Upload
donhu
View
217
Download
2
Embed Size (px)
Citation preview
Draft
Another Look at Delineation of Uniform Pavement Sections
Based on FWD Deflections Data
Journal: Canadian Journal of Civil Engineering
Manuscript ID cjce-2015-0281.R1
Manuscript Type: Article
Date Submitted by the Author: 18-Sep-2015
Complete List of Authors: Haider, Syed; Michigan State University, Civil and Environmental Engineering Varma, Sudhir; Michigan State University, Civil and Environmental Engineering
Keyword: planning < Transportation, highways < Transportation, design < type of paper to review
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Another Look at Delineation of Uniform Pavement Sections Based on
FWD Deflections Data
Syed Waqar Haider, Ph.D, P.E.
Associate Professor (Corresponding Author)
Department of Civil and Environmental Engineering, Michigan State University,
Engineering Building, 428 S. Shaw Lane, Room 3546, East Lansing, MI 48824 ,
Phone: 517-353-9782; Fax: 517-432-1827; e-mail: [email protected]
and
Sudhir Varma, Ph.D
Graduate Research Assistant,
Department of Civil and Environmental Engineering, Michigan State University,
Engineering Building, 428 S. Shaw Lane, Room 3552, East Lansing, MI 48824
Phone: 517-355-8422; Fax: 517-432-1827; e-mail: [email protected]
Text Count = 5,848
Number of Figures and Table = 10 (Equivalent word count = 2500)
Total Word Count = 8,348
Page 1 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
2
Another Look at Delineation of Uniform Pavement Sections Based on
FWD Deflections Data
ABSTRACT
The large amount of data commonly used to characterize the pavement surface and
structural conditions offer a challenge to practitioners making decisions about the
representative value of a particular parameter for design. While a large number of
observations along the length of a road allow a better quantification of the expected
value and variance of a parameter, basing a design on an average parameter along the
project length, it will typically be uneconomical and less reliable. Therefore, pavement
surface and structural condition data along a project length needs to be delineated into
uniform sections. The design can be performed individually for each of these uniform
sections to achieve economy without compromising reliability level.
This paper documents delineation methods that explicitly address the problem of
segmentation of measurement series obtained from FWD deflections. Modifications in
the existing AASHTO delineation procedure were incorporated to address the mean
differences and the local variability. The results of delineation show that the AASHTO
methodology ignores the local variations along the project length which may not be valid
from a practical standpoint while designing rehabilitation or preservation strategies. The
inclusion of restrictions on mean difference and section length resulted in better
delineation than the AASHTO method but it could be sensitive to local variations of the
deflections within a section. The delineation approach can handle the local deflection
variations within a section if appropriate constraints on the local variations are imposed.
The results from the delineation of field deflections showed that the restrictions on mean
difference, minimum section length and location variability are vital to delineate the
Page 2 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
3
project length into appropriate homogenous sections which can be different from each
other from both statistical and practical viewpoints.
Keywords: Delineation, Uniform sections, Homogenous sections, FWD deflections,
Rehabilitation design.
Page 3 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
4
INTRODUCTION
Generally two types of evaluations are conducted for pavement rehabilitation: (a) surface
condition assessment, and (b) structural condition evaluation. The data collected from
such evaluations play a key role in decision making regarding the treatment type
selection and timing to fix an existing pavement (Haider and Dwaikat 2011; Haider and
Dwaikat 2012). The surface condition assessment data includes the type, extent and
severity of surface distresses while the structural condition data (i.e., surface deflections
and material properties) are used to assess the existing structural capacity of pavements.
Decisions about maintenance, rehabilitation or preservation action to extend the life of
the pavements in the network relies on the combination of functional or structural
distresses observed on those sections.
Pavement surface condition is comprised of load-related distresses such as fatigue
cracking and rutting, and functional distresses (non-load-related) such as transverse and
block cracking, ride quality etc. Pavement surface condition information is an integral
part of any pavement management system (PMS). On the other hand, falling weight
deflectometer (FWD) deflections are typically utilized at the project level to assess the
structural capacity of existing pavements. While deflection data can be used to evaluate
the construction quality of a newly constructed road, those are generally helpful to
backcalculate the existing layer moduli of asphalt, base/subbase, and subgrade layers for
designing an overlay thickness to meet anticipated traffic for the extended life. However,
only structurally sound pavements may be considered as candidates for pavement
preservation. Both types of data (surface conditions and deflections) are typically
reported over a unit length of a pavement; typical unit length for data collection purposes
Page 4 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
5
in the US is 0.1 mile (528 ft). Further, some of the surface condition data are collected
continuously (sensor-measured, e.g., IRI and rutting) while others are collected at
discrete locations (e.g., deflections, coring or boring etc.) (Haider et al. 2010; Haider et
al. 2011). Such data are used for designing new roads (reconstruction), or selecting
rehabilitation actions on existing roads. The large amount of data commonly used to
characterize the pavement surface and structural conditions offer a challenge to
practitioners making decisions about the representative value of a particular parameter for
design. While a large number of observations along the length of a road allow a better
quantification of the expected value and variance of a parameter, basing a design on an
average parameter along the project length, it will typically be uneconomical and less
reliable. Therefore, pavement surface and structural condition data along a long stretch
of pavement needs to be delineated into sections which are “relatively uniform”, referred
to as homogeneous sections, for which the design is performed individually. This results
in economy in design without compromising reliability level (Misra and Das 2003).
Currently, highway agencies need to identify homogeneous sections when
planning maintenance actions. In fact, identifying candidate sections for maintenance or
rehabilitation is essentially a task of determining which parts of the measurement series
(surface and structural condition data) exceed certain threshold values, and ensuring that
these sections are not too short to be meaningful candidates for actions such as repaving
(Thomas 2004). However, the large amount of data collected by road profilers can be
used for more than just identifying sections that fail some minimal requirements.
Furthermore, evaluating and comparing the information from different locations over
time in these measurement series allows for a systematic monitoring of the road surfaces.
Page 5 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
6
In general, a prerequisite for most of the delineation analyses is to identify the parts of the
measurement series that are homogeneous with respect to a particular criterion (Thomas
2004). However, the criteria selection and how best to combine different existing
segments of the road into a single uniform one will depend on the unique problem at hand
(Bennett 2004). While several criteria are available to accomplish the same objective of
determining uniform sections, the results could be different.
The main objectives of the paper are to review the existing delineation methods
and develop a procedure that addresses various shortcomings in the existing AASHTO
delineation methodology by considering the (a) mean differences for surface deflections,
and (b) local variations in the measured deflections between adjacent pavement sections.
In order to accomplish the above mentioned objectives, this paper documents a
delineation method that explicitly addresses the problem of segmentation of measurement
series obtained from FWD deflections. First, a review of the method recommended in
AASHTO (AASHTO 1993; AASHTO 2008) is presented. Further, some extensions
necessary to make the AASHTO delineation procedure a fully automatic method suitable
for the large amount of data are discussed. Second, additional modifications in the
existing AASHTO procedure were incorporated to address the mean differences and the
local variability. The modified algorithms are documented along with examples to
demonstrate their accuracy and efficiency. Finally, examples are presented to analyze the
peak deflection data from actual field projects to demonstrate the application of the
developed methodology.
Page 6 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
7
BACKGROUND
The AASHTO design guide documents a straightforward and powerful analytical method
for delineating statistically homogenous units from pavement response measurements
along a highway system (AASHTO 1993). The method is described the cumulative
difference approach (CDA). The approach can be used for a wide variety of measured
pavement response variables such as deflection, serviceability, surface roughness in terms
of IRI, skid resistance, pavement distress indices, etc. Figure 1 shows the overall concept
of the CDA using the assumption of a continuous and constant deflection (pavement
structural response) within various intervals along a project length.
The simplified scenario in Figure 1a shows three unique pavement sections
having different deflection magnitudes (i.e., 1 2 3, ,d d d ) while d represent the overall
average deflection on the entire project. The cumulative areas under deflections for
individual sections and overall average deflections can be calculated using Equations (1)
through (3) and are shown in Figure 1b. It should be noted that the slopes (derivatives) of
the cumulative area curves are simply the deflection for each unit (1 2 3, ,d d d ) while the
slope of the dashed line is the overall average deflection value ( d ) of the entire project
length considered.
1
1
1 2
0
x x
x
x
A d dx d dx= +∫ ∫ (1)
0
x
xA ddx d x= = ×∫ (2)
Page 7 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
8
31 2
1 2
1 2 3
0
xx x
x x T
s s
d dx d dx d dxA
dL L
+ +
= =∫ ∫ ∫
(3)
Equation (4) can be used to calculate the difference in the two areas called cumulative
difference variable as shown in Figure 1c.
x x xZ A A= − (4)
As shown in Figure 1b, x
Z is simply the difference in cumulative area values, at a given
distance, x between the actual and project average lines. However, if thex
Z value is
plotted with distance, x then Figure 1c results. An inspection of the figure illustrates that
the location of unit boundaries always coincides with the location (along x ) where the
slope of the x
Z function changes algebraic signs (i.e., from negative to positive or vice
versa). This fundamental concept is the ultimate basis used to analytically determine the
boundary location for the analysis units (AASHTO 1993). However, in practice, the
pavement response parameters (peak deflections in this paper) are never constant and
have inherent variability with distance due to changes in construction and material
properties along the project length. Therefore, in order to apply the CDA to real data, a
numerical difference approach is recommended by AASHTO and x
Z can be determined
by using Equation(5).
1
1 1
1where; 2
n
in ni
x i i
i is
i ii i i i
d
Z d xL
d dd x d x
=
= =
−
= −
+ = =
∑∑ ∑
(5)
Page 8 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
9
The approach can be further simplified for data collection at a constant interval as shown
by Equation(6):
1
1
; where, = 1,....,
where;
k
x i
i
n
i
i
Z d kd k n
d
dn
=
=
= −
=
∑
∑ (6)
where;
id = deflection at point i
d = average deflection on the project length
k = deflection at the th
k measurement
n = total number of measurements
The AASHTO CDA method is simple and can be suitable as an algorithm for a computer
program. However, due to subjectivity due visual inspection of results involved in the
final selection of homogenous sections, it may offer certain limitations in delineation.
Since, the method relies on the change of cumulative sum (CS) slope for identifying
uniform sections; it fails to recognize the variability of the parameter within the
homogenous sections. Therefore, for practical purposes, it is recognized that some
constraints need to be placed in the CDA algorithms on the delineation unit to filter out
higher variability, and to have homogeneous units that will be viable rehabilitation
projects. As a result, two types of constraints have been considered: (a) minimum
segment length, and (b) minimum difference in mean parameter for delineation (e.g., rut
depth, IRI, peak surface deflections etc.) between adjacent segments (Misra and Das
2003; Ping et al. 1999).
Page 9 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
10
For the minimum segment length criterion, it is important to consider the intended
application of the data. Certainly, the lower the minimum segment length, the better the
chances of minimizing the variability within delineated segments which will result in
establishing more uniform segments. However, in practice, there is a limit to how short a
section length can get in order to establish a viable rehabilitation project. Therefore, it is
advantageous to combine very short segments with other segments to form longer
segments for the purposes of overlay design and construction. On the other hand, in order
to consider practical and operational mean differences of the parameter considered for
delineating adjacent segments, the mean difference should be consistent with the
observed variability of the parameter within uniform pavement segments. In other words,
the mean difference should be dissimilar enough to trigger a different design or a
treatment. It should be noted that such practical mean difference magnitude will depend
upon the type of the parameter used for delineation. For example, the mean difference of
1 mil for peak deflection between adjacent segments may not trigger a different treatment
while a mean difference value of 4 mils may be practical enough to produce different
pavement rehabilitation or preservation treatment.
In light of above mentioned limitations of the CDA method, several modifications
have been proposed. Bennet highlighted different sectioning needs for pavement
management and documented the differences between sectioning of roads and analysis
sections based on data sources (Bennett 2004). Thomas provided an elaborated literature
on the-state-of-the-practice for generating homogenous road sections based on surface
measurements (Thomas 2004). He documented available methods for road segments such
as (a) cumulative differences, (b) absolute differences in sliding mean values, and (c)
Page 10 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
11
Bayesian segmentation algorithm. Several issues were highlighted and described for all
of these methods. It was reported that a successful implementation of the CDA rests upon
development of sensible criteria to interpret the calculated series of cumulative
differences. It is likely that any criteria that work well for a wide range of measurement
series will be data-dependent, for example, by explicitly accounting for the variability in
a particular measurement series under study. Unfortunately, such dependencies on the
data under study inevitably destroy the most attractive feature of CDA, namely, the
already mentioned simplicity in calculation (because the exact criteria have to be
calculated from the data) (Thomas 2004). On the other hand, when data smoothing is
utilized, it disguises the information about sudden changes in a measurement series
because (a) a suspected change in the measurement series is abrupt, the information about
the location of that change is “clearest” by comparing its immediate neighbors, and (b)
averaging of measurements corrupts this “pure” information in the neighborhood of that
location by mixing values from both sides of the suspected change. Therefore, smoothing
a measurement series by a sliding mean might be expected to do more harm than good
when the task is to identify the location of a sudden change (Thomas 2004). While the
statistical methods such as Bayesian algorithm (Thomas 2003; Thomas 2005) often
provides a good approximation of more involved processes and will consequently render
satisfying results even when the model assumptions do not hold exactly, the algorithm
should be expected to fail in cases of seriously violated model assumptions.
Several other researchers have used some modifications of the CDA approach and
suggested several improvements in the procedure for identifying homogenous or uniform
sections. For example, Misra and Das (Misra and Das 2003) suggested an improved yet
Page 11 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
12
simplistic methodology for identification of homogeneous sections based on a combined
approach of classification and regression tree (CART) and exhaustive search. Cafiso and
Graziano (Cafiso and Di Graziano 2012) proposed a methodology to detect a change
point by searching those points to minimize the sum of the squared errors respect to the
series of data.
Gendy and Shalaby (El Gendy et al. 2005) proposed two methods for
segmentation to divide the roughness profile into segments which have a specified IRI
range. They used absolute difference and combining segment approaches to establish
uniform sections based on IRI. The same authors also looked the fundamental concepts of
the quality control charts and their suitability for segmentation (El Gendy and Shalaby
2008). Shalaby and Tasdoken (Cuhadar et al. 2002) used a new algorithm based on
wavelet transform for automated segmentation of the pavement-condition data. They
developed a de-noising scheme to remove random noise caused by the collection device
and random extreme distress in the pavement while essentially preserving the important
information followed by a singularity detection-based segmentation algorithm.
From the above discussion of the literature on the detection of uniform or
homogenous pavement sections based on different response parameters, the following
take home points can be established:
1. The segmentation procedure should be able to consider the practical or
operational aspects, i.e., the mean difference in the response parameter. Such
attentions for practical mean differences among delineated pavement sections are
important when the uniform sections are to be used for rehabilitation design or for
preservation treatment selections.
Page 12 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
13
2. The procedure should also be able to detect the local variations in the response
parameter to reduce the risk of failure and increase the reliability of the selected
rehabilitation or preservation treatment.
3. The methodology should be robust and simple enough for practical application.
The new delineation methodology developed in this paper is documented below
along with some examples to demonstrate its application by using the deflection data.
DELINEATION METHODOLOGY
In this paper, three delineation methods are considered (1) the AASHTO cumulative
difference approach (CDA), (2) a delineation approach which considers the mean
difference, and (3) a delineation methodology which considers the mean difference and
local variability. All the above approaches consider the impact of minimum section
length (as a constraint) while establishing uniform sections based on FWD deflection
data. The main purpose of including multiple approaches is to compare the results among
those and recommend a practical and robust methodology for identifying homogenous
sections for preserving or rehabilitating an existing flexible pavement.
It should be noted that selection of mean difference of response parameter (in this
case peak deflection) between adjacent sections will depend on the:
a. Practical or operational significance of the mean difference for peak deflection.
For example, a mean difference of 2 to 3 mils between adjacent sections may
trigger a different preservation or rehabilitation treatment depending on traffic and
condition of an existing pavement structure. However, the mean difference
practical magnitude will depend on the response parameter to be considered for
delineation (e.g., IRI, friction, rutting etc.)
Page 13 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
14
b. The mean difference will also depend on the overall variability of deflections
along the project length. For example, if a mean difference of more than the
observed maximum difference in deflections is selected, there will be only one
uniform or homogenous pavement section.
The CDA approach (AASHTO 1993) as described in the background section
(method 1) was used to analyze deflection data. The algorithms for methods 2 and 3
developed in this paper are shown in Figures 2 and 3, respectively. The cumulative sum
for peak deflections is calculated based on Equation (6) for the project length. In method
2, the adjacent sections (e.g. section 1 followed by the section 2) are chosen based on the
minimum length specified and the slope of the cumulative sum is calculated by fitting a
linear line for both. It should be noted that the difference between the slopes for two
adjacent sections is same as the difference between their mean deflections. If the mean
deflection difference is less than a specified threshold, the adjacent sections are combined
and compared with next minimum length. On the other hand, if the mean difference
between sections 1 and 2 is more than the specified threshold, then section 2 is reduced in
length by a factor,λ , and then the new section 2 is compared with section 1. The length
reduction factor is used to find the change point within the minimum length specified.
The threshold (i.e., mean difference) criteria will be again checked to establish that the
two adjacent sections should be combined or considered as separate sections. The process
is iterative and will terminate when the entire project length ends (see Figure 2).
A similar algorithm to method 2 is utilized for method 3 but this time the mean difference
is tested statistically with 95% confidence to consider the impact of local variability. A t-
test (with pooled variance) was used when variance between adjacent sections is
Page 14 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
15
statistically similar; otherwise a t-test with unequal variances is used. The process is also
iterative and will terminate when the entire project length ends (see Figure 3). Table 1
shows the variables names and descriptions used in both methods shown in Figures 2 and
3.
Comparison of Different Delineation Methods
To illustrate the differences between the three methods described above, an example of
project delineation is shown in Figure 4. Figure 4a shows simulated peak deflections for a
project. The deflections data were simulated based on randomly generated normal
distributions with varying means and standard deviations. As shown in the figure, the
deflection data shows six (6) separate sections in the entire project length. Figure 4b
shows the delineation results based on the three methods. Based on the AASHTO
delineation method, the entire project length is divided into three uniform sections (0 to
400, 400 to 650, and 650 to 800). Applying method 2 results in seven uniform sections (0
to 200, 200 to 400, 400 to 450, 450 to 500, 500 to 650, 650 to 700, and 700 to 800).
The AASHTO method does not consider the variability between adjacent sections
because slope of cumulative sum does not change signs. For example, it ignored to
delineate between stations 0 to 400. Since, method 2 is based on the mean difference; it
captures any significant change in slope. Method 3 gave the exact delineation for the
simulated sections. The method 2 results are better than those of the AASHTO method
but method 2 could be sensitive to local variations of the deflections within a section.
Since, method 3 also considers the local variations of deflections while delineating the
deflection data; it can overcome the problem of local variations within a section. This
simple example shows the robustness of the method 3.
Page 15 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
16
Impact of Mean Difference and Local Variability on Delineation Methods
In order to verify the effectiveness of methods 2 and 3, deflection data were simulated for
a wide range of local variability with a specified number of sections (i.e., six
homogenous sections). The maximum and minimum differences between the average
deflections on adjacent sections were 22 and 10 mils, respectively. In addition, the
delineation was performed based on different thresholds (mean differences) to evaluate
its impact under different variability. Figure 5 shows the variability in the simulated
deflection data for a realization. However, the simulation was carried out for a total of
1000 cases to determine the distribution for a number of homogenous sections with
different delineation methods. Figures 6a and 6b show the percent of correct uniform
sections determined by methods 2 and 3, respectively. The result of method 2 indicates
that percentage of correct delineation depends on the threshold value (i.e., the mean
difference between adjacent sections) and local variability of deflections within each
homogenous section. If the threshold is less than 4 mils, method 2 fails to delineate the
correct number of sections, especially when the local variability is high. Similarly, when
the threshold is more than 9 mils, the error for identifying correct percentage of sections
increases (see Figure 6a). It seems that when the threshold is too low, method 2 will
delineate higher number of sections because of the local variations. On the other hand, if
the threshold is too high, the method will under predict the number of correct
homogenous sections. Since, method 3 considers the local variations in deflections; it is
more robust at lower threshold values than method 2. However, it also under predicts for
higher threshold values (see Figure 6b). From these results, it can be suggested that the
Page 16 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
17
method 3 is more efficient and robust than method 2, irrespective of local variations and
threshold values.
Application of the Developed Methodology
The measured deflection data for a 200 km (125 miles) highway section at spacing of 200
m were used to demonstrate the application of the developed delineation methods. Figure
7a shows the peak deflection variations along the entire project. Using method 2, the
project is delineated into 8 uniform sections (see Figure 7b). On the other hand, when
method 3 is used the same project length is delineated into 7 uniform sections based on
the peak deflections (see Figure 8).
It can be seen from the deflection data along the length in Figure 8a that the peak
deflections show high variations between stations 840 to 1000. Since, method 2 is only
based on the mean difference of peak deflection for delineation; it is more sensitive to the
local variation and does not consider variations statistically. Thus it resulted in multiple
sections between the stations. However, method 3 considers the local variations in
deflections because of the application of statistical methods (95% confidence for the
mean difference), and thus is a more rational way of considering variability. Therefore,
there are only two uniform sections between the stations as compared to three given by
method 2.
In order to evaluate the practical implication of the delineation, effective
structural number (SNeff) was calculated for the project length based on deflections. The
Falling Weight Deflectometer (FWD) deflection data were analyzed for each station to
characterize the structural capacity. The effective pavement modulus (Ep) and SNeff were
determined using the peak deflection and pavement layer thicknesses data based on the
Page 17 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
18
AASHTO overlay design procedure (Huang 2004). For a known pavement thickness D,
the effective modulus Ep of pavement layers above the subgrade can be estimated using
Equation (7). The do is the deflection measured at the center of the load plate and q is the
pressure on the loading plate. The deflections at the sensor located 36 inch from the
center of the load (dr = 36 inches) were used to estimate the subgrade modulus (MR) by
using Equation (8). SNeff was calculated using Equation (9).
2
0
2
3
11
11
1.5
1
− + = +
+
R
Pp
RR
D
aM d
qa EED
Ma M
(7)
0.24
R
r
PM
d r= (8)
30.0045eff pSN D E= (9)
Table 2 shows the summary results for SNeff within each of the uniform section
determined based on methods 2 and 3. Assuming a required structural number (SNf) is
equal to 6 for this pavement based on the design traffic and subgrade modulus, the
structural number for an overlay (SNOL) can be determined. The SNeff for overlay design
was calculated based on 5th
percentile ( 2µ σ− ). This will ensure that only 5% of the
SNeff will be below the design value. Based on the results of delineation for method 2,
difference in the overlay thicknesses is 0.03 inch between sections 6 and 7. If one
assumes that 0.5 inch overlay thickness difference is practical for uniform sections
delineation from cost point of view, then delineation of sections 6 and 7 does not make
Page 18 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
19
practical sense. The delineation results based on method 3 show that sections 6 and 7
obtained from method 2 should be combined which also makes practically sense. It
should be noted that delineation of uniform sections based on method 3 show the
difference in overlay thicknesses for adjacent sections more than 0.5 inch.
DISCUSSION OF RESULTS
The results from different delineation approaches show that the number and boundaries
(i.e., change points) of homogeneous pavement sections may vary for a same project with
a single response measure. While the AASHTO (AASHTO 1993) approach for
delineation is simple and easy to use, it ignores the impact of local variations in the
response measure. In addition, one may need judgement to determine an effective
delineation based on visual inspection of the cumulative differences. However, the
approach can be adopted with caveats for different response parameters (e.g., IRI, rutting,
deflections, etc.). For an effective delineation methodology, the homogenous segments
should be based on the: (a) practical or operational aspects i.e., the mean difference in the
response parameter. Such consideration is essential when the uniform sections are to be
used for rehabilitation design or preservation treatment selections, (b) the procedure
should detect the local variations in the response parameter to reduce the risk of failure
and increase the reliability of the selected rehabilitation or preservation treatment, (c)
methodology should be robust and simple enough for practical application.
The new delineation methodology developed in this paper addresses most of the
above mentioned attributes. Two new approaches were developed and demonstrated for
delineating project length based on FWD deflection data. Method 2 used a mean
difference in peak deflections between adjacent sections to determine the change point
Page 19 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
20
while method 3 considered the mean differences which are tested statistically with 95%
confidence to consider the impact of local variability. Both methods are iterative and will
terminate when the entire project length ends.
The results of simulations for both developed algorithms show that:
1. The percentage of correct delineation depends on the threshold value (i.e., the
mean difference between adjacent sections) and local variability of deflections
within each homogenous section for method 2. For the simulated deflection data,
if the threshold is very low, the method fails to delineate correct number of
sections (i.e., will give higher number of uniform sections), especially when the
local variability is high. Similarly, a very high threshold will also result in higher
error in delineation (i.e., under predicts the number of sections).
2. Since, method 3 considers the local variations in deflections; it is more robust at
lower threshold values than method 2. However, it also under predicts for higher
threshold values.
From the above findings, it can be suggested that method 3 is more efficient and robust
than method 2, irrespective of local variations and threshold values. The selection of
mean difference of deflections (i.e., the threshold) between adjacent sections will depend
on the: (a) practical or operational significance of the mean difference for peak
deflection, (b) mean difference will also depend on the overall variability of deflections
along the project length. However, the mean difference practical magnitude will depend
on the response parameter to be considered for delineation (e.g., IRI, friction, rutting
etc.). The developed delineation methodology was applied to the FWD deflections
conducted on a highway project. The results of delineation show that method 3 was able
Page 20 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
21
to delineate the project length into appropriate homogenous sections which were found to
differ from each other from both statistical and practical viewpoints.
The developed delineation methods employed the restrictions: (a) a threshold for
the minimal length of resulting sections, and (b) minimal differences of arithmetic mean
values of resulting adjacent sections. In addition, method 3 uses two-sided t-tests to
assess the statistical significance of differences in mean values. At least two conceptual
problems are associated with t-testing as reported in the literature (Thomas 2004):
1. A standard t-test requires the measurements to be statistically independent
(conditionally on the common mean), something which is not the case for the
measurement series. These measurements typically exhibit pronounced first-order
autocorrelation, thus violating the assumptions in a standard t-test.
2. Applying t-tests repeatedly a large number of times in different parts of a long
measurement may associate such a procedure with problems of mass-
significance. In other words, the type I error rate (i.e., comparison-wise error rate
for the experiment) may be much larger than assumed value of 0.05.
It is true that spatial correlation will contribute to the violation of independence
assumption for a standard t-test. In pavements, the spatial autocorrelation will be a
concern for measurement series to characterize the surface characteristics such as IRI,
rutting, friction etc. However, for surface deflections (shows the pavement structural
capacity) such problem may not be as severe as some of the other surface characteristics.
In addition, minor violation of such assumption will not significantly change the
conclusions. In fact, the results of the demonstrative example from the field deflections
show that the method is robust enough to give meaningful statistical significance which
Page 21 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
22
passes the test of operational and practical significance. Further, the simulated deflections
data used to validate the developed methodology were generated as independent normally
distributed random variable; therefore, no spatial correlation is expected. It is also valid
that multiple mean comparisons can be susceptible to problem of mass-significance.
However, in the developed methodology, only two adjacent sections were considered for
statistical testing at a time i.e., the means from a single section was not compared with
different pavement sections at the same time. The authors feel that such mean
comparisons will not be significantly impacted by mass-significance.
CONCLUSIONS
More data along the length of a road are appropriate in quantifying the parameter
expected value and variability, however; if design is based on the data of a particular
parameter of the whole project length, it will lead to an uneconomical design. Therefore,
pavement surface and structural condition data along a long stretch of road needs to be
delineated into sections which are “relatively uniform”, referred to as homogeneous
sections and the design performed individually for each of these homogeneous sections.
This results in economical design without compromising reliability level.
The paper documents delineation methods that explicitly address the problem of
segmentation of measurement series obtained from FWD deflections. Extensions
necessary to make the AASHTO delineation procedure a fully automatic method suitable
for the large amount of data are discussed. Modifications in the existing AASHTO
delineation procedure were incorporated to address the mean differences and the local
variability. The modified algorithms are documented along with examples to demonstrate
their accuracy and efficiency. Examples are presented to analyze the peak deflection data
Page 22 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
23
from actual field projects to demonstrate the application of the developed methodology.
The results of the analyses show that the AASHTO methodology (i.e. method 1) ignores
the local variations along the project length while delineating the homogenous sections.
Such delineated uniform sections may not be valid from a practical standpoint while
designing rehabilitation or preservation strategies. The results of method 2 are better than
those of the AASHTO method but method 2 could be sensitive to local variations of the
deflections within a section. Since, method 3 also considers the local variations of
deflections while delineating the deflection data; it can overcome the problem of local
variations within a section. The simulation results confirmed that the method 3 is more
efficient and robust than method 2, irrespective of local variations and threshold values.
When the developed delineation methods were applied to field deflections, the results
showed that method 3 is able to delineate the project length into appropriate homogenous
sections which were found to be different from each other from both statistical and
practical viewpoints.
REFERENCES
AASHTO (1993). "AASHTO Guide for Design of Pavement Structures, Appendix J:
Analysis Unit Delineation by Cumulative Differences." American Association of
State Highway and Transportation Officials, Washington, D.C.
AASHTO (2008). "Mechanistic-Empirical Pavement Design Guide: A Manual of
Practice: Interim Edition." American Association of State Highway and
Transportation Officials.
Page 23 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
24
Bennett, C. "Sectioning of Road Data for Pavement Management." Proc., 6th
International Conference on Managing Pavements, Brisbane, Australia, 19-24
October 2004.
Cafiso, S., and Di Graziano, A. (2012). "Definition of Homogenous Sections in Road
Pavement Measurements." Procedia-Social and Behavioral Sciences, 53, 1069-
1079.
Cuhadar, A., Shalaby, K., and Tasdoken, S. "Automatic Segmentation of Pavement
Condition Data using Wavelet transform." Proc., Electrical and Computer
Engineering, 2002. IEEE CCECE 2002. Canadian Conference on, IEEE, 1009-
1014.
El Gendy, A., and Shalaby, A. (2008). "Using Quality Control Charts to Segment Road
Surface Condition Data." Seventh International Conference on Managing
Pavement Assets.
El Gendy, A., Shalaby, A., and Eng, P. (2005). "Detecting Localized Roughness Using
Dynamic Segmentation." the First Annual Inter-University Symposium of
Infrastructure Management (AISIM).
Haider, S. W., Baladi, G. Y., Chatti, K., and Dean, C. M. (2010). "Effect of Pavement
Condition Data Collection Frequency on Performance Prediction." Transportation
Research Record (2153), 1, 67-80.
Haider, S. W., Chatti, K., Baladi, G. Y., and Sivaneswaran, N. (2011). "Impact of
Pavement Monitoring Frequency on Pavement Management System Decisions."
Transportation Research Record (2225), 1, 43-55.
Page 24 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
25
Haider, S. W., and Dwaikat, M. B. (2011). "Estimating Optimum Timings for Preventive
Maintenance Treatments to Mitigate Pavement Roughness." Transportation
Research Record, 2235, 43-53.
Haider, S. W., and Dwaikat, M. B. (2012). "Estimating Optimum Timings for Treatments
on Flexible pavements with Surface Rutting." Journal of Transportation
Engineering, 139(5), 485-493.
Huang, Y. H. (2004). Pavement Analysis and Design, Pearson–Prentice Hall, Upper
Saddle River, NJ.
Misra, R., and Das, A. (2003). "Identification of homogeneous sections from road data."
International Journal of Pavement Engineering, 4(4), 229-233.
Ping, W. V., Yang, Z., Gan, L., and Dietrich, B. (1999). "Development of procedure for
automated segmentation of pavement rut data." Transportation Research Record:
Journal of the Transportation Research Board, 1655(1), 65-73.
Thomas, F. (2003). "Statistical approach to road segmentation." Journal of transportation
engineering, 129(3), 300-308.
Thomas, F. (2004). "Generating Homogenous Road Sections Based on Surface
Measurements: Available Methods." 2nd Eurpean Pavement and Asset
Management Conference.
Thomas, F. (2005). "Automated road segmentation using a Bayesian algorithm." Journal
of transportation engineering, 131(8), 591-598.
Page 25 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
26
Table 1 Variables names and description
Variable Description of the variables
id = Field measured performance variable (e.g. peak deflection)
x∆ = Interval between each measured value
totn = Total number of measured points
meand = Over all mean of the total field measurements
iCS = Cumulative difference of the measured field variable (calculated using equation #)
TH = Mean difference of the measured performance between two adjacent homogeneous
sections. (1)
1p = Slope of the cumulative difference curve
(2)
1p = Slope of the cumulative difference curve
minL = Minimum length of a project
minn = Number of measurement points in minimum length.
λ = Reduction factor
1n = Starting point of a subsection
un = Last point on a subsection
minλ = Minimum reduction factor
Page 26 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
27
Table 2 Effect of delineation methods on SNeff
Sections
Method 2 Method 3
Average
SNeff
Std
SNeff CoV
SNeff for
Design
Average
SNeff
Std
SNeff CoV
SNeff for
Design
1 7.94 1.32 16.6% 5.307 7.94 1.32 16.6% 5.307
2 6.80 1.53 22.5% 3.741 7.00 1.53 21.9% 3.939
3 7.40 1.58 21.4% 4.237 7.34 1.55 21.1% 4.238
4 6.29 1.49 23.7% 3.312 6.25 1.48 23.7% 3.285
5 4.37 0.92 21.0% 2.541 4.37 0.92 21.0% 2.541
6 4.46 0.21 4.7% 4.043 4.64 0.36 7.8% 3.915
7 4.67 0.31 6.6% 4.057 5.08 0.47 9.2% 4.152
8 5.11 0.46 9.0% 4.192 - - - -
Page 27 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Haider and Varma
28
List of Figures
Fig. 1 AASHTO concept of cumulative difference approach (AASHTO 1993)
Fig. 2 Flow chart for method 2 (mean difference)
Fig. 3 Flow chart for method 3 (mean and variance differences)
Fig. 4 Example for comparing all delineation methods
Fig. 5 Impact of variability on delineation methods
Fig. 6 Impact of mean difference threshold and variability on delineation methods
Fig. 7 Example of delineating uniform section based on peak deflection (Method 2)
Fig. 8 Example of delineating uniform section based on peak deflection (Method 3)
Page 28 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
(a) Uniform response parameter
(b) Cumulative and average areas
(c) Cumulative area difference
Fig. 1 AASHTO concept of cumulative difference approach (AASHTO 1993)
Pavem
ent
Re
spon
se
Para
me
ter,
di
d1
d2
d3
x1 x2 x3=Lsx
dC
um
ula
tive
Are
a
x1 x2 x3=Lsx
xAxA
TA
x x xZ A A
x1 x2 x3=Lsx
xx
xZ
AA
0
(+)
(-)
Change Point
Change Point
Page 29 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Fig. 2 Flow chart for method 2 (mean difference)
End
YesNo
Start
Parameters: Measured data:
is a new
subsection
Yes
No
, ,i totd x n
minmin
Ln
x
2
1
1 totn
mean i
itot
d dn
1
i
i k mean
k
CS d i d
(1) (1)
1 ( )
:
i o i
l u
CS p p n
i n n
min
u
totn n n
(2) (2)
1
min
( )
:
i o i
u u
CS p p n
i n n n
min
(2) (1)
1 1| |p p TH
min
u un n n :l ui n n
min1,l un n n
u
totn n
min min, ,TH L
1
No
Yes
No
Yes
Page 30 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Fig. 3 Flow chart for method 3 (mean and variance differences)
End
Yes
No
Start
Parameters: Measured
data:
is a
new subsection
Yes
No
T-test
Similar meansdissimilar
means
2
, ,i totd x n
minmin
Ln
x
1
1 totn
mean i
itot
d dn
1
i
i k mean
k
CS d i d
(1) (1)
1 ( )
:
i o i
l u
CS p p n
i n n
min
u
totn n n min
u un n n :l ui n n
(2) (2)
1
min
( )
:
i o i
u u
CS p p n
i n n n
min
(2) (1)
1 1| |p p TH
min min, ,TH L
min1,l un n n
u
totn n
1
No
Yes
No
Yes
Page 31 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
Fig. 4 Example for comparing all delineation methods
0
10
20
30
40
50
0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800
De
fle
ctio
n, (m
ils)
Measurement point
Deflection data
Section means
Overall mean
0
5
10
15
20
25
30
35
-2000
-1500
-1000
-500
0
500
1000
0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800
De
fle
ctio
n, (m
ils)
Cu
mu
lative
su
m d
iffe
ren
ce,
(CS
D)
Measurement points
CS
Method 2
Method 3
Page 32 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
(a) CoV=10% (low variability)
(b) CoV=20% (medium variability)
(c) CoV=40% (high variability)
Fig. 5 Impact of variability on delineation methods
0
10
20
30
40
50
60
0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900 950 1000 1050 1100 1150 1200
Deflection
, (m
ils)
Measurement point
Deflection data
Section means
0
10
20
30
40
50
60
0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900 950 1000 1050 1100 1150 1200
De
flection
, (m
ils)
Measurement point
Deflection data
Section means
0
10
20
30
40
50
60
0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900 950 1000 1050 1100 1150 1200
De
fle
ctio
n, (m
ils)
Measurement point
Deflection data
Section means
Page 33 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
(a) Method 2 (mean difference)
(b) Method 3 (mean and variance difference)
Fig. 6 Impact of mean difference threshold and variability on delineation methods
0%
20%
40%
60%
80%
100%
0 2 4 6 8 10 12
Pe
rcen
t co
rre
ct
Threshold, (mils)
10
20
30
40
0%
20%
40%
60%
80%
100%
0 2 4 6 8 10 12
Pe
rcen
t co
rre
ct
Threshold, (mils)
10
20
30
40
Page 34 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
(a) Peak deflection
(b) Cumulative difference
Fig. 7 Example of delineating uniform section based on peak deflection (Method 2)
0 100 200 300 400 500 600 700 800 900 10000
10
20
30
40
50
Station number
De
fle
ctio
n (
mils)
0 100 200 300 400 500 600 700 800 900 1000-1200
-1000
-800
-600
-400
-200
0
200
400
Station number
Cu
mu
lative
diffe
ren
ce
(m
ils)
2 1 5 4 3 6 8 7
Page 35 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering
Draft
(a) Peak deflection
(b) Cumulative difference
Fig. 8 Example of delineating uniform section based on peak deflection (Method 3)
0 100 200 300 400 500 600 700 800 900 10000
10
20
30
40
50
Station number
De
fle
ctio
ns (
mils)
0 100 200 300 400 500 600 700 800 900 1000-1200
-1000
-800
-600
-400
-200
0
200
400
Station number
Cu
mu
lative
diffe
ren
ce
(m
ils)
1 2 3 4 5 6 7
Page 36 of 36
https://mc06.manuscriptcentral.com/cjce-pubs
Canadian Journal of Civil Engineering