Planning the AWA run schedule
1. Do experiments as quickly as possible2. Deliver meaningful results
Goals of this discussion
(planning)
(priorities)
Improve communication & Clarify roles
Strategy
Timeline for Upgrades and Initial Experiments
Jul2012
Oct2012
Jan2013
Apr2013
Jul2013
Oct2013
Jan2014
commission first new linac tank & generate high charge bunch trains with new gun
civil construction, electrical, etc
move and flip witness gun
run experiments using witness beam
install & commission beamline switchyard
start experiments with new drive beam
install & commission more linac tanks
New linac tanks delivered 75 MeV beam
Presented to DOE: March 2013
AWA SUPPORT SYSTEMSAWA Facility – Condea) Overall Coordination & Schedule – Conde b) Utilities and infrastructure – Doranc) Vacuum/Beamline installation – Wisniewskid) Laser – Powere) 1.3 GHz LLRF – Jingf) Modulator/Klystron – Liu g) Diagnostic – Powerh) Cathode – Wisniewski i) Beamline Physics Design – Powerj) Beamline Mechanical Design – Doran k) Control system – Liu
System mini-group leader
AWA PROJECTS
• DL: High Q, 19 MeV Train (Measure: Current, Flatness)• DL: High Q, 75 MeV Single Bunch (Measure: charge,
energy, bunch length, emittance )• DL: High Q, 75 MeV Train, (Measure: Charge Flatness,
Energy Droop)• DL: 11.7GHz metallic wakefield power
extractor(16x60nC)• DL: 26GHz Dielectric Based Wakefield Power Extractor
with BBU solenoid (16x20nC)• WL: Ring beam and coaxial two channel structure • WL: EEX based bunch shaping• Many more…
*Each project is assigned a PI by Wei
High Q, 19 MeV Train
High Q, 75 MeV Single Bunch
High Q, 75 MeV Train
11.7GHz metallic PETS
26GHz Dielectric PETS
Experimental Schedule
Utilities and infrastructure
Vacuum/Beamline installation
Laser
1.3 GHz LLRF
Modulator/Klystron
Diagnostic
Beamline Physics Design
Beamline Mechanical Design
Control system
Match systems to projects
Experimental planning strategy
PI makes a to-do list
To-do list divided up into AWA SYSTEMS
AWA SYSTEMS lead makes a to-do list
AWA SYSTEMS lead gives job assignments
Wee
kly
open
mee
tings PI makes a to-do list
To-do list divided up into AWA SYSTEMS
AWA SYSTEMS lead makes a to-do list
AWA SYSTEMS lead gives job assignments
Wee
kly
open
mee
tings
1. Set Priorities2. Name a PI for a project3. Establish deliverables for the project
Wei
Meetings1. AWA group meeting
1. Frequency: Weekly2. Purpose: discuss plan for that week3. Participants: everyone
2. Project meetings (PI initiated)1. Frequency: As needed (weekly in begin) 2. Purpose: discuss plan for that week3. Participants: as required
3. System meetings (system lead initiated)1. Frequency: As needed (weekly in begin) 2. Purpose: discuss plan for that week3. Participants: as required
4. Priorities Meeting (called by Wei)1. Frequency: As needed?? Monthly?? Quarterly??2. Purpose: Are we going in the right direction? Review AWA schedule3. Participants: as required
PRIORITIES (highest level meeting)1. Demonstrate 1 GW2. Witness gun experiments
1. Ring beam2. coaxial two channel structure 2nd run
3. Demonstrate the high current drive beam in the new AWA drive beamline 4. Can we get 1 GW with minimal diagnostics. (deflecting cavity, emittance,
energy?)5. Purchase EEX equipment6. Clean and install EEX beamline7. Installation of LLRF feedback8. Improvement of Modulator9. Improvement of Control System10. Improvement of Multisplitter