19
Placing Equipment Chapter 5

Placing Equipment

  • Upload
    garren

  • View
    59

  • Download
    0

Embed Size (px)

DESCRIPTION

Placing Equipment. Chapter 5. Chapter Topics. Placing concrete directly from trick mixers Manual or motorized buggies Crane and bucket Concrete conveyors Concrete pumps. Placing Directly from Truck Mixers. Most economical placing method Minimal handling; minimizes segregation - PowerPoint PPT Presentation

Citation preview

Page 1: Placing Equipment

Placing Equipment

Chapter 5

Page 2: Placing Equipment

Chapter Topics

• Placing concrete directly from trick mixers• Manual or motorized buggies• Crane and bucket• Concrete conveyors• Concrete pumps

Page 3: Placing Equipment

Placing Directly from Truck Mixers

• Most economical placing method• Minimal handling; minimizes segregation• With chute extensions up to 20 ft• Deliver 8 to 10 cy and weigh up to 80,000 lbs• Avoid cracking sidewalks and driveways• Avoid open excavations or walls– If wall 6 ft deep, stay 6 feet away

• Take advantage of mixer-mounted conveyors

Page 4: Placing Equipment
Page 5: Placing Equipment
Page 6: Placing Equipment
Page 7: Placing Equipment
Page 8: Placing Equipment

Manual or Motorized Buggies• Transport from mixer to deposit

• Walk-behind or riding

• Some can fit through 36 inch doorways

• Placing capacity ranges from 15 to 20 cy/hr

• Consider costs– Buggy may need temporary ramps– Can’t run over reinforcing

Page 9: Placing Equipment
Page 10: Placing Equipment

Crane and Bucket• Lift concrete bucket to desired location

• Typically for small placements: columns

• Two buckets increase production

• Buckets– Different sizes: 1/3 to 3 cy– Different attachments: rubber discharge chutes

Page 11: Placing Equipment
Page 12: Placing Equipment

Conveyors

• Mounted to ready mix truck

• Separate conveyors

• Can discharge concrete quickly

Page 13: Placing Equipment
Page 14: Placing Equipment
Page 15: Placing Equipment

Concrete Pumps

• Trailer pumps– General purpose: 20 to 35 cy/hr– Pump up to 250 ft vertically – Pump up to 1000 ft horizontally– 4 to 5 inch diameter pipelines– Labor intensive for pipeline placing and removal

Page 16: Placing Equipment
Page 17: Placing Equipment

Concrete Pumps

• Boom-mounted pumps– Most efficient method for large placements

• Consider these factors– Delivery output– Pump layout and boom length– Site conditions– Number of pumps needed

Page 18: Placing Equipment
Page 19: Placing Equipment

End of Chapter 5