Planning Package for Project

Embed Size (px)

Citation preview

COMMENTS RESOLUTION SHEET [ CRS ]CONTRACT NUMBER CONTRACT TITLE QP EXTERNAL TRANSMITTAL REFERENCE DOCUMENT NUMBER DOCUMENT TITLE EngineeringGC11106200

QP PROJECT NUMBER DATE DOCUMENT REVISION

3392

EPIC for new 16 Jet A1 Fuel pipeline from QP Refinery to BSV-3 EDL/GC11106200/EXT/TN/0107 3392-00-69-00-0003 The Planning Package 19/7/2012 5

No.1

QP COMMENTSEngineering plan submitted is not acceptable as the rate of deliverable submission to QP is un realistic. Contractor to review the rate of deliverable submission to QP, leveling to be carried out.

CONTRACTOR RESPONSEDone (EDR is part of the PMS)

Page 1 of 6

COMMENTS RESOLUTION SHEET [ CRS ]CONTRACT NUMBER CONTRACT TITLE QP EXTERNAL TRANSMITTAL REFERENCE DOCUMENT NUMBER DOCUMENT TITLE ScheduleGC11106200

QP PROJECT NUMBER DATE DOCUMENT REVISION

3392

EPIC for new 16 Jet A1 Fuel pipeline from QP Refinery to BSV-3 EDL/GC11106200/EXT/TN/0047 3392-00-69-00-0003 The Planning Package 19/7/2012 5

No.1

QP COMMENTSContractor is advised to review the critical path activities considered for the Pre comm and commissioning, It is unrealistic to assume all activities under the pre comm. and commissioning are activities are critical. No forced critical activities are allowed repeated comments were raised on the same subject Done

CONTRACTOR RESPONSE

2

Please clarify the duration allowed and basis of assumption for the pipeline precomm activities for 60 days??

Original duration of commissioning included in the schedule program according to:

contract Appendix A Page No 201 10.1 General (9.The operators shall provide coverage 24 hrs/day 7 days per week, for a duration of 60 days, working a 12 hour per day shift system)

3

On Plot Piping Tie in works at station area to be included in the schedule Done and construction verification sheet with wt factor

Page 2 of 6

COMMENTS RESOLUTION SHEET [ CRS ]CONTRACT NUMBER CONTRACT TITLE QP EXTERNAL TRANSMITTAL REFERENCE DOCUMENT NUMBER DOCUMENT TITLE ScheduleGC11106200

QP PROJECT NUMBER DATE DOCUMENT REVISION

3392

EPIC for new 16 Jet A1 Fuel pipeline from QP Refinery to BSV-3 EDL/GC11106200/EXT/TN/0047 3392-00-69-00-0003 The Planning Package 19/7/2012 5

No.4

QP COMMENTSOn Plot Piping Tie in works at station area to be included in the schedule Done and construction verification sheet with wt factor

CONTRACTOR RESPONSE

EPIC contractor is obliged to achieve the Mechanical completion and the Pre-commissioning & Commissioning for PL and all related facilities as per Appendix(H)

5

Response against the comments # 3 under the section schedule (Previous QP comments) is not acceptable, advised to provide the list of compliance/ non compliance (with dates) to the key events table in the appendix H in tabular format.

Achieving commencement of construction activation shall not start as appendix (H) demands finalizing the drawing of Route and Alignment sheets, which hasn't started yet due to Topography survey delay. Thus, PETROJET cannot start this activity at the date of Key events (completion date from the Effective Date (26-2-2012)

Page 3 of 6

COMMENTS RESOLUTION SHEET [ CRS ]CONTRACT NUMBER CONTRACT TITLE QP EXTERNAL TRANSMITTAL REFERENCE DOCUMENT NUMBER DOCUMENT TITLE Progress measurementsGC11106200

QP PROJECT NUMBER DATE DOCUMENT REVISION

3392

EPIC for new 16 Jet A1 Fuel pipeline from QP Refinery to BSV-3 EDL/GC11106200/EXT/TN/0047 3392-00-69-00-0003 The Planning Package 19/7/2012 5

No.1

QP COMMENTSProject handover and closeout activities such as built submission , dossier , closeout , ACS et are not appearing in the progress measurement system

CONTRACTOR RESPONSEDone and listed in the construction phase

Progress Curves and histogram

No.1

QP COMMENTSContractor has not provided the Late curves as per the item #2 under the section Progress Curves and histogram (Previous QP comments) Done

CONTRACTOR RESPONSE

Page 4 of 6

COMMENTS RESOLUTION SHEET [ CRS ]CONTRACT NUMBER CONTRACT TITLE QP EXTERNAL TRANSMITTAL REFERENCE DOCUMENT NUMBER DOCUMENT TITLEGC11106200

QP PROJECT NUMBER DATE DOCUMENT REVISION

3392

EPIC for new 16 Jet A1 Fuel pipeline from QP Refinery to BSV-3 EDL/GC11106200/EXT/TN/0047 3392-00-69-00-0003 The Planning Package 19/7/2012 5

No.Procurement

QP COMMENTS

CONTRACTOR RESPONSE

1

It is advised adopt the wt factor allowed for individual line item under the procurement based on the overall value of procurement rather than based upon long lead and other item individually ( however long lead /Bulk item category shall be retained as it is ) . It is noted in the Procurement Status Register that Bulk Progress scale is adopted for other items listed in the sheet, there are many of the items in the list cannot be considered as bulk items. Please clarify?

Done

2

Done

Page 5 of 6

COMMENTS RESOLUTION SHEET [ CRS ]CONTRACT NUMBER CONTRACT TITLE QP EXTERNAL TRANSMITTAL REFERENCE DOCUMENT NUMBER DOCUMENT TITLE ConstructionGC11106200

QP PROJECT NUMBER DATE DOCUMENT REVISION

3392

EPIC for new 16 Jet A1 Fuel pipeline from QP Refinery to BSV-3 EDL/GC11106200/EXT/TN/0047 3392-00-69-00-0003 The Planning Package 19/7/2012 5

No.

QP COMMENTSDone

CONTRACTOR RESPONSESome point was taken into consideration:

1

The Rate of ROW is 200m/Day because of ROW include that(Grading and compacting of the ROW and access road Response against the comment # 03 under the Construction including any fill and cutting of the existing ground & section(Previous QP comments) on production rate is not reasonable. reinstatement of other pipeline access tracks in the corridor It cannot be construed the standard production rate (200Mtrs) for all where used during the construction of the new pipelines & activities in the pipeline and prepare schedule, for eg. It is not removal of obstructions alone the ROW , Removal of appropriate to consider Survey, Row, the Pipeline line stringing rate obstructions shall be extended to include obstructions is 200 mtr / day. Contractor review this schedule accordingly. between pipelines and the new pipeline) Page No 80 Appendix(A) so that ROW does not include right of way only but include the previous demands. The rate of survey = 400 m/ Day The rate of stringing = 300 m/Day

Page 6 of 6

Page 1 of 266

EPIC FOR 16-36 KM JET A1 FUEL PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

REV 5

DATE

JULY 19,2012

DOUMENT TITLE

PLANNING PACKAGE

______________________________________ METHOD STATEMENT FOR PROJECT CONTROL ______________________________________

Page 2 of 266

EPIC FOR 16-36 KM JET A1 FUEL PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

REV 5

DATE

July 19,2012

DOUMENT TITLE

PLANNING PACKAGE

CONTENTS

1. METHOD STATEMENT FOR PROJECT CONTROL AND PROGRESS MEASUREMENT . 2. WORK BREAKDOWN STRUCTURE . 3. INTEGRATED PLANNING NETWORK . 4. MANPOWER SCHEDULE AND HISTOGRAM . 5. EQUIPMENT DEPLOYMENT . 6. PROGRESS MEASUREMENT SYSTEM (PMS) .

Project Overall Progress Measurement . Engineering Document Register (EDR) . Procurement Status Register (PSR) . Construction Progress Measurement . Pre-Commissioning & Commissioning Progress Measurement . The Optional Items Progress Measurement .

7. PROGRESS S-CURVES & TABLES .

Project Overall Progress S-Curve . Engineering Progress S-Curve Procurement Progress S-Curve. Construction Progress S-Curve. Pre-Commissioning & Commissioning Progress S-Curve. The Optional Items Progress S-Curve .

Page 3 of 266

EPIC FOR 16-36 KM JET A1 FUEL PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

REV 5

DATE

July 19,2012

DOUMENT TITLE

PLANNING PACKAGE

8. CONSTRUCTION VERIFICATION SHEET. 9. MARCHING CHART 10. CASH FLOW CURVE & TABLE . 11. INVOICING SYSTEM . 12. ATTACHMENT .

Daily Progress Report (DPR) Format . Weekly Progress Report (WPR) Format . Monthly Progress Report (MPR) Format .

Page 4 of 266

EPIC FOR 16-36 KM JET A1 FUEL PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

REV 5

DATE

July 19,2012

DOUMENT TITLE

PLANNING PACKAGE

1. Introduction This method statement outline the procedure and requirements of the progress measurement methodology and control for the project EPIC of 16" - 36 km Jet A1 Fuel Pipeline from the QP refinery to BSV-3 . 2. Purpose The purpose of this method statement is to ensure that the project schedule will be monitored and implemented on time without any delay according to appendix-H as the following dates : Contract Effective Date : Feb 26,2012 Achieve Mechanical Completion of Pipeline and all Facilities : Nov 25,2013. Milestone (1) : Achieve Commissioning of Pipeline and All Facilities : May 25,2014 . Complete Baseline Survey (Optional) : July 25,2014 Scheduled Project Completion :Aug 25,2014 (30-Months from the Effective Date) 3. Project Control 3.1 General Petrojet will develop comprehensive project control procedures and detailed plans based upon the Appendix-H of the contract and Appendix-D (Attachment D-3) of the contract . It is the responsibility of the project control to identify the scope of the work in complete details and project control will support the project in order to ensure its completion on time by the following functions : Highlight the Milestones for the project , highlight the interfaces of the project with others. Close coordination and monitoring of sub-contractors and suppliers progress of works for their scope through an agreed progress reporting mechanism . Detecting any obstacle which may affect the planned dates/cost, studying the situation, and determining both the best solution and any corrective action which will ensure that the baseline end date of the project is met without any deviation . Analysis Assuring that the project progress is occurring in accordance with the approved time schedule .

Page 5 of 266

EPIC FOR 16-36 KM JET A1 FUEL PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

REV 5

DATE

July 19,2012

DOUMENT TITLE

PLANNING PACKAGE

Using a specialized software Primavera Version 6.7 to provide electronic schedules that can be used in either electronic or printout forms to illustrate planning information, look ahead/behind schedules, etc.

Preparing a periodic reports to be submitted to the client management. Integrating all of the work to ensure the quality of the project.

Petrojet project control, as deliverables will issue ninety days lookahead schedule and within the time specified in the contract , will develop Comprehensive Project Planning Package which will form the basis for the monitoring of the works . The Planning Package will be submitted to QP for approval and once approved will be used as the basis of progress monitoring . To retain the consistency on progress reporting , the weight factors shall not be modified during the course of the contract . 3.2 Integrated Planning Network Petrojet project control will establish a comprehensive time schedule using primavera P6 . the schedule will be resource loaded . The total project schedule will be fully integrated showing all activities more than 1000 activities - related to engineering, procurement, construction, pre-commissioning, commissioning in addition to the optional items . The CPM network will include all aspects of the work and will be sufficiently detailed to the satisfaction of the QP representative . Detailed activities of the work/service will include all parties, vendors and sub-contractors necessary to complete the works . 3.3 Progress Measurement Petrojet project control will develop, maintain and update a computerized progress measurement system . the progress measurement system will enable monitoring and follow-up of progress (actual versus planned) for all activities performed by Petrojet. The progress will be calculated from the lowest control level and electronically rolled up to the upper levels . The progress basis shall be as the following : The engineering progress will be Milestone progress and based on the estimated manhours that will be related to the engineering document register (EDR). The procurement progress will be Milestone progress and based on the cost that will be related to the procurement status register (PSR) .

Page 6 of 266

EPIC FOR 16-36 KM JET A1 FUEL PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

REV 5

DATE

July 19,2012

DOUMENT TITLE

PLANNING PACKAGE

The construction progress will be based on the estimated man-hours/efforts that will be exported from Primavera time schedule to the progress control Excel sheets. The pre-commissioning and commissioning progress will be based on the manhours/efforts that will be exported from Primavera time schedule to the progress control Excel sheets . The progress of optional items (Laying new FOC, Kahrama option (1) and the Baseline survey) will be based on the man-hours/efforts that will be exported from Primavera time schedule to the progress control Excel sheets .

3.4 Weight Factors Level (1) weight factor will be as the following : Engineering Procurement Construction Pre commissioning & Commissioning Optional Items 5% 40 % 48 % 5% 2%

-----------------------------------------------------------------------------------------------------------------------------The Engineering progress chain milestones will be according to the contract as the following : Started Issued For QP Review (IFR) Issued For QP Approval (IFA) Issued as AFC with hold Issued Approved For Const. (AFC) Issue As Built 5% 35 % 25 % 20 % 10 % 5% Cumulative Cumulative Cumulative Cumulative Cumulative Cumulative 5% 40 % 65 % 85 % 95 % 100 %

-----------------------------------------------------------------------------------------------------------------------------The Procurement progress chain milestones will be as the following :A) Equipment 5% 5% 5% 15 % 10%Page 7 of 266

Issue MR for QP Approval Issue RFQ to Vendors Issue Purchase Order Vendor Drawing Approval Receipt of Filled SPIR

Cumulative Cumulative Cumulative Cumulative Cumulative

5% 10 % 15 % 30 % 40%

EPIC FOR 16-36 KM JET A1 FUEL PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

REV 5

DATE

July 19,2012

DOUMENT TITLE

PLANNING PACKAGE

Inspection Cleared and Factory Tested Ex-Works Delivery Material Received & Inspected at Site QP Inspected & cleared Material at Site All Spare Parts Recd &SPIR Completed B) Bulk Material Issue RFQ to Vendors Place Order For Bulk Material Material Delivery Ex-Works (50% of Qty) Material Delivery Ex-Works (90% of Qty) Material Received at Site (50% of Qty) Material Received at Site (90% of Qty) All Material Received 3.5 Progress S-Curves

20% 10 % 15 % 5% 10%

Cumulative Cumulative Cumulative Cumulative Cumulative

60 % 70 % 85 % 90 % 100 %

5% 10 % 15 % 10 % 10 % 30 % 20 %

Cumulative Cumulative Cumulative Cumulative Cumulative Cumulative Cumulative

5% 15 % 30 % 40 % 50 % 80 % 100 %

Project control will provide the progress S-Curves for different phases of the project and overall S-Curve derived from the information contained in the EDR & PSR & Construction progress measurement & Pre-commissioning and Commissioning progress measurement & the optional items progress measurement. 4. Progress Reporting 4.1 General Petrojet will report to QP on the progress of the work throughout the duration of the contract. The purpose of these reports is to apprise all parties involved regarding the comprehensive status of the project. The Daily reports will be submitted next day, Weekly reports will have the cut off date of last Thursday and will be issued each Sunday and the Monthly reports will have a cut off date of last Thursday of the month and will be submitted by first week of succeeding month. 4.2 Daily Reports The Daily Progress Report (DPR) will be submitted on daily basis through e-mail for the construction activities.

Page 8 of 266

EPIC FOR 16-36 KM JET A1 FUEL PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

REV 5

DATE

July 19,2012

DOUMENT TITLE

PLANNING PACKAGE

The reports will be generated from the day of commencement of ROW activity. This report will be indicating quantitative scope and the progress achieved daily and the cumulative progress in terms of quantity and percentage in addition to the planned quantity for each activity. The report will include the progress achieved in all disciplines in both pipeline and QP refinery. This report will indicate the weather conditions. 4.3 Weekly Reports The Weekly Progress Report (WPR) will be submitted covering all activities under each phase during the entire duration of the contract. The report will be generated on weekly basis with progress cut-off every Thursday. Hard and soft copy of this report will be officially submitted to QP. The contents of the WPR will be as per the Appendix D (Attachment 3 Clause 4.3). 4.4 Monthly Reports The Monthly Progress Report (MPR) will be submitted during the entire duration of the contract within 3 working days from the cut off date, Last weekly cut off-date in a calendar month will be treated as monthly as agreed with QP. The contents of the MPR will be as per the Appendix D (Attachment 3 Clause 4.6) . 4.5 Engineering Document Register The Engineering Document Register (EDR) will be submitted as part of the planning package. Once approved it will be used as the main tool for monitoring the progress of the engineering deliverables . Updated engineering document register (EDR) will be submitted along with the weekly progress report. The register will be updated on weekly basis with progress cut-off every Thursday. All deliverables will be listed and will be monitored as per agreed percentage weightings . The register will serve as a tool in registering, planning, tracking, monitoring, expediting and reporting the status of all engineering deliverables .

Page 9 of 266

EPIC FOR 16-36 KM JET A1 FUEL PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

REV 5

DATE

July 19,2012

DOUMENT TITLE

PLANNING PACKAGE

4.6 Procurement Status Register The Procurement Status Register (PSR) will be submitted as part of the planning package. Once approved it will be used as the main tool for monitoring the progress of all items related to the procurement phase . Updated procurement status register (PSR) will be submitted along with the weekly progress report. Two different sheets will be used for monitoring the long lead items and the Other items . The register will be updated on weekly basis with progress cut-off every Thursday . The register will indicate the important milestone stage from receipt of material requisition until the delivery of material at site . Agreed percentage weightings will be used throughout the duration of the project to monitor each progress . 4.7 Subcontracting Status Register Major subcontractors that will be mobilized for the entire project activities will be reported accordingly . Subcontractor company profile will be submitted for QP approval prior to site mobilization . 4.8 Construction Verification Sheet The Construction Verification Sheet will be submitted at the end of the month as supporting documents for the monthly invoice . The progress will be reviewed and approved by disciplined QP representative . This includes project activities, Man-hours for each activity , and Percentage weightings . 4.9 Project Close Out Report Petrojet will prepare and submit the Project close out report in line with the requirements laid down in the contract . The report will be based on all the data accumulated throughout the course of the project especially the lessons learnt and will be submitted to QP for future reference for upcoming QP projects . 5. Invoicing The monthly invoice will be prepared and issued based on the following : Invoice will be submitted on monthly basis . All the standard invoicing formats will be used .

Page 10 of 266

EPIC FOR 16-36 KM JET A1 FUEL PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

REV 5

DATE

July 19,2012

DOUMENT TITLE

PLANNING PACKAGE

The cut-off date of the monthly progress report will be used as the same cut-off date for the invoicing . Advanced copy of draft invoice will be submitted to QP by email prior to official issuance . The supported document for the monthly invoice will be the engineering document register, Procurement different Documents and the approved construction verification sheet . The monthly progress payment will be submitted to QP thru an official letter . 6. Cost Control The purpose of the Project Cost Control System is to provide the Project Manager with a status of the Project with respect to the financial budget . For this reason the cost control engineer will perform the following: Coordinate change control program, as required and initiate change identification and develop approximate cost impact to serve as decision making tool. Follow up with more detailed estimate to meet Project and contractual requirements. Maintain cost and commitment data to assist in forecasting. Monitor Sub-contractors costs. Update forecast for each subcontract as variances are identified through the change control program. Prepare monthly cost control report. 7. Project Calendar The Progress Review Meeting will be held on weekly basis on Monday . The Weekly Progress Report will be submitted every Sunday . The Monthly Progress Report will be submitted on the first Sunday of the month. The Monthly Invoice for the achieved works will be submitted during the first week of the month. Achieve Mechanical Completion of Pipeline and all Facilities : (21) Months. Milestone (1) : Achieve Commissioning of Pipeline and All Facilities : (27) Months . Scheduled Project Completion : (30) Months from the Effective Date

Page 11 of 266

EPIC FOR 16-36 KM JET A1 FUEL PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

REV 5

DATE

July 19,2012

DOUMENT TITLE

PLANNING PACKAGE

8. References Appendix A: Appendix B: Appendix D: Appendix F: Appendix H: Scope of Work. Schedule of Prices Administration Instruction FEED Drawings & Documents Contract Execution Plan

Page 12 of 266

EPIC FOR 16-36 KM JET A1 FUEL PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

REV 5

DATE

JULY 19,2012

DOUMENT TITLE

PLANNING PACKAGE

______________________________________ WORK BREAK DOWN STRUCTURE ______________________________________

Page 13 of 266

EPIC For 16"-36 Km Jet A1 Fuel Pipeline From QP Refinery To BSV-3Contract Number GC 11106200 Document Description Work Breakdown Structure Date July 19,2012 Issued For Review & Approval ETROJET

EPIC FOR 16" - 36 KM JET A1 FUEL PIPELINE FROM QP REFINERY TO BSV-3

100.00%

ENGINEERING 5.00%

PROCUREMENT 40.00%

CONSTRUCTION 48.00%

PRECOMMISSIONING & COMMISSIONING 5.00%

OPTIONAL 2.00%

LONG LEAD ITEMS 77.25%

BULK MATERIALS 22.75%

PIPELINE FROM QP REFINERY TO BSV-3 47.75%

QP REFINERY 46.88%

BSV-3 5.37%

GENERAL =4.65% PROCESS =6.42% LOSS PREVENTION =1.44% FIRE & GAS =6.77% PIPELINES =8.55% MECH/PIPING =10.76% INSTRUMENTATION =10.36% TELECOMMUNICATION =1.00% ELECTRICAL =16.88% CIVIL & STRUCTURAL =28.21% BUILDING & SERVICES =2.26% CATHODIC PROTECTION =2.70% ____________________________ TOTAL =100%

PIG LAUNCHER =1.44% EOT CRANE =2.27% JIB CRANE =0.62% MAINLINE PUMPS =28.33% BOOSTER PUMPS =15.75% SWITCHGEAR PANELS =12.11% DISTRIBUTIONBOARDS =0.31% UPS SYSTEM =1.18% CONTROL VALVE =2.73% ESD VALVE =0.57% ISOLATION VALVES =0.47% MOV =5.49% ALL OTHER VALVES =2.85% CORIOLLIS FLOWMETER =3.22% JUNCTION BOXES =1.29% FIRE DETECTORS =0.93% SCADA =16.79% TELECOM EQUIPMENS =0.33% LEAK DETECTION SYSTEM=3.31% ___________________________ TOTAL =100%

PIPES & FITTINGS =46.90% INSULATION JOINTS =0.95% STUD BOLTS, NUTS =0.36% LOCAL CONTROL PANELS =0.95% LIGTIING FIXTURES =1.93% ELECTRICAL CABLES =4.85% PRESSURE TRANSMITTERS=2.61% TEMP. TRANSMITTERS =0.33% INSTRUMENT CABLES =15.20% INST. CABLE ACCESSORI. =17.61% CORROSION MONITORI =0.72% TEMPORARY CP =1.90% PERMANENT CP =5.70% ___________________________ TOTAL =100%

STRAIGHT RUN =63.85% OPEN CUT CROSSING =8.43% HDD CROSSING =13.29% CATHODIC PRPTECT. =4.22% ANCHOR BLOCK = 1.90% HYDRAULIC TEST =4.75% COMMON ACTIVITIES=3.56% ________________________ TOTAL = 100%

CIVIL WORKS =49.64% MECH. WORKS =34.38% E&I WORKS = 15.98% ________________________ TOTAL = 100%

CIVIL WORKS =25.71% MECH. WORKS =18.57% E&I WORKS = 55.72% ________________________ TOTAL = 100%

Page 14 of 266

EPIC FOR 16-36 KM JET A1 FUEL PIPELINE FROM QP REFINERY TO BSV-3

DOC NO

3392-00-69-00-0003

CONTRACT NO: GC11106200

REV 5

DATE

JULY 19,2012

DOUMENT TITLE

PLANNING PACKAGE

______________________________________ INTEGRATED PLANNING NETWORK ______________________________________

Page 15 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EPIC For 16" - 36 Km Jet A1 Fuel PipelineGeneralMilestones

781 651 911

26-Feb-12 26-Feb-12 26-Feb-12 26-Feb-12

25-Aug-14 25-Aug-14 25-Aug-14

18-Jan-12 18-Jan-12 26-Feb-12 26-Feb-12

25-Aug-14 25-Aug-14 25-Aug-14

0 0 0 0

GCM1100 GCM1110 GCM1120

Contract Effective Date Milestone (1) : Achieve Commissioning Of Pipeline And All FacilitiesCompletion Date Scheduled

0 0 0 127 90 20 75 110

25-May-14 25-Aug-14 28-Mar-12 28-Mar-12 20-May-12 26-Aug-12 14-Jul-12 13-Jun-12 16-Apr-12 16-Apr-12 09-Jun-12 17-Jun-12 18-Jan-12 18-Jan-12 14-May-12 03-Jul-12 24-Jan-12

25-May-14 25-Aug-14 15-Sep-12 01-Aug-12 02-Jul-12 15-Sep-12 09-Sep-12 24-Jan-12 03-Jul-12 09-Sep-12 25-Aug-14

0 0 17 17 17 17 26 -31 49 26 563

Essential Documents to be Issued

GED1100 GED1110 GED1120Mobilization

Project Management Documents (PL. PKG.,HSE Plan,PQP,Etc.) Cost Break Down Government and Other Legal Authorities Permits to be Issued

29-May-12 26-Aug-12 04-Mar-12 04-Mar-12 07-Mar-12 05-Aug-12 07-Mar-12 26-Apr-12

GMOB1100 GMOB1110 GMOB1120Engineering Phase

Mobilization Of Key Personnel TCF To Be Established Mobilization For Labour & Equipment

3 36 48 193

29-May-12 05-Aug-12 27-Mar-12 06-Nov-12

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 16 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

General

114 Detailed Design Awarding to Penspen Penspen Team Mobilization Engineering Kick off Meeting Design Review Meeting 0 18 0 0 192 106 Site Visits / Data Collection Site Visit Report Design Basis Memorandum FEED Design Review Report Tie-in and Commissioning Philosophy 3 46 73 76 42 86 67 54

27-Mar-12 27-Mar-12 27-Mar-12 22-Apr-12 03-Sep-12 28-Mar-12 08-Apr-12 24-Apr-12 29-Apr-12 16-Apr-12 08-Apr-12 05-Jul-12

03-Sep-12

24-Jan-12 24-Jan-12

02-Aug-12

-22 -45

EGN-1000 EGN-1010 EGN-1080 EGN-1130Detail EngineeringCommon

19-Apr-12

24-Jan-12 19-Feb-12 02-Aug-12

16-Feb-12

-45 -45 -22

06-Nov-12 02-Sep-12 26-Apr-12 01-Jul-12 25-Jul-12 22-Jul-12 02-Sep-12

21-Feb-12 21-Feb-12 21-Feb-12 26-Feb-12 15-Mar-12 07-Mar-12 23-Sep-12 29-May-12 29-May-12 29-May-12

25-Aug-14 20-Nov-12 23-Feb-12 29-Apr-12 25-Jun-12 20-Jun-12 20-Nov-12 25-Aug-14 25-Aug-14 12-Aug-12

563 57 -45 -45 -22 -22 57 499 518 0

EGN-1020 EGN-1030 EGN-1040 EGN-1050 EGN-1110Process

29-May-12 25-Sep-12 29-May-12 29-Aug-12 29-May-12 12-Aug-12

Reports

EPR-1010 Steady State Hydraulic Analysis/Report

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 17 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EPR-1020 Transient/Surge Analysis Report EPR-1030 Operating Control and Safeguarding Philosophy EPR-1040 HAZOP & SIL Closeout Report EPR-1080 Instrument air consumption calculationProcess - Drawings

50 47 45 46 83 44 45 13 12 5 10 15 83 65 45

10-Jun-12 21-Jun-12 25-Jun-12 27-Jun-12 03-Jun-12 04-Jun-12 03-Jun-12 04-Jun-12 21-Jun-12 15-Aug-12 22-Aug-12 05-Sep-12 17-Jun-12 04-Jul-12 01-Aug-12

16-Aug-12 26-Aug-12 26-Aug-12 29-Aug-12 25-Sep-12 02-Aug-12 02-Aug-12 20-Jun-12 08-Jul-12 21-Aug-12 04-Sep-12 25-Sep-12 09-Oct-12 02-Oct-12 02-Oct-12

15-Jul-12 21-Aug-12 23-Jun-14 13-Sep-12 03-Jun-12 03-Jun-12 03-Jun-12 03-Jun-12 20-May-14 14-Jul-14 21-Jul-14 04-Aug-14 16-Aug-12 11-Sep-12 13-Sep-12

20-Sep-12 25-Oct-12 25-Aug-14 18-Nov-12 25-Aug-14 02-Aug-12 02-Aug-12 20-Jun-12 05-Jun-14 21-Jul-14 04-Aug-14 25-Aug-14 22-Nov-12 15-Nov-12 15-Nov-12

25 44 521 57 499 0 0 0 499 499 499 499 32 32 32

EPR-1100 Schematic Flow Diagrams EPR-1110 PFDs EPR-1120 P&IDs EPR-1130 -- Review by Company EPR-1140 -- Issue for HAZOP EPR-1150 -- HAZOP Comments Incorporated and re-issue EPR-1160 -- Receive approvalLoss Prevention

Lists/Schedules/Reports

ELP-1000 Fire Protection and Safety Philosophy

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 18 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

ELP-1010 Hazardous Area Schedule ELP-1020 Safety Equipment ListSpecifications

45 47 68 51 51 51 51 51 48 48 48 44 46 105 79

25-Jul-12 04-Jul-12 17-Jun-12 17-Jun-12 17-Jun-12 17-Jun-12 17-Jun-12 10-Jul-12 05-Aug-12 05-Aug-12 05-Aug-12 05-Aug-12 05-Aug-12 12-Jun-12 12-Jun-12

25-Sep-12 06-Sep-12 18-Sep-12 26-Aug-12 26-Aug-12 26-Aug-12 26-Aug-12 18-Sep-12 09-Oct-12 09-Oct-12 09-Oct-12 03-Oct-12 07-Oct-12 05-Nov-12 30-Sep-12

11-Sep-12 11-Sep-12 16-Aug-12 16-Aug-12 16-Aug-12 16-Aug-12 16-Aug-12 10-Sep-12 17-Sep-12 17-Sep-12 17-Sep-12 17-Sep-12 17-Sep-12 24-Jul-12 24-Jul-12

13-Nov-12 15-Nov-12 20-Nov-12 28-Oct-12 28-Oct-12 28-Oct-12 28-Oct-12 20-Nov-12 22-Nov-12 22-Nov-12 22-Nov-12 18-Nov-12 20-Nov-12 25-Aug-14 26-Dec-12

35 50 45 45 45 45 45 45 32 32 32 32 32 470 63

ELP-1030 Specs- Fire Protection ELP-1040 Specs - Safety Equipment ELP-1050 Specs - Hydrants & Related Accessories ELP-1060 Specs/Data Sheet Deluge System ELP-1070 Specs - F&G Detection SystemSafety & Loss Prevention - Drawings

ELP-1090 Fire Protection and Safety Equipment Layout - Pump ELP-1100 House Fire Protection and Safety Equipment Layout - Pig Launcher Area ELP-1130 Escape Evacuation Route Pump House ELP-1140 Escape Evacuation Route - Pig Launcher AreaF&G Detection System

Specifications

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 19 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EFG-1020 Specification for F & G Devices (Detectors & Alarm Devices) EFG-1030 Specifications for F&G System ( Modfication) EFG-1035 Specifications for FIRE Supression System ( Modfication) for HSSD system EFG-1040 SpecificationsData Sheets

47 48 41 41 70 49 49 49 49 44 49 49 49 52 42

12-Jun-12 03-Jul-12 05-Aug-12 05-Aug-12 14-Jun-12 14-Jun-12 14-Jun-12 14-Jun-12 14-Jun-12 22-Jul-12 14-Jun-12 14-Jun-12 14-Jun-12 13-Jun-12 13-Jun-12

15-Aug-12 06-Sep-12 30-Sep-12 30-Sep-12 19-Sep-12 21-Aug-12 21-Aug-12 21-Aug-12 21-Aug-12 19-Sep-12 21-Aug-12 21-Aug-12 21-Aug-12 23-Aug-12 09-Aug-12

24-Jul-12 27-Sep-12 30-Oct-12 30-Oct-12 26-Jul-12 26-Jul-12 26-Jul-12 26-Jul-12 26-Jul-12 16-Oct-12 26-Jul-12 12-Sep-12 12-Sep-12 25-Jul-12 25-Jul-12

27-Sep-12 04-Dec-12 26-Dec-12 26-Dec-12 17-Dec-12 03-Oct-12 03-Oct-12 03-Oct-12 03-Oct-12 17-Dec-12 03-Oct-12 20-Nov-12 20-Nov-12 25-Aug-14 23-Sep-12

31 63 63 63 63 31 31 31 31 63 31 65 65 522 31

EFG-1050 Flame Detectors EFG-1060 Manual Call Points EFG-1070 Smoke Detectors EFG-1080 Heat Detectors EFG-1090 HSSD system EFG-1100 Hydrogen Detectors EFG-1110 Beacons/Warning lights EFG-1120 HornsMaterial Requisitions

EFG-1130 MRs for F&G Devices (Detectors & Alarm Devices)

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 20 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EFG-1140 MRs for F&G System ( Modfication) EFG-1145 MRs for FIRE Supression System ( Modfication) EFG-1150 MRs for HSSD systemDocuments / Drawings

42 42 42 77 59 42 45 45 62 54 46 46 45 44 43

27-Jun-12 27-Jun-12 27-Jun-12 22-Jul-12 15-Aug-12 09-Sep-12 15-Aug-12 21-Aug-12 22-Jul-12 01-Aug-12 22-Jul-12 22-Jul-12 24-Jul-12 07-Aug-12 30-Jul-12

23-Aug-12 23-Aug-12 23-Aug-12 05-Nov-12 05-Nov-12 05-Nov-12 16-Oct-12 22-Oct-12 15-Oct-12 15-Oct-12 23-Sep-12 23-Sep-12 24-Sep-12 07-Oct-12 26-Sep-12

23-Sep-12 26-Jun-14 23-Sep-12 05-Aug-12 12-Sep-12 23-Sep-12 12-Sep-12 18-Sep-12 05-Aug-12 15-Aug-12 05-Aug-12 19-Aug-12 10-Jun-14 24-Jun-14 22-Jun-14

20-Nov-12 25-Aug-14 20-Nov-12 25-Aug-14 20-Nov-12 20-Nov-12 14-Nov-12 20-Nov-12 25-Aug-14 30-Oct-12 08-Oct-12 22-Oct-12 12-Aug-14 25-Aug-14 20-Aug-14

63 522 63 470 11 11 21 21 485 11 11 21 491 491 495

Common

EFG-1190F&G devices typical installation details EFG-1200 F&G cable schedule EFG-1210 F&G JB scheduleQP Refinery

EFG-1220 F&G Cause and Effect EFG-1230 F&G I/O schedule EFG-1240 Cable Block Diagrams EFG-1250 F&G Interconnection & Termination Diagrams EFG-1260 & G Loop Diagrams F EFG-1270 & G Devices Layout F (Detectors & Alarm Devices)

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 21 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EFG-1280 F&G Cable Routing Layout DrawingPipelines

43 160 160 0 0 0 50 42 56 36 51 50 33 50 58

02-Aug-12 28-Mar-12 28-Mar-12

01-Oct-12 06-Nov-12 06-Nov-12 03-Jun-12 06-Nov-12 19-Aug-12

25-Jun-14 14-Mar-12 14-Mar-12

25-Aug-14 20-Nov-12 20-Nov-12 10-May-12 20-Nov-12 09-Oct-12

495 10 10 -15 10 37 59 -10 82 82 82 82 82 82 90

Reports

EGN-1090 Receive Survey Data EGN-1100 Design Issue for Construction EGN-1120 Receipt of Soil Investigation Report EPL-1030 Pipeline Pigging Philosophy EPL-1040 SOW - Topographical SurveyCalculation

21-Jun-12 28-Mar-12 09-May-12 09-May-12 16-May-12 17-May-12 14-May-12 17-May-12 29-Apr-12

29-Aug-12 24-May-12 25-Jul-12 27-Jun-12 25-Jul-12 25-Jul-12 27-Jun-12 25-Jul-12 17-Jul-12

11-Sep-12 14-Mar-12 30-Aug-12 30-Aug-12 06-Sep-12 09-Sep-12 04-Sep-12 09-Sep-12 28-May-12

20-Nov-12 10-May-12 18-Nov-12 21-Oct-12 18-Nov-12 18-Nov-12 21-Oct-12 18-Nov-12 20-Nov-12

EPL-1050 Pipeline Wall Thickness Calculation EPL-1060 Upheaval Buckling Calculations EPL-1070 Elastic Bend Radius & Combined Stress EPL-1080 Pipeline Crossing Design Report EPL-1090 Pipeline Anchor Force CalculationSpecifications

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 22 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EPL-1110 Specifications for Electrical Isolation Joints EPL-1120 Specifications for Pipeline Barred Tees EPL-1130 Specifications for Hot Induction Bends EPL-1140 Specifications for Pipeline Valves EPL-1160 Specification for Pipeline fittings and flanges EPL-1170 Specification for Pig signallerData sheets

55 55 56 56 53 41 39 39 27 27 27 35 35 35 35

30-Apr-12 30-Apr-12 29-Apr-12 29-Apr-12 06-May-12 07-May-12 09-May-12 09-May-12 09-May-12 09-May-12 09-May-12 05-Jun-12 05-Jun-12 05-Jun-12 05-Jun-12

15-Jul-12 15-Jul-12 15-Jul-12 15-Jul-12 17-Jul-12 02-Jul-12 02-Jul-12 02-Jul-12 14-Jun-12 14-Jun-12 14-Jun-12 23-Jul-12 23-Jul-12 23-Jul-12 23-Jul-12

29-May-12 03-Jun-12 28-May-12 28-May-12 04-Jun-12 24-Sep-12 07-Jun-12 07-Jun-12 07-Jun-12 12-Jun-12 11-Jul-12 04-Jul-12 05-Aug-12 09-Jul-12 04-Jul-12

14-Aug-12 19-Aug-12 14-Aug-12 14-Aug-12 16-Aug-12 20-Nov-12 16-Aug-12 01-Aug-12 16-Jul-12 19-Jul-12 16-Aug-12 24-Sep-12 20-Sep-12 27-Aug-12 22-Aug-12

22 25 22 22 22 101 33 22 22 25 45 45 43 25 22

EPL-1200 Data Sheet for Hot Induction Bends EPL-1210 Data Sheet for Isolation Joints EPL-1220 Data Sheet for Pipeline Barred Tees EPL-1230 Data sheet for Pipeline Anchor FlangesMaterial Requisitions

EPL-1000 MR for Isolation Joints EPL-1010 MR for Pipeline Barred Tees EPL-1020 MR for Pipeline Anchor Flanges

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 23 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EPL-1100 MR for Pipeline Hot Bends EPL-1150 MR for Coating of Fittings EPL-1180 MR for Field Joint Coating

35 35 35

05-Jun-12 05-Jun-12 05-Jun-12 05-Jun-12 10-Jun-12 12-Jun-12 18-Jun-12 18-Jun-12 03-Jul-12 05-Jul-12 23-Jul-12 10-Jul-12 10-Jun-12 05-Jul-12 10-Jul-12

23-Jul-12 23-Jul-12 23-Jul-12 23-Jul-12 23-Sep-12 15-Aug-12 26-Aug-12 26-Aug-12 02-Sep-12 02-Sep-12 23-Sep-12 09-Sep-12 20-Aug-12 03-Sep-12 23-Jul-12

04-Jul-12 04-Jul-12 04-Jul-12 07-Aug-12 09-May-12 13-May-12 17-May-12 17-May-12 03-Jun-12 05-Jun-12 21-Aug-12 22-Aug-12 09-May-12 22-Jul-12 08-Aug-12

22-Aug-12 22-Aug-12 22-Aug-12 24-Sep-12 23-Oct-12 15-Jul-12 25-Jul-12 25-Jul-12 01-Aug-12 01-Aug-12 23-Oct-12 23-Oct-12 19-Jul-12 19-Sep-12 22-Aug-12

22 22 22 45 22 -22 -22 -22 -22 -22 22 32 -22 12 22

EPL-1190 MR for Pipeline 35 Flanges/Fittings/Gaskets/StudBolts Drawings 76 EPL-1280 Pipeline Overall Route Map EPL-1290 Key Plan Pipeline Route Map EPL-1300 Pipeline Routing Plan EPL-1310 Keyplan Pipeline Alignment Sheets EPL-1320 Pipeline Alignment Sheets EPL-1330 Pipeline Station Approach Drawing - Block Sectionalizing Valve Station (BSV3) EPL-1340 Pipeline Station Approach Drawing - QP Refinery EPL-1350 Typical Details EPL-1370 Crossing Matrix - Roads & 3rd Party ServicesMTO

46 50 50 44 42 45 44 52 43 10

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 24 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EPL-1250 Pipeline Material Take-OffMechanical / Piping

10 115 58 50 44 44 52 46 46 46 46 46 46 46 46

10-Jul-12 09-May-12

23-Jul-12 16-Oct-12

08-Aug-12 21-May-12 24-May-12 24-May-12 02-Jul-12 18-Sep-12 03-Jun-12 15-Jul-12 15-Jul-12 16-Jul-12 16-Jul-12 14-Jun-12 14-Jun-12 14-Jun-12 01-Jul-12

22-Aug-12 20-Nov-12 19-Nov-12 01-Aug-12 02-Sep-12 19-Nov-12 13-Aug-12 17-Sep-12 17-Sep-12 18-Sep-12 18-Sep-12 19-Aug-12 19-Aug-12 19-Aug-12 03-Sep-12

22 25 70 0 20 74 0 34 34 35 35 13 13 13 24

Specifications

24-May-12 13-Aug-12 24-May-12 01-Aug-12 05-Jun-12 07-Jun-12 03-Jun-12 29-May-12 29-May-12 29-May-12 29-May-12 29-May-12 29-May-12 29-May-12 29-May-12 05-Aug-12 07-Aug-12 13-Aug-12 31-Jul-12 31-Jul-12 31-Jul-12 31-Jul-12 31-Jul-12 31-Jul-12 31-Jul-12 31-Jul-12

EME-1000 Specs - Pumps EME-1010 Specs - Pig Launcher EME-1020 Spec for Surge Relief skid EME-1110 Piping Material Specifications EME-1120 Specs- Station CS Pipes EME-1130 Specs- CS Fittings and Flanges EME-1140 Specs- Nuts and Bolts EME-1150 Specs-Gaskets EME-1160 Specs - Gate Valves EME-1170 Specs - Ball Valves EME-1180 Specs - Globe Valves EME-1190 Specs - Check Valves

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 25 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J Data sheets

21-Jul-12 22:12

2014

93 49 43 40 40 47 42 42 42 42 42 44 109 45 41

03-Jun-12 17-Jun-12 11-Jun-12 10-Jun-12 11-Jun-12 05-Jun-12 07-Jun-12 03-Jun-12 07-Jun-12 07-Jun-12 07-Jun-12 09-Aug-12 14-May-12 21-May-12 13-Jun-12

09-Oct-12 22-Aug-12 08-Aug-12 02-Aug-12 05-Aug-12 08-Aug-12 05-Aug-12 30-Jul-12 05-Aug-12 05-Aug-12 05-Aug-12 09-Oct-12 11-Oct-12 22-Jul-12 08-Aug-12

10-Jun-12 09-Aug-12 20-Sep-12 10-Jun-12 11-Jun-12 02-Jul-12 10-Jul-12 15-Jul-12 25-Jun-12 10-Jul-12 16-Jul-12 17-Sep-12 21-May-12 15-Jul-12 24-Sep-12

20-Nov-12 17-Oct-12 20-Nov-12 02-Aug-12 05-Aug-12 05-Sep-12 06-Sep-12 11-Sep-12 22-Aug-12 06-Sep-12 12-Sep-12 18-Nov-12 20-Nov-12 16-Sep-12 20-Nov-12

30 40 74 0 0 20 24 31 13 24 28 28 28 40 74

EME-1030 Data sheet for EOT Crane EME-1040 Data sheet for Surge relief skid EME-1050 Datasheet for Main Transfer Pumps EME-1060 Datasheet for Booster Pumps EME-1070 Datasheet for Pig Launcher with Jib Crane EME-1200 Data Sheet for Gate Valves EME-1210 Data Sheet for Ball Valves EME-1220 Data Sheet for Globe Valves EME-1230 Data Sheet for Check Valves EME-1240 Data Sheet for Strainers EME-1250 Data Sheet for Special ItemsTechnical Requisitions

EME-1520 MR for EOT Crane EME-1530 MR for Surge relief skid

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 26 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EME-1540 MR for Main Transfer Pumps EME-1550 MR for Booster Pumps EME-1560 MR for Pig Launcher with Jib Crane EME-1570 MR for Gate Valves EME-1580 MR for Ball Valves EME-1590 MR for Globe Valves EME-1600 MR for Check Valves EME-1610 MR for Strainers EME-1620 MR for Special Items EME-1630 MR for CS station Pipes, Fittings & Flanges EME-1640 MR for Bolts, Nuts and GasketsPiping Calculations/Schedules/Reports

44 44 45 45 45 45 45 45 44 41 41 94 44 52 44

21-May-12 21-May-12 21-May-12 20-May-12 14-May-12 20-May-12 20-May-12 20-May-12 13-Aug-12 15-May-12 15-May-12 30-May-12 10-Jul-12 13-Jun-12 12-Jul-12

19-Jul-12 19-Jul-12 22-Jul-12 19-Jul-12 15-Jul-12 19-Jul-12 19-Jul-12 19-Jul-12 11-Oct-12 10-Jul-12 10-Jul-12 08-Oct-12 09-Sep-12 23-Aug-12 11-Sep-12

21-May-12 21-May-12 18-Jun-12 20-Jun-12 18-Sep-12 18-Sep-12 20-Jun-12 18-Sep-12 19-Sep-12 01-Jul-12 04-Jul-12 12-Jun-12 06-Aug-12 10-Jul-12 08-Aug-12

19-Jul-12 19-Jul-12 19-Aug-12 22-Aug-12 20-Nov-12 20-Nov-12 22-Aug-12 20-Nov-12 20-Nov-12 27-Aug-12 30-Aug-12 20-Nov-12 07-Oct-12 20-Sep-12 09-Oct-12

0 0 20 24 92 88 24 88 28 34 37 31 20 20 20

EME-1260 Line Schedule EME-1270 Equipment Schedule EME-1280 Valve Schedule

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 27 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EME-1290 Tie-in Schedule EME-1300 Pipe support Schedule EME-1320 Stress Analysis Report System1 EME-1321 Stress Analysis Report System2 EME-1322 Stress Analysis Report System3 EME-1330 Pipe wall Thickness Calculation EME-1331 Material Handling Study ReportDrawings

45 48 44 44 44 54 51 115 49 49 49 49 51 51 50

07-Jun-12 14-Jun-12 08-Aug-12 08-Aug-12 08-Aug-12

08-Aug-12 20-Aug-12 08-Oct-12 08-Oct-12 08-Oct-12

18-Sep-12 13-Sep-12 04-Sep-12 04-Sep-12 04-Sep-12 12-Jun-12 10-Sep-12 23-May-12 23-May-12 23-May-12 09-Jul-12 23-May-12 28-Jun-12 28-Jun-12 24-Jul-12

20-Nov-12 20-Nov-12 05-Nov-12 05-Nov-12 05-Nov-12 27-Aug-12 20-Nov-12 20-Nov-12 31-Jul-12 31-Jul-12 16-Sep-12 31-Jul-12 09-Sep-12 09-Sep-12 02-Oct-12

74 66 20 20 20 10 53 25 11 11 44 11 11 11 11

30-May-12 13-Aug-12 28-Jun-12 09-May-12 09-May-12 09-May-12 09-May-12 09-May-12 14-Jun-12 14-Jun-12 10-Jul-12 06-Sep-12 16-Oct-12 16-Jul-12 16-Jul-12 16-Jul-12 16-Jul-12 23-Aug-12 23-Aug-12 17-Sep-12

EME-1335 Overall Plot Plan - QP Refinery EME-1336 Overall Plot Plan BSV-3 EME-1340 Plot Plan - Jet A1 Pump House EME-1350 Plot Plan - BSV-3 EME-1360 Plot Plan - Pig Launcher Area EME-1410 Piping Key Plan QP Refinery EME-1420 Piping GA Jet A1 Pumps areaQP Refinery

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 28 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EME-1430 Piping GA Pig Launcher area QP Refinery EME-1440 Piping GA BSV-3 EME-1450 Piping GA Unit 32 - QP Refinery (Sector-31,32,39,40,41,42,20) EME-1460 Piping GA Unit 32 - QP Refinery (Demolition Sector 20) EME-1470 Piping GA - Deluge Piping System (1 to 4) EME-1480 Isometrics for above ground Piping EME-1490 Isometrics for underground piping EME-1500 Standard Pipe Support DetailsMTO

50 52 49 49 48 60 44 49 5 5 3 109 68

10-Jul-12 05-Jul-12 10-Jul-12 10-Jul-12 29-Jul-12 19-Jul-12 16-Aug-12 14-May-12 19-Jul-12 19-Jul-12 23-Jul-12 20-May-12

17-Sep-12 16-Sep-12 16-Sep-12 16-Sep-12 02-Oct-12 10-Oct-12 16-Oct-12 19-Jul-12 25-Jul-12 25-Jul-12 25-Jul-12 17-Oct-12

13-Aug-12 05-Aug-12 06-Aug-12 06-Aug-12 23-Aug-12 22-Aug-12 19-Sep-12 12-Sep-12 19-Aug-12 27-Aug-12 19-Aug-12 04-Jun-12 19-Jun-12 16-Jul-12 30-Jul-12

22-Oct-12 16-Oct-12 14-Oct-12 14-Oct-12 30-Oct-12 14-Nov-12 20-Nov-12 20-Nov-12 03-Sep-12 03-Sep-12 22-Aug-12 25-Aug-14 20-Dec-12 19-Sep-12 09-Oct-12

25 22 20 20 20 25 25 88 28 28 20 483 83 19 33

EME-1310 Piping Bulk MTO EME-1510 Valve MTOInstrumentation and Control

Specifications

24-May-12 27-Aug-12 20-Jun-12 14-Jun-12 23-Aug-12 23-Aug-12

EIN-1130 EIN-1140

Modification to PMS/UPS for Data Transfer to DCS/SCADA Specification for PLC/RTU System @ BSV-3 for 16" Jet A1 Fuel P/L.Critical Re... Milestone

47 51

Actual Work Remaining Work

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 29 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EIN-1150 EIN-1160 EIN-1170 EIN-1180 EIN-1190 EIN-1200 EIN-1210 EIN-1220 EIN-1230 EIN-1240 EIN-1250 EIN-1270 EIN-1280 EIN-1290 EIN-1292

Specification for Pressure Gauges Specification for Pressure & DP Transmitters Specification for Temperature Gauges Specification for Tempertaure Element & Transmitters Specification for ESD & On-Off Valves Specification for Electric Motor Operated Valves Specification for Mass Flow Meter & Flow Computer Specification for Safety Relief Valves Specification for Control Valves Specification for Pig Signallers Specification for Instrument,F&G,Control & Telecommunication Cables Specifications for conditioning monitoring system ( new UCP) interface ( as per design) Specifications for Leak Detection System Specification for DCS Specification for ESD

47 47 47 47 47 47 47 47 47 47 47 48 48 47 48

20-Jun-12 20-Jun-12 20-Jun-12 20-Jun-12 20-Jun-12 20-Jun-12 20-Jun-12 20-Jun-12 20-Jun-12 20-Jun-12 20-Jun-12 24-May-12 24-May-12 06-Jun-12 05-Jun-12

23-Aug-12 23-Aug-12 23-Aug-12 23-Aug-12 23-Aug-12 23-Aug-12 23-Aug-12 23-Aug-12 23-Aug-12 23-Aug-12 23-Aug-12 30-Jul-12 30-Jul-12 09-Aug-12 09-Aug-12

01-Jul-12 01-Jul-12 01-Jul-12 01-Jul-12 01-Jul-12 01-Jul-12 01-Jul-12 01-Jul-12 01-Jul-12 15-Jul-12 12-Aug-12 19-Jun-12 19-Jun-12 05-Jul-12 04-Jul-12

04-Sep-12 04-Sep-12 04-Sep-12 04-Sep-12 04-Sep-12 04-Sep-12 04-Sep-12 04-Sep-12 04-Sep-12 18-Sep-12 16-Oct-12 26-Aug-12 26-Aug-12 10-Sep-12 10-Sep-12

8 8 8 8 8 8 8 8 8 18 38 19 19 22 22

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 30 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EIN-1295 EIN-1300 EIN-1305Data Sheets

Specification for SCADA-RTU Specification for Instrument / Mech / Pneumatic hook ups and Mech/PneumaticElectrical hook Specification for Bulk material up and electrical bulk Material (Junction boxes and cable Data Sheet for Pressure & DP Gauges Data Sheet for Pressure & DP Transmitters Data Sheet for Temperature Element & Transmitters Data Sheet for Temperature Gauges Data Sheet for ESD Valves Data Sheet for Electric Moter Operated Valves Data Sheet for Mass Flow meter & Flow Computer Data Sheet for Safety Relief Valves Data Sheet for Pig Signallers Data Sheet for Control Valves

51 52 52 59 47 47 47 47 38 50 50 50 50 50 100

12-Jun-12 17-Jun-12 17-Jun-12

21-Aug-12 27-Aug-12 27-Aug-12

11-Jul-12 04-Oct-12 09-Oct-12 19-Jun-12 12-Aug-12 15-Aug-12 12-Aug-12 12-Aug-12 05-Jul-12 25-Jun-12 01-Aug-12 19-Jun-12 04-Jul-12 19-Jun-12 04-Jun-12

20-Sep-12 17-Dec-12 20-Dec-12 21-Oct-12 16-Oct-12 21-Oct-12 16-Oct-12 16-Oct-12 28-Aug-12 03-Sep-12 10-Oct-12 28-Aug-12 11-Sep-12 28-Aug-12 20-Nov-12

22 80 83 46 55 58 55 55 20 12 39 8 18 8 33

28-May-12 16-Aug-12 28-May-12 28-May-12 28-May-12 28-May-12 10-Jun-12 10-Jun-12 10-Jun-12 10-Jun-12 10-Jun-12 10-Jun-12 20-May-12 31-Jul-12 31-Jul-12 31-Jul-12 31-Jul-12 31-Jul-12 16-Aug-12 16-Aug-12 16-Aug-12 16-Aug-12 16-Aug-12 04-Oct-12

EIN-1310 EIN-1320 EIN-1330 EIN-1340 EIN-1350 EIN-1360 EIN-1370 EIN-1380 EIN-1390 EIN-1400

Material Requisitions

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 31 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EIN-1680 EIN-1690 EIN-1700 EIN-1710 EIN-1720 EIN-1730 EIN-1740 EIN-1750 EIN-1760 EIN-1770 EIN-1780 EIN-1790 EIN-1795 EIN-1800 EIN-1810

MR for Pressure Gauges MR for Pressure & DP Transmitters MR for Temperature Element & Transmitters MR for Temperature Gauges MR for ESD & On-Off Valves MR for Electric Moter Operated Valves MR for Mass Flow meter & Flow Computer MR for Safety Relief Valves MR for Pig Signallers MR for Control Valves MR for Instrument,F&G,Control & Telecommunication Cables MR for Instrument / Mech / Pneumatic hook ups and Mech/Pneumatichook up and MR for Electrical Bulk material electrical bulk Material (Junction boxes and cable glands MR for Leak Detection System MR for DCS

42 42 42 42 42 46 46 46 46 46 39 46 46 46 46

24-May-12 20-May-12 24-May-12 24-May-12 24-May-12 24-May-12 24-May-12 24-May-12 22-May-12 24-May-12 24-May-12 02-Aug-12 24-May-12 24-May-12 24-May-12

22-Jul-12 16-Jul-12 22-Jul-12 22-Jul-12 22-Jul-12 26-Jul-12 26-Jul-12 26-Jul-12 24-Jul-12 26-Jul-12 17-Jul-12 04-Oct-12 26-Jul-12 26-Jul-12 26-Jul-12

08-Aug-12 07-Aug-12 08-Aug-12 08-Aug-12 04-Jun-12 04-Jun-12 17-Jul-12 24-Jun-12 17-Jun-12 24-Jun-12 16-Jul-12 17-Sep-12 17-Sep-12 19-Jun-12 24-Jun-12

07-Oct-12 04-Oct-12 07-Oct-12 07-Oct-12 01-Aug-12 07-Aug-12 19-Sep-12 27-Aug-12 19-Aug-12 27-Aug-12 09-Sep-12 20-Nov-12 20-Nov-12 22-Aug-12 27-Aug-12

55 58 55 55 8 8 39 22 18 22 38 33 83 19 22

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 32 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EIN-1820 EIN-1825 EIN-1830

MR for ESD MR for SCADA-RTU

46 46 46 46 91 71 43 43 42 44 45 45 43 3 46

24-May-12 24-May-12 24-May-12 24-May-12 13-Jun-12 01-Jul-12 18-Jul-12 23-Jul-12 09-Aug-12 24-Jul-12 30-Jul-12 05-Aug-12 05-Aug-12 30-Jul-12 01-Jul-12

26-Jul-12 26-Jul-12 26-Jul-12 26-Jul-12 17-Oct-12 07-Oct-12 16-Sep-12 19-Sep-12 07-Oct-12 23-Sep-12 30-Sep-12 04-Oct-12 02-Oct-12 01-Aug-12 02-Sep-12

24-Jun-12 24-Jun-12 09-Jul-12 09-Jul-12 02-Aug-12 02-Aug-12 17-Sep-12 20-Sep-12 24-Sep-12 10-Sep-12 16-Sep-12 20-Sep-12 20-Sep-12 12-Sep-12 02-Aug-12

27-Aug-12 27-Aug-12 11-Sep-12 11-Sep-12 25-Aug-14 22-Nov-12 15-Nov-12 20-Nov-12 21-Nov-12 11-Nov-12 18-Nov-12 22-Nov-12 20-Nov-12 17-Sep-12 07-Oct-12

22 22 33 33 483 34 44 44 33 35 35 35 35 33 25

MR for Modification to PMS/UPS for Data Transfer to DCS/SCADA EIN-1840 MR for PLC/RTU System at BSV-3 for 16" Jet A1 Fuel Pipeline Documents / DrawingsCommon

EIN-1510 Instrument process hook-up Diagrams EIN-1520 Instrument Installation details EIN-1530 Interface Block Diagrams EIN-1540 Instrument Cable schedule EIN-1550 Instrument JB Schedule EIN-1555 JB Connection Diagram EIN-1560 Instrument and Instrument signal earthing EIN-1570 Instrument Bulk MTO EIN-1580 Overall Control System Architecture Diagram (Modification)Actual Work Remaining Work Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 33 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J QP Refinery

21-Jul-12 22:12

2014

91 52 48 49 52 48 44 44 42 43 43 43 43 90 44

13-Jun-12 13-Jun-12 18-Jul-12 26-Jun-12 01-Jul-12 18-Jul-12 23-Jul-12 23-Jul-12 16-Aug-12 15-Aug-12 24-Jul-12 20-Aug-12 20-Aug-12 13-Jun-12 13-Jun-12

17-Oct-12 23-Aug-12 23-Sep-12 02-Sep-12 10-Sep-12 23-Sep-12 20-Sep-12 20-Sep-12 14-Oct-12 14-Oct-12 20-Sep-12 17-Oct-12 17-Oct-12 16-Oct-12 13-Aug-12

13-Aug-12 13-Aug-12 02-Oct-12 22-Aug-12 27-Aug-12 13-Sep-12 07-Oct-12 05-Sep-12 01-Oct-12 30-Sep-12 17-Jun-14 03-Oct-12 23-Sep-12 23-Aug-12 23-Aug-12

17-Aug-14 24-Oct-12 09-Dec-12 30-Oct-12 07-Nov-12 20-Nov-12 06-Dec-12 06-Nov-12 28-Nov-12 28-Nov-12 17-Aug-14 03-Dec-12 21-Nov-12 25-Aug-14 24-Oct-12

477 44 55 42 42 42 55 33 33 33 496 33 25 484 52

EIN-1850 Cause and Effect Diagrams (As per SOW) EIN-1860 Alarm & Trip Schedule EIN-1870 Instrument Schedule EIN-1875 I/O Schedule DCS EIN-1878 I/O Schedule ESD EIN-1880 I/O Schedule SCADA-RTU EIN-1890 Instrumentation Cable Block Diagrams EIN-1900 Instrument Interconnection Wiring Diagram EIN-1910 Instrument Loop Diagrams EIN-1920 Instrument Location Layout EIN-1930 Instrument Cable Routing/Cable tray Layouts EIN-1940 Instrument Equipment Room Layouts (Modification Scope)BSV-3

EIN-2050 Cause and Effect Diagrams (As per SOW)

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 34 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EIN-2060 Alarm & Trip Schedule EIN-2070 Instrument Schedule EIN-2075 I/O Schedule DCS EIN-2078 I/O Schedule ESD EIN-2080 I/O Schedule SCADA-RTU EIN-2090 Instrumentation Cable Block Diagrams EIN-2100 Instrument Interconnection Wiring Diagram EIN-2110 Instrument Loop Diagrams EIN-2120 Instrument Location Layout EIN-2130 Instrument Cable Routing/Cable tray Layouts EIN-2140 Instrument Equipment Room Layouts (Modification Scope)Telecom

47 49 44 44 43 43 43 43 43 42 42 86 45 45 45

18-Jul-12 24-Jun-12 24-Jun-12 24-Jun-12 23-Jul-12 23-Jul-12 30-Jul-12 01-Aug-12 09-Aug-12 20-Aug-12 20-Aug-12 03-Jun-12 15-Jul-12 15-Jul-12 15-Jul-12

20-Sep-12 29-Aug-12 22-Aug-12 22-Aug-12 19-Sep-12 19-Sep-12 26-Sep-12 30-Sep-12 08-Oct-12 16-Oct-12 16-Oct-12 30-Sep-12 13-Sep-12 13-Sep-12 13-Sep-12

02-Oct-12 19-Sep-12 19-Sep-12 19-Sep-12 11-Oct-12 10-Sep-12 01-Oct-12 25-Oct-12 25-Jun-14 04-Oct-12 23-Sep-12 04-Jul-12 14-Aug-12 14-Aug-12 14-Aug-12

06-Dec-12 27-Nov-12 20-Nov-12 20-Nov-12 11-Dec-12 08-Nov-12 29-Nov-12 25-Dec-12 25-Aug-14 03-Dec-12 20-Nov-12 25-Aug-14 25-Aug-14 16-Oct-12 16-Oct-12

55 64 64 64 59 36 46 62 490 34 25 496 507 23 23

Specification

ETL-1010 Specifications for Existing TELECOM systems modifications for Existing ETL-1020 Specifications PA/GA systems modifications

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 35 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

ETL-1100 Specifications for BMS ,Acess control System and CCTVMaterial Requisitions

45 42 42 42 46 43 43 127 73 44 44 44 44 67 50

15-Jul-12 03-Jun-12 03-Jun-12 03-Jun-12 29-Jul-12 29-Jul-12 01-Aug-12 08-May-12

13-Sep-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Sep-12 25-Sep-12 30-Sep-12 02-Oct-12

23-Jun-14 04-Jul-12 04-Jul-12 04-Jul-12 17-Sep-12 17-Sep-12 20-Sep-12 23-May-12 23-May-12 28-May-12 28-May-12 01-Jul-12 09-Jul-12 23-May-12 28-May-12

25-Aug-14 30-Aug-12 30-Aug-12 30-Aug-12 20-Nov-12 15-Nov-12 20-Nov-12 25-Aug-14 24-Sep-12 09-Sep-12 26-Jul-12 29-Aug-12 09-Sep-12 23-Aug-12 05-Aug-12

507 23 23 23 37 37 37 593 25 40 9 33 40 9 9

ETL-1000 MRs for Existing TELECOM systems/Network modifications ETL-1070 MRs for Existing PA/GA systems modificationsDrawing/Matrix

ETL-1030 Overall TELECOM system cable block diagram ETL-1040 BSV-3 PA/GA (Telephone) system modificationElectrical

Specifications

10-May-12 20-Aug-12 15-May-12 15-May-12 15-May-12 15-May-12 15-Jul-12 15-Jul-12 15-Jul-12 15-Jul-12

Common

EEL-1000Specification for Electrical Bulk Materials EEL-1120Specification for Distribution Boards EEL-1530Specification for Electrical Power, Control & Earthing Cables QP Refinery EEL-1540Specification for 11KV & 3.3KV Switchboard Modifications

10-May-12 12-Aug-12 15-May-12 23-Jul-12

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 36 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EEL-1550Specification for 415V Switchboard Modifications EEL-1570Specification for Interposing relay panel EEL-1580Specification for 110V AC UPS EEL-1590Specification for HV MotorsBSV-3

42 42 41 41 43 43 43 84 42 42 42 70 45 43 43

14-Jun-12 14-Jun-12 10-May-12 13-May-12 21-Jun-12 21-Jun-12 21-Jun-12

12-Aug-12 12-Aug-12 05-Jul-12 08-Jul-12 20-Aug-12 20-Aug-12 20-Aug-12

26-Jun-12 26-Jun-12 23-May-12 24-May-12 25-Jul-12 25-Jul-12 25-Jul-12 10-Jun-12 05-Jul-12 23-Sep-12 05-Jul-12 10-Jun-12 08-Jul-12 23-Jul-12 10-Jun-12

23-Aug-12 23-Aug-12 18-Jul-12 19-Jul-12 24-Sep-12 24-Sep-12 24-Sep-12 20-Nov-12 20-Nov-12 20-Nov-12 02-Sep-12 19-Sep-12 06-Sep-12 19-Sep-12 08-Aug-12

9 9 9 9 25 25 25 85 90 90 33 27 38 27 21

Option-1

EEL-1600 Specification for 415V Switchboard modificaion (Option-1 Kahrama connection) Data SheetsCommon

08-May-12 13-Aug-12 21-May-12 21-May-12 21-May-12 17-Jul-12 17-Jul-12 17-Jul-12

EEL-1080Data Sheet for Power, Control and Earthing Cable EEL-1110Data Sheet for Distribution BoardsQP Refinery

08-May-12 13-Aug-12 15-May-12 14-Jun-12 13-May-12 16-Jul-12 13-Aug-12 10-Jul-12

EEL-1070Data Sheet for 11 & 3.3 KV Switchgear Modification EEL-1630Data Sheet for 415V Switchboard Modifications EEL-1640Data Sheet for 110V AC UPS

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 37 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EEL-1650Data Sheet for 11KV Motors EEL-1660Data Sheet for 3.3KV MotorsBSV-3

43 43 0 71 44 44 48 44 44 42 42 42 42 97 97

08-May-12 08-May-12

05-Jul-12 05-Jul-12

23-Jul-12 10-Jul-12

19-Sep-12 06-Sep-12

54 45 0

Material Requisitions

16-May-12 22-Aug-12 23-May-12 23-May-12 16-May-12 22-May-12 16-May-12 26-Jun-12 26-Jun-12 26-Jun-12 26-Jun-12 23-Jul-12 23-Jul-12 22-Jul-12 22-Jul-12 16-Jul-12 22-Aug-12 22-Aug-12 22-Aug-12 22-Aug-12

13-Jun-12 09-Jul-12 09-Jul-12 13-Jun-12 28-Jun-12 13-Jun-12 23-Sep-12 23-Sep-12 23-Sep-12 26-Jun-14 15-Jul-12 23-Aug-12

25-Aug-14 06-Sep-12 06-Sep-12 28-Aug-12 28-Aug-12 14-Aug-12 25-Aug-14 25-Aug-14 20-Nov-12 25-Aug-14 22-Jan-13 22-Jan-13

523 33 33 27 27 21 523 523 64 523 84 84

Common

EEL-1700MR for Distribution BoardsQP Refinery

EEL-1710MR for 11KV, 3.3KV & 415V Switchboard Modifications EEL-1720MR for 110V AC UPSBSV-3

Option-1

EEL-1730 for 415V Switchboard MR modificaion (Option-1 Kahrama connection) Switchboard EEL-1920 for 415V MR modificaion (Substation 6003)Calculations/Reports

15-May-12 26-Sep-12 15-May-12 26-Sep-12

QP Refinery

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 38 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EEL-1010Cable Sizing EEL-1030Lighting Calculations EEL-1040UPS/Battery Sizing Calculations EEL-1050Power system study EEL-1060Protection co-ordination studyBSV-3

43 43 43 43 49 58 45 44 82 52 43 44 45 5 44

26-Jun-12 22-Jul-12 15-May-12 30-Jul-12 20-May-12 12-Jun-12 12-Jun-12 02-Jul-12

23-Aug-12 18-Sep-12 12-Jul-12 26-Sep-12 25-Jul-12 30-Aug-12 13-Aug-12 30-Aug-12

23-Aug-12 16-Sep-12 09-Sep-12 22-Nov-12 12-Sep-12 15-Jul-12 15-Jul-12 15-Aug-12 04-Jul-12 12-Aug-12 12-Aug-12 15-Aug-12 29-Aug-12 29-Aug-12 23-Aug-12

22-Oct-12 14-Nov-12 07-Nov-12 22-Jan-13 20-Nov-12 16-Oct-12 13-Sep-12 16-Oct-12 20-Nov-12 20-Nov-12 10-Oct-12 16-Oct-12 30-Oct-12 04-Sep-12 23-Oct-12

42 41 84 84 84 33 23 33 47 53 33 33 38 25 38

EEL-1760Cable Sizing Calculation EEL-1770Lighting CalculationLists/Schedules

24-May-12 16-Sep-12 27-Jun-12 27-Jun-12 02-Jul-12 08-Jul-12 25-Jul-12 02-Jul-12 06-Sep-12 26-Aug-12 30-Aug-12 06-Sep-12 31-Jul-12 30-Aug-12

QP Refinery

EEL-1125Electrical load list EEL-1130Electrical Equipment List EEL-1140Electrical Cable Schedule EEL-1150Electrical Bulk MTO EEL-1160Electrical Tie-in Schedule

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 39 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EEL-1190DB SchedulesBSV-3

45 82 44 45 45 5 45 45 101 46 98 98 43 43 43

08-Jul-12

06-Sep-12

18-Sep-12 04-Jul-12 04-Jul-12 18-Sep-12 26-Aug-12 02-Sep-12 26-Jul-12 18-Sep-12 18-Jul-12 19-Jul-12 18-Jul-12 18-Jul-12 25-Sep-12 30-Sep-12 03-Oct-12

20-Nov-12 20-Nov-12 03-Sep-12 20-Nov-12 25-Oct-12 06-Sep-12 26-Sep-12 20-Nov-12 03-Dec-12 20-Sep-12 03-Dec-12 03-Dec-12 25-Nov-12 28-Nov-12 03-Dec-12

53 47 29 66 29 29 29 63 44 20 47 47 47 47 47

24-May-12 16-Sep-12 24-May-12 19-Jun-12 16-Jul-12 23-Jul-12 17-Jun-12 24-Jun-12 15-May-12 21-Jun-12 24-Jul-12 20-Aug-12 16-Sep-12 29-Jul-12 16-Aug-12 23-Aug-12 02-Oct-12 23-Aug-12

EEL-1780Electrical load list EEL-1790Electrical Equipment List EEL-1800Electrical Cable Schedule EEL-1810Electrical Bulk MTO EEL-1820Electrical Tie-in Schedule EEL-1830DB SchedulesDrawings/Layouts

EEL-1290 Typical Installation DetailsSLD

15-May-12 27-Sep-12 15-May-12 27-Sep-12 23-Jul-12 26-Jul-12 31-Jul-12 19-Sep-12 24-Sep-12 27-Sep-12

QP Refinery

EEL-1200 11KV SLD EEL-1210 3.3KV SLD EEL-1220 415V SLD

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 40 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EEL-1230 110V AC UPS SLD EEL-1240 MOV DB SLD-Pump House EEL-1250 SLD modification- SER 12 LPN Extension EEL-1260 MOV DB-Pig Launcher area EEL-1270 - Pig Launcher area LPN EEL-1280 SLD - Pump house LPNBSV-3

49 45 43 45 43 43 46 46 46 44 44 73 71 46 44

15-May-12 28-May-12 10-Jul-12 03-Jun-12 15-Jul-12 18-Jul-12 05-Jul-12 05-Jul-12 05-Jul-12 15-Jul-12 15-Jul-12 21-Jun-12 25-Jun-12 24-Jul-12 24-Jul-12

22-Jul-12 29-Jul-12 06-Sep-12 02-Aug-12 11-Sep-12 16-Sep-12 06-Sep-12 06-Sep-12 06-Sep-12 12-Sep-12 12-Sep-12 01-Oct-12 01-Oct-12 25-Sep-12 23-Sep-12

18-Jul-12 31-Jul-12 12-Sep-12 06-Aug-12 17-Sep-12 20-Sep-12 11-Sep-12 11-Sep-12 17-Sep-12 19-Sep-12 19-Sep-12 24-Jul-12 09-Aug-12 28-Aug-12 30-Aug-12

25-Sep-12 02-Oct-12 12-Nov-12 08-Oct-12 15-Nov-12 20-Nov-12 20-Nov-12 14-Nov-12 20-Nov-12 20-Nov-12 20-Nov-12 20-Nov-12 20-Nov-12 30-Oct-12 30-Oct-12

47 47 47 47 47 47 53 49 53 49 49 36 36 25 27

EEL-1840 415V SLD EEL-1850 SLD - Plant area LPNStation-T1

EEL-1870 SLD modification DBLayouts

QP Refinery

EEL-1300 Cable Routing Layout - Pump House/SS/SER-12 EEL-1310 Cable Routing Layout - Pig Launcher area

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 41 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EEL-1320 Earthing Layout - Plump House/SS/SER-12 EEL-1330 Earthing Layout - Pig Launcher area EEL-1340 Lighting Layout - Pump House EEL-1350 Lighting Layout - Pig Launcher area EEL-1360 Lighting Layout-SER 12 Extension EEL-1370 Lightning Protection Layout-SER 12 Extension EEL-1380 Equipment Layout modification-S/S 6003 EEL-1390 Equipment Layout-SER 12 ExtensionBSV-3

44 44 44 44 44 44 45 45 52 44 45 42 43 43 45

01-Aug-12 30-Jul-12 25-Jul-12 25-Jul-12 25-Jul-12 08-Jul-12 15-Jul-12 25-Jun-12 04-Jul-12 15-Jul-12 15-Jul-12 04-Jul-12 21-Jun-12 21-Jun-12 01-Aug-12

01-Oct-12 27-Sep-12 24-Sep-12 24-Sep-12 24-Sep-12 05-Sep-12 13-Sep-12 26-Aug-12 13-Sep-12 12-Sep-12 13-Sep-12 30-Aug-12 20-Aug-12 20-Aug-12 02-Oct-12

19-Sep-12 19-Sep-12 19-Sep-12 19-Sep-12 19-Sep-12 19-Sep-12 12-Sep-12 09-Aug-12 15-Aug-12 15-Aug-12 29-Aug-12 20-Aug-12 24-Jul-12 24-Jul-12 18-Sep-12

20-Nov-12 20-Nov-12 20-Nov-12 20-Nov-12 20-Nov-12 20-Nov-12 14-Nov-12 11-Oct-12 31-Oct-12 15-Oct-12 31-Oct-12 17-Oct-12 20-Sep-12 20-Sep-12 20-Nov-12

36 38 41 41 41 54 44 34 34 23 34 34 23 23 35

EEL-1400 Cable Routing Layout EEL-1410 Earthing Layout EEL-1420 Lighting LayoutStation-T1

EEL-1445 Cable Routing Layout (Station T1)Area classification drawings

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 42 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EEL-1880Hazardous Area Classifications QP Refinery EEL-1890Hazardous Area Classifications BSV-3Protection & Control Schematics

45 44 44 44 192 52

01-Aug-12 01-Aug-12 22-Jul-12 22-Jul-12 28-Mar-12 06-May-12 06-May-12 08-May-12 08-May-12 08-May-12 16-May-12 16-May-12 28-Mar-12 28-Mar-12 27-May-12

02-Oct-12 01-Oct-12 19-Sep-12 19-Sep-12 06-Nov-12 16-Jul-12 02-Jul-12 08-Jul-12 08-Jul-12 08-Jul-12 16-Jul-12 16-Jul-12 27-May-12 27-May-12 15-Oct-12

18-Sep-12 19-Sep-12 19-Sep-12 19-Sep-12 17-May-12 03-Jun-12 03-Jun-12 05-Jun-12 05-Jun-12 05-Jun-12 13-Jun-12 13-Jun-12 17-May-12 17-May-12 11-Jun-12

20-Nov-12 20-Nov-12 20-Nov-12 20-Nov-12 27-Dec-12 14-Aug-12 31-Jul-12 06-Aug-12 06-Aug-12 06-Aug-12 14-Aug-12 14-Aug-12 17-Jul-12 17-Jul-12 20-Nov-12

35 36 44 44 44 21 21 21 21 21 21 21 37 37 26

EEL-1910Scheme for HV motorsCivil and Sructural

Specifications

ECI-1000 ECI-1010 ECI-1020 ECI-1030 ECI-1040 ECI-1050Scope of Work

Specifications for Structural Steel Specifications for Fencing Specifications for Concrete Works Specifications for Earth works Specificaitons for Building & Architectural Works Specifications for Road and Paving Works

42 44 44 44 44 44 43

ECI-1140

Scope Of Work For Geotechnical Investigation

43 102

Typical Details / Calculations

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 43 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

ECI-1080 ECI-1090 ECI-1095 ECI-1096 ECI-1110 ECI-1120 ECI-1130 ECI-1150 ECI-1160

General Notes, Abbreviations & Symbols Typical & Standard Detail Drawings Typical Steel Platform Layout & Details Structural Calculation For Steel Platform Typical Structural Calculation For Light Pole Foundation Typical Structural Calculation For Anchor Block Typical Structural Calculation For Concrete Protection Slab Typical Structural Calculation For Pipeline Sleeper Typical Structural Calculation For Culverts

43 86 43 46 44 46 44 45 46 104 87 47 47 47 47

27-May-12 05-Jun-12 17-Jul-12 13-Aug-12 19-Jun-12 02-Jul-12 31-May-12 02-Jul-12 01-Jul-12 09-Jul-12 09-Jul-12 21-Aug-12 20-Aug-12 21-Aug-12 09-Jul-12

24-Jul-12 02-Oct-12 13-Sep-12 15-Oct-12 19-Aug-12 03-Sep-12 31-Jul-12 02-Sep-12 02-Sep-12 06-Nov-12 06-Nov-12 24-Oct-12 23-Oct-12 24-Oct-12 11-Sep-12

11-Jun-12 20-Jun-12 01-Aug-12 17-Sep-12 27-Aug-12 09-Sep-12 30-Jul-12 29-Aug-12 17-Sep-12 02-Aug-12 02-Aug-12 05-Sep-12 24-Oct-12 17-Sep-12 05-Sep-12

09-Aug-12 18-Oct-12 01-Oct-12 20-Nov-12 25-Oct-12 11-Nov-12 30-Sep-12 31-Oct-12 20-Nov-12 27-Dec-12 27-Dec-12 11-Nov-12 27-Dec-12 21-Nov-12 11-Nov-12

12 12 12 26 49 49 43 43 57 44 37 12 47 20 43

Drawings & Calculations

QP Refinery

ECI-1180 Civil GA - Pump Area ECI-1190 Civil GA - Pig Launcher AreaECI-1200 Civil GA - Pipe Supports Location Plan ECI-1210 Pipe Supports - Sleepers

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 44 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

ECI-1220 Pipe Supports - T Posts ECI-1230 Pipe Supports - Portal Supports ECI-1240 Pipe Rack Details ECI-1250 Pipe Rack Foundation Details ECI-1260 Pig Launcher Foundation Details ECI-1270 Pig Trap & Jib Crane Foundation Details ECI-1280 Impact Wall Details ECI-1290 Pump Shed - Architectural Details ECI-1300 Pump Shed - Structural Details ECI-1310 Structural Calculation For Pipe Supports ECI-1320 Calculation For French Drain Refinery Area ECI-1380 SER12 - Demolition Details ECI-1390 SER12 - Architectural Details ECI-1400 SER12 - Foundation Details ECI-1410 SER12 - Structural Details

47 45 45 45 44 44 44 72 78 44 46 48 48 44 44

09-Jul-12 14-Aug-12 22-Aug-12 22-Aug-12 13-Aug-12 13-Aug-12 19-Aug-12 22-Jul-12 22-Jul-12 14-Aug-12 31-Jul-12 10-Jul-12 10-Jul-12 22-Jul-12 22-Jul-12

11-Sep-12 15-Oct-12 23-Oct-12 23-Oct-12 11-Oct-12 11-Oct-12 17-Oct-12 29-Oct-12 06-Nov-12 14-Oct-12 02-Oct-12 13-Sep-12 13-Sep-12 19-Sep-12 19-Sep-12

10-Sep-12 10-Sep-12 18-Sep-12 18-Sep-12 13-Sep-12 13-Sep-12 19-Sep-12 02-Aug-12 02-Aug-12 10-Sep-12 17-Sep-12 26-Aug-12 26-Aug-12 03-Oct-12 03-Oct-12

14-Nov-12 12-Nov-12 20-Nov-12 20-Nov-12 14-Nov-12 14-Nov-12 20-Nov-12 12-Nov-12 20-Nov-12 11-Nov-12 20-Nov-12 31-Oct-12 31-Oct-12 04-Dec-12 04-Dec-12

46 20 20 20 24 24 24 10 10 20 35 34 34 54 54

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 45 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J BSV-3

21-Jul-12 22:12

2014

54 44 44 44 47 50 45 45 0 78 42 42 40 40 44

17-Jul-12 23-Jul-12 17-Jul-12 23-Jul-12 26-Jul-12 08-Aug-12 08-Aug-12 15-Aug-12

30-Sep-12 20-Sep-12 16-Sep-12 20-Sep-12 30-Sep-12 16-Oct-12 09-Oct-12 16-Oct-12

13-Sep-12 19-Sep-12 13-Sep-12 19-Sep-12 17-Oct-12 11-Sep-12 11-Sep-12 18-Sep-12

20-Dec-12 20-Nov-12 14-Nov-12 20-Nov-12 20-Dec-12 20-Nov-12 13-Nov-12 20-Nov-12

59 43 43 43 59 25 25 25 0

ECI-1330 Civil GA (BSV-3) ECI-1360 Pipe Supports - Sleepers (BSV-3) ECI-1370 Pipe Supports - T Posts (BSV-3) ECI-1470 Structural Calculation For Pipe supportsElevated Transformer near BSV-3 (Option-1)

ECI-1480 Foundation Details of Transformer ECI-1490 Calculations For Foundation Details of TransformerKahramaa Substation near BSV-3 (Option-2)

Building Services

12-Jun-12 18-Jun-12 18-Jun-12 20-Jun-12 20-Jun-12 12-Jun-12

27-Sep-12 14-Aug-12 14-Aug-12 14-Aug-12 14-Aug-12 12-Aug-12

25-Jul-12 25-Jul-12 25-Jul-12 29-Jul-12 29-Jul-12 02-Aug-12

20-Nov-12 23-Sep-12 23-Sep-12 23-Sep-12 23-Sep-12 03-Oct-12

38 28 28 28 28 38

Specification

EBS-1000 Building Services SpecificationMaterial Requisition

EBS-1100 MR for HVAC Equipments for SER-12 Building ExtensionCalculation

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 46 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

EBS-1010 HVAC Load CalculationDrawings

44 74 44 44 44 42 41 41 43 3 43 149 134 60 50

12-Jun-12 18-Jun-12 18-Jun-12 18-Jun-12 18-Jun-12 24-Jun-12 30-Jul-12 02-Aug-12 24-Jun-12 19-Aug-12 24-Jun-12 01-Apr-12 01-Apr-12 01-Apr-12 26-Jul-12

12-Aug-12 27-Sep-12 16-Aug-12 16-Aug-12 16-Aug-12 20-Aug-12 24-Sep-12 27-Sep-12 21-Aug-12 21-Aug-12 21-Aug-12 24-Oct-12 03-Oct-12 21-Jun-12 03-Oct-12

02-Aug-12 08-Aug-12 08-Aug-12 08-Aug-12 08-Aug-12 14-Aug-12 19-Sep-12 24-Sep-12 20-Sep-12 15-Nov-12 20-Sep-12 26-Jun-12 26-Jun-12 26-Jun-12 21-Aug-12

03-Oct-12 20-Nov-12 09-Oct-12 09-Oct-12 09-Oct-12 11-Oct-12 15-Nov-12 20-Nov-12 20-Nov-12 20-Nov-12 20-Nov-12 20-Nov-12 30-Oct-12 18-Sep-12 30-Oct-12

38 38 38 38 38 38 38 38 65 65 65 19 19 63 19

EBS-1020 SER-12 Building Extension HVAC Layout EBS-1030 SER-12 Building Extension HVAC Section and Miscellaneous Details EBS-1040 SER-12 Building Extension HVAC Schematic and Control EBS-1050 Flow Diagram Extension SER-12 Building Water Supply and Drainage Layout Notes and Symbols EBS-1060 Plumbing EBS-1070 Miscellaneous Plumbing DetailsSchedules / Lists

EBS-1080 SER-12 Building Extension HVAC MTO EBS-1090 SER-12 Building Extension HVAC Equipment ScheduleCathodic Protection

Reports/Calculations/Schedule

ECP-1000 Site Survey and Soil Resistivity Measurement ECP-1005 CP Design Report (including Calculations)

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 47 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 JSpecifications/SOW

21-Jul-12 22:12

2014

70 43 43 39 43 43 49 44 45 387 382 29 21 7 402

10-Jul-12 09-Aug-12 16-Aug-12 10-Jul-12 14-Aug-12 14-Aug-12 19-Aug-12 19-Aug-12 23-Aug-12 25-Apr-12 02-May-12 02-May-12

15-Oct-12 08-Oct-12 15-Oct-12 02-Sep-12 11-Oct-12 11-Oct-12 24-Oct-12 17-Oct-12 24-Oct-12 17-Oct-13 17-Oct-13 12-Jun-12

08-Aug-12 04-Sep-12 16-Sep-12 08-Aug-12 09-Sep-12 09-Sep-12 12-Sep-12 12-Sep-12 18-Sep-12 03-Apr-12 05-Jun-12 05-Jun-12 05-Jun-12 05-Jul-12 19-Aug-12

13-Nov-12 04-Nov-12 13-Nov-12 01-Oct-12 07-Nov-12 07-Nov-12 20-Nov-12 13-Nov-12 20-Nov-12 25-Nov-13 17-Nov-13 16-Jul-12 04-Jul-12 16-Jul-12 17-Nov-13

21 19 21 21 19 19 19 19 19 26 21 25 25 25 80

ECP-1020 CP Material Specification ECP-1030 CP Installation Specification (Installation Procedures) ECP-1040 SOW for CP SystemData Sheets

ECP-1010 CP Material Data sheetDrawings

ECP-1045 CP Detail drawings ECP-1050 CP Schematic DiagramProcurement PhaseLong Lead Items (Equipment)QP Supplied Free Issue Material

PP1100 PP1110Mechanical Items

16"- 36 KM Coated Pipes To Be Checked & Verified ( Abo Nakhla ) 16"- 36 KM Coated Pipes Ready For Transporting

02-May-12 31-May-12 03-Jun-12 23-Jul-12 12-Jun-12 29-Aug-13

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 48 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J Pig Launcher

21-Jul-12 22:12

2014

401 2 7 7 30 60 200 15 45 7 45 367 2 7 7

24-Jul-12 24-Jul-12 26-Jul-12 16-Aug-12 06-Sep-12 06-Oct-12 21-Oct-12

29-Aug-13 26-Jul-12 02-Aug-12 23-Aug-12 06-Oct-12 05-Dec-12 09-May-13

19-Aug-12 19-Aug-12 21-Aug-12 11-Sep-12 02-Oct-12 01-Nov-12 16-Nov-12 04-Jun-13 19-Jun-13 03-Aug-13 03-Oct-13 26-Sep-12 26-Sep-12 28-Sep-12 19-Oct-12

17-Nov-13 21-Aug-12 28-Aug-12 18-Sep-12 01-Nov-12 31-Dec-12 04-Jun-13 19-Jun-13 03-Aug-13 10-Aug-13 17-Nov-13 13-Oct-13 28-Sep-12 05-Oct-12 26-Oct-12

80 26 26 26 26 26 26 26 26 26 80 71 56 56 56

PLPL1100 Pig Launcher MR Approved PLPL1110 Pig Launcher RFQ to Vendors to be Issued PLPL1120 Pig Launcher Purchase Order PLPL1130 Pig Launcher Vendor Document Approved PLPL1140 Pig Launcher Receipt Of Filled SPIR PLPL1150 Pig Launcher Inspection Cleared & Factory Tested PLPL1160 Pig Launcher Ex. Work Delivery & FOB Complete PLPL1170 Pig Launcher Received at Site PLPL1180 Pig Launcher Inspected by QP at Site PLPL1190 Pig Launcher Spare Parts & SPIR's to be ApprovedEOT Crane

09-May-13 24-May-13 24-May-13 08-Jul-13 15-Jul-13 01-Aug-12 01-Aug-12 03-Aug-12 24-Aug-12 08-Jul-13 15-Jul-13 29-Aug-13 03-Aug-13 03-Aug-12 10-Aug-12 31-Aug-12

PLEO1100 EOT Crane MR Approved PLEO1110 EOT Crane RFQ to Vendors to be Issued PLEO1120 EOT Crane Purchase Order

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 49 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

PLEO1130 EOT Crane Vendor Document Approved PLEO1140 EOT Crane Receipt Of Filled SPIR PLEO1150 EOT Crane Inspection Cleared & Factory Tested PLEO1160 EOT Crane Ex. Work Delivery & FOB Complete PLEO1170 EOT Crane Material Received at Site PLEO1180 EOT Inspected by QP at Site PLEO1190 EOT Crane Spare Parts & SPIR's to be ApprovedJib Crane

30 60 180 15 45 7 45 367

31-Aug-12 30-Sep-12 15-Oct-12 13-Apr-13 28-Apr-13 12-Jun-13 19-Jun-13 23-Jul-12 23-Jul-12 25-Jul-12 15-Aug-12 22-Aug-12 21-Sep-12 06-Oct-12 04-Apr-13

30-Sep-12 29-Nov-12 13-Apr-13 28-Apr-13 12-Jun-13 19-Jun-13 03-Aug-13 25-Jul-13 25-Jul-12 01-Aug-12 22-Aug-12 21-Sep-12 20-Nov-12 04-Apr-13 19-Apr-13

26-Oct-12 25-Nov-12 10-Dec-12 08-Jun-13 23-Jun-13 07-Aug-13 29-Aug-13 07-Sep-12 07-Sep-12 09-Sep-12 30-Sep-12 07-Oct-12 06-Nov-12 21-Nov-12 20-May-13

25-Nov-12 24-Jan-13 08-Jun-13 23-Jun-13 07-Aug-13 14-Aug-13 13-Oct-13 13-Oct-13 09-Sep-12 16-Sep-12 07-Oct-12 06-Nov-12 05-Jan-13 20-May-13 04-Jun-13

56 56 56 56 56 56 71 80 46 46 46 46 46 46 46

PLJI1100 PLJI1110 PLJI1120 PLJI1130 PLJI1140 PLJI1150 PLJI1160

Jib Crane MR Approved Jib Crane RFQ to Vendors to be Issued Jib Crane Purchase Order Jib Crane Vendor Document Approved Jib Crane Receipt Of Filled SPIR Jib Crane Inspection Cleared & Factory Tested Jib Crane Ex. Work Delivery & FOB Complete

2 7 7 30 60 180 15

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 50 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J

21-Jul-12 22:12

2014

PLJI1170 PLJI1180 PLJI1190Pumps

Jib Crane Received at Site Jib Crane Inspected by QP at Site Jib Crane Spare Parts & SPIR's to be Approved

45 7 45 455 455 2 7 7 30 60 268 15 45 7 45

19-Apr-13 03-Jun-13 10-Jun-13 19-Jul-12 19-Jul-12 19-Jul-12 21-Jul-12 11-Aug-12 18-Aug-12 17-Sep-12 02-Oct-12 27-Jun-13 12-Jul-13 26-Aug-13 02-Sep-13

03-Jun-13 10-Jun-13 25-Jul-13 17-Oct-13 17-Oct-13 21-Jul-12 28-Jul-12 18-Aug-12 17-Sep-12 16-Nov-12 27-Jun-13 12-Jul-13 26-Aug-13 02-Sep-13 17-Oct-13

04-Jun-13 19-Jul-13 29-Aug-13 21-Jul-12 21-Jul-12 21-Jul-12 23-Jul-12 13-Aug-12 20-Aug-12 19-Sep-12 04-Oct-12 29-Jun-13 14-Jul-13 28-Aug-13 08-Sep-13

19-Jul-13 26-Jul-13 13-Oct-13 23-Oct-13 23-Oct-13 23-Jul-12 30-Jul-12 20-Aug-12 19-Sep-12 18-Nov-12 29-Jun-13 14-Jul-13 28-Aug-13 04-Sep-13 23-Oct-13

46 46 80 6 6 2 2 2 2 2 2 2 2 2 6

Main Transfer Pumps

PLMP1100 Main Transfer Pumps MR Approved PLMP1110 Main Transfer Pumps RFQ to Vendors to be Issued PLMP1120 Main Transfer Pumps Purchase Order PLMP1130 Main Transfer Pumps Vendor Document Approved PLMP1140 Main Transfer Pumps Receipt Of Filled SPIR PLMP1150 Main Transfer Pumps Inspection Cleared & Factory Tested PLMP1160 Main Transfer Pumps Ex. Work Delivery & FOB Complete PLMP1170 Main Transfer Pumps Received at Site PLMP1180 Main Transfer Pumps Inspected by QP at Site PLMP1190 Main Transfer Pumps Spare Parts & SPIR's to be Approved

Actual Work Remaining Work

Critical Re... Milestone

EPIC For 16" JET A1 FUEL PL FROM QP REFINERY

Date 19-Jul-12

Revision Rev(5)

Checked Y .Abdalshaf...

Approved

PETROJET CO

Page 51 of 266

EPIC For 16" - 36 Km Jet A1 FuelActivity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float 2012 2013 J Booster Pumps

21-Jul-12 22:12

2014

455 2 7 7 30 60 268 15 45 7 45 393 357 2 7

19-Jul-12 19-Jul-12 21-Jul-12 11-Aug-12 18-Aug-12 17-Sep-12 02-Oct-12 27-Jun-13 12-Jul-13 26-Aug-13 02-Sep-13 31-Jul-12 31-Jul-12 31-Jul-12 02-Aug-12

17-Oct-13 21-Jul-12 28-Jul-12 18-Aug-12 17-Sep-12 16-Nov-12 27-Jun-13 12-Jul-13 26-Aug-13 02-Sep-13 17-Oct-13 28-Aug-13 23-Jul-13 02-Aug-12 09-Aug-12

21-Jul-12 21-Jul-12 23-Jul-12 13-Aug-12 20-Aug-12 19-Sep-12 04-Oct-12 29-Jun-13 14-Jul-13 28-Aug-13 08-Sep-13 04-Sep-12 07-Sep-12 07-Sep-12 09-Sep-12

23-Oct-13 23-Jul-12 30-Jul-12 20-Aug-12 19-Sep-12 18-Nov-12 29-Jun-13 14-Jul-13 28-Aug-13 04-Sep-13 23-Oct-13 13-Oct-13 13-Oct-13 09-Sep-12 16-Sep-12

6 2 2 2 2 2 2 2 2 2 6 46 82 38 38

PLBP1100 Booster Pumps MR Approved PLBP1110 Booster Pumps RFQ to Vendors to be Issued PLBP1120 Booster P