18
Jørn Spiten 18 October 2013 Pipelines and seabed intervention Workshop on seabed habitats of environmental concern

Pipelines and seabed intervention

Embed Size (px)

Citation preview

Page 1: Pipelines and seabed intervention

Jørn Spiten

18 October 2013

Pipelines and seabed intervention

Workshop on seabed habitats of environmental concern

Page 2: Pipelines and seabed intervention

© Det Norske Veritas AS. All rights reserved.

Pipelines and seabed intervention

18 October 2013

Content

Pipeline

- route design

Seabed Intervention

- Trenching

- Ploughing

- Dredging

- Rock installation

2

Page 3: Pipelines and seabed intervention

© Det Norske Veritas AS. All rights reserved.

Pipelines and seabed intervention

18 October 2013

Pipeline routes

3

Page 4: Pipelines and seabed intervention

© Det Norske Veritas AS. All rights reserved.

Pipelines and seabed intervention

18 October 2013

Pipeline Routing - General

Minimise route length

- Installation aspects

- minimum curvature

- start/end, shore approach, tie-in

- laying tolerances/corridor

Minimise seabed intervention costs

- free span intervention

- rock outcrop, boulders

- trenching/burial

Avoid/minimise risks/hazards

- geohazards

- sand waves

- environmental forces

- ship lanes, anchoring, wrecks

- dropped objects

Minimise disadvantages for 3rd parties

- fishing areas

- other licences, future wells/platforms

- distance to parallel pipelines

Environmental aspects

- coral reeves

- threatened specimens

- oil spill

4

Page 5: Pipelines and seabed intervention

© Det Norske Veritas AS. All rights reserved.

Pipelines and seabed intervention

18 October 2013

Slide 5

DEVELOPMENT

AREA WATER DEPTH = 850 m

TOP OF SLIDE EDGE WATER DEPTH = 250 m

10 KM

N

TO SHORE

Survey coverage of the slide area

Ormen Lange case - slide area

Page 6: Pipelines and seabed intervention

© Det Norske Veritas AS. All rights reserved.

Pipelines and seabed intervention

18 October 2013

Slide 6

Long free spans

Page 7: Pipelines and seabed intervention

© Det Norske Veritas AS. All rights reserved.

Pipelines and seabed intervention

18 October 2013

Slide 7

Advanced routing

KP 12

KP 11

KP 8

KP 9

KP 10

Page 8: Pipelines and seabed intervention

© Det Norske Veritas AS. All rights reserved.

Pipelines and seabed intervention

2011-11-13

Seabed intervention

Page 9: Pipelines and seabed intervention

© Det Norske Veritas AS. All rights reserved.

Pipelines and seabed intervention

18 October 2013

Main methods

Commonly used

- Jet trenching – post-lay

- Ploughing – pre- and post-lay

- Dredging – pre- and post-lay

- Rock dumping - pre- and post-lay

Occasionally used

- Mechanical excavator – post-lay

- Remotely operated grab-dredger – pre-lay

- Sand/cement bags – post-lay

- Other mechanical supports

- Directional drilling

Slide 9

Page 10: Pipelines and seabed intervention

© Det Norske Veritas AS. All rights reserved.

Pipelines and seabed intervention

18 October 2013

Jet trenching

Slide 10

System that employs water jets to cut or

liquefy the soils around and in front of a

pipeline.

Soils removed by air lifts, water ejectors or

submersible pumps.

Used post-lay

Typical for cables, umbilicals and small

diameter pipelines

Page 11: Pipelines and seabed intervention

© Det Norske Veritas AS. All rights reserved.

Pipelines and seabed intervention

18 October 2013

Ploughing

Basically giant version of the agriculture plough

Pulled along the pipeline route and opens a wide trench

Both before and after pipe laying

Post-lay ploughing is steered by the pipeline

May use a backfilling plough or share

Different ploughs for different soil conditions

Multi-pass to get deeper

Large, heavy equipment – may damage pipeline in case of malfunction

Ploughing is fast

Associated with relatively high mobilization costs.

Slide 11

Page 12: Pipelines and seabed intervention

© Det Norske Veritas AS. All rights reserved.

Pipelines and seabed intervention

18 October 2013

Plough dimensions

Slide 12

Page 13: Pipelines and seabed intervention

© Det Norske Veritas AS. All rights reserved.

Pipelines and seabed intervention

18 October 2013

Ploughing trial

Slide 13

Page 14: Pipelines and seabed intervention

© Det Norske Veritas AS. All rights reserved.

Pipelines and seabed intervention

18 October 2013

Dredging

Soil is grabbed and lifted away or

Soil is sucked into a hose

Transported away from the area

(through either blasting it out through a

pipe or through storage tanks onboard

the dredging vessel).

Typically used in very shallow waters

and in landfalls.

Used pre-lay

Slide 14

Page 15: Pipelines and seabed intervention

© Det Norske Veritas AS. All rights reserved.

Pipelines and seabed intervention

18 October 2013

Dredging

Slide 15

Page 16: Pipelines and seabed intervention

© Det Norske Veritas AS. All rights reserved.

Pipelines and seabed intervention

18 October 2013

Rock dumping

Used for several purposes:

- protection

- upheaval resistance

- free span limitation

- sectioning

- crossings

- stabilisation

- supports

Slide 16

Used pre- and post-lay

Used for pipelines in operation

Relatively fast and cheap method if

transport distance not too long

Cheap in North Sea

Disadvantages for fisheries (trawling)

Page 17: Pipelines and seabed intervention

© Det Norske Veritas AS. All rights reserved.

Pipelines and seabed intervention

18 October 2013

Rock dumping

Rock dumped through fall pipe

Fall pipe end position controlled

by ROV

Slide 17

Page 18: Pipelines and seabed intervention

© Det Norske Veritas AS. All rights reserved.

Pipelines and seabed intervention

18 October 2013

Safeguarding life, property

and the environment

www.dnv.com

18