18
PIP Status Report Linac Startup plans 12/05/2012

PIP Status Report

  • Upload
    halima

  • View
    53

  • Download
    0

Embed Size (px)

DESCRIPTION

PIP Status Report. Linac Startup plans 12/05/2012. Linac Shutdown Activities. Active year for Linac… HE shutdown started with the lab shutdown LE region stayed ON NTF patient treatment Detailed MP file developed ** 34 major tasks ** 600 lines of work description. - PowerPoint PPT Presentation

Citation preview

Page 1: PIP Status Report

PIP Status Report

Linac Startup plans12/05/2012

Page 2: PIP Status Report

2

Linac Shutdown Activities

12/5/2012 F.G. Garcia - PIP Mtg: Linac Startup Plans

Active year for Linac…• HE shutdown started with the lab shutdown• LE region stayed ON

NTF patient treatment

Detailed MP file developed** 34 major tasks ** 600 lines of work description

Page 3: PIP Status Report

F.G. Garcia - PIP Mtg: Linac Startup Plans 3

Linac Tunnel Activities

12/5/2012

Page 4: PIP Status Report

F.G. Garcia - PIP Mtg: Linac Startup Plans 4

Linac Low Energy Activities

12/5/2012

Page 5: PIP Status Report

F.G. Garcia - PIP Mtg: Linac Startup Plans 5

Linac HE Activities

12/5/2012

Page 6: PIP Status Report

F.G. Garcia - PIP Mtg: Linac Startup Plans 6

Linac PerformancePrior Shutdown 2012

12/5/2012

Average Input beam current: 48.5 mAOutput beam current: 35.0 mAEfficiency: 72%

Peak ValuesInput beam current: ~57 mAOutput beam current: ~38.7 mAEfficiency: 74% (not at these peak values)

Nominal:Beam current: 34.5 mA

Page 7: PIP Status Report

F.G. Garcia - PIP Mtg: Linac Startup Plans 7

NTF at a Glance

12/5/2012

Treatment occurs 3 times a week Tuesday, Thursday and Friday Time: 8:00 A.M. 11:30 A.M.

Treatment typically lasts 4 weeks Not counting the setup time which takes a couple of hours typically one week prior the setup

Beam to NTF extract at 66 MeV H- beam, 15 Hz, nominal Linac intensity (34.5 mA), 64 msec macro pulse length

http://www-bd.fnal.gov/ntf/ntf_home.html

Page 8: PIP Status Report

F.G. Garcia - PIP Mtg: Linac Startup Plans 8

A glance at the NTF program

12/5/2012

Courtesy of T. Kroc

Page 9: PIP Status Report

9

Typical NTF Beam

12/5/2012 F.G. Garcia - PIP Mtg: Linac Startup Plans

CTOR2~ 30 mA

TO1IN47.2 mA

TO4OUT~ 34 mA

Eff~ 72%

CTOR2 50 50TO1IN 50

TO4OUT

TO4OUT/TO1IN 0

1

0.9

0.8

.0.7

0.6

0.5

14-Nov-2011 – 28-Nov-2011

Page 10: PIP Status Report

10

Lower Beam Intensity = Longer Treatment Time

12/5/2012 F.G. Garcia - PIP Mtg: Linac Startup Plans

Treatment times are inversely proportional, but linear, to TLG percentage & beam current

Tom Kroc

On Feb. 24, 2012:CTOR2 = 32.5 mAThe given dose was 0.765 MUBeam time was 2.23 min(0.343 MU/min)

On Sept. 10, 2012: CTOR2 = 27 mA The given dose was 0.909 MU Beam time was 3.67 min(0.248 MU/min)

Holding stilltime causesall the stress.

T. Kroc

Page 11: PIP Status Report

F.G. Garcia - PIP Mtg: Linac Startup Plans 11

RIL & 66 MeV Commissioning

12/5/2012

RIL delivered 750 keV to entrance of DTL tk1 Nov 14th, first day of RFQ commissioning

poor capture and transmission small intensity beam seen at 37.5 MeV (DTL tk3)

12 days later, a buncher phase scan was performed better matching into Linac transmission improved

Initial beam study the beam pulse length and rep.rate set to 10 msec long and 1 Hz, respectively

to avoid possible accelerator components damage

rr

rr

Page 12: PIP Status Report

F.G. Garcia - PIP Mtg: Linac Startup Plans 12

NTF Schedule

NTF has been off since September 10, 2012 for RFQ Installation

Treatment schedule resumes December 11, 2012 3 patients booked setup time occurring this week

NTF beam permit was revised and signed November 16, 2012

NTF staff is ready for resuming treatment … and so is RIL and Linac

12/5/2012

Page 13: PIP Status Report

F.G. Garcia - PIP Mtg: Linac Startup Plans 13

Beam is making to NTF

12/5/2012

Oct 2011 Nov 2012

Page 14: PIP Status Report

Linac PerformanceRIL – 66 MeV Commissioning

12/5/2012 F.G. Garcia - PIP Mtg: Linac Startup Plans 14

Average Input beam current: 24.7 mAOutput beam current: 21.8 mAEfficiency: 88%

PeakInput beam current: 27 mAOutput beam current: 23 mAEfficiency: 90%

Nominal:Beam current: 34.5 mA

Unofficial

Page 15: PIP Status Report

F.G. Garcia - PIP Mtg: Linac Startup Plans 1512/5/2012

LINAC 400 MeV Startup Schedule

Dec JanShutdown Wk 32 33 34 35 36 37 38 39 40

Mon 3 10 17 24 31 7 14 21 28

Tues NTF NTF 1 NTF NTF NTF NTF

Wed

Thur NTF NTF NTF NTF NTF NTF NTF NTF

Frid NTF NTF NTF NTF NTF NTF NTF NTF

Sat

Sun

66 MeV beam commissioning continues400 MeV beam to Linac absorber400 MeV beam to Booster

24

HE turn-oncontinues

31

Page 16: PIP Status Report

F.G. Garcia - PIP Mtg: Linac Startup Plans 16

LINAC 400 MeV Startup Studies Plan

12/5/2012

Dec 17th 2012 – Jan 7th 2013

400 MeV beam commissioning (Linac absorber area)

Beam commissioning 23-34.5 mA, 10 msec, 1-5 Hz Limited by beam losses, beam heating interceptive instrumentsstudies will be performed by a small group

Beam diagnostic Beam position monitors (new electronics/readout system)Multi Wire (new device installed at 400 MeV)Toroids (new electronics/readout system)

Turn-on & Commissioning Measurements

Transmission efficiency differential current meas. (toroids)Transverse matching beam size (wire scanners) Position measurements beam position (BPMs)

Feb 2013 … Goal: beam study time schedule to take into account NTF treatment and to be negotiated among Booster study groups & Operations

After MI comes online

Goal: beam study time schedule to take into account NTF treatment or it can be performed parasitic or integrated into shift time

Page 17: PIP Status Report

F.G. Garcia - PIP Mtg: Linac Startup Plans 1712/5/2012

FIM

Page 18: PIP Status Report

1812/5/2012 F.G. Garcia - PIP Mtg: Linac Startup Plans

TO1IN Toroid Prototype Module

Threshold set at 10 mA

Two ways of calculating: pulse width (PW) average or window set (WS)

2% agreement is obtained