reactive current

    output 3) VSC total current output and HSVM on duration............................. 101

    Figure 5.2-4: Operating State # 7; System response to step changes in wind speed, 1) dc bus

    voltage 2) load bus rms voltage ........................................................................ 102

    Figure 5.2-5: Operating State # 7; System Operation under Load Transients, 1) load bus rms

    voltage 2) dc bus voltage load 3) rectifier output current................................ 103

    Figure 5.2-6: Operating State # 7; Control performance under load transients, 1) VSC active

    current 2) VSC reactive current 3) VSC total current and HSVM on duration

    ............................................................................................................................ 104

    Figure 5.2-7: Operating State # 7; System response during dynamic wind speed and load

    transients, 1) wind speed 2) generator optimum, reference and actual speed.. 106

    Figure 5.2-8: Operating State # 7; System Control during dynamic input wind speed and load

    transients, 1) load bus rms voltage 2) dc bus voltage ...................................... 107

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    14/249

    xiv

    Figure 5.2-9: Operating State # 7; System response to dynamic wind conditions and load

    transients, 1) & 2) VSC active and reactive current components 2) space

    vector magnitude of the VSC current ................................................................ 107

    Figure 5.3-1: Single line diagram and control schematic of the study system in the operating

    state #4 consisting of the two system modules of (a) wind energy conversion unit

    (b) battery storage and dc-dc converter.............................................................. 109

    Figure 5.3-2: Operating State # 4; System response to changes in wind speed, 1) dc bus voltage

    2) generator L-L terminal voltage and capacitor switching events 3) wind speed

    ............................................................................................................................ 111

    Figure 5.4-1: Single line diagram and control schematic of the study system in operating statenumber #9 consisting of the two system modules of (a) battery storage and dc-dc

    converter (b) VSC-Utility Grid ......................................................................... 112

    Figure 5.4-2: Operating State # 9; Response to load switching events, 1) dc bus voltage 2) 3

    phase rms voltage at the load bus....................................................................... 114

    Figure 5.4-3: Operating State # 9; Response to load switching events, VSC terminal currents,

    1) active current component 2) reactive current component 3) maximum

    current limit and actual output current of the VSC and OCC duration.............. 114

    Figure 5.4-4: Operating State # 9; Response to step changes in the dc current, 1) dc current 2)

    dc bus reference and actual voltage 3) reference and actual rms voltage at the

    load bus .............................................................................................................. 116

    Figure 5.4-5: Operating State # 9; Response to step changes in reference voltage signals, 1)

    reference and actual dc bus voltages 2) reference and acutal rms voltages of the

    load bus .............................................................................................................. 117

    Figure 5.5-1: Single line diagram and control schematic of the study system in the operating

    state number #3 consisting of the battery storage and dc-dc converter module

    interfaced to the load through the VSC.............................................................. 119

    Figure 5.5-2: Operating State # 3; Response to load switching and step changes in external dc

    current , 1) reference and actual dc bus voltage 2) reference and actual rms

    voltage at the PCC 3) reference and actual rms voltage at the load bus .......... 120

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    15/249

    xv

    Figure 5.5-3: Operating State # 3; Response to load switching and step changes in the external

    dc current, 1) external dc source current 2) active current component of the VSC

    3) reactive current component of the VSC 4) total output current of the VSC. 121

    Figure 5.5-4: Operating State # 3; Response to step changes in reference signals, 1) reference

    and actual voltages of the dc bus 2) reference and actual rms voltages at the PCC

    3) reference and actual rms voltages at the load bus ......................................... 122

    Figure 5.6-1: Single line schematic and control structure of the study system in the operating

    state #6 (WECU + Storage + Utility) where all the three system modules are in

    service ................................................................................................................ 125

    Figure 5.6-2: Operating State # 6; Response to variations in wind speed, 1) wind speed 2)optimum, reference and actual speed of the generator 3) output current of the

    thyristor-controlled rectifier............................................................................... 128

    Figure 5.6-3: Operating State # 6; Response during load switching, wind speed changes and

    step changes in the reference voltage signals, 1) dc bus voltage 2) rms voltage at

    the load bus ........................................................................................................ 128

    Figure 5.6-4: Operating State # 6; Response to load switching and step changes in reference

    signals, 1) active current components 2) reactive current components 3)

    converter limit, total output current and HSVM on duration............................. 129

    Figure 5.6-5: Operating State # 6; Response of the storage element to load switching and

    reference step changes, 1) battery terminal voltage 2) battery terminal current

    ............................................................................................................................ 129

    Figure 6.2-1: Startup and Standby Operation, 1) dc bus voltage 2) reference and actual rms

    voltage at the PCC 3) phase voltages at the PCC ............................................. 136

    Figure 6.2-2: Startup and Standby Operation, 1) orthogonal current components of the VSC 2)

    battery terminal voltage 3) reference and inductor current............................... 137

    Figure 6.3-1: Off-grid operation; Inter-state transitions among state #2 (Standby), state #3

    (Storage + VSC) and state #4 (WECU + Storage), 1) dc bus reference and actual

    voltage 2) reference and actual rms voltage at the PCC and ITI performance

    limits 3) reference and actual rms voltage at the load bus and ITI performance

    limits 4) Operating state of the system.............................................................. 139

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    16/249

    xvi

    Figure 6.3-2: Off-grid operation; Inter-state transitions among state #2 (Standby), state #3

    (Storage + VSC) and state #4 (WECU + Storage), 1) orthogonal current

    components of the VSC 2) orthogonal current components of the load bus 3)

    rectifier output current, total instantaneous current of the load branch and the

    output current of the VSC .................................................................................. 140

    Figure 6.3-3: Off-grid operation; Inter-state transitions among state #2 (Standby), state #3

    (Storage + VSC) and state #4 (WECU + Storage), 1) battery terminal voltage 2)

    reference and actual battery terminal currents ................................................... 140

    Figure 6.3-4: State transitions during on-grid mode of operation, 1) reference and actual dc bus

    voltage 2) reference and actual rms voltage at the PCC 3) reference and rmsvoltage at the load bus 4) system operating state and OCC operation intervals142

    Figure 6.3-5: On-grid mode of operation; transitions during normal operation, 1) reference and

    actual active current component of the converter 2) reference and actual reactive

    current component of the converter 3) rectifier output current and total current of

    the load branch and the VSC ............................................................................. 144

    Figure 6.3-6: On-grid mode of operation; transitions during normal operation, 1) battery

    terminal voltage 2) reference and actual battery current................................... 144

    Figure 6.3-7: On-grid operating mode; state transitions caused by single line to ground fault, 1)

    dc bus and thyristor-controlled rectifier output voltage 2) three phase rms

    voltage at the PCC and the upper and lower limits defined by the ITI curve 3)

    single phase rms voltage at the PCC and the ITI curve 4) control signals used for

    state transition management............................................................................... 147

    Figure 6.3-8: On-grid operating mode; State transitions caused by single line to ground faults,

    1) VSC active current output 2) VSC reactive current output 3) rectifier

    output current, total current of the load branch and output current of the VSC 148

    Figure 6.3-9: On-grid operating mode; State transitions caused by single line to ground faults,

    1) battery terminal voltage 2) reference and inductor current ......................... 149

    Figure 6.4-1: Mode transitions; synchronization, 1) a phase voltage waveforms at the two

    sides of the TCB and the synchronization interval 2) reference frequency and

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    17/249

    xvii

    PLL outputs for the two sides of the TCB 3) reference and actual rms voltages

    on the utility side of the TCB, at the PCC and at the load bus .......................... 151

    Figure 6.4-2: Mode transitions; synchronization, 1) reference and actual dc bus voltage 2)

    reference and actual rectifier current, reference and actual active current

    component of the converter 3) reference and actual reactive current of the

    converter 4) system operating state and duration of the OCC operation.......... 152

    Figure 6.4-3: Mode transitions; no load synchronization, 1) control signals 2) wind energy

    conversion and storage system operating states................................................. 152

    Figure 6.4-4: Pre-planned on-grid to off-grid mode transition, 1) reference and actual dc bus

    voltage 2) reference and actual rms voltage at the PCC 3) reference and actualrms voltage at the load bus 4) operating state................................................... 153

    Figure 6.4-5: Pre-planned on-grid to off-grid mode transition, 1) active current component of

    the VSC 2) reactive current component of the VSC 3) space vector magnitude

    of the load branch and the VSC output current.................................................. 154

    Figure 6.4-6: Pre-planned on-grid to off-grid mode transition, 1) battery terminal voltage 2)

    battery terminal current...................................................................................... 154

    Figure 6.4-7: Un-planned on-grid to off-grid mode transition, 1) reference and actual dc bus

    voltage 2) reference and actual rms voltage at the PCC 3) reference and actual

    rms voltage at the load bus 4) operating state and OCC operation duration .... 156

    Figure 6.4-8: Un-planned on-grid to off-grid mode transition, 1) active current component of

    the VSC 2) reactive current component of the VSC 3) space vector magnitude

    of the load branch and the VSC output current.................................................. 157

    Figure 6.4-9: Un-planned on-grid to off-grid mode transition, 1) battery terminal voltage 2)

    battery terminal current...................................................................................... 157

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    18/249

    xviii

    NOMENCLATURE

    Instantaneous quantities are represented by lower case letters e.g., x

    Space vector quantities are represented with an underscore e.g., tv

    Average and DC quantities are represented by upper case letters e.g., dcV

    Small perturbations in a signal are represented by a tilde over the instantaneous symbol

    for the signal e.g., dcv~

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    19/249

    xix

    ABBREVIATIONS

    WECU:

    VSC:

    IGBT:

    BES:

    SPWM:

    HSVM:

    CPM:

    RHP:

    LHS:

    RHS:

    OLD:

    STD:

    FHA:

    FOS:

    SOS:

    OCC:

    Wind Energy Conversion Unit

    Voltage-Sourced Converter

    Insulated-Gate Bipolar Transistor

    Battery Energy Storage

    Sinusoidal Pulse-Width Modulation

    Hysteresis Space Vector Modulation

    Current Programmed Mode

    Right Hand Plane

    Left Hand Side

    Right Hand Side

    Operating Logic Diagram

    State Transition Diagram

    Finite Hybrid Automata

    Fault Operating State

    Synchronization Operating State

    Over Current Control

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    20/249

    1

    CHAPTER 1

    INTRODUCTION

    his chapter introduces the research work reported in this thesis. General background of

    the subject has been presented first which is followed by the problem statement. A

    description of the study system used in the research reported in this thesis has been presented and

    research objectives are outlined. Limitations of the reported work have been pointed out

    followed by an outline of the thesis given at the end of the chapter

    1.1 BACKGROUNDThe depletion of conventional energy sources e.g. oil and gas and the desire to limit their use

    due to environmental concerns has led to the search for increased utilization of renewable energy

    sources to meet the ever-growing demand of electrical power [1], [2]. Wind is one of the most

    promising among the different types of available renewable energy sources [1]-[3]. During the

    past decade considerable research has been carried out to improve wind turbine design and

    control for increased power conversion efficiency and availability. Recently, the deregulated

    electricity market has also opened the doors for customers owned distributed generation due to

    perceived economic and technical benefits [4], [5]. Distributed generators are commonly

    connected to the system at distribution voltage levels [6]-[8]. To date, distributed generators are

    not operated in islanded conditions due to safety concerns of both personnel and equipment, and

    are required to disconnect and shutdown in response to disturbances on the utility grid [9]. The

    diversified and distributed nature of the supply system, due to increased penetration of

    distributed generators and distributed storage devices, has the potential to increase overall

    security and reliability of power supply [10]-[11]. Customized power quality and reliability

    levels can be achieved according to the individual needs of the customers by using power

    electronic based power processing units [12]-[13]. The diversified nature of the power system

    together with the use of power electronics based power processing units can result in a power

    system capable of providing the desired level of service under a variety of operating conditions.

    Using conventional control methods commonly used in power systems, the control of a

    system with limited energy capabilities in the off-grid operating mode is a difficult task [14]. The

    T

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    21/249

    2

    situation becomes even more complex if the system contains a renewable energy source such as

    wind energy power conversion unit(s), since this type of primary energy source is often

    intermittent in availability. It becomes necessary to include a dispatchable energy source, such as

    a storage device, in the scheme [15]. The control design of such a system also requires a

    radically different approach when operation of these systems is required to weather changes in

    operating conditions over a wide range. The operating conditions may include on-grid and off-

    grid mode of operation and changes in the combination of the internal energy sources supplying

    the load during the two operating modes [16].

    In this research work the automatic control and management problem of a wind energy

    conversion and battery storage system has been tackled from a supervisory hybrid control point

    of view. Hybrid control systems are composed of both discrete and continuous state variables

    [17], provide superior performance as compared to conventional control schemes [18]-[20] and

    allow the pursuit of multiple control objectives [21]. Hybrid control has found widespread

    applications from automotive, manufacturing and process industries to aerospace industry [22]-

    [25]. Hybrid control has also found limited application in drives control and power systems [26],

    [27].

    The supervisory hybrid control scheme presented in this thesis for the wind energy

    conversion and battery storage system provides automatic control of the system in islanded and

    in grid-connected modes of operation under steady state as well as during transient operating

    conditions including accidental state transitions caused by faults in the external supply system.

    1.2 PROBLEM STATEMENTConnection of the wind energy conversion units to the utility system through power electronic

    converters has the advantage that the units can be operated at variable speeds to maximize

    energy capture from the prevailing wind conditions and to alleviate stresses in the drive train

    [28]. The converter interface to the utility also shields these units from normal disturbances on

    the utility side and provides the ability to transfer the wind-generated power to the utility sidewith improved power quality [29]. However, conventional control schemes employed for the

    interfacing power electronic converters do not provide satisfactory operation during temporary

    faults on the utility systems and these may also be taken out of service due to the operation of the

    switch overload protection during such faults. The majority of faults on the utility system are

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    22/249

    3

    temporary single line to ground faults [30] and these can contribute considerably to the

    downtime of these wind conversion systems.

    As wind is stochastic in nature therefore permanent faults on the system also cause

    shutdown of the wind conversion units even if sufficient wind power is available to serve localloads. It is therefore desirable that the wind conversion system is capable of operation during

    islanded conditions. This can be a particularly useful feature in case of rural communities or far-

    flung areas with abundant wind energy potential and which are supplied through long radial

    feeders. A low cost system in terms of initial investment and environmental impacts besides low

    maintenance and operational requirements would be the desirables of a distributed energy system

    in such communities.

    The following are the desirable characteristics of operation of the subject wind energy

    conversion and battery storage system to provide economical, reliable and acceptable quality

    electrical power:

    1. Automatic system operation

    2. Fault ride through capability for temporary faults on the utility feeder

    3. Protection and control integration for the power converters

    4. Ability to operate in on-grid and off-grid modes

    5. A control scheme based on available local system information

    6. Control performance that conforms to specifications provided in section 2.4.

    There is no available literature on wind energy conversion systems that addresses all the above

    desirable control and operational requirements. The research presented in this thesis is focused

    on the design of a control scheme for a wind energy conversion and battery storage system that

    incorporates the above-mentioned desirable economic, control and operating features.

    1.3 STUDY SYSTEMFigure 1.3-1 shows the wind energy conversion and battery storage system used for the research

    reported in this thesis. The study system is composed of a Wind Energy Conversion Unit

    (WECU) and a battery storage element connected to a common dc bus. The system is interfaced

    to the load and the utility grid at the Point of Common Coupling (PCC) through a Voltage-

    Sourced Converter (VSC) unit. The complete system parameters are given in appendix A.

    The WECU itself consists of a horizontal axis, three-blade wind turbine mechanically

    coupled through a gearbox to an induction generator with a squirrel cage rotor construction. The

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    23/249

    4

    wind turbine has a maximum output capability of 360kW (1.2 per unit based on 300kVA base).

    The generator has a matching maximum rating of 1.2 per unit and a rated voltage of 690V. The

    generator unit is connected to the dc bus through a six-pulse thyristor-controlled rectifier and

    delivers wind generated power at 1000 volts on the dc side. Static capacitor banks connected at

    the generator terminals meet the reactive power demand of the generator and the thyristor

    rectifier. The thyristor based rectifier interface gives the wind energy conversion unit the

    capability of variable speed operation for maximum energy capture from the prevailing wind

    conditions [31], [32].

    The storage element is composed of series and parallel combination of battery banks, which

    are connected to the dc bus through a dc-dc converter. The wind energy conversion and battery

    storage system is connected to the utility grid and to the load at the PCC through the VSC

    interface. The VSC is assumed to be composed of three legs, each containing a pair of Insulated-

    Gate Bipolar Transistors (IGBTs). The utility grid has been represented by its Thevenin

    equivalent at 132kV level and a long (25km) radial feeder at 13.8kV has been assumed for

    connection to the wind energy conversion and battery storage system. The local load is served at

    480 volts and is connected to the PCC through a step-up transformer. The load consists of both

    constant impedance static and dynamic induction motor loads.

    The storage device shown in Figure 1.3-1 can be used for transient power support of the

    wind energy conversion unit during islanded operation. The storage can be used in combination

    with the wind energy conversion unit or on its own to cater to the local load demand in the

    absence of the utility supply. The presence of the storage device gives the system the desirable

    characteristic of dispatchability. The use of a squirrel cage induction machine reduces system

    initial cost and subsequent operational and maintenance requirements [33]. The use of a battery

    storage device is environmentally benign and apart from some initial investment has no

    significant operational and maintenance costs. The study system therefore provides a very

    attractive solution to the power quality and reliability problems of isolated rural communities.

    The following are the main features of the proposed system configuration:

    1. Use has been made of an induction generator with squirrel cage construction. The output of

    the generator is regulated through a thyristor-controlled rectifier. This means less initial

    investment and low operation and maintenance costs of the wind energy conversion unit

    making it economically more attractive.

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    24/249

    5

    2. The inclusion of a storage element on the dc bus side has a number of advantages than if it

    is connected to the system at some other location:

    a. The same power electronic interface to the utility grid is utilized for the wind energy

    conversion unit and the battery storage element thus reducing the overall cost of the

    system.

    b. Simple system control: Active and reactive power sharing control has been avoided

    which would have been required if the storage were connected at some other point to

    the system. This would have been necessary in order to control system frequency and

    to regulate node voltages in the system, respectively [33].

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    25/249

    6

    Figure 1.3-1: Wind energy conversion and battery storage system

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    26/249

    7

    1.4 RESEARCH OBJECTIVESAs described in chapter 2, section 2.1, the wind energy conversion and battery storage system

    has two operating modes i) on-grid and ii) off-grid. Within these two basic operating modes a

    number of operating states could be identified in which the system has different state spacecompositions based on the traditional definition of a state space involving state variables of the

    system.

    The primary objective of this thesis is to present a simplified approach based on hybrid

    control theory to tackle the control design and analysis problem of the study system. Based on

    the proposed approach a supervisory hybrid control scheme for the wind energy conversion and

    battery storage system shown in Figure 1.3-1 has been presented. The supervisory hybrid

    controller will operate the wind energy conversion and storage system in both on-grid and in off-

    grid mode of operations, in steady state and during transient system operating conditions as

    described in section 2.3.2. The supervisory controller for the study system will use local

    information to steer its operation along pre-specified transition routes in response to different

    system events. The transition routes are given by the hybrid automata shown in Figure 4.2-1.

    The following tasks have been identified to achieve the above stated objective:

    1. To develop a systematic approach towards the hybrid automata based hybrid modeling and

    control of the wind energy conversion and battery storage system.

    The hybrid automata of a system describes the allowable operating states of the system and

    transition paths between these operating states that the system will follow in response to some

    discrete events. An operating state of the system will be based on the possible combinations of

    the energy sources in the system (and not based on its state space composition). This point is

    further elaborated in Appendix B in which a State Transition Diagram (STD) has been

    developed from the Operating Logic Diagram (OLD) of the study system. The STD depicts

    only those operating states in which the system is capable of steady state operation. The STD

    will be complemented with transient states as described in CHAPTER 4, to develop the finalFinite Hybrid Automata (FHA) for the wind energy conversion and battery storage system. The

    transient states are the temporary operating states of the system during its transition from one

    stable operating state in the on-grid operating mode to another in the off-grid mode of operation

    and vice versa.

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    27/249

    8

    2. To devise control schemes based on the traditional control techniques using Proportional-

    plus-Integral (PI) compensators for the three system modules i.e. the wind energy

    conversion unit, the battery storage and dc-dc converter and the VSC-utility grid

    independent of each other as described in section 2.3. The operation of the three system

    modules under the proposed control schemes will be investigated separately for stability

    and performance evaluation. Operational stability and selection of proper control

    parameters for the three system modules will be based on eigenvalue sensitivity analysis

    with respect to operating point and with respect to control parameters, respectively [35]-

    [43].

    3. To combine and configure the control schemes developed for the three system modules of

    WECU, the battery storage and dc-dc converter and the VSC-utility grid respectively, to

    control operation of the wind energy conversion and battery storage system during the

    permissible operating states as depicted by the state transition diagram developed in

    Appendix B.

    4. To devise control schemes for operation of the wind energy conversion and storage system

    during the transient operating states depicted in the hybrid automata of the system which

    is shown in Figure 4.2-1.

    5. To develop suitable transition management strategies to minimize system transients caused

    by state transitions and switching of the associated control schemes.

    6. To develop supervisory control scheme for the wind energy conversion and storage system

    to perform the following actions:

    a. Oversee control transfer between different candidate controllers and control

    schemes in response to changing operating states.

    b. Manage transitions between different operating states. In other words to

    reconfigure the wind energy conversion and storage system according to the

    system events.

    c. Provide suitable reference and feedback signals to the active controllers.

    d. Provide control reset and initialization signals to the candidate controllers.

    e. Perform power and load management in the wind energy conversion and storage

    system.

    f. Implement state and control transition management strategies.

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    28/249

    9

    The supervisory controller will infer the changing operating states of the system based on

    information from selected indicators. Referring to Figure 1.3-1, the open or closed state of the

    TCB (tiebreaker) will indicate the operating mode of the wind energy conversion and storage

    system (i.e., on-grid or off-grid mode). The availability of the utility grid will be decided based

    on the single phase rms voltages on the utility side of the TCB when these are within the normal

    operating range specified by ANSI C84.1- 1995 [44]. Islanding detection algorithms have not

    been implemented and islanding has been assumed as a known event. Availability of the battery

    storage is assumed to be known a priori (this information could come from an energy

    management system for the battery storage). Availability of the wind energy conversion unit will

    be inferred from the dc output current of the thyristor-controlled rectifier. Fault on the utility side

    will be determined from the peak value of the phase voltages on the utility side of the TCB. For

    this purpose the algorithm described in reference [45] will be implemented. Status of the load

    (connected or disconnected) will be inferred from the load breaker (LCB) shown in Figure 1.3-1.

    In the absence of any theoretical guarantees for the control stability of the wind energy

    conversion and storage system, digital time domain simulations of the nonlinear system will be

    performed using PSCAD/EMTDC to investigate system operation under the proposed

    supervisory hybrid control scheme both for stability and for performance evaluation [46]. This

    will also require that suitable performance criteria be specified for the performance assessment

    of the study system. Performance specifications have been described in section 2.4.

    1.5 LIMITATIONSThe following are the main limitations of this thesis:

    1. Linear integral and proportional-plus integral compensators have been used.

    2. Parametric sensitivity analysis has been performed with respect to a single control variable

    at a time; no inter-parametric sensitivity analysis has been attempted.

    3. Aspects concerning economics of the system management have not been treated in this

    research.

    4. System protection issues are not of primary concern.

    5. Neither system nor control parameters have been optimized.

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    29/249

    10

    1.6 THESIS OUTLINEChapter 2 gives details of operation of the wind energy conversion and storage system and

    describes management of the system from a hybrid control point of view. Different possible

    operating states are enumerated. Load and power management strategies are described andperformance criteria are presented. The chapter also gives a methodology for the control design

    of the wind energy conversion and storage system and provides a strategy for evaluating stability

    and performance of the system in its different operating states.

    Chapters 3 provides control schematics and results of the linear and nonlinear analysis of the

    three system modules of the study system i) the wind energy conversion unit consisting of the

    wind turbine, the induction generator, static capacitor banks and the thyristor-controlled rectifier

    ii) the storage element consisting of the battery storage and the dc-dc converter and iii) the VSC-

    utility grid system module, respectively. Each system module contains one energy source and is

    treated in the following order:

    1. Module: Wind Energy Conversion Unit

    2. Module: VSC-Utility Grid

    3. Module: Battery Storage and DC-DC Converter

    In this chapter associated control schemes for the three system modules have been elaborated

    whereas mathematical models have been presented in the appendices.

    Chapter 4 deals with the subject of the hybrid supervisory control of the wind energy

    conversion and battery storage system. It provides background information into the hybrid

    control systems. In this chapter a finite hybrid automata of the wind energy conversion and

    storage system has been presented which depicts system operating states and the uni- and bi-

    directional links between these states which the system is required to follow while moving from

    one state to another. The chapter introduces the concept of transition management used for the

    supervisory hybrid control of the wind energy conversion and battery storage system.

    Chapter 5 provides stability and performance evaluation of the operation of the study system

    during all the operating states under normal operating conditions as depicted by the hybrid

    automata of the system shown in Figure 4.2-1. In all these operating states two or more of the

    system modules are interacting with each other under normal load switching conditions. Control

    schemes have been developed for the operation of the wind energy conversion and battery

    storage system in each of the normal operating state. These control schemes have been derived

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    30/249

    11

    from the control schemes proposed for the three system modules of the study system and also

    incorporate elements of transition management strategies described in chapter 4. Results of the

    stability and performance evaluation of the study system using digital time domain simulations

    of the nonlinear system in PSCAD/EMTDC have been presented in this chapter. The following

    normal operating states have been considered:

    1. Operating State: Wind Energy Conversion Unit-Utility Grid

    2. Operating State: Storage-Utility Grid

    3. Operating State: Storage-VSC-Load

    4. Operating State: Wind Energy Conversion Unit -Storage

    5. Operating State: Wind Energy Conversion Unit -Storage-Utility Grid

    Chapter 6 provides simulation results for the operation of the wind energy conversion and

    storage system during state transitions under the proposed supervisory hybrid control scheme.

    The operation of the study system has been investigated for stability and performance, during

    state transitions, through time domain simulations in PSCAD/EMTDC environment. Worst case

    scenarios for transitions between the permissible operating states of the study system given by

    the proposed hybrid automata have been considered.

    Chapter 7 concludes the research reported in this thesis. It provides conclusions based on the

    reported work and lists thesis contributions. Future research opportunities have been identified at

    the end of the chapter.

    Appendices are given at the end of the thesis:

    1. System parameters are given in appendix A.

    2. Appendix B provides a method to determine operating states of the system using simple

    Boolean logic to arrive at a State Transition Diagram (STD) for the study system.

    3. Appendix C gives modeling details of the wind energy conversion unit.

    4. Appendix D provides modeling details of the VSC-Utility grid system.

    5. Appendix E details modeling of the battery storage and dc-dc converter.

    References are provided at the end of the thesis.

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    31/249

    12

    CHAPTER 2

    OPERATION AND CONTROL

    n this chapter issues concerning the operation and hybrid control of the wind energy

    conversion and storage system have been treated. Methodology for the control design,

    selection of control parameters, criterion for performance evaluation and a methodology for

    performance verification have been the main subjects of this chapter.

    2.1 OPERATION OF THE STUDY SYSTEMReferring to Figure 1.3-1, the wind turbine driven by the lifting force of the wind blowing acrossthe blades drives the mechanically coupled induction generator thereby converting the kinetic

    energy of the wind into electrical energy. The electrical output power of the generator is

    controlled and delivered at the dc bus through the thyristor rectifier. The generated power could

    be delivered to the grid, used for battery charging, or else it could be partly delivered to the grid

    and partly stored in the battery storage device for later use.

    In the grid-connected mode, the load in the wind energy conversion and storage system can

    be served by the energy sources internal to the system as well as by the external utility supply.The load can be supplied with power from the utility feeder with or without any contribution

    from the local energy sources and proper system operation can be ensured during both steady

    state and dynamic operating conditions. In the isolated mode of operation, the VSC alone

    transfers the available power from the wind energy conversion unit and the battery storage at the

    desired voltage level and frequency. Power management is required in both grid connected and

    during islanded operation in order to control power contribution from the energy sources in the

    wind energy conversion and storage system and to direct it to proper sinks.

    The two energy sources in the wind energy conversion and battery storage system are

    limited in capacity and also a maximum capacity of 1.3 per unit has been assumed for the VSC,

    therefore during islanded operation quality power can be assured only with a limited amount of

    dynamic motor load connected at the load bus. Some load management is therefore required for

    proper off-grid operation regardless of the level of availability of the energy sources in the wind

    energy conversion and battery storage system.

    I

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    32/249

    13

    The objective of the load management and the power management strategies is to achieve power

    balance between the energy sources and the loads at any given time. However power

    management is also concerned with the load sharing among the active energy sources in the

    system and achieves the objective by continuously controlling power contributions from the

    different energy sources in the system. Load management on the other hand, is provided to assist

    in power management by ensuring that only that much power is demanded that can be supplied

    by the available energy sources within the power quality constraints. Load management is a

    discrete phenomenon while power management may involve discrete actions in that one or the

    other energy source in the system may be taken in or out of service.

    2.1.1 POWER MANAGEMENTThe power management strategy is based on the assumption that the storage will be used as a

    backup supply and to provide steady state and transient power support during islanded mode of

    operation. Provisions will be made to use the battery storage while the system is operating on-

    grid for maintaining the dc bus voltage during severe disturbances including faults on the utility

    feeder. Also the wind energy conversion unit will be operated to follow the maxim output curve

    of the turbine for maximum power extraction from the prevailing wind.

    2.1.1.1 Steady State Power ManagementThe steady state power management is concerned with power delivery from the energy sourcesin the wind energy conversion and battery storage system over longer periods of time usually

    called energy management, in both grid connected and in isolated mode of operation.

    The following strategy will be used during the grid-connected mode of operation:

    1. The WECU will be operated to extract maximum power from the prevailing wind

    conditions at all times.

    2. All the wind-generated power will be transferred directly to the utility side when the storage

    element is fully charged.

    3. All or part of the wind-generated power will be used for charging the battery storage when

    required.

    4. In the absence of wind-generated power, utility supply will be used for charging the storage

    element if necessary.

    The following strategy will be used in the islanded mode of operation:

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    33/249

    14

    1. Battery storage will be used to cater to the load demand together with WECU when the

    power output of the latter is not enough to meet the load demand.

    2. When the power output of the WECU exceeds the load demand then the excess power will

    be used for charging the batteries.

    3. In the absence of wind power generation, storage alone will meet the load power demand.

    The case where the batteries are fully charged and the power output of the wind energy

    conversion unit exceeds load demand has not been treated in this thesis. One solution in such a

    scenario would be to operate the wind energy conversion unit at sub optimal level to match its

    output to that of the load demand. Another strategy however is to use some dummy load (for

    example some heating load) preferably connected to the dc bus to be able to extract maximum

    power from the wind at all times.

    2.1.1.2 Transient Power ManagementTransient power management is concerned with the momentary power imbalance in the system

    during the course of its operation.

    During grid-connected mode of operation, variations in power from the wind energy

    conversion unit caused by variations in wind speed as well as variations in load power demand

    will be reflected in the amount of power delivered by the utility feeder. In other words, utility

    supply will be relied upon for transient power support during grid-connected operation of thewind energy conversion and storage system. Battery storage support during grid-connected

    operation will only be used when dc bus voltage variations exceed certain limits in order to

    ensure control stability of the system. This point is further explained in section 4.3.2.

    In the isolated mode of operation, power transients from WECU and load power variations

    will be absorbed by the storage element. In the absence of wind power generation, storage alone

    will provide the required transient power support besides meeting steady state power demand.

    2.1.2

    LOAD MANAGEMENT

    The amount of dynamic load that the wind energy conversion and storage system is able to

    supply, in the islanded mode of operation without compromising power quality depends on the

    capacity of the energy sources internal to the system. Also the VSC, which will transfer the

    available energy from the internal sources to the load side, has a limited capacity (1.3 per unit).

    Therefore a limited amount of load could be supplied during islanded operation of the system.

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    34/249

    15

    The inrush current at startup of a motor load (predominantly induction motors) which contains a

    large reactive component causes voltage dips which in turn causes these loads to lose rotational

    speed and in turn demand increased reactive current. This situation slows down the system

    voltage recovery and may exceed converter rating and the available power capability of the

    energy sources in the wind energy conversion and storage system. A similar situation exists

    when motor load is subjected to transient voltage disturbances.

    In this thesis a simple load management strategy has been adapted in which the higher rated

    motor load ML2 (Figure 1.3-1) will be disconnected following system transition from grid-

    connected to islanded mode of operation. The transients caused by the rest of the load are within

    the handling capability of the VSC and the energy sources in the system.

    2.2 STATE TRANSITION DIAGRAMReferring to Figure 1.3-1, the wind energy conversion and storage system has two basic

    operating modes:

    1. Grid Connected Mode

    2. Islanding Mode

    The system has the following two possible operating conditions in each mode of operation:

    1. Steady State

    2. Transient

    In steady state conditions, load and generation are in perfect balance. Under transient conditions

    however, there exists a transitory imbalance between the load and generation and the system

    settles down to a new equilibrium condition if it remains stable. System transients can be broadly

    classified as:

    1. Pre-planned Transients

    2. Accidental Transients

    Pre-planned transients are those resulting from intentional switching e.g. shutting down of the

    utility feeder for maintenance work. Accidental transients on the other hand are random in nature

    and are caused by system faults and switching in or out of the load as well as the power factor

    correction capacitors, among others.

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    35/249

    16

    Both pre-planned and accidental transients can cause the combination of active energy sources in

    the system to change leading to a change of the system operating state. Transient system

    conditions accompanied by a change in the system operating state will be called a transition

    while the dynamic conditions where the operating state of the system remains unchanged will

    simply be called transients. A transition may be a result of a permanent system fault e.g. on the

    utility feeder, followed by a disconnection from the utility (accidental transition) in which case

    the system will switch from the grid connected mode to the isolated mode of operation. The

    transition from one mode to the other may also be a pre-planned event e.g. due to maintenance

    work on the feeder.

    The wind energy conversion and storage system can have finitely many operating states and

    in the absence of any analytical tool, in the context of hybrid control systems, the hybrid control

    design for the wind energy conversion and storage system and its evaluation for stability and

    performance is a very difficult task. It is therefore necessary to curtail the number of states that

    the supervisory hybrid control scheme has to manage. Figure 2.2-1 gives the State Transition

    Diagram (STD) of the study system with a limited set of operating states for which a supervisory

    hybrid control scheme will be devised. Appendix B gives a systematic procedure for determining

    the possible operating states of a system with multiple energy sources.

    Referring to the STD in Figure 2.2-1, during grid connected mode when storage needs to be

    built up, the system enters into the state WECU + Storage + Utility and falls back to the state

    WECU + Utility when the storage element is toped up to a pre-specified level. In the VSC +

    Utility operating state where only utility is supplying the load; the VSC will be used only for

    voltage support at the PCC. Full converter capacity could be utilized for reactive power support

    during this mode of operation. During islanding operation, there are three steady state operating

    conditions namely:

    1. The standby state in which the dc bus is energized using the battery storage but the load

    bus is kept disconnected.

    2. The storage operating state where the battery storage alone is supplying the load.

    3. The WECU + Storage operating state where the output from the wind energy conversion

    unit and the storage are used together to meet the load demand.

    During the latter two operating states load may or may not be present. The operating state in the

    off-grid mode where only wind energy conversion unit is active is not sustainable due to the

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    36/249

    17

    absence of external transient power support and is therefore not represented. In the start up

    operating state, the dc bus voltage will be energized in a controlled manner using the battery

    storage and its voltage will be stabilized at the nominal value of 1.0 per unit (1000V).

    Figure 2.2-1: State Transition Diagram (STD) of the wind energy conversion and storage system

    2.3 CONTROL DESIGNControl of the wind energy conversion and storage system using linear compensators and

    Sinusoidal Pulse-Width Modulation (SPWM) based switching of the VSC necessarily cannot

    provide for adequate control during accidental state transitions caused by faults on the utility

    feeder and may not ensure performance requirements during transient operating conditions (e.g.

    motor load switching) within each operating state. Considering that a reasonable limit has been

    imposed on the output current of the VSC (1.3 p.u. = 1.2 p.u from WTU + 0.1 p.u. margin for

    transient conditions as also for reactive power support; combined load is rated at 1.0 p.u.), it will

    not be possible to contain its output current below the limit (1.3 p.u.) during a fault (particularly

    a close up fault) on the utility feeder (also possibly during motor load switching) and the over

    current protection of the VSC associated with its switching elements will take the unit out

    causing interruption in service. It is therefore necessary to handle the management of the wind

    energy conversion and storage system from a hybrid control perspective [19], [47] and [48].

    The hybrid control problem is usually concerned either with switching between a number of

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    37/249

    18

    controllers for a single plant for optimum operation under changing operating conditions or

    control of a plant whose state space composition is subject to change due to some discrete time

    events or both. In a hybrid control structure the supervisory controller is at the top level of the

    hierarchy and interacts both with the unit level regulators as well as the regulated plant(s). Figure

    2.3-1 adapted from [49], illustrates the supervisory control structure. The thick solid lines

    represent all the external inputs to the plant and all the outputs of the plant while thin solid lines

    represent a subset of the plant outputs and the set of (control signal) inputs from the primary

    regulators. The dotted lines represent information flow (monitoring and control signals) to and

    from the supervisory control layer.

    Figure 2.3-1: Supervisory hybrid control structure

    The control action by the supervisory layer on the primary regulator may involve switching

    between different controllers or updating control parameters for a single regulator or may

    involve a combination of the two. Control action on the plant itself may include taking in or out asubsystem (module) of the plant.

    The control of the wind energy conversion and storage system will involve all the above-

    mentioned aspects of a supervisory hybrid control scheme. Control action on the plant will

    involve taking in or out one or more of the energy sources in the wind energy conversion and

    battery storage system including the utility supply. The different operating states given by the

  • 8/8/2019 plugin-KHAN_MUHAMMAD_S_200806_PhD_thesis

    38/249

    19

    STD of the wind energy conversion and storage system (the plant) correspond to different state

    space compositions as a result of the supervisory control actions on the system. This is further

    explained in the subsequent sections and in CHAPTER 4 in the context of supervisory hybrid

    control of the study system.

    2.3.1 MODULAR DESIGN PHILOSOPHYThe wind energy conversion and storage system is a Multiple-Input-Multiple-Output (MIMO)

    system and the control design could be tackled as such. As explained in section 2.2, the wind

    energy conversion and battery storage system has two possible operating modes (on-grid and off-

    grid). There are a number of possible operating states within the two basic modes of operation of

    the system. Control design for each operating state using MIMO control approach represents a

    considerably difficult design task. As pointed out in the previous section, control and mode

    transitions will still have to be considered under a supervisory control layer (section 2.3.2).

    The complexity associated with the control design of the study system using MIMO control

    philosophy can be avoided by following the approach proposed in [50]. According to the

    proposed approach the problem of modeling and control design for a complex system can be

    simplified if the system could be partitioned along a suitable axis. The STD of Figure 2.2-1

    points to such a partitioning axis i.e., the dc bus. It can be seen from