Piping – slide 29 Schlumberger Private PIPING Line sizing: gas/fluid velocities limitations to maximum : - 80 ft/sec if solids (sand) or 2-phase flow. - 160 ft/sec for dry gas. •if higher velocity expected, a full HAZOP is required as : - increase pipe ID, flare tip ID. - divers flow through more than one pipe. - reduce as much as practical the line length and number of bends - reduce the choke size. See FOH 1, Section 11 page 13 for gas velocity chart.

Piping Compatibility Mode

Embed Size (px)

DESCRIPTION

piping compat

Citation preview

Page 1: Piping Compatibility Mode

Piping – slide 29

Schlumberger Private

PIPINGLine sizing:• gas/fluid velocities limitations to maximum :

- 80 ft/sec if solids (sand) or 2-phase flow.- 160 ft/sec for dry gas.

•if higher velocity expected, a full HAZOP is required as :- increase pipe ID, flare tip ID.- divers flow through more than one pipe.- reduce as much as practical the line length and

number of bends- reduce the choke size.

See FOH 1, Section 11 page 13 for gas velocity chart.