89
Planning and Environment Act 1987 Panel Report Greater Bendigo Planning Scheme Amendment C221 Bendigo Urban Flood Controls Front page 21 November 2016

Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Planning and Environment Act 1987 

Panel Report 

Greater Bendigo Planning Scheme Amendment C221 

Bendigo Urban Flood Controls  

 

Front page  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

21 November 2016 

    

Page 2: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Planning and Environment Act 1987 

Panel Report pursuant to section 25 of the Act 

Greater Bendigo Planning Scheme Amendment C221 

Bendigo Urban Flood Controls 

21 November 2016 

 

   

Chris Harty, Chair  Greg Sharpley, Member 

 

Page 3: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

  

 

Contents   Page 

1  Introduction ................................................................................................................ 1 

1.1  The Amendment ...................................................................................................... 1 1.2  Flooding in the Bendigo urban area ........................................................................ 2 1.3  Proposed Overlays and Local Floodplain Development Plan .................................. 5 1.4  Panel process ........................................................................................................... 7 1.5  Issues dealt with in this Report ............................................................................... 8 

2  Strategic planning context .......................................................................................... 9 

2.1  Planning and Environment Act 1987 ....................................................................... 9 2.2  Policy framework ..................................................................................................... 9 2.3  Planning scheme provisions .................................................................................. 13 2.4  Ministerial Directions and Practice Notes ............................................................. 15 2.5  Discussion .............................................................................................................. 16 2.6  Conclusion ............................................................................................................. 16 

3  Technical basis and mapping of the Amendment ...................................................... 17 

3.1  The issue ................................................................................................................ 17 3.2  Submissions and evidence .................................................................................... 17 3.3  Discussion .............................................................................................................. 19 3.4  Conclusion ............................................................................................................. 21 

4  Site specific issues ..................................................................................................... 22 

4.1  The issues .............................................................................................................. 22 4.2  Hydraulic modelling details ................................................................................... 22 4.3  Existing and approved development ..................................................................... 23 4.4  Removal of the ESO1 ............................................................................................. 26 4.5  Kangaroo Flat ......................................................................................................... 27 4.6  Junortoun / Strathfieldsaye ................................................................................... 28 4.7  Central Bendigo ..................................................................................................... 29 4.8  Epsom/Huntly ........................................................................................................ 29 4.9  Back Creek ............................................................................................................. 32 4.10  Agreed mapping changes ...................................................................................... 33 4.11  Recommendations ................................................................................................ 33 

5  Other matters ........................................................................................................... 35 

5.1  The issues .............................................................................................................. 35 5.2  Land values and insurance .................................................................................... 35 5.3  Amendment drafting ............................................................................................. 38 5.4  Waterway maintenance ........................................................................................ 40 5.5  Recommendations ................................................................................................ 40 

    

Page 4: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

  

 

Appendix A  Submitters to the Amendment 

Appendix B  Parties to the Panel Hearing 

Appendix C  Document list 

Appendix D  Agreed changes to mapping for the LSIO and SBO 

 

List of Tables      Page Table 1  Comparison of permit exemptions between LSIO1 and LSIO2 ............................... 6 

 

List of Figures   Page 

Figure 1  Overall application of the Land Subject to Inundation Overlay and Special Building Overlay .......................................................................................... 3 

Figure 2  The catchments affected by the Bendigo Urban Flood Study ................................ 4 

 

   

Page 5: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

  

 

List of Abbreviations  

AEP  Annual Exceedance Probability 

AHD  Australian Height Datum 

ARI  Average Recurrence Interval 

BLFDP  Bendigo Local Floodplain Development Plan 

CMA  Catchment Management Authority 

DELWP  Department of Environment, Land, Water and Planning 

ESO  Environmental Significance Overlay 

FO  Floodway Overlay 

FZ  Farming Zone 

LFDP  Local Floodplain Development Plan 

LiDAR  Light Detection and Ranging 

LPPF  Local Planning Policy Framework 

LSIO  Land Subject to Inundation Overlay 

MSS  Municipal Strategic Statement 

NCCMA  North Central Catchment Management Authority 

SBO  Special Building Overlay 

SPPF  State Planning Policy Framework 

UFZ  Urban Floodway Zone 

VPP  Victoria Planning Provisions 

    

Page 6: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

  

 

Overview  

Amendment Summary    

The Amendment  Greater Bendigo Planning Scheme Amendment C221 

Common name  Bendigo Urban Flood Controls 

Brief description  Incorporate the findings of the Bendigo Urban Flood Study by amending policy at Clause 21.02‐3 for Key Issues under Environment and Clause 21.08 for Environment, the schedules to the Land Subject to Inundation Overlay and Special Building Overlay and their coverage, and including the ‘Bendigo Local Floodplain Development Plan’ as an incorporated document. 

Subject site  Areas within the urban environs of Bendigo 

Planning Authority  Greater Bendigo City Council 

Authorisation   A03301 on 12 April 2016 

Exhibition  19 May to 30 June 2016 

Submissions  Number of Submissions: 53  Opposed: 49. 

A list of submitters is included in Appendix A 

 

Panel Process    

The Panel  Chris Harty, Chair and Greg Sharpley 

Directions Hearing  Bendigo, 28 September 2016 

Panel Hearing  Bendigo, 18 to 20 October 2016 

Site Inspections  Unaccompanied, 26 October 2016 

Date of this Report  21 November 2016 

 

Page 7: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

 

Executive Summary 

(i) Summary 

Greater  Bendigo  Planning  Scheme  Amendment  C221  seeks  to  implement  the  planning outcomes of  the Bendigo Urban  Flood  Study, November 2013 by making  changes  to  local policy and applying the Land Subject to Inundation Overlay and Special Building Overlay over approximately  5,700  properties  identified  as  liable  to  flooding  in  the  Bendigo  area.    The Amendment also seeks to include the Bendigo Local Floodplain Development Plan, May 2016 as an incorporated document. 

The Land Subject to  Inundation Overlay  is proposed to be amended to  introduce two new schedules addressing areas subject to flooding up to 350mm (Schedule 1) and deeper than 350mm (Schedule 2) and to retain the existing schedule (renamed Schedule 3).  The Special Building Overlay is proposed to be introduced, with two schedules addressing areas subject to flooding from poor urban drainage (Schedule 1) and areas in the Epsom / Huntly area at risk of flooding from the Bendigo Creek levee (Schedule 2).  The Land Subject to Inundation Overlay  Schedules  1  and  2  and  the  Special  Building  Overlay  Schedule  2  contain  permit exemptions  for  certain  types  of minor works,  small,  new  and  replacement  buildings  and extensions to existing buildings. 

Amendment C221 was prepared by Greater Bendigo City Council as Planning Authority and supported by the North Central Catchment Management Authority and was placed on public exhibition between 19 May and 30 June 2016, attracting 53 submissions of which 49 were opposed or sought changes to the proposed Amendment. 

Key issues raised in submissions related to: 

Inaccuracies in the flood modelling and mapping 

Extent of coverage of the overlays 

Land  devaluation  and  insurance  difficulties  attributed  to  the  application  of  flood controls. 

The  need  for  Amendment  C221 was  generally  not  disputed,  given  the  flood  events  that affected various parts of the Greater Bendigo area in 2010 and 2011.  The main concerns of submitters was the accuracy of the flood modelling, the extent of coverage of flood mapping and impacts on land values and flood insurance. 

The Panel  considers  the  technical evidence provided  in  relation  to  the preparation of  the flood modelling and extent of overlay coverage supports the application of the Land Subject to  Inundation Overlay and Special Building Overlay.    In particular, the Panel notes that the flood  modelling  methodology  and  mapped  outputs  have  all  been  subject  to  expert independent peer review.  No technical evidence was provided disputing the accuracy of the flood  modelling,  but  rather  questioning  the  extent  of  flood  mapping  given  previous approvals  for  flood mitigation works  as  part  of  proposed  or  approved  developments.    It appears  to  the  Panel  that  submitters’  concerns  in  relation  to  the  extent  of  the  overlays resulted more  from  their  experience  during  the  2010  and  2011  floods  and  earlier  floods from  the 1970s, where  the perception was  that, generally  the extent of  flooding does not match  that mapped under  the Amendment.   This  is a misconception given  the mapping  is 

Page 8: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

 

based on the State policy benchmark of a 1 in 100 year flood event which would be a much larger event than what has been witnessed in living memory. 

The Panel concludes: 

Amendment C221  is  strategically  justified and supports State policy  for  floodplain management by identifying areas liable to flood risk hazard based on a 1 in 100 year probability. 

The  flood  modelling  undertaken  to  support  Amendment  C221  was  based  on accurate  ground  levels  and data,  calibration  and modelling  and  is  appropriate  to inform  the  application  of  the  Land  Subject  to  Inundation  Overlay  and  Special Building Overlay. 

The  form and  content of  the proposed  changes  to  local policy, overlay  schedules and  the  incorporated  document  Bendigo  Local  Floodplain Development  Plan  are generally  consistent  with  relevant  Ministerial  Guidelines  and  Planning  Practice Notes,  and  are  appropriate  for managing development  that warrants  assessment with respect to effects on and from flood processes and environmental values and hazards associated with flood processes. 

The  structure  of  the  overlay  schedules  and  the  Bendigo  Local  Floodplain Development  Plan  are  appropriate  and  offer  a  useful  guide  to  the  controls  for practitioners and decision makers. 

The  post  exhibition  changes  to  the  mapping  of  the  overlays  in  response  to submissions are supported. 

(ii) Recommendations 

Based on the reasons set out in this Report, the Panel recommends that Greater Bendigo Planning Scheme Amendment C221 be adopted as exhibited subject to the following: 

  Amend  Schedules  1,  2  and  3  of  the  Land  Subject  to  Inundation  Overlay  and 1.Schedule  2  of  the  Special  Building  Overlay  to  include  the  following  additional permit requirement: 

Buildings and works on land subject to an existing planning permit, restriction or agreement 

  if  land  has  been  developed  in  accordance  with  a  planning  permit, restriction or Section 173 agreement requiring its ground surface level to be finished at least 300mm above the 100 year ARI flood level; and 

  survey plans confirm that the ground surface  level has been constructed in accordance with the requirements of a planning permit, restriction or subdivision; and 

  any buildings and works do not lower the ground surface level or result in a finished floor  level for a dwelling that  is below 300mm above the 100 year ARI flood level. 

  Amend Schedule 1 of the Special Building Overlay Clause 1.0 Permit requirements 2.to replace the words “No exemptions specified” with the following: 

A  permit  is  not  required  to  construct  a  building  or  construct  or  carry  out works as follows: 

Page 9: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

 

Buildings and works on land subject to an existing planning permit, restriction or agreement 

  if  land  has  been  developed  in  accordance  with  a  planning  permit, restriction or Section 173 agreement requiring its ground surface level to be finished at least 300mm above the 100 year ARI flood level; and 

  survey plans confirm that the ground surface  level has been constructed in accordance with the requirements of a planning permit, restriction or subdivision; and 

  any buildings and works do not lower the ground surface level or result in a finished floor  level for a dwelling that  is below 300mm above the 100 year ARI flood level. 

  Review  the  flood mapping  and  application  of  the  Land  Subject  to  Inundation 3.Overlay  and/or  the  Special  Building  Overlay  for  land  at  105  Trotting  Terrace, Junortoun  to  include  only  those  areas  affected  by  flooding  from  the  unnamed tributary of Splitters Creek. 

  Review the base modelling of the BMT WBM model against the Water Technology 4.model to  identify  if there are any discrepancies, which warrant a revision of the flooding overlays in the Epsom/Huntly area. 

  Adopt the changes shown in the maps in Appendix D to the coverage of the Land 5.Subject to Inundation Overlay and the Special Building Overlay. 

  Amend Schedule 1 of  the Land Subject  to  Inundation Overlay and Schedule 2 of 6.the Special Building Overlay under “New or replacement buildings” to include the following additional permit requirement: 

  A relocatable building associated with a caravan park where floor  levels are at least 300mm above the 1% AEP Flood level. 

  Replace the fifth dot point under “Other buildings and works” in Schedules 1 and 7.2 of the Land Subject to Inundation Overlay to read: 

  A curtain style fence for a tennis court  if constructed  in accordance with the  requirements  of  the  Bendigo  Local  Floodplain  Development  Plan 2016. 

  Amend  Section  5.1  of  the Bendigo  Local  Floodplain Development  Plan  2016  by 8.introducing  the  following  dot  point  under  “Subdivisions  in  the  Low  Density Residential Zone or Rural Living Zone”: 

  All new lots and new road reserves are set back a minimum of 30 metres from any waterway. 

  Update  the  Section  8  Flood  Risk  Guide  map  of  the  Bendigo  Local  Floodplain 9.Development Plan 2016 in accordance with the changes agreed to by Council and shown  in  Appendix  D  to  the  Land  Subject  to  Inundation  Overlay  and  Special Building Overlay mapping. 

 

Page 10: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 1 

 

1 Introduction 

1.1 The Amendment  

Greater  Bendigo  Planning  Scheme  Amendment  C221  (the  Amendment)  proposes  to implement  the  findings  of  the  Bendigo  Urban  Flood  Study,  November  2013  prepared  by Water  Technology  Pty  Ltd.    The  Amendment  proposes  to  apply  flooding  controls  to properties across the Bendigo urban area that have been  identified to be  located  in active flow  paths,  to  ensure  that  flooding  is  considered  in  development  proposals.    The Amendment proposes to apply either the Land Subject to  Inundation Overlay (LSIO) or the Special Building Overlay  (SBO).    It also proposes  to exempt planning permit  requirements when certain conditions are met, and introduce guidelines for various forms of development within flood prone areas through the Bendigo Local Floodplain Development Plan. 

The Amendment applies to approximately 5,700 properties in total across the Bendigo urban area.  These properties are located in the catchment of the Bendigo Creek and parts of the Myers  Creek  and  Axe  Creek  /  Campaspe  River  catchments.    The  properties  affected  are located in the following areas: 

Maiden Gully, Sailors Gully and Eaglehawk (Myers Creek catchment). 

Big  Hill,  Kangaroo  Flat,  Golden  Square,  Bendigo,  Spring  Gully,  Kennington,  East Bendigo, White  Hills,  Ascot,  Epsom,  Huntly,  Huntly  North  and  Bagshot  (Bendigo Creek Catchment). 

Strathfieldsaye, Emu Creek, Axe Creek and Junortoun (Axe Creek / Campaspe River Catchment). 

The Amendment proposes to: 

Rezone  land at 16 Rosemundy Road, Epsom,  from Urban Floodway Zone  (UFZ)  to the Farming Zone (FZ) and amend zone map 15 accordingly 

Insert  the  following  new  overlay maps  –  14LSIO,  21LSIO,  26LSIO,  8SBO,  12SBO, 14SBO, 15SBO, 16SBO, 18SBO, 19SBO, 22SBO, 23SBO and 26SBO 

Delete the following overlay maps – 19ESO and 20ESO 

Amend the following overlay maps – 18ESO, 22ESO, 23ESO, 24ESO, 26ESO, 31ESO, 1LSIO, 5LSIO, 6LSIO, 8LSIO, 9LSIO, 12LSIO, 13LSIO, 15LSIO, 16LSIO, 17LSIO, 18LSIO, 19LSIO,  20LSIO,  22LSIO,  23LSIO,  24LSIO,  25LSIO,  28LSIO,  30LSIO,  31LSIO,  33LSIO, 39LSIO, 44LSIO and 45LSIO 

Amend Clause 21.02 – Key  Issues and  Influences and Clause 21.08  ‐ Environment of  the Municipal  Strategic  Statement  (MSS)  to  refer  to  the  importance  of  flood management and planning 

Amend Clause 21.10 – Reference Documents of  the MSS  to  include  the Bendigo Urban Flood Study 2013 as a reference document in the planning scheme 

Delete the Environmental Significance Overlay Schedule 1 – Watercourse Protection (ESO1)  from approximately 1200 properties  that are  located within 100 metres of waterways that are constructed channels or non‐designated waterways 

Amend  the  Schedule  to  Clause  44.04  ‐  Land  Subject  to  Inundation Overlay  and insert new Schedules 1, 2 and 3  to  identify different  types of  flooding and permit exemptions 

Page 11: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 2 

 

Delete the LSIO from all land in the study area, approximately 2000 properties 

Apply the LSIO Schedule 1 – Flooding from Waterways (Depths up to and including 350mm) to approximately 4,031 properties that experience flooding up to 350mm depth 

Apply  the  LSIO  Schedule  2  –  Flooding  from  Waterways  (Depths  greater  than 350mm)  to approximately 1,583 properties  that experience  flooding greater  than 350mm depth 

Replace the LSIO with LSIO Schedule 3 in the rural areas outside urban Bendigo (this is a change to the schedule number only) 

Insert  Clause  44.05  –  Special  Building  Overlay  to  identify  land  that  is  liable  to inundation  from  overland  flows  from  the  urban  drainage  system  and  insert Schedules 1 and 2 to identify particular types of overland flow 

Apply  the SBO Schedule 1 – Urban Drainage Management Area  to approximately 392 properties throughout the municipality 

Apply  the  SBO  Schedule  2  –  Bendigo  Creek  Levee  Management  Area  to approximately 327 properties protected by the Bendigo Creek earthen levee 

Amend the Schedule to Clause 61.03 ‐ What does this scheme consist of? to update the list of maps in the planning scheme 

Amend  the  Schedule  to Clause 81.01  ‐  Table of Documents  Incorporated  in  this Scheme to include the Bendigo Local Floodplain Development Plan, May 2016 as an incorporated document in the planning scheme. 

Figure 1 shows the proposed coverage of the LSIO and SBO.   They trigger the requirement for a planning permit for buildings, works and subdivision on land affected by flooding.  The Amendment proposes modified schedules to the LSIO and SBO that provide exemptions to a number of  those permit  requirements  for buildings and works.   Both overlays  rely on  the Bendigo  Local  Floodplain  Development  Plan,  which  is  proposed  to  be  included  as  an incorporated  document,  and  form  part  of  the  decision‐making  framework  of  the Greater Bendigo Planning Scheme. 

1.2 Flooding in the Bendigo urban area 

Most of urban Bendigo drains  into  the Bendigo Creek  via numerous  tributaries.   Bendigo Creek flows north from Kangaroo Flat through the Bendigo CBD and on to Huntly.  The urban areas of Strathfieldsaye, Junortoun and Maiden Gully are also  included  in the Amendment.  Maiden  Gully  drains  into Myers  Creek  and  Strathfieldsaye  and  Junortoun  drain  into  Axe Creek (refer to Figure 2). 

Urban development  in Bendigo began  in the 1850s  following the discovery of gold.    In the absence  of  sound  land  use  planning  strategies,  this  development  has  progressively obstructed  floodplain  land,  diminishing  its  ability  to  convey,  store  and  drain  floodwater.  Bendigo  Creek  itself  has  been  substantially modified  by  deepening, widening  and  lining, creating a constructed drain for much of its length through Bendigo. 

There is a history of flooding in Bendigo Creek associated with high intensity short duration storm events due to a combination of intense thunderstorms and relatively small catchment areas. 

Page 12: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 3 

 

 

Figure 1  Overall  application  of  the  Land  Subject  to  Inundation  Overlay  and  Special  Building Overlay 

Page 13: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 4 

 

 

Figure 2  The catchments affected by the Bendigo Urban Flood Study 

   

Page 14: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 5 

 

1.3 Proposed Overlays and Local Floodplain Development Plan 

The LSIO currently applies to urban areas across the municipality and was primarily derived from  a  1984  flood  investigation  prepared  by  the  former  State  Rivers  and Water  Supply Commission.   The application of  the LSIO  is now viewed by Council and  the North Central Catchment Management  Authority  (NCCMA)  as  being  out  of  date  and  inaccurate.    The Amendment proposes to replace the current LSIO with an expansion of coverage based on the Bendigo Urban Flood Study. 

Council  advised  that  there  is  currently  no  distinction  in  the  Greater  Bendigo  Planning Scheme  between  the  two main  causes  of  flooding, mainstream  flooding  and  stormwater flooding, nor in the type of mainstream flooding.  Hence, the Amendment proposes to apply an  expanded  and more  sophisticated  coverage  of  the  LSIO  through  the  use  of  two  new schedules, and to introduce the SBO with two schedules. 

1.3.1 Overlay selection 

Apart  from  addressing  the  types  of  flooding,  Council  submitted  it  had  taken  into consideration  the  various  planning  tools  available  under  the  Victoria  Planning  Provisions (VPP)  used  by  planning  authorities  to  identify  and  manage  flooding.    The  selection  of overlays  under  the  Amendment  has  also  been  guided  by  Planning  Practice  Note  12  – Applying the Flood Provisions in Planning Schemes – A guide for councils, June 2015 (Planning Practice Note 12). 

Council advised that: 

In choosing the planning scheme tools, extensive consideration was given to: 

the purpose and operation of each overlay; 

the  experience  of  the  NCCMA  in  working  with  the  overlay  in  different municipalities; 

the findings of recent planning panels; 

the  experience  of  other  municipalities  that  have  developed,  or  are developing, new flooding provisions; 

the development of the Local Floodplain Development Plan that gives more detailed guidance for development; 

other relevant technical guidance prepared by authorities or governments; and 

the  relevant  flood  characteristics  for  all  areas  within  the  catchment, including flood depth, velocity, frequency, duration of flood, flood warning, and rate of rise. 

The LSIO identifies land affected by mainstream flooding.  This occurs when there is a large amount of  run‐off  and water overflows  the banks of waterways on  to  adjacent  low‐lying land.   The new Schedule 1 to the LSIO generally denotes the edge of the floodplain where flooding  is shallower and slower moving; where depth  is  less than or equal to 0.35 metres and where  the depth  times velocity  is  less  than 0.4m2/s during  the 1 per cent AEP design flood event.  The new Schedule 2 to the LSIO is the higher hazard portion of the floodplain, where deeper and faster flowing floodwater can be expected; where the depth of flooding has been modelled at greater than 0.35 metres and where the depth times velocity exceeds 

Page 15: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 6 

 

0.4m2/s during the 1 per cent AEP design flood event.    It will generally be more difficult to comply with  development  performance  criteria  in  areas  affected  by  the  LSIO2  due  to  a greater risk to life and property. 

The  schedules  to  the  LSIO  provide  opportunities  for  further  planning  permit  exemptions.  The differences with permit exemptions between  the proposed  schedules  are outlined  in Table 1. 

Table 1  Comparison of permit exemptions between LSIO1 and LSIO2 

LSIO1 permit exemptions  LSIO2 permit exemptions 

Works less than 50mm change to existing surface levels 

Works that don’t change existing surface levels 

An extension to a dwelling with a gross floor area not greater than 40 square metres, provided flor level not less than existing 

An extension to a dwelling with a gross floor area not greater than 20 square metres, provided flor level not less than existing 

Extension to an outbuilding or new outbuilding if floor level 150mm above 1% AEP 

No exemption for outbuildings 

A replacement dwelling with no size limitations if built 300mm above the 1% AEP 

A replacement dwelling no bigger than previous than 20 square metres if built 300mm above the 1% AEP 

An agricultural shed used for storage/workshop with no permanent openings with a floor area not greater than 200 square metres 

No exemptions for agricultural sheds 

A replacement fence built out of the same materials 

No exemption for replacement fence 

A pergola, deck water tank or carport  A pergola, deck water tank or carport with unclosed foundations 

A sportsground, racecourse or recreation area with no permanent raised grandstand 

No exemption for a sportsground, racecourse or recreation area with no permanent raised grandstand 

A sign which is 350mm above the natural surface level 

A sign which is 350mm above the 1% AEP flood level 

Earthworks associated with a dam where no imported fill, not constructed on a waterway, not bigger than 3 megalitres and no embankment 

No exemption for earthworks 

The  SBO  is  proposed  to  be  introduced  to  identify  urban  areas where  land  is  affected  by overland flows that are caused by a lack of capacity in the piped drainage system and where no provision has been made for overland flows.   Council advised that the model generated by  the Bendigo Urban Flood Study  found  that  this  issue affected approximately half of all properties  in Bendigo, so a series of criteria was applied to refine the extent of the SBO to apply to only critical locations.  The criteria included: 

Where development could affect neighbouring property owners 

Page 16: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 7 

 

A catchment area greater than 40 hectares 

Where  the  City  cannot  reasonably  eliminate  the  flooding  problem  through  its capital works program 

Where the combination of depth and velocity of flooding would pose a safety risk to residents. 

The new Schedule 1  to  the SBO denotes  land  that  is affected by overland  flows  from  the urban drainage system during the 1 per cent AEP design flood event.   The new Schedule 2 to the  SBO denotes  land  that  is protected by  the earthen  levees  along Bendigo Creek.    The levees  are  at  risk  of  breaching  as  they  were  constructed  many  years  ago,  often  by landholders and not to modern engineering standards.  This land also experiences drainage problems and overland flows due to its very low lying nature. 

The Victorian Floodplain Management Strategy 2016 identifies councils as being responsible for urban  levees.   Council advised that  it  is currently undertaking a study  into the potential mitigation  options  for  flooding  in  the  lower  Bendigo  Creek  catchment  in  Epsom/Huntly, including works  required  to bring  the  levee up  to  current  standards.    It  is envisaged  that when this study is finalised, and the works implemented, that the SBO2, and possibly some LSIO, can be considered for removal in a future planning scheme amendment. 

The  SBO2  schedule also  includes permit exemptions  for  certain  types of  identified works, buildings and extensions to existing buildings. 

1.3.2 Bendigo Local Floodplain Development Plan 

The  Amendment  also  introduces  the  Bendigo  Local  Floodplain  Development  Plan  as  an incorporated document  to guide decision making.   The  local  floodplain development plan sets out performance‐based criteria  for  the assessment of planning permit applications on all  land  affected by  the  LSIO  and  SBO.   Performance  criteria  are  included  for  subdivision, buildings, commercial and residential development, fences, earthworks and water tanks. 

1.3.3 ESO1 

The Amendment also affects areas where  the ESO1  currently applies.   The ESO1  seeks  to manage water quality, protect creeks from erosion, ensure development does not occur on land  liable  to  flooding,  and  protect  habitat.   Applications  received  under  this  overlay  are referred  to  the NCCMA.    The  Amendment  proposes  to  remove  the  ESO1  from  land  that adjoins fully constructed channels or pipes, or non‐designated waterways under the Water Act 1989.   These  ‘constructed waterways’ offer  little environmental value and  the ESO1  in these urban locations has largely been operating as a flooding control mechanism and not as an environmental control.   Applying the LSIO under the Amendment  in these areas means the ESO control becomes redundant. 

1.4 Panel process 

The Amendment was prepared by Greater Bendigo City Council as Planning Authority.   The Amendment was authorised by the Department of Environment, Land, Water and Planning (DELWP) on 12 April 2016. 

Page 17: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 8 

 

The Amendment was placed on public exhibition between 19 May and 30 June 2016, with 52 submissions  received,  of  which  four  (4)  were  in  support  and  48  were  opposed  to  the Amendment. 

At its meeting of 10 August 2016, Council resolved to refer 42 submissions to a Panel.1  As a result,  a  Panel  to  consider  the  Amendment  was  appointed  under  delegation  from  the Minister for Planning on 25 August 2016, comprising Chris Harty (Chair) and Greg Sharpley. 

A Directions Hearing was held  in relation  to  the Amendment on 28 September 2016.   The Panel  then met  in Bendigo on 18, 19 and 20 October 2016  to hear submissions about  the Amendment.  Those in attendance at the Panel Hearing are listed in Appendix B.  Following the Panel Hearing, the Panel undertook an unaccompanied  inspection of the Bendigo area on 26 October 2016. 

1.5 Issues dealt with in this Report 

The  Panel  considered  all written  submissions made  in  response  to  the  exhibition  of  the Amendment,  as well  as  further  submissions,  evidence  and other material  presented  to  it during the Hearing, and observations from site visits.  The 49 submissions originally objecting (including the 41 submissions that now remaining unresolved) to the Amendment focussed primarily  on  site‐specific  concerns.    The  issues  that  emerge  from  consideration  of  the objecting submissions include: 

Inaccuracies in the flood mapping 

Land  devaluation  and  insurance  difficulties  attributed  to  the  application  of  flood controls. 

The Panel has reviewed a large volume of material.  The Panel has been selective in referring to the more relevant or determinative material in this report.  All submissions and materials have been considered by the Panel, regardless of whether they are specifically mentioned in the report. 

This report deals with the issues under the following headings: 

Strategic planning context 

Technical basis and mapping of the Amendment 

Site specific issues 

Other matters including: -  land values and insurance - Amendment drafting and - waterway maintenance. 

                                                       1  At the time the submissions were considered by Council, of the 48 submissions requesting a change, 6 were 

considered accommodated with changes made to the Amendment, and 42 were referred.  Since the Council meeting  another  submission has been  received  requesting  a  change, 4  submissions have been  resolved through  changes  to  the  Amendment  and  2  that  were  considered  resolved  are  no  longer,  leaving  41 unresolved for consideration by the Panel. 

Page 18: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 9 

 

2 Strategic planning context 

Council  provided  a  response  to  the  Strategic  Assessment  Guidelines  as  part  of  the Explanatory Report. 

The Panel has reviewed Council’s response and the policy context of the Amendment, and has made  a  brief  appraisal  of  the  relevant  overlay  controls  and  other  relevant  planning strategies. 

2.1 Planning and Environment Act 1987 

The Planning and Environment Act 1987 (the Act) provides for the establishment of planning schemes  in  Victoria  to  regulate  land  use  and  development.    Section  6(2)(e)  of  the  Act enables  planning  schemes  to  regulate  or  prohibit  any  use  or  development  in  hazardous areas,  or  areas  likely  to  become  hazardous.    Flooding  is  a  land management  hazard  and planning  schemes  contain  State  planning  policy  for  floodplain management  (as  one  of  a number of environmental  risks),  requiring  that  flood  risk be considered  in  the preparation and amendment of planning schemes and in land use decision making. 

2.2 Policy framework 

(i) State Planning Policy Framework 

The  State Planning Policy  Framework  (SPPF) provides  the broad  framework  for  floodplain management policy and provisions  in  the planning  scheme.    It provides guidance on how land affected by flooding should be treated  in planning schemes and  in planning decisions.  Flood risk must be considered when decisions are made about the use and development of land.   The  level of  flood  risk  should be  reflected  in  the  type of  flood provisions  that have been applied to the land. 

Council and the Panel considers that the Amendment  is supported by the following clauses in the SPPF: 

Clause  10.02  ‐  Goal  where  the  application  of  up  to  date  and  accurate  flood  controls integrates economic, social and environmental objectives in the interests of net community benefit and sustainable forms of development. 

Clause  11  ‐  Settlement, which  provides  for  planning  to  recognise  and  contribute where practical  towards  health  and  safety.    Under  Clause  11.02‐1  ‐  Supply  of  urban  land  the strategy  recognises  that  planning  for  urban  growth  should  consider  the  limits  of  land capability and natural hazards and environmental quality.  Council considers implementation of  the  Bendigo  Urban  Flood  Study  will  enable  improved  planning  of  urban  areas  by identifying limitations due to natural hazards and environmental sensitivity due to flooding. 

Clause 11.02‐3 – Structure Planning seeks to facilitate orderly development of an area.  The Amendment will have a broad  impact across Bendigo’s urban areas, and provide valuable information to ensure effective planning and management of land uses and development. 

Under  Clause  11.05‐4  ‐  Regional  planning  strategies  and  principles  the  strategy  under climate change, natural hazards and community safety seeks  to respond  to  the  impacts of natural hazards by: 

Page 19: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 10 

 

Siting  and  designing  new  dwellings,  subdivisions  and  other  development  to minimise  risk  to  life,  property,  the  natural  environment  and  community infrastructure from natural hazards, such as bushfire and flood. 

Identifying  areas  liable  to  flooding under  the Amendment provides  a  response  to natural hazards and community safety through enabling the siting and design of new development from flood hazards. 

Clause 13 ‐ Environmental Risks provides that: 

Planning  should  adopt  a  best  practice  environmental management  and  risk management  approach  which  aims  to  avoid  or  minimise  environmental degradation and hazards.  Planning should identify and manage the potential for  the  environment,  and  environmental  changes,  to  impact  upon  the economic, environmental or social well‐being of society. 

Clause 13.02 ‐ Floodplains and Clause 13.02‐1 – Floodplain Management contains a number of  objectives  and  strategies  that  support  the  Amendment.    This  is  evident  through  the Amendment  identifying  flood hazards  to  life, property and  infrastructure and  flood  risk  in planning scheme maps, and avoiding development that may adversely affect flood flows and storage.  The objective of the policy is: 

To assist the protection of: 

Life, property and community infrastructure from flood hazard. 

The natural flood carrying capacity of rivers, streams and floodways. 

The flood storage function of floodplains and waterways.  Floodplain areas of environmental significance or of importance to river 

health. 

The policy includes the following strategies: 

Identify land affected by flooding, including floodway areas, as verified by the relevant  floodplain management authority,  in planning  scheme maps.    Land affected by  flooding  is  land  inundate by  the 1  in 100 year  flood event or as determined by the floodplain management authority. 

Avoid  intensifying  the  impacts  of  flooding  through  inappropriately  located uses and developments. 

Other strategies refer to particular uses, including emergency and community facilities, and uses which involve the storage or disposal of hazardous materials. 

The policy also refers to the Victorian Floodplain Management Strategy as a policy guideline to be considered where relevant. 

Clause 14.02‐2  ‐ Water Quality helps prevent  incompatible development  in the floodplain, which may lead to poor water quality. 

Having  considered  the  relevant  clauses  of  the  SPPF,  the  Panel  concludes  that  the Amendment supports and implements the relevant aspects of State policy.  The Amendment provides  clear mapping  for  the  coverage  of  the  LSIO  and  SBO.    These  overlays  regulate development  in  those areas  identified as  liable  to  flooding and allow  the planning permit 

Page 20: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 11 

 

application process to assess the potential effects of what  is proposed on the environment and  the  potential  effects  of  the  environment  on  what  is  proposed.    The  Amendment establishes a process where flood risks can be assessed and development designed and sited to minimise detrimental impacts. 

Clause  19.03‐3  –  Stormwater  seeks  to  reduce  the  impact  of  stormwater  on  catchments through  a  range  of  strategies,  including  reductions  in  run‐off  and  peak  flows.  Implementation of the SBO will assist  in the management of stormwater to enhance  flood protection. 

(ii) Local Planning Policy Framework 

The  Local  Planning  Policy  Framework  (LPPF),  comprising  both  the  Municipal  Strategic Statement  (MSS)  and  Local  Planning  Policies,  can  contain  policies  that  provide  the  local context  for  identifying  issues  and  setting objectives  and  strategies  to  address  them.    The Planning  Scheme  currently  contains  brief  reference  to  flooding.    It  is  noted  that  the Amendment proposes  to update  the MSS at Clauses 21.02 and 21.08  to  identify  that  land affected by flooding responds to flood risks and recognises the Bendigo Urban Flood Study. 

Council submitted that the Amendment supports the following policies in the LPPF: 

Clause 21.05‐8 – Managing risk identifies that the Greater Bendigo area is a unique landscape  that  has  some  environmental  risks  that  need  to  be  considered when planning  for growth.   The policy  identifies  that  the precautionary principle should be used when making  land use planning decisions.   The policy objective  includes managing development  in  areas of  risk  from  flooding.    Strategies  supporting  this objective  include  adopting  a  three  step  approach  based  on  the  precautionary principle  to  manage  risk  from  flooding  by  directing  development  into  low  risk locations, carefully considering development in medium risk locations and avoiding development in high risk locations. 

Clause  21.08  –  Environment  aims  to maintain  and  enhance  ground  and  surface water quality, reduce pollution of watercourses and protect the values of forested land  and  waterways  by  minimising  urban  drainage  discharge  and  discouraging development that affects water quality. 

Clause  21.08‐4  –  Implementation,  identifies  the  need  for  revised  flood mapping and  the  need  to  provide  design  and  development  guidelines  for  land  use  and development in and near floodplains. 

The Amendment  responds  to  the above policies  through  the  identification of areas at  risk from  flooding  and  ensuring  new  development  is  appropriately  managed  through  the planning permit application process. 

Having  considered  the  relevant  clauses  of  the  LPPF,  the  Panel  concludes  that  the Amendment  supports  and  implements  the  relevant  local policy directions of  the planning scheme.   Management  of  flood  risks  and  informed  assessment  of  development  in  flood liable  areas  is promoted by  the  local  suite of planning policies  and  are  supported by  the Amendment. 

Page 21: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 12 

 

(iii) Other planning strategies or policies used in formulating the Amendment 

Victorian Floodplain Management Strategy 

The  Victorian  Floodplain Management  Strategy,  2016  (the  Strategy)  is  listed  as  a  policy guideline under Clause 13.02‐1 and the latest version was released by the State Government in  2016.    It  provides  statewide  policy  direction  for managing  floodplains  and minimising flood  risks  in  cities,  towns,  regional  areas  and  rural  communities,  including  guidance  on riverine flooding, flash flooding and coastal flooding. 

The Strategy includes in Policy 13a that: 

The 1% Annual Exceedance Probability flood will remain the design flood event for the land use planning and building system in Victoria. 2 

One of  the policy  foundations of  the Strategy  includes avoiding or minimising  future  flood risks and endorsing land use planning controls to manage the potential growth in flood risk.  In this regard, the Strategy promotes the expansion of the land use planning system to cover areas in the 1 per cent AEP.3 

One of the actions  in the Strategy  is for greater State government assistance with councils and CMAs regarding preparing consistent floodplain development standards and statewide floodplain development guidelines.   The Strategy  recognises value  in ensuring appropriate planning controls are applied consistently across the State. 

Loddon Mallee South Regional Growth Plan 

The  Loddon Mallee  South  Regional Growth  Plan, May  2014  is  listed  as  a  policy  guideline under Clause 11.12 and recognises flooding as a challenge to settlements and urban growth in the region.  The Regional Growth Plan aims to encourage growth away from flood prone land (Principles 1 and 6).  It also identifies as a land use action, the need for accurate flood mapping  and  planning  provisions  to  be  developed  in  the  City  of  Greater  Bendigo.    The Amendment facilitates this action and assists achieving the objective to facilitate the growth of Bendigo as the regional city in the Loddon Mallee South Region. 

Bendigo Urban Flood Study 

The  Bendigo  Urban  Flood  Study,  November  2013  (the  Study)  was  the  primary  report identified by Council relevant to the Amendment. 

The Panel notes the Study and the summary provided in the expert evidence of Mr Warwick Bishop, civil engineer and flood modelling expert from Water Technology Pty Ltd on behalf of Council.  The Study is further discussed later in the report in terms of how it supports the technical basis of the LSIO and SBO mapping. 

                                                       2  Page 40. 3  For simplicity and clarity, the 1 per cent AEP is referred to as the 1 in 100 year event in this report. 

Page 22: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 13 

 

2.3 Planning scheme provisions 

(i) Zones 

The  Amendment  proposes  to  rezone  one  parcel  of  land  located  at  16  Rosemundy  Road, Epsom from the UFZ to the FZ.  The land is a 1.3 hectare site bordered by land in the General Residential  Zone  (GRZ)  to  the west  and  the  FZ  to  the  east.    It  is  the  only  parcel  of  land currently  in  the  UFZ.    This  zone  is  no  longer  considered  appropriate  for  the  site  in  the context of proposed new LSIO1 and LSIO2  that  is proposed  to apply  to  the site.   The FZ  is considered to be the most appropriate zone for the site given its location adjoining Bendigo Creek and limited development potential. 

(ii) Overlays 

The  Amendment  proposes  to  amend  the  application  of  Clause  44.04  –  Land  Subject  to Inundation  Overlay  (LSIO)  and  to  introduce,  and  apply  Clause  44.05  –  Special  Building Overlay  (SBO)  to  flood  affected  land  across  the  Bendigo  urban  area.    The  LSIO  currently includes a single schedule with limited permit exemptions, whilst the SBO is currently not in the planning scheme. 

The LSIO includes the following purposes: 

To implement the State Planning Policy Framework and the Local Planning Policy  Framework,  including  the Municipal  Strategic  Statement  and  local planning policies. 

To  identify  land  in a flood storage or flood fringe area affected by the 1  in 100  year  flood  or  any  other  area  determined  by  the  floodplain management authority. 

To  ensure  that  development maintains  the  free  passage  and  temporary storage  of  floodwaters, minimises  flood  damage,  is  compatible with  the flood  hazard  and  local  drainage  conditions  and  will  not  cause  any significant rise in flood level or flow velocity. 

To  reflect  any  declaration  under Division  4  of  Part  10  of  the Water Act, 1989 where a declaration has been made. 

To protect water quality in accordance with the provisions of relevant State Environment Protection Policies, particularly in accordance with Clauses 33 and 35 of the State Environment Protection Policy (Waters of Victoria). 

To  ensure  that  development  maintains  or  improves  river  and  wetland health, waterway protection and flood plain health. 

As  described  earlier,  the  LSIO  identifies  land  affected  by mainstream  flooding  with  the Amendment introducing two new schedules to address shallow and deep flooding. 

The SBO includes the following purposes: 

To implement the State Planning Policy Framework and the Local Planning Policy  Framework,  including  the Municipal  Strategic  Statement  and  local planning policies. 

Page 23: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 14 

 

To identify land in urban areas liable to inundation by overland flows from the urban drainage system as determined by, or  in consultation with,  the floodplain management authority. 

To  ensure  that  development maintains  the  free  passage  and  temporary storage  of  floodwaters, minimises  flood  damage,  is  compatible with  the flood  hazard  and  local  drainage  conditions  and  will  not  cause  any significant rise in flood level or flow velocity. 

To protect water quality in accordance with the provisions of relevant State Environment Protection Policies, particularly in accordance with Clauses 33 and 35 of the State Environment Protection Policy (Waters of Victoria). 

The SBO has been used to identify urban areas where land is affected by overland flows that are  cause by a  lack of  capacity  in  the piped drainage  system and where no provision has been made for overland flows. 

The  schedules  to both overlays exempt various works, extensions and new buildings  from the need for planning approval.   Both trigger the need for planning permit applications for buildings, works and subdivision and both require an application to be consistent with any local floodplain development plan incorporated into the planning scheme. 

The appropriateness of overlay selection 

In  response  to  a  Panel  direction  regarding why  the  Floodway Overlay  (FO)  had  not  been selected for application under the Amendment, Council advised that the more restrictive FO was  not  chosen  in  lieu  of  using  the  proposed  LSIO2  primarily  because  of  the  nature  of deeper flooding experienced in Bendigo.  Generally, such flooding is not excessively fast, is of a  relatively  short duration,  and development  can be  assessed using  a performance based approach  through  the  Bendigo  Local  Floodplain Development  Plan  and  supported  by  the modelling that has been undertaken. 

Although  the  FO  is  usually  applied  in  circumstances  where  flooding  may  be  deep  and floodwaters  fast  flowing,  the situation  in Bendigo was considered different by Council and the NCCMA due to the urban character of the areas affected by the Amendment.  Mapping by  the  NCCMA  found  that  there  were  pockets  of  land  which  could  be  subdivided  and developed, which  if  included  in  the  FO would  unduly  restrict  development  that  could  be considered, particularly against the local floodplain development plan.  Mapping also found that the areas prone to fast moving and deeper flooding were generally on Crown Land or within waterway reserves where they have been heavily modified, and that some areas were already  substantially  developed.    These  factors  would  make  the  application  of  the  FO illogical and difficult to explain and implement. 

Council also indicated that extensive research into what other councils and CMAs have done across the State determined that there is no consistent approach or requirements, and there is flexibility to choose the tools that work for the local situation. 

Planning Practice Note 12 provides sufficient discretion to use two schedules to the LSIO to denote the full range of flooding risks identified under the Bendigo Urban Flood Study 2013.  Planning Practice Note 12  states  that  in general, areas  covered by  the  LSIO have a  lower flood risk than UFZ or FO areas.  Table 1 of Planning Practice Note 12 also indicates that the 

Page 24: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 15 

 

LSIO may be used in areas that cover the total extent of land subject to inundation, including the higher risk floodway component. 

The Panel  considers  that  the provisions of  the  LSIO  and  SBO will  adequately manage  the relevant  flood  risks and enable appropriate consideration of development proposals.   The use of multiple schedules in both overlays will ensure that the areas of greatest flood risk are formally  identified  in  the  planning  scheme,  together  with  development  exemptions  and performance criteria that are commensurate with the level of flood risk. 

(iii) General provisions 

Clause 62 – Uses, Buildings, Works, Subdivisions and Demolition not  requiring a permit, Clause  62.02  –  Buildings  and works  is  relevant  because  it  includes  certain  buildings  and works that are exempt from the need for a planning permit.  Some of the listed buildings and works under Clause 62.02‐2 – Buildings and works not requiring a permit unless specifically required by the planning scheme have been included under the LSIO and SBO as requiring a permit.4   The  schedules  to  the overlays can also be used  to  re‐exempt  such buildings and works from the need for a permit if deemed unnecessary by the planning authority. 

Clause 65 – Decision Guidelines requires the responsible authority, when assessing a permit application, to consider, amongst other matters, the degree of flood risk associated with the location of the land and the use, development or management of the land to minimise flood risk. 

Clause 66 – Referral and Notice Provisions under Referrals describes how applications listed under  relevant  sub‐clauses must be  referred  to  the person or body  specified as a  referral authority in accordance with Section 55 of the Act.  It also indicates that a referral does not apply  if  in  the opinion of  the  responsible authority,  the proposal satisfies  requirements or conditions previously agreed  in writing between  the responsible authority and  the referral authority.  Similarly, a referral may not be necessary if the referral authority has considered the proposal for which the application is made within the past three months, and has stated in writing that it does not object to the granting of the permit for the proposal.  The issue of referrals is addressed in the proposed local floodplain development plan. 

2.4 Ministerial Directions and Practice Notes 

(i) Ministerial Directions 

Council  submitted  that  the Amendment meets  the  relevant  requirements of  the  following Ministerial Directions: 

Ministerial Direction No 11 ‐ Strategic Assessment of Amendments 

The  Amendment  is  consistent  with  Ministerial  Direction  11  (Strategic  Assessment  of Amendments) and Planning Practice Note 46 (Strategic Assessment Guidelines). 

                                                       4  Refer to clauses 44.04‐1 and 44.05‐1. 

Page 25: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 16 

 

The Form and Content of Planning Schemes (s7(5)) 

The Amendment  is  consistent with  the Ministerial Direction on  the  Form  and Content of Planning Schemes under Section 7(5) of the Act. 

(ii) Planning Practice Notes 

Council  submitted  that  the  Amendment  uses  the  most  appropriate  VPP  tools  and  is consistent with Planning Practice Note 11 ‐ Applying for a Planning Permit under the Flood Provisions (August 2015) and Planning Practice Note 12 ‐ Applying the Flood Provisions in Planning Schemes (June 2015). 

In particular, the Practice Notes identify the LSIO and SBO as the appropriate tools to apply in circumstances where relatively shallow overland flows occur in urban areas during rainfall events of an intensity which exceeds the capacity of the established drainage infrastructure. 

2.5 Discussion 

The Amendment  is  supported by State and  local planning policy.    It  is consistent with  the directions from the Victorian Floodplain Management Strategy.   Planning Practice Notes 11 and 12  support  the use of  the  LSIO and SBO.   The  selection of  the overlays  is considered suited  to  the  local  flooding  conditions experienced  in Bendigo.   Schedules  to  the overlays have been drafted to  limit unnecessary planning permit applications, and are supported by the Bendigo Local Floodplain Development Plan to assist in the preparation and assessment of planning permit applications. 

An  important  element with  the  overlays  is  that  they  do  not  affect  land  use  and  do  not prohibit development, but do  require  that development  requiring  a permit  is assessed  to determine if such development would impact on, or be impacted by, flood processes. 

The Panel considers the Amendment is necessary to implement the policy regime under the planning scheme and has appropriately demonstrated strategic justification. 

2.6 Conclusion 

The Panel  concludes  that  the Amendment  is  supported by,  and  implements,  the  relevant sections of the SPPF and LPPF, and is consistent with the relevant Ministerial Directions and Practice  Notes.    The  Amendment  is  well  founded  and  strategically  justified,  and  the Amendment  should  proceed  subject  to  addressing  the  more  specific  issues  raised  in submissions as discussed in the following chapters. 

Page 26: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 17 

 

3 Technical basis and mapping of the Amendment 

3.1 The issue 

Are the proposed flood controls for Bendigo based on data and flood modelling and mapping that has an appropriate level of accuracy and rigour? 

3.2 Submissions and evidence 

Ms Camille White, Floodplain Manager for the NCCMA provided the Panel with background to the  flood modelling which had been commissioned by the NCCMA  in collaboration with Greater Bendigo City Council. 

She advised that the  flood study covered an area similar  in size to greater Melbourne and when  commenced  was  one  of  the  largest  flood models  prepared  in  Victoria.    This  has resulted in difficulties identifying appropriate storms to use in calibration, as different levels of rainfall were experienced in different parts of the catchment.  The final model represents the worst flooding that  is  likely to occur  in each area of the catchments, at the same time, which would be an impossibility, as no 1 in 100 year storm could uniformly cover the entire catchment. 

She advised that as Bendigo is surrounded by State forests there is considerable pressure on infill development, which occurs frequently  in flood prone areas.   She noted that there are no  high  quality  studies  or  mapping.    Previous  modelling  of  the  Bendigo  Creek  was undertaken in 1994, but without calibration. 

The existing LSIO is a carryover from the old format scheme and has not been updated.  The Bendigo Urban Flood Study was one of the flood studies where an independent peer review process had not yet commenced on a regular basis.  As a result the independent peer review commenced part way through the study’s process. 

Ms White advised that the NCCMA had thoroughly reviewed the results from approximately 50,000  properties  and was  confident  that  the modelling  correctly  identifies  properties  as being affected by flooding, but there may be variation in the depth of flooding.  She further advised  that  due  to  the  confidence  the  NCCMA  has  in  the  flood mapping,  it  has  been prepared  to place  the mapping on NCCMA’s website as a property  search engine entitled “Flood Eye”.   This  search  facility allows  the general public  to  interrogate  the modelling  in relation to a particular address to identify if the property is subject to flooding and to what depth. 

Ms Emma Bryant, Amendments and Heritage Coordinator, Statutory Planning on behalf of Council advised that representatives of Council and the NCCMA had met with many of the initial submitters to review site specific issues.  In several cases the extent of flood mapping had been revised and in some cases the objection withdrawn. 

Mr Bishop  gave  evidence  to  the  Panel  in  relation  to  the modelling.   He  advised  that  the terrain data  (LiDAR) was  specifically undertaken  for  the  flood modelling  study  in 2009/10 and was of very high quality.  He did acknowledge that, particularly at the early stages of the modelling,  the hydrological  information was  lacking due  to  the  large number of hydraulic structures  such  as  pipes  and  culverts  throughout  the  urban  areas  of  Bendigo.    He  also 

Page 27: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 18 

 

acknowledged  that calibration data was  less  than  ideal, as  rainfall  is not uniform over  the whole of the catchment  in any one storm due to the  large size of the catchment.   Further issues were encountered due  to  the  lack of  local  rainfall  gauges  and  stormwater  gauging stations and consistent records. 

Mr Bishop advised that a paucity of gauging  information frequently occurs when modelling river  catchments  is  undertaken.    As  a  result,  hydrologists  and  hydraulic modellers  have developed a variety of tools to assist in developing appropriately accurate models. 

The adopted methodology considered the catchment in two parts.  The first was the “spine” or main creek and tributaries which utilised a traditional rainfall and run‐off model, and then a “Rain on Grid” method was used to model discrete inflow and rainfall over each area.  He advised that this approach has been used successfully elsewhere over the last five years for similar flood modelling studies. 

Mr Bishop advised that was not common to include fences, houses and the like in a study of this  size  due  to  practicality  issues.    Modelling  uses  assumptions  to  account  for  broad impacts, which give a good representation of  the  flood  flow  impacts.   He advised  that  the impact of fences and other buildings would be used in much more detailed modelling, such as  for  an  individual  development.    He  also  advised  that  it  was  neither  feasible  nor appropriate to try and  include all pipes within the modelling, due to the size of the model but also due to the fact that the stormwater pipe system is designed for a 1 in 10 year storm event and not a 1  in 100 year  storm event.    In his opinion,  for a 1  in 100 year  storm  the hydraulic capacity of the standard stormwater pipe system becomes insignificant.  Mr Bishop stated  that  the  accuracy of  the modelling  is  suitable  for use  in  the planning  scheme  and notes  that  it would be expected  to be upgraded  in  the  future as  individual developments occur and software and data management further improves. 

Several submitters5 raised concerns in relation to the potential impact on the modelling due to the effect of subdivisions, buildings and other works, which had occurred since the LiDAR data had been captured and the modelling commenced.6 

Mr Gavan Conroy (Submitter 18) presented several instances where he considered there to be inaccuracies related to the modelling information available on the Flood Eye portal of the NCCMA website.  As an example he quoted the St Killian’s Church, which is a landmark site within Bendigo and has not been flooded  in  living memory.   He notes that the flood height on Flood Eye  for a 1  in 10 year storm  is higher  than  from 1  in 100 year storm.    It was his opinion  that  this  and  other  examples  demonstrated  considerable  inaccuracy  in  the modelling, which should result in the Panel rejecting the proposed flood mapping. 

Ms Andrea Metcalfe (Submitter 38) and supported by Mr Ralph Conboy both raised concerns that  the  modelling  had  not  considered  the  residents’  experiences  during  major  rainfall events  in the Ascot area.    It was their contention that a storm  in  January 2011 resulted  in considerably higher flooding than the storm which occurred in February 2011.  However, the January 2011 storm was not considered during the calibration or modelling.  They therefore consider that the modelling underrepresents the 1 in 100 year flood in the Epsom area. 

                                                       5  Submitters 2, 28, 36 and 40. 6  LiDAR data was dated 2009. 

Page 28: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 19 

 

Mr  Gerard  Gilfedder,  Town  Planner  on  behalf  of  Bendigo  Properties  (Submitter  36), Mr Bruce  Beasley  (Submitter  2), Mr  Ron  Bergmeier  Chairman  of  the  Epsom/Huntly Drainage Committee  (Submitter  28)  and  others  raised  concerns  in  relation  to  the  accuracy  of  the mapping due to a number of mitigation options being  identified  in the flood study but not modelled.    In  general  terms  they  requested  that  the mitigation options be modelled  and included in the planning scheme. 

Mr Bergmeier advised the Panel that the Committee was formed at the commencement of drainage studies in the area and has been working with Council throughout the process.  He advised that additional studies undertaken by BMT WBM and commissioned by Council have identified discrepancies in the flood modelling in the Epsom Huntley area.  He acknowledged the lack of data and options for further revision of the flood mapping but confirmed that the Committee remains concerned  in relation to the accuracy of the modelling  in different rain events.  It is the Committee’s opinion that Council should spend more money to improve the accuracy of the modelling. 

3.3 Discussion 

The Panel queried Mr Bishop in relation to the level of independent peer review undertaken, as  his  witness  statement  stated  that  the  study  method  was  peer  reviewed  by  an independent panel of  technical experts  appointed by DELWP, but not  the  results nor  the calibration.  He advised that the modelling outcomes were thoroughly reviewed by both in‐house experts and the NCCMA. 

This evidence was  contradicted by Ms White, who provided  the Panel with a  copy of  the Traffic Light Report of the final report, prepared by the  Independent Peer Reviewers, after Mr Bishop had completed giving his evidence.   When queried  in relation  to  this Ms White advised  that  the  Traffic  Light  Report  had  been  forwarded  to Water  Technology  and  the NCCMA assumed that all relevant comments were incorporated into the modelling and final report, despite the Panel noting that the response column in the Traffic Light Report has not been completed by Water Technology. 

Whilst the Panel has some reservations in relation to whether the Independent Peer Review panel’s  comments were all  incorporated  in  the  final  report,  the Panel  is  satisfied  that  the modelling  has  been  checked  by Water  Technology  and  in many  instances  verified  by  the NCCMA as part of their site  inspections undertaken  in conjunction with Council.   The Panel has noted some instances where further review and modelling could assist in better refining the  overlays,  but  is  of  the  opinion  that  these  instances  are  not  sufficiently  significant  to warrant  the  Amendment  not  proceeding  or  being  delayed  until  additional  modelling  is undertaken. 

Regarding  the application of overlays based on modelled mapping of  flood extent and  its associated accuracy, the Panel notes that the  level of accuracy  is commensurate with cost‐benefit.  Greater accuracy can be achieved with finer scale modelling, however, the cost and time  involved  in  conducting  such work may not be  commensurate with  the benefits  that accrue for an area that is urban in character. 

Page 29: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 20 

 

The Panel notes the commentary provided in the Final Report New Format Planning Schemes on the introduction of flooding controls:7 

In  the  panels’  view,  if  accurate  flood mapping  has  not  been  completed  by DNRE, the relevant floodplain management authority should determine what land is potentially or likely to be affected by flooding and that land should be included in a Land Subject to Inundation Overlay.  It does not matter that the boundaries may not be accurate at the time the overlay  is applied.   The Land Subject  to  Inundation  Overlay  only  requires  that  a  permit  be  obtained  for buildings and works.  It does not prohibit either use or development.  The time to examine the evidence  in detail about where the flood  levels  lie  in fact  is at the time a permit application is made. 

The  same approach needs  to be adopted even when  flood  levels have been verified  by  DNRE  but  individual  landowners  dispute  their  accuracy.    Panels usually do not have the resources to examine  in detail competing arguments about where the flood levels lie on an individual property when there is a lack of agreement about this.  At the amendment stage it is usually irrelevant.  It is a matter more appropriately sorted out at the time any permit may be applied for. 

The panels recognise that in those very flat parts of Victoria prone to flooding, the  Land  Subject  to  Inundation  Overlay  may  cover  huge  areas  of  a municipality.   Minimal variations  in height will make a substantive difference to whether  the  land  floods or not.    In  those circumstances,  landowners may well be  reluctant  to see  the whole or substantial portions of  their properties covered by the Land Subject to  Inundation Overlay  if they believe that  in fact their land does not flood.  However, it needs to be recognised that the overlay is not the last word.  Its application will not alter the fact of whether the land floods or not.   Rather,  it  indicates that  flooding  is a problem  in the area and needs  to  be  carefully  considered when making  any  planning  or  other  land management decisions concerning the property. 

The  Panel  considers  the  above  comments  are  relevant  to  this matter  and  considers  the accuracy  of  the  extent  of  coverage  of  the  LSIO  and  SBO  is  somewhat  secondary  to  the following: 

Identification  of  flood  risk  on  a  parcel  of  land.    This  is  based  on  the  benchmark established in State policy under Clause 13.02‐1 for 1 in 100 year flood extents to be mapped. 

Introducing a permit process for forms of development that Council and the NCCMA would  want  to  consider  and  through  which  the  key  impacts  of  the  proposed development both from and on flood processes can be appropriately assessed and determined. 

Both Mr Bishop and Ms White advised that there are always  limitations on the availability and  quality  of  data when  undertaking  storm modelling,  particularly when  considering  an 

                                                       7  Compiled by Helen Gibson, Chief Panel Member, Planning Panels Victoria, April 1999 at page 64. 

Page 30: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 21 

 

urban area as  large as Bendigo.   While they acknowledged that there may be areas where further  refinement  of  the mapping  could  be  considered,  both  stated  that  based  on  their experience  the  flood mapping as presented  is at an appropriate  level of accuracy  for use within the planning scheme.   The Panel was presented with several  instances where either additional modelling  was  undertaken  or  reviewed  by  the  NCCMA  and  Council  to  refine individual  sites  subsequent  to  completion  of  the modelling.   Ms White  advised  that  site inspections had been undertaken with  individual owners at approximately 700 sites, which resulted in recommended changes to the flood mapping presented to the Panel for 16 sites.  Having  undertaken  site  inspections  at  16  locations  and  driven  extensively  around  the catchment to gain an understanding of submitters’ concerns, the Panel is also of the opinion that the flood mapping as proposed, including recommended modifications presented at the hearing, are suitable for adoption for the planning scheme. 

While the accuracy of the Flood Eye portal does not form part of the Panel’s considerations, it  was  noted  that  issues  relating  to  its  mapping  accuracy  had  been  raised  in  various submissions, prompting the Panel to seek comment from the NCCMA.  Ms White’s response was  that  Flood  Eye  had  only  recently  been  established  and  currently  is  only  accurate  in relation  to  the  1  in  100  year  storm.    She  advised  that  additional  modelling  is  being undertaken  by Water  Technology  to  establish  lesser  flood  levels.    In  relation  to  the  St Killian’s Church example she advised that as the flood modelling abuts one corner of the site Flood Eye automatically  lists the whole property as being  impacted.   It does not mean that the whole property will be underwater – only that flooding may be an  issue and should be investigated further. 

Both Ms Bryant and Ms White in their respective rights of reply submitted that a number of mitigation options had been identified and some are currently being investigated.  Further, it would not be appropriate to hold up the planning review until the mitigation options have been both modelled and implemented, as this could be a number of years away.  It was their opinion that the Amendment should proceed and that following resolution of the mitigation options,  it may  be  necessary  to  amend  the  planning  scheme  at  some  future  date  via  a separate amendment process. 

Based  on  the  expert  evidence  provided  and  the  testing  of  that  evidence,  the  Panel  is satisfied  that  the  data, methodology,  calibration,  independent  review  and  flood mapping undertaken for the Bendigo Urban Flood Study  is of a  level of accuracy which  is more than sufficient to identify properties which are likely to be flood affected in a 1 in 100 year flood event.   The Panel  is  therefore supportive of  the proposed application of  the extent of  the LSIO and SBO under the Amendment. 

Panel  notes  that  the  inclusion  of  these  overlays  on  a  property  does  not  preclude development, but is used to identify that flooding may be an issue for any development on that land and therefore requires further investigation via the planning permit process. 

3.4 Conclusion 

The Panel concludes that the hydraulic modelling and mapping for the 1  in 100 year storm event, which was used in the preparation of the LSIO and SBO maps, is of a suitable level of accuracy to be used for planning purposes. 

Page 31: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 22 

 

4 Site specific issues 

4.1 The issues 

A  number  of  submitters  raised  concerns  regarding  the  flood  modelling  and  mapping affecting  their  particular  properties  and  the  level  of  accuracy  of  such mapping.   General issues relating to the lack of detail with hydraulic modelling were raised, as well the effects of  the  Amendment  on  existing  and  approved  development.    Submitters  raised  issues regarding  the  future  of  the  Environmental  Significance Overlay  Schedule  1  (that  seeks  to protect waterways) given the changes arising from approved developments, and queried the necessity of retaining the overlay. 

Based on the submissions received and the Panel’s site inspections, different regions of the various  catchments  affected  by  the  Amendment  have  been  identified  as  having  similar issues.  As a result, the Panel has addressed particular issues as they relate to different areas of the various catchments.  This is not to say that the same issues don’t occur in other areas but rather that there was more of an emphasis on these  issues  in these areas, or that the issues raised were applicable across other parts of the catchment areas. 

4.2 Hydraulic modelling details 

4.2.1 Submissions and evidence 

Ms  Andrea  Tomkinson  (Submitter  40)  on  behalf  of  the  Northern  Chapter  of  the  Urban Development Institute of Australia (UDIA) raised a concern in relation to the accuracy of the hydraulic modelling for having not included existing buildings, fences and the like.  She noted that  in some cases  the deepest  flooding  is shown where  there are existing dwellings.   She contended  that  if  the mapping  is  not  100  per  cent  accurate,  the  policy  should  recognise situations  where  more  detailed  or  up‐to‐date  information  should  be  taken  into consideration. 

Ms White  advised  that  due  to  the  size  of  the model  it would  be  impossible  to map  all buildings,  fences and  the  like.   This was also confirmed by Mr Bishop, who reiterated  that physical features such as fences, individual dwellings and sheds that may influence overland flood  flow  behaviour  are  not  explicitly  modelled  and  that  such  detail,  at  an  individual property level, is not feasible to be included given current data and modelling capabilities. 

He advised  that  it  is accepted  industry practice  to adopt hydraulic model parameters  that allow  the model  to  best  represent  the  terrain,  structures  and  vegetation  present.    This means  that whilst  local  flow details  around  individual buildings,  for example, may not be accurately  represented,  the  overall  pattern  of  floodplain  inundation  is  reproduced  with some  confidence.   Ms White  further  advised  that  the  purpose  of  the mapping  and  the Amendment is to identify land that is liable to flooding so that development can be planned for  accordingly.    She  noted  that  detailed modelling  can  be  provided when  development applications  are prepared, which may  result  in  changes  to  the  coverage of  the overlay  in future. 

Page 32: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 23 

 

4.2.2 Discussion  

The Panel accepts that the Council and the NCCMA have made all reasonable endeavours in relation to the accuracy of the modelling given the constraints of the size and the amount of data available.   As previously stated  in Section 3.3, the benefit of the LSIO and SBO are to identify properties that are liable to flooding and to put in place a permit trigger and process through which further detailed assessment of flood risk can be undertaken against the form of proposed development.  If a proposed development can appropriately mitigate flood risk and gain approval, then the necessity of the overlays may alter.  Ms Bryant also advised that Council undertakes  regular  reviews of  the planning  scheme, which  can  include  correcting amendments  that  can  include  changes  to  the  coverage  of  the  overlays.    The  Panel  is reassured by these processes. 

4.2.3 Conclusion 

The  Panel  concludes  that  the  nature  of  the  hydraulic modelling  is  fit  for  purpose  in  the application of the LSIO and SBO to ensure flood risk is appropriately taken into consideration through the planning permit process, which includes referral to the NCCMA. 

4.3 Existing and approved development 

4.3.1 Submissions and evidence 

The Panel heard submissions primarily from Mr Gilfedder (Submitter 36) and Mr Lou Garita (Submitter 30) relating to the impact of proposed flooding overlays on several developments that included subdivisions.  The key issue related to the development of subdivisions within the catchment for which a planning permit has already been issued but may now be affected by the LSIO and SBO.   Submitters were seeking removal of the overlays  in areas which had either been developed or were proposed to be developed as part of approved developments including subdivisions. 

Mr Gilfedder submitted that the proposed application of the LSIO1 under the Amendment to a  29.61  hectare  industrial  site  beside  the  Bendigo  Airport  in  East  Bendigo would  be  an onerous constraint on the development of the site.  The industrial site has the benefit of an existing Planning Permit No DS/763/2010  issued on 9 March 2011  for a staged subdivision with  a  ten  year  expiry.    Preparation  of  plans  for  the  development  of  the  industrial subdivision  has  included  consideration  and  design  for  flooding.    This  includes  floodway treatments within  the  road design of  the development  to convey and manage  floodwater flows.   Application of  the extent of  the LSIO1 proposed under  the Amendment would not reflect  the ultimate development outcome of  the  existing planning permit,  and  the  site’s true flood risk. 

Mr Gilfedder’s submission was supported by evidence from Mr Thomas Zahle, civil engineer from  Spiire, who  reiterated  that  the  application  of  the  new  LSIO1  overlay would  extend through the middle of the site based on the existing site conditions and not the ultimate site conditions that had been approved, that would contain the 1 in 100 year flows and manage flood  risk.    Mr  Zahle  considered  the  imposition  of  the  proposed  LSIO1  would  be  an unrealistic impediment to both the future viability of industrial development and land sales.  This is due to the longer lead time for industrial development and the lengthier time period within  which  the  overlay  would  act  as  a  constraint  compared  to  when  on‐site  flood 

Page 33: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 24 

 

mitigation works  are  undertaken  for  each  progressive  stage  of  the  industrial  subdivision.  This  time  lag would be  reflected by  the  slowness  involved with adjusting or  removing  the overlay under future amendments to the planning scheme. 

The imposition of the LSIO would act as a constraint with future staged development of the subdivision  and  through  triggering  unnecessary  permits  and  becoming  ‘out  of  sync’ with development as it progressed in each future stage of development. 

Mr Gilfedder considered that the LSIO1 should be contained to the flood channel and road reserves  designed  for  flood mitigation  as  part  of  the  engineering  plans  prepared  for  the industrial subdivision.  Mr Gilfedder stated that this change to the Amendment would: 

Accurately reflect the ultimate development outcome for the site and how the 1 in 100 year flood would be managed 

Better  reflect  the  proposed  development  works  that  would  allow  for  the appropriate passage and management of  stormwater and manage any  significant rise in flood level or flow velocity 

Integrate with  the development of  the  land  that would only occur  in accordance with  the  approved  development  plan  so  there  is  no  increased  flooding  risk  to property in the interim period until the works are completed. 

In the event that the reduction in the coverage of the proposed LSIO1 was not accepted, Mr Gilfedder suggested an alternative position, with reference to the status of existing planning permits  being  reflected  in  the  Schedule  to  the  LSIO  by  way  of  a  permit  exemption  for building  and works.    He  advised  this  issue was  recognised  in  the  processes  for  Ballarat Planning Scheme Amendment C178 relating  the Burrumbeet Creek  flood controls where  it was considered  that applying  the overlay was contrary  to approved planning permits  that had appropriately addressed flooding matters. 

In that  instance  it was considered that an exemption be  included to ensure that permitted developments do not require additional planning approvals under the LSIO for building and works. 

He included the following suggested wording: 

Permit requirement 

A permit is not required for the following: 

If land has been developed in accordance with a planning permit, restriction or section 173 agreement requiring its ground surface level to be finished at least 300m above the designated 1% AEP flood level; and, 

Survey plans confirm that the ground surface level has been constructed in accordance with  the  requirements  of  the  planning  permit,  restriction  or section 173 agreement; and, 

Any buildings and works do not lower the ground surface level or result in a finished floor level for a dwelling that is below 300m above the designated 1% AEP flood level. 

Similarly, Mr Garita  submitted  that  applying  the  overlays where  future  development  has been the subject of extensive and detailed planning that includes consideration of flood risk should avoid creating excessive and unnecessary permit requirements.   He recognised that 

Page 34: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 25 

 

removal  of  the  LSIO  prior  to  the  granting  of  development  approvals  would  be  difficult, however he sought that adjustment to the extent of the overlays should be processed  in a timely manner and not be held up with lengthy planning scheme amendment processes that become costly for landowners, developers and the community. 

The  NCCMA  were  not  supportive  of  removing  the  overlays  from  sites  where  existing approved development had been factored into the flood mapping.  Regarding development that has been approved but not completed,  the  response  from Ms White was  that where works are yet to be undertaken, removal of the overlays  is not supported because there  is no surety as to when the works will occur or whether they may be changed in the future. 

Council  also  appeared  somewhat  reluctant  to  extend  permit  exemptions  and  considered that, if anything, they would primarily benefit larger subdivision proposals.  Difficulties with amendment processes are acknowledged, but Council does undertake regular reviews of its planning  scheme  and prepares  correction  amendments  every  two or  so  years, which  can update anomalies and take into account on‐ground changes that make the extent of overlay coverage out of date. 

4.3.2 Discussion  

The Panel acknowledges the concerns expressed  in submissions from Mr Gilfedder and Mr Garita.   However,  it agrees with the NCCMA’s views that changes can occur between what might  be  approved  and what  actually  is  built, which  can  be  problematic with  respect  to issues such as flood risk.   In response to questions from Ms White, Mr Zahle admitted that drainage works had not been completed for the industrial subdivision in East Bendigo apart from Stage 1, and that without the LSIO1 other  lots could be developed without referral to the  NCCMA  for  review  of  flood  risk.    Mr  Zahle  also  acknowledged  that  the landowner/developer  could either  commit  to developing all  required  flood mitigation and drainage works upfront, or accept the extent of the LSIO1 mapping until such works are fully completed.  For these reasons, the Panel does not support removal or changes to the extent of  the  LSIO  or  SBO  for  areas where  development might  be  proposed  but  has  not  been approved and where development has been approved but not completed. 

The Panel does see merit  in recognising areas where development has been approved and completed  in  the overlay schedules.    In  this  regard,  the Panel considers  the LSIO and SBO schedules would  benefit  from  an  additional  permit  exemption  for  development  that  has been completed in accordance with an existing planning approval.  Modifying the exhibited LSIO  and  SBO  schedules  to  include  an  exemption  for  development  where  flood mitigation/onsite water management works have been proposed or  completed appears  a sensible  response.    The modification  would  be  to  exempt  buildings  and  works  on  land subject to an existing planning permit, restriction or agreement pursuant to section 173 of the  Act.    It  would  ensure  permitted  developments  that  have  already  addressed  flood concerns are not unnecessarily required to apply for additional planning permits. 

4.3.3 Conclusion 

The  Panel  concludes  that  removal  of  the  overlays  entirely  from  development  sites  is  not appropriate, given the risk of alterations to proposals, but does see merit in providing scope for approved development to be exempted under the overlays. 

Page 35: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 26 

 

4.4 Removal of the ESO1 

4.4.1 Submissions  

The ESO1 seeks to protect waterways in the Bendigo area and has been used in part as a de‐facto control  for  flood  risk management purposes.   The application of  the LSIO under  the Amendment replaces the flood risk management role performed by the ESO1.  The intention is to remove the ESO1 from land within the Bendigo area that is adjacent to fully constructed channels  or  pipes,  or  non‐designated waterways  that  have  little  biodiversity  value.    The overlay is only proposed to be removed from areas where it is located in urban situations of low environmental values where it has largely been operating as a flooding control and not as an environmental control. 

Arguing along  similar  lines, Mr Gilfedder presented on behalf of Arbor Estates Pty  Ltd  for land  in  Jobs  Gully  Road,  Jackass  Flat  (Submitter  21)  and MG  Estates  Pty  Ltd  for  land  in Edwards Road, Maiden Gully (Submitter 22) that waterways within their respective proposed residential developments should have the ESO1 removed.  He reasoned this was due to the waterways  running  through  both  these  sites  being  proposed  to  be  re‐constructed  / rehabilitated  as  part  of  the  overall  development  works  for  each  estate.    Mr  Gilfedder suggested  the  approved  works  associated  with  both  waterways  effectively  alter  their respective  environmental  values  and  given  they  form  part  of  the  developed  open  space networks of both  residential estates,  they would be  located within an urban environment with  little environmental and biodiversity value.   The approved works  for each  respective waterway are supported by planning permits, master plans, landscape plans and vegetation precinct plans. 

Both Council and NCCMA do not support additional changes to the ESO1 apart from those proposed under  the Amendment.   The NCCMA submitted  that a comprehensive review of the ESO1 has not been undertaken and  that  such an exercise  is outside  the  scope of  the Amendment.   Council  and  the NCCMA, however have  recognised  that  the ESO1  could be further reviewed, both the mapping and the planning scheme provisions, however this was not considered within the scope of this current Amendment. 

4.4.2 Discussion  

Ms White’s  submission  referred  to  the  fact  that discussions had been held with Goulburn Murray Water who are a determining referral authority under the ESO1 and who had agreed that on the basis of the following criteria, removal of the ESO1 could be pursued under the Amendment: 

There is no designated waterway 

The waterway is a concrete lined channel with no environmental values. 

Goulburn  Murray  Water  also  indicated  that  it  wanted  to  be  involved  in  a  more comprehensive  review  if  the  overlay  was  proposed  to  be  removed  from  other  areas.  Accordingly,  the  NCCMA  does  not  support  further  changes  to  the  ESO1  without  a comprehensive review that involves all stakeholders including Goulburn Murray Water. 

The Panel agrees with Council and the NCCMA  in this regard.    It notes that the purpose of the  redevelopment  of  the waterways  in  these  residential  estates  seeks  to  improve  their environmental condition and to perform a role as a natural open space environment for the 

Page 36: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 27 

 

benefit of both  residential estate developments.   Accordingly,  they are not concrete  lined sections of waterway and hence have remnant environmental value that would continue to benefit from the ESO1. 

In addition, the waterway through the MG Estates site and affected by the ESO1 runs wholly through  that site and any  removal of  the overlay  from  that site would effectively create a gap in the lineal extent of coverage of the overlay. 

Similar  issues are present with the Arbor Estates site, although the ESO1 coverage  is at the end of its lineal extent, which would not be as problematic in terms of creating any gaps in the coverage of the overlay if it was removed. 

However,  the purpose of  this Amendment  is  flood  risk management  and  control  and  the changes proposed to the ESO1 are confined  in terms of the criteria used to determine any changes to its coverage, which are not evident with Submitters 21 or 22. 

4.4.3 Conclusion 

Given the above and the concerns of Council and the NCCMA, the removal of the ESO1 from the MG Estates and Arbor Estates land would be a poor planning outcome.  Accordingly, the Panel  concludes  that no  additional  changes  to  the ESO1  should be made other  than  that proposed in the Amendment. 

4.5 Kangaroo Flat 

4.5.1 Submissions 

The topography of the Kangaroo Flat area typically comprises the Bendigo Creek running in a broad  valley  parallel  to  the  Calder  Highway  (High  Street  through  the  central  area  of Kangaroo  Flat)  approximately  200  metres  apart,  through  typical  residential  and  some commercial forms of development.  The 1 in 100 year flood modelling typically identifies the immediate  vicinity  of  the  creek  as  fast  flowing  with more  extensive  shallow  inundation primarily to the east between the creek and the Calder Highway. 

Submitter concerns centred generally around the extent of  flooding modelled,  including  in relation  to  the  impact  of  the  recently  upgraded Wesley  Street  Bridge, which  crosses  the creek.   Also of concern was the accuracy of the modelling as demonstrated by the multiple disclaimers  and  references  to  issues  associated  with  poor  quality  data  in  the  Water Technology  report.    Submitters  disagreed with  the Water  Technology  statement  that  the omission of smaller diameter stormwater pipes would have limited effect on flooding. 

Ms White advised that Water Technology undertook additional modelling  in relation to the Wesley Street Bridge, which  identified no  impact on downstream water  levels and  limited impact on upstream water  levels.    It was acknowledged  that  there are  inaccuracies  in  the modelling due to the limited availability of relevant data. 

Mr and Mrs Daniel and Megan Kreutzer (Submitter 12) raised a specific concern  in relation to the impact of a neighbouring property being covered with fill and the likely impact of this on their property during floods. 

Ms White advised that the fill is unauthorised and that Council and the NCCMA are working with the current landowner to resolve the issue.  The developer of the adjacent property has 

Page 37: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 28 

 

engaged  the services of a consultant  to determine whether  the  fill can  remain.   However, detailed development plans have yet to be provided and the landowner has not applied for a planning permit to either remove or retain the fill.  Ms White advised that there is potential for  the  proposed  LSIO  to  require  an  amendment  in  the  event  that  the  fill  is  allowed  to remain on the adjacent property. 

4.5.2 Discussion  

The Panel accepts the contention from both Water Technology and the NCCMA that it would be extremely rare for any flood modelling project to have all relevant data available for an area as  large as the Bendigo Creek catchment.   The Panel notes the evidence of Mr Bishop that stormwater reticulation pipes are generally designed for a 1 in 10 year storm event and not  a  1  in  100  year  storm  event,  where  the  capacity  of  the  stormwater  reticulation  is relatively  insignificant compared to the overall extent of overland  flows.   Having  inspected the general area the Panel accepts that there may be  inaccuracies  in the flood  levels but  is generally  satisfied  that  the  overall  extent  of  flooding  appears  reasonable.    As  further development is undertaken in this area the opportunity exists for further refinement of the extent of the overlay in the planning scheme. 

Regarding Mr and Mrs Kreutzer, as the resolution of the issue of fill on adjoining land is still outstanding, the Panel has  identified that the proposed LSIO should remain until such time as a planning permit application  is submitted which  identifies the  impact on flood flows on land in the vicinity of the proposed development. 

4.5.3 Conclusion 

The  Panel  concludes  that  flood modelling  in  Kangaroo  Flat  is  based  on  the  State  policy benchmark  for  flood  risk management  and  appropriately  supports  the  application  of  the overlays under the Amendment. 

4.6 Junortoun / Strathfieldsaye 

4.6.1 Submissions 

Junortoun  and  Strathfieldsaye  are  situated  to  the  east  of  Bendigo  in  the  Axe  Creek catchment.   They have been  included  in  the modelling as  they are considered part of  the urban area of Bendigo. 

Several  submitters  (Mr  Leigh Osborne  (Submitter 16), Ms Karyn Broad  (Submitter 20), Ms Joyce Beaumont  (Submitter 24), Mr Tony Knox  (Submitters 44  and 45)  and Mr Don Koch (Submitter 53)) from this area disagreed with the extent of the proposed overlay based on their experience over some years of living on their property and not experiencing flooding. 

Ms White  advised  that  there  had  been  a  number  of  other  submissions  from  this  area requesting  a  revision  of  the  LSIO,  following which  the  NCCMA  and  Council  conducted  a review  resulting  in  the  extent  of  the  LSIO  either  being  reduced  or  removed.   With  the exception  of  Mr  Koch’s  property,  Ms  White  advised  that  in  relation  to  the  submitters mentioned above the NCCMA and Council were unable to recommend further modification of the LSIO based on the modelling results and following their site inspections.  In relation to Mr  Koch’s  property,  Ms  White  indicated  that  following  further  review  the  NCCMA recommends  that  the  LSIO  be  amended  to  only  include  those  areas  affected  by  flooding 

Page 38: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 29 

 

from  the  tributary  of  Splitters  Creek.    She  provided  the  Panel with  an  aerial  photomap depicting  the  proposed  draft  area  to  be  amended  but  advised  that  further  refinement  is required. 

4.6.2 Discussion and conclusion 

Having  inspected  several  of  these  properties  the  Panel  accepts  the  submission  by  the NCCMA that the extent of LSIO should remain as proposed, with the exception of Mr Koch’s’ property.  For Mr Koch, the Panel considers that further investigation should be undertaken to better ascertain the extent of the application of the LSIO and/or SBO. 

4.7 Central Bendigo 

4.7.1 Submissions 

Within  central  Bendigo,  the  Bendigo  Creek  is  confined within  a  large  brick  lined  channel which receives stormwater from the surrounding pipe drainage system as well  is from  land further upstream. 

Mr  and Mrs  Kevin  and Margaret McDonald  (Submitter  47)  queried  the  accuracy  of  the modelling  based  on  their  experience  living  in  the  area  and  the  apparent  difference  in elevations between the creek and their property. 

Ms White  advised  that  the McDonalds’  property  is  existing  flood  prone  land  under  the current planning scheme and  that  the  recent modelling has better defined  flooding  in  the area.  However as the modelling indicates that the property will be flood prone during a 1 in 100 year flood the overlay should remain on the property. 

4.7.2 Discussion and conclusion 

The  Panel  agrees  with  the  NCCMA’s  response  in  relation  to  Submitter  47.    The  area  is currently  identified  as  liable  to  flooding  and  the  Amendment  proposes  to maintain  this recognition based on the State policy benchmark.  The Panel concludes no further change is necessary. 

4.8 Epsom/Huntly 

4.8.1 Submissions and evidence 

The Epsom/Huntly area  lies to the north of Bendigo on the comparatively flat plains to the east  of  the  Bendigo  Creek.    Much  of  the  area  is  protected  by  levee  banks  that  were constructed  in  the  1920’s  along  the  Bendigo  Creek  in  order  to  contain  flood  flows  from inundating the agricultural land to the east.  During flood flows the water level in the creek is higher  than  the  surrounding  land.    Council  and  the NCCMA  have  proposed  to  adopt  the SBO2 to identify land which would be inundated in the event of a breach of the levee banks. 

Several submitters (Mr Lindsay Sargeant (Submitter 19), Mr Charles Cornish (Submitter 31), Mr Robert Scheuffele (Submitter 34) and Mr Thomas Byrne (Submitter 48)) queried the need for  the overlay.   They considered  that  the overlay was unnecessary, on  the basis  that  the levees had been in place for many years and had not breached, or that in the event of flood flows  their properties would either not be affected or be affected  to a  lesser extent  than 

Page 39: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 30 

 

shown in the overlay mapping.  Submitters advised of no flooding in the past and highlighted failures by Council in the provision of adequate drainage infrastructure. 

Concerns in relation to flooding in this area were comprehensively addressed by the Epsom Huntley Drainage Committee (EHDC) represented by Mr Bergmeier.  The EHDC membership comprises  many  of  the  landholders  in  the  area  and  raised  issues  related  to  potential mitigation works, the peer review analysis of the flood modelling, the effect of development since  the  capture of  LiDAR data,  the accuracy of  the base data and  the effects of  climate change on flood modelling outputs. 

Potential Flood Mitigation Options 

The EHDC had received funding from the State Government and the Council to fund a flood mitigation options  study by BMT WBM.   Mr Bergmeier  advised  that early base modelling information  indicated differences between the modelling by the two specialist consultants.  These  discrepancies  raised  concerns  with  the  EHDC  in  relation  to  the  accuracy  of  the modelling  undertaken  by Water  Technology.    The  Panel was  advised  by Council  that  this work  is ongoing and currently the report  is with Council for comment and to resolve some technical  issues prior to release.   Ms White advised that Mr Bishop has acknowledged that there may be some differences between the two models, however  in his opinion there will be  no  major  changes  to  the  area  that  is  affected  by  the  Amendment.    Mr  Bergmeier requested that the Panel obtain a copy of the BMT WBM report to assist in decision‐making.  Council’s response was that the report is not yet publicly available. 

Peer review analysis  

The EHDC had raised concerns over the peer review of the outputs of the Water Technology final report.  Mr Bishop’s written expert evidence stated: 

The method adopted  for  the  study was peer  reviewed and  the  study  results were  internally  reviewed  by  Water  Technology  as  the  project  progressed.  Council  and  CMA  also  reviewed  the  study  outputs  at  various  stages.    The outputs  from  the  study  are  of  a  quality  and  standard  consistent with  best practice in floodplain mapping. 

The EHDC raised concerns in relation to the final report being reviewed internally by Water Technology and by Council and the NCCMA.  Also raising concern was Mr Bishop’s response to  the  Panel  that  the methodology  had  been  externally  peer  reviewed,  but  not  the  final report.   The EHDC questioned the accuracy of the Bendigo Urban Flood Study, given  it had not been peer reviewed in accordance with best practice and noting that the accuracy of the flood study had recently been called into question at a VCAT hearing.8 

Recent development 

Subsequent to the LiDAR capture  in 2009 new development has altered the  landscape and flow paths, which could impact on the flood mapping.  Mr Bergmeier advised that the EHDC provided video evidence to Council relating to flooding issues, which in its opinion have not been accurately represented in the flood modelling.  In particular, he noted the potential for 

                                                       8  Ethan Property Group v Greater Bendigo CC [2014] VCAT 824. 

Page 40: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 31 

 

water  to  flow  out  of  the  creek  rather  than  into  the  creek  via  drainage  pipes  during  high flows, and questioned whether this has been modelled. 

Mr Bishop  in his expert evidence addressed  the  concerns of  the EHDC  stating  that where Council had identified erroneous data due to modification of the topography, the model had been adjusted accordingly.  However, he pointed out that for a study of this scale there will be cases where terrain data is out of date compared to current conditions. 

Accuracy of base data 

The  EHDC  submitted  that  the  accuracy  of  the  base  data  is  not  of  a  standard  suitable  to enable  the  preparation  of  the  flood mapping  and  subsequent  flooding  overlays  for  the planning scheme. 

Mr Bishop acknowledged the limitations of available historical data but advised that this is a common problem with such flood studies and the best approach is to adopt a best practice approach and review the results as additional information becomes available. 

Climate change  

The future effects of climate change have not been considered in the modelling.  The EHDC considers that climate change may make extreme events more  frequent and  intense.   The EHDC considers that climate change should have been addressed in accordance with Clause 11.05‐4 of the SPPF. 

Mr  Bishop  stated  that  consideration  of  climate  change was  not within  the  scope  of  the project but noted that while the recurrence interval for storms may become shorter due to climate change it could be useful to consider a 1 in 200 year storm to understand what the effects of climate change may be. 

4.8.2 Discussion  

As  noted  elsewhere,  the  Panel  accepts  that  there  are  inaccuracies  associated  with  the modelling  of  such  a  large  area  and  in  particular  in  this  area where  there  is  a  paucity  of rainfall and gauging information.  However given the extended period over which the EHDC has been  raising  concerns  in  relation  to  the modelling  accuracy,  the Panel  considers  that there is merit in undertaking an early review of the flooding overlays in this area.  To this end the Panel considers that based on a technical review of the base modelling prepared by the two consultants, Council and the NCCMA should consider undertaking further refinement of the overlays in the Epsom Huntley area and if necessary undertake a further amendment to the planning scheme.   As the BMT WBM report has yet to be  finalised the Panel does not consider it appropriate for it to review the report. 

As noted  in  Section 3.3  above  the Panel notes  the  apparent  inconsistencies between  the submission of Ms White of the NCCMA and Mr Bishop in relation to whether the final report was externally peer reviewed and all concerns addressed.   While the Panel would be more reassured had both Mr Bishop and Ms White confirmed  that an external peer  review had been undertaken of all aspects of the final report, the Panel is satisfied that given the timing of  the  introduction of  the peer  review  system,  all  reasonable  efforts have been made  to ensure the accuracy of the modelling.  Accordingly, the Panel considers the mapping for the proposed Amendment is satisfactory. 

Page 41: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 32 

 

Panel  acknowledges  that  no  flood modelling  can  be  completely  up‐to‐date,  however  the Panel  is satisfied that the accuracy of the Bendigo Creek  flood modelling  is suitable as the basis  for  the application of  the overlays.   The Panel notes  that  future development  in  this area will provide opportunities for further refinement of the overlays. 

State policy relating to inland flooding influenced by climate change is currently vague.  The State policy benchmark for flood liability is based on the 1 in 100 year flood event.  Predicted effects from climate change include more intense and possibly more frequent storm events which may  result  in  flash  flooding events becoming more common.   The Panel  is satisfied that the Amendment  is soundly based given the current State planning policy directions  in the planning  scheme.   Addressing  climate  change may or may not  increase  the extent of coverage  of  the  overlays  or  trigger  the  need  for  a  review  of  the  type  of  planning  tools required to address the changed nature of future flooding events and processes.  Given this uncertainty,  the Panel  is not  in a position  to  comment.   Accordingly,  the Panel  concludes that  the  Amendment  is  satisfactory  and,  until  such  time  as  State  policy  provides  clearer guidance, the application of the LSIO and SBO as proposed is considered appropriate. 

The  EHDC  advised  that  the  Panel  process  had  provided  an  opportunity  for  positive community  consultation,  which  in  their  opinion  had  been  lacking  in  the  past.    They considered  they  have  a  much  better  understanding  of  the  magnitude  of  the  issues associated with the flood study, but have formed an opinion that the flood study should not be adopted this stage as they believe the necessary data has not been captured. 

The Panel appreciates the  level of practical detail provided by the EHDC on behalf of many landowners in the area.  It is acknowledged that there are gaps in the data and questions in relation  to  the  accuracy  of modelling  compared  actual  flooding  experienced  in  the  area.  However  the  application  and  use  of  overlays  such  as  the  LSIO  and  SBO  are  designed  to identify  those  areas  where  additional  consideration  needs  to  be  given  to  development within a floodplain.   

4.8.3 Conclusion 

The  Panel  concludes  that  the  approach  taken  to  flood mapping was  based  on  the  best available information, and is appropriate and should be adopted. 

4.9 Back Creek 

4.9.1 Submissions and evidence 

Back Creek is a tributary to the Bendigo Creek, which runs parallel to the east of the Bendigo Creek  prior  to  their  confluence  to  the  north  of  Epsom.    The  Back  Creek  is  an  ungauged catchment, which resulted  in a requirement to adopt  industry best practice to produce the estimates of flooding. 

Ms Metcalfe supported by Mr Conboy raised concerns that the modelling underrepresents the  1  in  100  year  flood  based  on  their  experience  during major  flooding  events  which occurred in January and February 2011.  They noted that the modelling had considered the February 2011 flood but not the January 2011 flood, and provided photos in support of their contention  that  the  January  flooding  level was  higher  than  February.   Ms Metcalfe  also raised concerns that the modelling had not  included the culverts under Taylor Street, thus 

Page 42: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 33 

 

further reducing the predicted  flood  levels downstream.   They advised that despite having previously  raised  these  issues with  the NCCMA  and Council,  the modelling  had  not  been updated to address their concerns. 

Mr Bishop’s evidence stated that the January 2011 flood was not as large in Bendigo as the February  2011  flood,  which  was  the  reason  it  was  not  chosen  as  a  calibration  event.  However, the anecdotal evidence provided by residents was considered where possible.  He advised that the method adopted for the study was peer reviewed and the adopted design flow verified by an independent panel of technical experts.  He was therefore confident the study results for this catchment are appropriate.   

In relation to the culverts at Taylor Street, Mr Bishop advised that they were subsequently added to the hydraulic model, however the results show that whilst these culverts have an impact on smaller  flood events,  they had  limited downstream  impact  in  the 1  in 100 year storm  event.    He  also  noted  that  in major  storm  events  there  is  a  likelihood  of  culvert blockage based on a high level of vegetation cover in waterways upstream, and therefore in his  opinion  the  original mapping  results  are  considered  appropriate  for  risk management purposes. 

4.9.2 Discussion  

While acknowledging  the difficulties associated with  the  lack of gauging stations and  local rainfall records, the Panel accepts that the modelling as presented is the best available and should be adopted for this area.  The Panel also acknowledges that the anecdotal evidence and photographs provided by Ms Metcalfe highlight the need for further refinement of the planning scheme as better data becomes available, particularly as  it  indicates the potential for an increase in the area affected by flooding. 

4.9.3 Conclusion 

The Panel concludes that the Amendment  is appropriate, but that Council and the NCCMA are encouraged to regularly review the flood modelling and mapping and make adjustments as necessary over time, as further information becomes available. 

4.10 Agreed mapping changes 

During  the  Hearing,  Council  and  the  NCCMA  advised  that  following  exhibition  of  the Amendment,  active engagement with  submitters has occurred  to  review  the Amendment mapping based on submissions received.   Ms Bryant and Ms White advised the Panel that agreed changes had been reached with a number of submitters regarding adjustment of the mapped coverage of  the LSIO and SBO.   Both Ms Bryant and Ms White  tabled a  series of correspondence and maps showing agreed changes to the LSIO and SBO mapping between what was exhibited and what has been agreed to be changed. 

The  Panel  notes  these  changes  and  considers  that  they  are  acceptable  and  should  be adopted as changes to the Amendment.  The mapped changes are included in Appendix D of this report. 

4.11 Recommendations 

The Panel makes the following recommendations: 

Page 43: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 34 

 

Amend  Schedules  1,  2  and  3  of  the  Land  Subject  to  Inundation  Overlay  and 1.Schedule  2  of  the  Special  Building  Overlay  to  include  the  following  additional permit requirement: 

Buildings and works on land subject to an existing planning permit, restriction or agreement 

if  land  has  been  developed  in  accordance  with  a  planning  permit, restriction or Section 173 agreement  requiring  its ground surface  level to be finished at least 300mm above the 100 year ARI flood level; and 

survey plans confirm that the ground surface level has been constructed in accordance with the requirements of a planning permit, restriction or subdivision; and 

any buildings and works do not lower the ground surface level or result in a  finished  floor  level  for a dwelling that  is below 300mm above the 100 year ARI flood level. 

Amend  Schedule  1  of  the  Special  Building Overlay  to  replace  under  Clause  1.0 2.Permit requirements the words “No exemptions specified” with the following: 

A permit is not required to construct a building or construct or carry out works as follows: Buildings and works on land subject to an existing planning permit, restriction or agreement 

if  land  has  been  developed  in  accordance  with  a  planning  permit, restriction or Section 173 agreement  requiring  its ground surface  level to be finished at least 300mm above the 100 year ARI flood level; and 

survey plans confirm that the ground surface level has been constructed in accordance with the requirements of a planning permit, restriction or subdivision; and 

any buildings and works do not lower the ground surface level or result in a  finished  floor  level  for a dwelling that  is below 300mm above the 100 year ARI flood level. 

Review  the  flood mapping  and  application  of  the  Land  Subject  to  Inundation 3.Overlay  and/or  the  Special  Building  Overlay  for  land  at  105  Trotting  Terrace, Junortoun  to  include  only  those  areas  affected  by  flooding  from  the  unnamed tributary of Splitters Creek. 

Review the base modelling of the BMT WBM model against the Water Technology 4.model to  identify  if there are any discrepancies, which warrant a revision of the flooding overlays in the Epsom/Huntly area. 

Adopt the changes shown in the maps in Appendix D to the coverage of the Land 5.Subject to Inundation Overlay and the Special Building Overlay. 

Page 44: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 35 

 

5 Other matters 

5.1 The issues 

Expansion  of  the  LSIO  and  introduction  of  the  SBO  has  generated  social  and  economic concerns  regarding  loss of  land values and challenges with  flood  insurance  through either increased premiums or inability to obtain cover for flooding. 

Drafting  issues  have  been  identified with  respect  to  permit  exemptions  in  the  proposed schedules  regarding  setbacks  from  waterways,  approved  developments,  building  size thresholds, relocatable dwellings and fencing associated with tennis courts. 

Flood mitigation through waterway maintenance has also been highlighted where the lack of maintenance has had an effect on flood extent and risk. 

5.2 Land values and insurance 

(i) Submissions and evidence 

A number of submitters expressed concerns that the disclosure of the flood prone nature of their properties will have a detrimental  impact on property values and  result  in  increased insurance premiums or inability to obtain insurance cover for flood.9 

Ms  Tomkinson  best  summed  up  these  concerns  regarding  land  values  and  insurance impacts.  She summarised correspondence dated 18 October 2016 from Mr Michael Easton, Director of McCormick Harris Insurance, a local insurance provider who stated that once the flood mapping from the Amendment is provided to the insurance industry, this information would join the range of inputs on which insurance advice, and premiums, are provided.  She submitted  that  Mr  Easton’s  advice  is  that  this  information  has  the  potential  to  cause concerns to existing property owners and any new developments.  It may see the customer faced with very high premiums for the cover or having only a select few  insurers willing to offer flood cover, or even fewer offering the customer the ability to elect not to have flood cover at all.  These constraints were considered by the submitter to lead to potential for an uninsured financial loss. 

Ms Tomkinson also submitted the disclosure of property at potential risk of flooding due to the application of the LSIO or SBO could impact on the sale and sale price of such property.  She considered that the lack of focus in advising affected property owners in relation to this issue  as  part  of  the Amendment  process meant  that many  property  owners may  not  be aware of the implications of the overlays until such time as they decide to sell or propose to undertake some form of development of their land. 

Council’s response to these  issues was that the mapping and Amendment seeks to  identify land  that  is  liable  to  flooding  to  facilitate orderly planning and appropriate assessment of proposed development.   Flooding constraints should not be  ignored  just because they may affect land values and insurance premiums. 

                                                       9  Submitters 24, 32, 34, 40, 42 and 47. 

Page 45: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 36 

 

Council considered that insurance premiums often can fall once flood studies are completed and are used by the insurance industry.  This is due to the risk of the unknown having been reduced.  High premiums are often because the insurer is uncertain of what the flooding risk will be and whether the land can be safely developed.  Once the risk is quantified in a study and the  land  is developed according to that risk, then  insurance premiums are  likely to be reduced. 

Land values will mostly be affected where  flooding  is significant and development has not been undertaken in accordance with the known risk of flooding. 

The NCCMA considered that properties that are  liable to flooding but have a development that specifically  responds  to  flood  risk are  likely  to have  lower  insurance costs.   Ms White advised  that  insurance  information was provided  in  the  information bulletin  sent  to every household  and  on  the  Amendment  web  page,  including  links  to  further  information.  Additional printed material was also available at the drop in sessions. 

The NCCMA submitted  that more  information provides more  informed outcomes and  that provision  of  high  quality  flood  data  will  help  insurers  to  price  risk  appropriately  and accordingly improve the level of service to the community. 

The evidence of Mr Bishop was that: 

Good floodplain management requires the identification of properties that are potentially  subject  to  significant  flood  risk  through  planning  overlays.    Any potential impact on land value and insurance premiums is not a consideration in appropriately identifying and managing flood risk to life and property. 

He  reiterated  the  point  that  the more  accurate  information  provided  on  flood  risk,  the better  insurers  can  define  risks,  allowing  them  to  take  a  less  conservative  approach  to insurance cover. 

Mr  and  Mrs  McDonald  indicated  that  their  insurance  premium  had  risen  considerably.  However, Ms White advised that the NCCMA had not yet provided the results of the Bendigo Urban Flood Study to the insurance industry.  Hence, the Panel understands that any recent increases  in  insurance  premiums  are  not  the  result  of  the  current  Amendment  or  flood mapping. 

(ii) Discussion 

The  Panel  notes  that  the  Amendment  seeks  to  apply  the  LSIO  and  SBO  on  the  basis  of mapping derived from an analysis of flood risk based on the State policy benchmark of a 1 in 100 year flood event.  This is a major flood event and one that the Panel, and probably most parties, acknowledge has not yet occurred in Bendigo.  The flood mapping and application of the overlays reflects the risk from flooding on properties that would be affected by such a large flood event.   

As the Panel has discussed earlier, the coverage of the overlays is a reflection of flood risk on a property and not necessarily an accurate depiction of where floodwaters may specifically reach,  or  whether  and  to  what  extent  a  particular  parcel  of  land  might  be  affected.  Accordingly, the overlays trigger the need for a planning permit, which is the process where finer scale assessment can occur. 

Page 46: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 37 

 

The Panel reflects on the Final Report on the New Format Planning Schemes  (1999) which expressed  the view  that  it  is not  the application of an overlay which makes  land prone  to flooding.   The  flood prone nature of some  land  is an existing  fact.   The overlay  is simply a mechanism  for  identifying,  for  strategic  and  statutory  planning  purposes,  the  flooding characteristics of that land. 

This is borne out in the evidence of Mr Bishop that: 

Whilst  there will  be  areas where  the  flood mapping  can  be  improved,  it  is necessary  to  provide  flood  overlays  as  a  means  of  triggering  the  referral process.    This  allows  for  the  assessment  of whether  flood‐related  planning conditions  are  necessary  at  a  particular  site.    This  is  part  of  the  orderly planning  process  that minimises  risk  for  individual  land  owners  and  for  the community more generally. 

With respect  to  land values,  the Panel notes  the commentary of  the Panel  in Amendment C50 to the Moreland Planning Scheme, which sought to introduce the SBO: 

… The value of any property  is determined by the complex  interplay of many different factors such as overall economic conditions, public economic policies, location,  streetscape and amenity, and  it  is difficult  to assign what effect,  if any,  the  identification  of  land  as  liable  to  overland  flows may  have  on  the value of a property. 

The comments of the Panel in Amendment C18 to the Stonnington Planning Scheme are also noted: 

….Panels have consistently found that there is no justification for setting aside of  any  SBO  amendment  on  the  basis  of  requests  for  compensation,  loss  of property value and possible increase in insurance premiums. 

The Panel considers the LSIO, the SBO and the Bendigo Local Floodplain Development Plan are in effect a suite of planning tools that: 

Are a depiction of a  flooding event  that has been ascertained  through  recognised assessment processes and in essence reflects an existing situation 

Outlines  the processes and procedures  for dealing with development applications for  land within  the overlay  limits and  is an approach  supported by both Planning Practice Notes 11 and 12 

Are directed towards meeting the responsibilities of Council as a planning authority as  required under Section 6(2)(e) of  the Act and  the broad  range of policies  that exist  in  regard  to  flooding  and  water  policy  statements  found  in  the  Greater Bendigo Planning Scheme. 

(iii) Conclusion 

The Panel concludes that  issues relating to  impacts on  land values and  insurance  from the application  of  the  LSIO  and  SBO  over  a  property  are  not  relevant when  considering  the introduction of the proposed Amendment.  The Panel also accepts that all reasonable efforts have been made in regards to informing the public affected by this Amendment. 

Page 47: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 38 

 

5.3 Amendment drafting 

(i) Submissions and evidence 

Council  submitted  that  it  has  considered  post  exhibition  changes  to  the  drafting  of  the overlay schedules and the local floodplain development plan in response to submissions. 

Goulburn‐Murray Water (Submitter 46) supported the Amendment particularly with regards to waterway setbacks for development.  They suggested the performance criteria for major residential  subdivisions  in  Section  5.1  of  the  Bendigo  Local  Floodplain Development  Plan relating to all new lots and new road reserves being set back a minimum of 30 metres from any waterway should be extended to all subdivision applications.  This includes those within residential,  Low  Density  Residential  and  Rural  Living  zones  regardless  of  lot  numbers.  Goulburn‐Murray Water  considered  the  change would  better  protect  surface water  and groundwater infrastructure, flows and quality from development. 

Council’s  response,  together with  the NCCMA, was  that  the  suggested  change would  be acceptable in the Low Density Residential and Rural Living zones, but not in other residential areas where  it was  considered difficult  to  achieve due  to  smaller  average  lot  sizes which would not have the capacity to achieve a 30 metre setback. 

Council advised that in conjunction with agreed changes to the coverage of the LSIO and SBO maps shown in Appendix D, the Flood Risk Map in Section 8 of the Bendigo Local Floodplain Development Plan would also require updating. 

Regarding the LSIO Schedule 1 and SBO Schedule 2, the Gold Nugget Tourist Park (Submitter 39) submitted that the installation or relocation of Unregistrable Movable Dwellings (UMDs) should be exempt  from  requiring a planning permit.    It was submitted  that  these  types of structures  are  currently  regulated  under  the  Residential  Tenancies  (Caravan  Parks  and Movable  Dwellings  Registration  and  Standards)  Regulations  2010  and  do  not  require additional regulation imposed under the proposed LSIO and SBO. 

Council supports the requested change and that an additional exemption in LSIO1 and SBO2 be included under new or replacement buildings for: 

A relocatable building associated with a caravan park where floor levels are at least 300mm above the 1% AEP Flood level. 

The  NCCMA  also  supported  Council  and  submitted  that  it  would  be  unlikely  to  oppose installation of a UMD  in an established caravan park but would recommend that, wherever practicable the finished floor level of the UMD be constructed a minimum of 300mm above the 1 per cent AEP flood level. 

Ms Tomkinson’s submission sought to amend the overlay schedules to remove building area threshold limits from the permit exemptions.  She contended that as the hydraulic modelling for the Bendigo Urban Flood Study had not factored in existing structures such as buildings, fences,  trees  and  the  like,  there  was  no  reason  to  limit  permit  exemptions  for  existing buildings to minimum or maximum floor areas and for the provisions to control the size of buildings. 

Page 48: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 39 

 

Mr Bishop’s evidence in this regard was that the hydraulic modelling for the Bendigo Urban Flood  Study  was  consistent  with  other  urban  flood mapping  studies.    As mentioned  in Section  4.2  features  such  as  fences,  dwellings  and  other  buildings  that  may  influence overland  flood  flow  behaviour  are  not  explicitly  modelled  and  that  individual  property details are not feasible to be included given current data and modelling capabilities. 

Accepted  industry practice  is to adopt hydraulic model parameters that allow the model to best represent the terrain, structures and vegetation present, allowing the overall pattern of floodplain inundation to be reasonably reproduced. 

He stated that at an individual lot level there could be refinement to enhance the resolution of  flood analysis as part of a specific planning application.   However, no  further details or analysis is required for the proposed overlays to be adopted. 

(ii) Discussion 

The Panel accepts Council’s position with respect to changes to the Bendigo Local Floodplain Development  Plan.    The  inclusion  of  the  performance  criteria  for  a  30 metre waterway setback  in the Low Density Residential Zone and the Rural Living Zone, as apart from other residential  zones,  is acceptable given  the  larger areas of  land under development and  the greater  scope  for  achieving  such  setbacks.   Council’s  reluctance  to  extend  the  setback  in residentially zoned areas for non‐major residential subdivisions appears to be based on the land area quantum.   The Panel considers this acceptable and  is aware that,  irrespective of what  the Bendigo  Local Floodplain Development Plan  indicates, State policy under Clause 14.02‐1 – Catchment planning and management includes the strategy for retaining natural drainage corridors with vegetated buffer zones at least 30 metres wide along each side of a waterway.   This aims  to maintain drainage  function,  stream habitat, wildlife corridors and landscape values.    It also seeks to minimise erosion reduce pollution.   Such a policy would remain  a  consideration  with  respect  to  any  planning  permit  application  as  a matter  of course. 

Changes  to  the  LSIO1  and  SBO2  to  address  UMDs  is  also  considered  acceptable  and appropriate  and would  ensure  that  such  structures  in  established  caravan  parks  are  not unnecessarily caught up in red tape. 

The Panel does not consider the overlay schedules require amendment to remove building area  threshold  limits based on  the assumptions built  in  to  the hydraulic modelling.   These types  of  permit  exemptions  have  been  used  with  some  consistency  in  other  planning schemes.    The  limitations  on  the  permit  exemptions  for  building  size  provides  a  level  of caution particularly with respect to providing an opportunity, through the permit process, to  assess  the  location of  buildings  and works with  respect  to  any  effects  they may have on flood  processes with  regards  to  other  properties  and  on  the  floodplain  storage  capacity itself. 

A matter identified by the Panel was the permit exemption under the LSIO1 and LSIO2 for a tennis court at existing surface  level with curtain fencing  if constructed  in accordance with the requirements of the Bendigo Local Floodplain Development Plan for earthworks.  Given the  permit  requirements  for  tennis  courts  under  Clause  52.21  –  Private  Tennis  Court  it 

Page 49: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 40 

 

would appear sensible to re‐focus the exemption on the type of fencing rather than for the tennis court itself.  Council agreed with this suggestion. 

(iii) Conclusion 

The  Panel  concludes  that minor  drafting  changes  to  both  the  Bendigo  Local  Floodplain Development Plan and the overlay schedules be incorporated as part of the Amendment. 

5.4 Waterway maintenance 

(i) Submissions 

Concerns regarding waterway maintenance and how the lack of maintenance affected flood behaviour and extent were raised by submitters.10 

The NCCMA’s response was that the presence of macrophyte vegetation such as Common Reeds  (Phragmites australis) and Cumbungi or Bullrush  (Typha spp.) are often assumed  to choke waterways and limit floodwater flows.  This is a misconception because these types of macrophyte  plants  are  usually  flattened  in  large  flood  events  and  have  little  impact  on floodwater  conveyance.    These  wetland/riparian  vegetation  communities  offer environmental value with respect to filtering pollutants and providing stream stabilisation by protecting the bed and banks of the waterways. 

(ii) Discussion and conclusion 

The  Panel  agrees  with  the  NCCMA’s  response  and  acknowledges  that  waterway maintenance  is  important  in  terms  of maintaining  environmental  health  and  function  of waterways.   Keeping  them  clear of obstruction  from  rubbish debris and exotic vegetation assists  in waterway health.   However, macrophyte vegetation does not  impede  floodwater flows  in  large  flood  events  and  their  retention  facilitates  the  continued  environmental function of waterways. 

5.5 Recommendations 

The Panel makes the following recommendations: 

Amend Schedule 1 of  the Land Subject  to  Inundation Overlay and Schedule 2 of 6.the Special Building Overlay under “New or replacement buildings” to include the following additional permit requirement: 

A relocatable building associated with a caravan park where floor levels are at least 300mm above the 1% AEP Flood level. 

Replace the fifth dot point under “Other buildings and works” in Schedules 1 and 7.2 of the Land Subject to Inundation Overlay to read: 

A curtain style fence for a tennis court if constructed in accordance with the  requirements  of  the  Bendigo  Local  Floodplain  Development  Plan 2016. 

                                                       10  For example, Submitters 1, 10, 49 and 52. 

Page 50: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 41 

 

 Amend  Section 5.1 of  the Bendigo  Local  Floodplain Development Plan 2016 by 8.introducing  the  following  dot  point  under  “Subdivisions  in  the  Low  Density Residential Zone or Rural Living Zone”: 

All  new  lots  and  new  road  reserves  are  set  back  a minimum  of  30 metres from any waterway. 

Update  the  Section  8  Flood  Risk  Guide  map  of  the  Bendigo  Local  Floodplain 9.Development Plan 2016 in accordance with the changes agreed to by Council and shown  in  Appendix  D  to  the  Land  Subject  to  Inundation  Overlay  and  Special Building Overlay mapping. 

 

Page 51: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 42 

 

Appendix A  Submitters to the Amendment 

No.  Submitter 

1  Clive & Bev Arnold 

2  B L & D E Beasley 

3  P F Comer 

4  A V Egan  

5  L G Morrison 

6  C F Pavletich 

7  P G & M L Holmes 

8  J R & N I Tate 

9  VicRoads – Northern Region 

10  N E Punton 

11  J A Lock 

12  M J & D R Kreutzer 

13  Environment Protection Authority 

14  P J Young 

15  M E & N J Bruhn 

16  L E Osborne 

17  S L Murtagh & A P Fuller 

18  G M Conroy on behalf of Matty High Pty Ltd 

19  L N & H Sargeant 

20  K J Broad 

21  Currie & Brown on behalf of Arbor Estates Pty Ltd 

22  Currie & Brown on behalf of MG Estates Pty Ltd 

23  Coliban Water 

24  J E Beaumont 

25  N T & C A Wilson 

26  D J & R J Ruedin 

27  D J & R J Ruedin 

28  Epsom Huntly Drainage Committee 

29  G J Power 

30  QOD Property Group  

31  C A Cornish 

Page 52: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 43 

 

32  H T & W D Hall 

33  R Lewis 

34  R W Scheuffele 

35  P J Trewartha 

36  Currie & Brown on behalf of Bendigo Properties Pty Ltd 

37  R Kumar 

38  A M Metcalf 

39  Gold Nugget Tourist Park 

40  UDIA Northern Chapter 

41  Department of Environment, Land, Water and Planning 

42  Total Property Developments 

43  A H Knox 

44  A H Knox 

45  A H Knox 

46  Goulburn‐Murray Water 

47  K A & M E McDonald 

48  T J Byrne 

49  W J Kane 

50  Country Fire Authority 

51  Lorient No 30 Pty Ltd 

52  L J Lubeck 

53  D Koch 

 

Page 53: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 44 

 

Appendix B  Parties to the Panel Hearing 

Submitter  Represented by 

Greater Bendigo City Council  Ms Emma Bryant, Amendments and Heritage Coordinator, Statutory Planning who called the following expert witness: 

‐ Mr Warwick Bishop, Civil Engineer and Flood Modeller from Water Technology Pty Ltd 

North Central Catchment Management Authority 

Ms Camille White, Floodplain Manager 

Bendigo Properties Pty Ltd  Mr Gerard Gilfedder, Town Planner from Currie & Brown (Australia) Pty Ltd who called the following expert witness: 

‐ Mr Thomas Zahle, Civil Engineer and hydrology engineering from Spiire 

Arbor Estates Pty Ltd  Mr Gerard Gilfedder, Town Planner from Currie & Brown (Australia) Pty Ltd 

MG Estates Pty Ltd  Mr Gerard Gilfedder, Town Planner from Currie & Brown (Australia) Pty Ltd 

Mr Don Koch   

Matty High Pty Ltd  Mr Gavan Conroy 

QOD Property Group Pty Ltd  Mr Lou Garita 

Mr Lindsay Sargeant   

Bruce L  and Dianne E Beasley  Mr Bruce Beasley 

Ms Karyn Broad   

Joyce Beaumont  Mr Craig Beaumont 

Mrs Megan & Mr Daniel Kreutzer   

UDIA Northern Chapter  Ms Andrea Tomkinson, Town Planner and Chair, Northern Chapter UDIA (VIC)  

Ms Andrea Metcalf   

Mr Kevin & Mrs Margaret McDonald    

Epsom Huntly Drainage Committee  Mr Ron Bergmeier 

Harold & Wanda Hall  Mr Harold Hall 

 

Page 54: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 45 

 

Appendix C  Document list 

No.  Description  Presented by 

  Tuesday 18 October 2016   

C1  Submission by Greater Bendigo City Council  Emma Bryant 

C2  Folder of documents ‐ Greater Bendigo City Council  “            “ 

C3  Planning Practice Note 12 – Applying Flood Provisions In PS’s  “            “ 

C4  Loddon Mallee South  Regional Growth Plan – March 2014  “            “ 

N5  North Central  CMA submission  Camille White 

N6  2 plans ‐ 183 Maiden Gully Road, Maiden Gully  “            “ 

N7  2 plans ‐ 165 Sullivans Road, Strathfieldsaye  “            “ 

N8  2 plans ‐ 31 Orchard Drive, Strathfieldsaye  “            “ 

N9  2 plans ‐ 5659 Calder Highway, Big Hill  “            “ 

N10  2 plans ‐ 23 Grantham Terrace, Kangaroo Flat  “            “ 

N11  2 plans ‐ 3 Page Court,  Kangaroo Flat  “            “ 

N12  LiDAR map of 126 – 128 High Street, Kangaroo Flat  “            “ 

N13  2 plans ‐ 244 Edwards Road, Maiden Gully   “            “ 

N14  2 plans ‐ 277 Howard Street, Jackass Flat  “            “ 

N15  2 plans ‐ 50 Leans Road, Huntly  “            “ 

N16  8 plans – 21 Plumridge Street, White Hills. 9, 10 and 11 Carrington Close, White Hills. 11A Arrawalli Avenue, Ascot. and 340A High Street, Kangaroo Flat 

“            “ 

N17  2 plans ‐ 746 McIvor Highway, Junortoun  “            “ 

K18  Submission by Don Koch [Submitter 53]  Don Koch 

CO19  Submission by Gavan Conroy [Submitter 18]  Gavan Conroy 

  Wednesday 19 October 2016   

C20  Correspondence regarding agreed changes between Council and land owners 

Emma Bryant 

CB21  Submission for Bendigo Properties P/L  Gerard Gilfedder 

CB22  Submission for Arbor Estates  “            “ 

CB23  Jackass Flat Vegetation Precinct Plan 2009  “            “ 

CB24  A3 Plan of Phase 2 for Evergreen Waters v3  “            “ 

CB25  Planning permit AM/904/2011/1A for Evergreen Waters  “            “ 

CB26  A4 Evergreen Waters Staging plan v3  “            “ 

CB27  A3 Canterbury landscape concept plan 6/6/16  “            “ 

Page 55: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 46 

 

No.  Description  Presented by 

CB28  Submission for MG Estates  “            “ 

CB29  Native Vegetation Precinct plan 244 Edwards Road June 2014  “            “ 

CB30  A3 plan Birchgrove revision H  “            “ 

CB31  2 x A3 plans Open space schematic and landscaping Aug 2015 Rev A 

“            “ 

CB32  A3 master plan Forest Park  “            “ 

CB33  A3 Design response – double sided  “            “ 

G34  Submission for Loma Estate P/L  Lou Garita 

B35  Submission by Bruce Beasley  Bruce Beasley 

KB36  Submission by Karen Broad  Karen Broad 

  Thursday 20 October 2016   

N37  Submission site plans with contours  Camille White 

C38  4 A4 aerial photos with contours  50 Bakers Lane and 628 Strathfieldsaye Road 

Emma Bryant 

T39  Submission by UDIA  Andrea Tomkinson 

T40  A3 plan of 367 Napier Street, White Hills  Emma Bryant 

M41  Submission by Andrea Metcalf  Andrea Metcalf 

M42  Copy of NCCMA information sheet 29/11/2011  “           “ 

M43  Copy of  Submission to VCAT P2692/13  “           “ 

M44  Appendix 3 from VCAT submission  “           “ 

M45  Appendix 4 from VCAT submission  “           “ 

M46  Appendix 5 from VCAT  submission  “           “ 

M47  Appendix 6 from VCAT submission  “           “ 

M48  Appendix 7 from VCAT submission  “           “ 

M49  Appendix 8 from VCAT submission  “           “ 

M50  Statement from Ralph Conboy  “           “ 

MD51  Statement from Kevin & Margaret McDonald  Kevin & Margaret McDonald 

H52  Statement from Epsom Huntly Drainage Committee  Ron Bergmeier 

H53  2 copies of Flood Eye reports dated 25 August 2016 for 343 Midland  Highway and Wallenjoe Road 

“           “ 

H54  2 copies of Flood Eye report dated 19 October 2016 for 343 Midland Highway and Wallenjoe Road 

“          “ 

H55  Submission by Max Turner  Max Turner 

Page 56: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 47 

 

No.  Description  Presented by 

HA56  Submission by Harold Hall  Harold Hall 

C57  2 additional agreed mapped changes for Submitter 42 for 58 Victoria Street, Eaglehawk 

Amanda Bryant 

M58  Copy of VCAT decision 824 of 10 July 2014  Andrea Metcalf 

 

Page 57: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 48 

 

Appendix D  Agreed changes to mapping for the LSIO and SBO 

   

Page 58: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 49 

 

 

Page 59: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 50 

 

Page 60: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 51 

 

 

Page 61: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 52 

 

Page 62: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 53 

 

 

Page 63: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 54 

 

Page 64: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 55 

 

 

Page 65: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 56 

 

Page 66: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 57 

 

 

Page 67: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 58 

 

Page 68: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 59 

 

 

Page 69: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 60 

 

Page 70: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 61 

 

 

Page 71: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 62 

 

 

Page 72: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 63 

 

Page 73: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 64 

 

Page 74: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 65 

 

 

Page 75: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 66 

 

 

Page 76: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 67 

 

 

Page 77: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 68 

 

Page 78: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 69 

 

 

Page 79: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 70 

 

 

Page 80: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 71 

 

 

Page 81: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 72 

 

 

Page 82: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 73 

 

 

Page 83: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 74 

 

Page 84: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 75 

 

 

Page 85: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 76 

 

 

Page 86: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 77 

 

 

Page 87: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 78 

 

 

Page 88: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 79 

 

 

Page 89: Planning and Environment Act 1987 - City of Greater Bendigo · resulted more from their experience during the 2010 and 2011 floods and earlier floods from the 1970s, where the perception

Greater Bendigo Planning Scheme Amendment C221  Panel Report  21 November 2016 

 

Page 80