PIP Update. Sept 26 2012. Agenda. Summary Update Current Activities Updates/Talks: Ken Domann - Schedule Update and Statusing Ryan Crawford - Linac MCC/Transformer, Hatch, Booster Transformers, Anode Supply Dave Hixson - Booster LCW. Update. General Info Current Work - PowerPoint PPT Presentation

Citation preview

Page 1: PIP Update

PIP Update

Sept 26 2012

Page 2: PIP Update

Agenda

• Summary Update– Current Activities

Updates/Talks:• Ken Domann - Schedule Update and Statusing• Ryan Crawford - Linac MCC/Transformer, Hatch,

Booster Transformers, Anode Supply• Dave Hixson - Booster LCW

Page 3: PIP Update

UpdateGeneral Info• Current Work

– Booster RF cavity – RF5 is back (~11 weeks) RF 6 work has begun– Transformers (Linac and Booster) Update talk today– LCW – Started Refilling yesterday – Update talk today– RFQ – Electrical work underway, Install will start next week– HPower RF – A 1.4M is waiting for 2nd floor signature– High Power Ferrite Testing – No news– Booster Absorber – Shelving installed – Install Procedure Written– Linac Modulator – Need to firm up FY13 plan – Planning meeting?– Booster Solid State – 82 amplifiers checked, LLRF chassis' are completed – Booster Modulator work – 10 done yet?– Tuner with new ferrite – Any tests yet?

Shutdown - comments (Fernanda, Todd, Mary – updated the schedule yesterday and will meet tomorrow at 10 in the Huddle )

END OF Fiscal Year No guarantee that reqs in process will be approved! Working to finish rest of requisitions for FY12. Last day today – may actually be closed. I have no more reqs to sign.

Page 4: PIP Update

Upcoming • Finish up RLS – Update Request went out this morning– Lots of progress– Need to work through the FY13 budget( labor/M&S) into RLS

• End of Fiscal year– Today – No more requisitions (final numbers – next week) – Reports (October)

• PMG• Quarterly Report

– Will have special Wednesday meeting with Ann to discuss FY13• PIP talk at PAC (Oct)• SAD meeting last week – information exchanged between PIP and

safety with some items identified to be worked on.• No news on lab budget meetings last week – lots of issues!• Stuart asked us to think about University help for PIP – Items?

Page 5: PIP Update
Page 6: PIP Update
Page 7: PIP Update

Talks

• Ken Domann - Schedule Update and Status• Ryan Crawford - Linac MCC/Transformer,