55
1 Pinto Valley Mine BMO Investor Tour – February 2015

Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

  • Upload
    hatu

  • View
    214

  • Download
    2

Embed Size (px)

Citation preview

Page 1: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

1

Pinto Valley MineBMO Investor Tour – February 2015

Page 2: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

22

This presentation, and the documents incorporated by reference herein, may contain “forward-looking information” within the meaning of Canadian securities legislation and “forward-looking

statements” within the meaning of the United States Private Securities Litigation Reform Act of 1995 (collectively, “forward-looking statements”). These forward-looking statements are made as of

the date of this document and Company does not intend, and does not assume any obligation, to update these forward-looking statements, except as required under applicable securities

legislation.

Forward-looking statements relate to future events or future performance and reflect Company management’s expectations or beliefs regarding future events and include, but are not limited to,

statements with respect to the estimation of mineral reserves and mineral resources, the realization of mineral reserve estimates, the timing and amount of estimated future production, costs of

production, capital expenditures, success of mining operations, environmental risks, unanticipated reclamation expenses, title disputes or claims and limitations on insurance coverage. In certain

cases, forward-looking statements can be identified by the use of words such as “plans”, “expects” or “does not expect”, “is expected”, “outlook”, “guidance”, “budget”, “scheduled”, “estimates”,

“forecasts”, “intends”, “anticipates” or “does not anticipate”, or “believes”, or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”,

“might” or “will be taken”, “occur” or “be achieved” or the negative of these terms or comparable terminology. In this document, certain forward-looking statements are identified by words

including “may”, “future”, “expected”, “intends” and “estimates”. By their very nature forward-looking statements involve known and unknown risks, uncertainties and other factors which may

cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the forward-

looking statements. Such factors include, among others, risks related to actual results of current exploration activities; changes in project parameters as plans continue to be refined; future prices

of resources; possible variations in ore reserves, grade or recovery rates; accidents, dependence on key personnel, labour pool constraints, labour disputes; availability of infrastructure required

for the development of mining projects; delays or inability to obtain governmental and regulatory approvals for mining operations or financing or in the completion of development or

construction activities; compliance with debt covenants, and other risks of the mining industry as well as those factors detailed from time to time in the Company’s interim and annual financial

statements and management’s discussion and analysis of those statements, all of which are filed and available for review under the Company’s profile on SEDAR at www.sedar.com.

Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there

may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. The Company provides no assurance that forward-looking statements will prove to be

accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking

statements.

Alternative Performance Measures“C1 Cash Cost”, “Cash Cost” and “Adjusted Net Earnings” are Alternative Performance Measures. Alternative performance measures are furnished to provide additional information. These

performance measures are used by management to monitor performance, to plan and to assess the overall effectiveness and efficiency of mining operations. These performance measures may

not be comparable to similar data presented by other mining companies. These performance measures should not be considered in isolation as a substitute for measures of performance included

in the Company’s unaudited condensed interim consolidated financial statements prepared in accordance with IFRS.

CurrencyAll amounts are in US$ unless otherwise specified.

Cautionary Note Forward Looking Information

Page 3: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

33

Located ~10 km west of the town of Miami in Gila, County, Arizona

129 km from Phoenix to Pinto Valley via US Highway 60

Close proximity to other copper mining operations

Fully permitted with established infrastructure and skilled workforce

Location: Historical Mining District

The Globe-Miami historical mining district is one of the world’s most favorable jurisdictions for tax, regulation and labour

Page 4: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

4

Close Proximity to Other Mining Sites

Source: Google maps.

City of Miami

Pinto Valley

FreeportMiami

KGHMCarlota

BHPB Copper Cities

BHPB Miami

Potential for future strategic relationships

Page 5: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

55

History of Pinto Valley Mine

Pinto Valley Historical Production / Copper Prices

Source: BHP Copper

Page 6: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

66

Collective Bargaining Agreement

Collective Bargaining Agreement at Pinto Valley

Contract expired on June 30, 2014

Capstone currently in negotiation process

Hourly employees represented by a joint union comprised of six constituent unions:

The United Steel, Paper and Forestry, Rubber, Manufacturing, Energy, Allied Industrial and Services Workers International Union, AFL-CIO-CLC

International Brotherhood of Teamsters, Chauffeurs, Warehousemen & Helpers of America, Local No. 104

International Union of Operating Engineers, Local No. 428, AFL-CIO

International Brotherhood of Electrical Workers, Local No. 518, AFL-CIO

International Brotherhood of Boilermakers, Iron Ship Builders, Blacksmiths, Forgers and Helpers, Local No. 627, AFL-CIO

United Association of Journeymen and Apprentices of the Plumbing and Pipefitting Industry of the United States and Canada, Local No. 469, AFL-CIO

Page 7: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

77

Geology

Page 8: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

88

Regional Geology

Basement rocks: Proterozoic units

Pinal schist (~1,700 Ma)

Ruin granite (1,420 Ma)

Apache Group sediments

Apache diabase sills (~1,150 Ma)

Overlain by Paleozoic marine sediments

Subduction of Farallon Plate initiated arc magmatism (80-50 Ma)

Schultze granite intruded (~65-59 Ma) and brought source fluids responsible for the deposits in the district s

Pinto Valley

Modified from Creasey (1980)

Late porphyry phase magmatism mineralized Pinto Valley ~60-59 Ma

Page 9: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

99

Regional Geology

Extensional faulting facilitated exposure of Cu deposits

Tertiary basin and range extension and faulting (35-15 Ma) facilitated dismemberment and exposure of deposits

Preservation through deposition of Whitetail conglomerate (Oligocene) and Apache Leap tuff (Miocene)

Further extension and faulting deposited the Gila conglomerate (Pliocene) into basins

Modified from Creasey (1980)

Page 10: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

1010

Local Geology

Schultze granite represented at PV by granodiorite and granite porphyry intrusions along South Hill fault

Ruin granite and Apache diabase host mineralization (chalcopyrite, pyrite, magnetite, molybdenite)

Development of oxide cap and supergene blanket, since mined out; sulphide ore mineralogy remain

Approximate PV pit outline

Modified from Peterson (1962)

Long lived fault systems provided structural conduits for mineralizing fluids

Page 11: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

1111

Operations

Page 12: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

1212

2012 BHPB Restart Capital Cost ($US M)1

Mine Fleet $63.8 (33%)

Processing $43.7 (22%)

Owner Cost $27.1 (14%)

Infrastructure $21.2 (11%)

EPCM $14.2 (7%)

SMARRCO $11.4 (6%)

Contractors' Indirect (2)

$8.9 (5%)

Mine$3.9 (2%)

1.Source BHP Copper. 2. The cost of employing contractors during project execution.

Lessons learned from previous restart incorporated in $194 million restart capital

Acquired new mining fleet

Upgraded electrical and controls

Significantly improved plant conditions to HSEC standards

In-sourced mining

Pinto Valley operations have been elevated to world-class standards

Page 13: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

1313

Restart Investment

Restart capital focused on enhancing the stability of operations

Infrastructure Installed new IM network Repaired water system

Tailings Thickeners Replaced piping

Flotation Replaced regrind lube

system Upgraded instrumentation

Primary Crusher Refurbished crusher Replaced belt Installed new feeder drive Upgraded instrumentation

Fine Crushing Plant Improved feed chutes Installed new tertiary feeder

drives Installed bin spiling Upgraded instrumentation

Grinding Replaced 1 bull gear &

1 discharge trunion Replaced clutches Replaced lube systems Installed new electrical

switchgear Upgraded Instrumentation

Page 14: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

1414

Mining Fleet Original PV2 Additional

15 haul trucks, 3 loaders, 2 track dozers, 2 wheel dozers, 2 water trucks, 2 graders, 2 rotary blast hole drills, 1 air track drill

4 haul trucks, 2 hydraulic shovels, 1 rotary blast hole drill, 1 grader, 2 track dozers, 1 wheel dozer, 1 water truck, 1 fuel truck, 1 townhaul

ConcentratorProduction Facilities

Concentrate production facilities include: primary crusher, secondary & tertiary crushers, 6 ball mills, copper concentrate & molybdenum flotation circuits

SX/EW Production Facilities

SX/EW production facilities includes:

Low grade dump leach field, PLS pumping, solvent extraction, electrowinning & raffinate distribution system

Tailings Storage

Tailings storage capacity in place through Phase 2 production

Studies required for future expansions

Pinto Valley Operations

Page 15: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

1515

Processing

Page 16: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

1616

Pinto Valley Mine: Process Flow Sheet

Page 17: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

1717

SX/EW Production Facilities – Sulphide Dump Leach

Electrowinning

Copper is plated onto starter sheets (Cu2+→Cu0) Starter sheets are plated on stainless steel blanks Water dissociates to oxygen gas and acid at anode

(hydrolysis – H2O→2H++½O2) Anodes are lead alloy Production currently averages 9-10 tonnes per day 5N copper LME grade Tank house capacity maximum 27M lbs/year Current density 120A/m2

Solvent Extraction

Pregnant leach solution (PLS) is mixed with organic Copper is selectively extracted into organic Transfer of copper is driven by pH (exchange

of 2H+ for Cu2+) PV PLS is extremely clean Copper is stripped from organic into a low pH electrolyte Solution flow rate capacity 7,000 gpm

Run of mine material above 0.10% and below 0.18% copper grade

Page 18: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

1818

By-Products

Molybdenum and silver by-products lower cash cost

MoS2 concentrate is produced –Molybdenum (Mo) is the payable metal

600 tonnes of contained Mo annually LOM

2014 recovery at 20% in start-up, PV2 PFS LOM 47%

Silver is recovered from copper concentrate

235,000 ounces of contained silver annually

Page 19: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

1919

Marketable Products

Copper concentrate grade 29% – majority sold in the international market

MoS2 concentrate grade 85% - sold domestically

6.3 million pounds of copper cathode produced annually – sold domestically

Pinto Valley produces clean and high grade concentrate

Truck

Pinto Valley Operations

San Manuel, Arizona

Hayden, Arizona

Guaymas, Mexico

International Markets

SMARRCO Third-Party Rail Shipping

Page 20: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

2020

Marketing Strategy

US

Trader

Korea Japan

China

Direct Smelter

Trader

Diversification of customer base and geographies

Maintain flexibility

Mitigate counterparty risk

Develop strategic relationships

Freight savings on US shipments (20% of 2015 pdn)

Spot sales provide market information

Korean sales supports KORES’ objectives

Logistics (per wmt of concentrate)

Includes truck transport, SMARRCO transloading, rail, port costs, ocean transport, supervision, sampling and assaying

• $77 domestic, $133 international

• $125 combined rate per wmt of concentrate

Page 21: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

2121

2014 Improvement Initiative:Standing on Stable Ground

Page 22: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

22

Ramp-up to 50 ktpd Stabilizing at 50 - 52 ktpd

2013 Ramp-up 2014/15 Stabilize

Steady at 52 ktpd

2016+ Optimize

Pinto Valley 2014 Improvement Strategy

Engaged and empowered workforce to improve site performance

Leveraged existing organizational structure to facilitate continuous improvement

30-week project scope:

Communication, Alignment & Training

Production Planning

Mine Operations

Mobile Maintenance

Plant Maintenance

Concentrator Production

Supply

Page 23: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

23

Supply: Sourcing Prioritization Matrix

Easy

Difficult

HighLowCost Savings Opportunity Potential

Ease

of

Imp

lem

en

tati

on

= Implemented

General Contractor

Services

Wave 4 & 5 Categories(TBD)

Pumps & Pump Parts

Fuel

Earth Moving Tires

Supplemental Manpower

Sulfuric Acid for SXEW

= Not Active / Planned

FreightConcentrate/

Acid

Overhead Crane

ServiceLiners (Primary / Secondary Crushers

Grinding Media($ 12.5 M)

qualification phase

Explosives

Empire Parts & W/H

Strategy

LinersBall Mill

Bearings / Belts / Power

Transmission

Wear Metal Parts(TBD)

Chemicals & Reagents

(TBD)

Envir.Sampling

Safety Supplies

High Priority (Wave 1)Medium Priority (Wave 2 & 3)

Lower Priority (Wave 4, etc.)

Lubes

Electrical Supplies

Lime

Drill Fleet Service

Empire MobileEquip. Servic3

= Active

Page 24: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

2424

Supply Savings Summary

Category (or Project) Savings (percentage)

Sulfuric Acid (for SXEW Plant) 9.7%

Lubricants 15.3%

Warehouse Delivery Process (in-sourcing) N/A (53.0% net cost reduction)

Lime 13.9%

H/D Mechanics (Mill 12.1% (from 2014 budget)

Goodyear Tire 25% Overall Savings, Haul Truck/Support Eq. Tires

Purcell Tire 15% Overall Price Reduction on Remaining 2014/2015 Contracted Tires

Pump Parts (Warman) 32% Savings based on historical spend

Tire Life Tire Compound 20% Savings based on historical spend, price has one year lock

Nordback Backing Compound 13.5% Savings based on historical spend, price has one year lock

Fuel – Red Dyed #2 Continue to generate weekly savings

Sulfuric Acid 18.3% Savings that will be realized in 2015

Janitorial Services 15.35% Savings under historical spend

Security Services 9.92% Savings

Crane Inspections/Repair 7.2%

5.3% in supply savings totaling $6.6M to date

Page 25: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

2525

Asset Reliability Improvement Project

Implement a sound and effective Asset Management Program

Reduce production variance caused by unplanned downtime and poor reliability of equipment

Partner with a Subject Matter Expert (Consultant) with the required skills and expertise to:

Assess existing Maintenance Process (organization, practices, ERP, metrics, etc.)

Propose Maintenance Structure and Maintenance Methodology

Introduce Best Practices (reliability, condition monitoring, KPI’s, parts support, etc.)

Page 26: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

2626

Infrastructure

Page 27: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

2727

Overview of Water Requirements of Pinto Valley

The Pinto Valley operation requires ~4,200 to 5,000 gallons per minute (gpm) of water

Source: PVM Hydrologist.

Ore

(Moisture)

Fresh

Water

370gpm

Mill

800gpm

Tailings

18,000gpm

22,000gpm

Mo Plant/

Filter PlantCopper Con.

#4 Tailings

Pond

Evaporation

Mill

Tanks

Evaporation

250gpmOpen Pit

Reclaim

370gpm

4,200-5,000gpm

Mill

800gpm

80gpm

Cu+Mo

Thickeners

11,000gpm

18,000gpm

22,000gpm

9gpm

Mill

Tanks

Cottonwood

Reservoir

250gpm

5,000gpm

11,000gpm

720gpm

Tailings

Thickeners

Page 28: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

2828

Overview of Water Systems

Burch Pump Station

Burch Booster Pump Station

New water is currently supplied by the water from both the West Water System (Pinto Valley) and the

East Water System (owned by BHPB) which contain a large number of groundwater wells that provide a

high level of confidence in continuous water supply.

East Water SystemWest Water System

SolitudeWells

Miami Garden Wells

Peak WellsSystem

1,800 gpm

Cottonwood Reservoir850 gpm

Diamond H Pit

Myberg Basin 600 gpm

Old Dominion Shaft

700 gpm

Source: PVM Hydrologist. (1) Not operated by BHP Copper

Kiser Basin Well Field1

600 gpm

Miller Well190 gpm

Hoopes Wells 160 gpm

Additional 500 gpm combined

Page 29: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

2929

Overview of Electric Power

115 kV redundant power lines from SRP

Three 25 MW transformers in sub-station (current need is 42 MW at full production)

13.8 kV back bone throughout site

4,160 V transformers at various locations

480 V, 240 V and 120 V transformers as needed

Power cost $6.5 cents/kWh

Average monthly cost $1.7M

Electric power supplied by existing Salt River Project (SRP) utility grid.

Page 30: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

3030

Tailings Management

/

Page 31: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

3131

PV2 Implementation

Page 32: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

3232

PV2 PFS March 20141 - Pushbacks

Original pushback (PV1)

PV2 pushback commencing in 2015

PV2 ore production constrained first by permitted capacity of the tailings dam and eventually by surface ownership

Significant amount of additional mineral resource that could be mined if constraints removed

PV2

PV1

PV2

1. Pinto Valley Mine 2014 Pre-Feasibility Study, April 2014. See Forward-Looking Statements and Cautionary Note for NI 43-101 information. The mine design was completed using standard open pit assumptions and slope design angles as defined by Call & Nicholas, Inc., geotechnical consultants.

Page 33: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

3333

Savings recognized in 2014 through competitive bidding

Tailings

New tailings line to Tailings Dam 4

Tailings Dam 4 booster station upgrades

Water

Refurbished peak wells

Water conservation initiatives underway

PV2 Implementation

Mine Equipment

First shovel in production October 2014

Second shovel, trucks, and auxiliary equipment in 2015/16

Page 34: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

3434

PV2 PFS March 20141 – Summary

Mine Life (years) 12.3

Mineral Resources 1,[email protected]%

Mineral Reserves [email protected]%

Planned Throughput (ktpd) 50 - 52

Avg. Annual Production – Contained in Concentrate (M lbs)

119.5

Avg. Annual Production – Cathode (M lbs)

6.3

Est. LOM Avg. C1 Cash Costs $2.00

LOM Sustaining Capital ($ millions) $187.9

After-tax NPV, 8% ($M) $738

1. Pinto Valley Mine 2014 Pre-Feasibility Study, April 2014. Mineral Reserves and Resources take into account mining activities until January 1, 2014, and are reported above 0.18% Cu Cut-off Grade. See Forward-Looking Statements and Cautionary Note for NI 43-101 information.

Page 35: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

3535

PV2 PFS March 20141 - Mine Plan

PV2 extended production to 2026

Mining rate increases from 22.5 M tonnes in 2014 to 42 M tonnes in 2016 and decreases from 2020 onwards

2 hydraulic shovels and 4 haul trucks added

LOM strip ratio is 0.65

0.00%

0.05%

0.10%

0.15%

0.20%

0.25%

0.30%

0.35%

0.40%

0

5

10

15

20

25

30

35

40

45

50

2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026

Co

pp

er G

rad

e %

Mat

eria

l Min

ed (

M t

/yea

r)

Total Material Moved

Capital Expenditure ($M) 47 62 12 12 9 11 14 6 5 5 3 2 0

Payable Copper (k tonnes) 64.1 54.8 65.1 55.8 56.2 54.1 57.0 56.1 54.7 52.3 59.7 41.0 12.0

1. Pinto Valley Mine 2014 Pre-Feasibility Study, April 2014. See Forward-Looking Statements and Cautionary Note for NI 43-101 information.

Page 36: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

3636

PV2 PFS March 20141 - Mine Plan

Concentrator operates until Q1 2026, SX/EW operates until 2030, with potential to continue operating longer

Payable copper production varies from 115-140 M lbs/year, averaging 119.4 M lbs/year until processing of lower grade ore begins in 2025. SX/EW cathode copper production averages 6.3 M lbs/year

0

20

40

60

80

100

120

140

160

2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

Co

pp

er lb

s P

ayab

le (

M)

Copper Payable by Year

Concentrator SX-EW

1. Pinto Valley Mine 2014 Pre-Feasibility Study, April 2014. See Forward-Looking Statements and Cautionary Note for NI 43-101 information.

Page 37: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

3737

PV2 PFS March 20141 - Economic Assumptions

Key Assumptions

Cu Price - Average 2014-2022 $/lb 3.15

Cu Price - long term (2023+) $/lb 2.75

Mo Price $/lb 12.50

Ag Price $/oz 20.00

Copper concentrate grade - Cu % 27.5%

Copper payable % 96.5%

Copper treatment charge $/dmt 85.00

Copper refining charge $/lb Cu 0.085

Concentrate sold internationally % 90

1. Pinto Valley Mine 2014 Pre-Feasibility Study, April 2014. See Forward-Looking Statements and Cautionary Note for NI 43-101 information.

Page 38: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

38

Ore(M tonnes)

Copper (%)

Molybdenum (%)

Contained Copper (M lbs)

Contained Molybdenum

(M lbs)

Proven 218.97 0.33 0.008 1,593.1 38.6

Probable 13.25 0.33 0.008 96.4 2.3

Total Proven & Probable 232.22 0.33 0.008 1,689.5 41.0

Pinto Valley Mineral Reserves1 – March 2014

PV2 PFS brings reserves to 12.3 years, all within patented property boundaries

1. Mineral Reserve Estimate, January 1, 2014. Economic inputs to the block model were $2.75 per pound copper, mining $2.02 per tonne moved, mill $5.50 per tonne processed, G&A $1.65 per tonne processed and an average copper recovery of 88%. Cut-off Grade – 0.18% Cu 2014 – 2022, excess ore below 0.20% Cu was stockpiled for processing in 2025 -2026. An internal cut-off grade of 0.17% Cu was applied in 2023-2025. Qualified Person is John Marek, Independent Mining Consultants Inc.

Page 39: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

3939

Sustaining Capital Costs Estimate ($US M) 2014 PV2 LOM

Mine Equipment $21.1 $47.6

Mine Infrastructure and Mine Maintenance 5.4 13.0

Concentrator and SX/EW 8.5 23.5

Tailings and Water 2.7 41.3

Other Infrastructure 1.5 51.2

G&A and Engineering Studies 7.6 11.3

Subtotal $46.8 $187.9

PV2 PFS March 20141 - Summary of Capital Costs

0.0

10.0

20.0

30.0

40.0

50.0

60.0

70.0

20

14

20

15

20

16

20

17

20

18

20

19

20

20

20

21

20

22

20

23

20

24

20

25

20

26

US$

Mill

ion

s

Sustaining Capital Requirements G&A and Engineering Studies

Other Infrastructure

Tailings and Water

Concentrator and SX/EW

Mine Infrastructure and Mine Maintenance

Mine Equipment

1. Pinto Valley Mine 2014 Pre-Feasibility Study, April 2014. See Forward-Looking Statements and Cautionary Note for NI 43-101 information.

Page 40: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

4040

PV2 PFS March 20141 - Financial Analysis

Financial Analysis $M

Copper Revenue 4,656

Moly Revenue 210

Silver Revenue 52

Total Revenue 4,918

Site Costs -2,600

Conc. Transport, TC/RCs -716

Operating Cash Flow 1,602

Sustaining Capital Costs -188

Closure Costs -129

Net Cash Flow, Pre-Tax, Undiscounted 1,285

NPV (8%) Pre-Tax 931

Taxes Payable -274

Net Cash Flow, Post-Tax, Undiscounted 1,011

NPV (8%) Post-Tax 738

1. Pinto Valley Mine 2014 Pre-Feasibility Study, April 2014. See Forward-Looking Statements and Cautionary Note for NI 43-101 information.

Page 41: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

4141

PV2 PFS March 20141 - Financial Analysis

-300

-100

100

300

500

700

900

1,100

1,300

-40

-20

0

20

40

60

80

100

120

140

160

20

14

20

15

20

16

20

17

20

18

20

19

20

20

20

21

20

22

20

23

20

24

20

25

20

26 C

um

ula

tive

Cas

h F

low

, US$

Mill

ion

s

Year

ly C

ash

Flo

w, U

S$ M

illio

ns

Post-Tax Cash-Flow

Post-Tax Cash Flow Cumulative Cash Flow

2015 has high capital expenditures (related to the pushback) and lower copper production (lower head grades)

Closure costs begin in 2026 and are projected until 2055

1. Pinto Valley Mine 2014 Pre-Feasibility Study, April 2014. See Forward-Looking Statements and Cautionary Note for NI 43-101 information.

Page 42: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

4242

PV2 PFS March 20141 - LOM Operating Cost Breakdown

1. Pinto Valley Mine 2014 Pre-Feasibility Study, April 2014. See Forward-Looking Statements and Cautionary Note for NI 43-101 information. 2. Per tonne mine costs based on mined tonnage. 3. Per tonne mill and other costs based on milled tonnage. 4. SX/EW cost is $1.80/Cu cathode. Costs are calculated separately outside of the $/tonne milled. 5. Includes payable copper concentrate and copper cathode.

PV2 LOM$/tonne milled

PV2 LOM$/lb5

Mine2 3.48 0.53

Mill3 5.35 0.81

G&A 1.53 0.24

Total Site Costs 10.36 1.58

SX/EW 0.83 0.124

TC/RCs 1.52 0.23

Freight 1.56 0.24

By product credits (1.13) (0.17)

Total C1 Cash Costs 13.14 2.00

Page 43: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

4343

PV2 PFS March 20141 - Sensitivities

VARIATIONAFTER TAX NPV AFTER TAX NPV

@ 0%($M)

@ 8.0%($M)

Copper Price

-20% 306 254

-10% 682 512

Base Case 1,011 738

10% 1,324 952

20% 1,620 1,155

Total Operating Costs

-20% 1,415 1,011

-10% 1,221 880

Base Case 1,011 738

10% 785 585

20% 537 418

1. Pinto Valley Mine 2014 Pre-Feasibility Study, April 2014. See Forward-Looking Statements and Cautionary Note for NI 43-101 information.

Page 44: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

4444

Arizona Benchmark Data

OperationConcentrator Throughput Owner

G&A CostUS$M/year

G&A Cost $/t ore

Mining CostUS$/t moved

Milling CostUS$/t ore

Morenci 50ktpd FCX $172.00 $4.00 $1.76 $6.53

Sierrita 100ktpd FCX $149.73 $3.64 $2.04 $6.24

Mission 60ktpd ASARCO $67.33 $3.09 $1.52 $5.29

Bagdad 75ktpd FCX $57.28 $1.43 $1.95 $3.25

Ray 46ktpd ASARCO $50.69 $0.62 $2.19 $5.81

PV2 LOM PFS 52ktpd Capstone $29.00 $1.53 $2.18 $5.35

Safford SX/EW FCX $26.40 $1.24 $1.31 SX/EW

Miami SX/EW FCX $13.40 $1.00 $1.94 SX/EW

Silver Bell SX/EW ASARCO $10.80 $0.60 $1.55 SX/EW

Morenci 50ktpd FCX $172.00 $4.00 $1.76 $6.53

2015 Wood Mackenzie Estimates

Page 45: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

4545

2014 Operating Results & 2015 Guidance

Page 46: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

4646

Year-End Results and 2015 Guidance

2014 Actual 2015 Guidance

Tonnes milled (millions) 17.2 19.0

Copper grade (%)1 0.41 0.35

Copper recovery (%)1 88.9 88.1

Production (contained in concentrates)

Copper (tonnes) 62,716 56,300

Copper cathode (tonnes) 2,413 2,700

Total Copper (tonnes) 65,129 59,000

Molybdenum (tonnes) 113 480

Silver (million ounces) 285,877 300,000

C1 cash costs/lb payable Cu net of by-product credits and selling costs2

$2.03 $2.00 - $2.10

1. Grade and recoveries were estimated based on concentrate production. 2. This is an alternative performance measure.

Page 47: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

4747

2014 Operating Cost Breakdown

1. Per tonne mine costs based on mined tonnage. 2. Per tonne mill and other costs based on milled tonnage. 3. Includes cathode production costs.

2014 Actual $/lb

Mine1 0.43

Mill2 0.86

G&A 0.34

Total Site Costs 1.633

TC/RCs and Freight 0.46

By product credits (0.06)

Total C1 Cash Costs 2.03

Primary focus remains on plant reliability and ongoing cost reduction activities.

Page 48: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

4848

Future Potential

Future potential based on Mineral Resource ~1.6 billion tonnes averaging 0.30% Cu

Scoping studies completed in 2014

PV3 PFS now underway; two cases:

10-15% increase in throughput and possible mine life extension

Throughput to 90,000 tpdcombined with possible mine life extension

PV1

PV2

Future PotentialCurrent PV2 mine plan

represents only 16% of the total M&I Resource

Page 49: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

4949

HSEC and Permitting

Page 50: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

5050

Safety Program – Reportable Incidents

Pinto Valley Safety Performance - 2014

Safety is non-negotiable; it ensures the well-being of our people and our business.

27 Reportable Incidents in 2014

22 Restricted Duty & Medical Aid

5 Lost Time Injury

Total Reportable Incident Frequency Rate

PV 12-month rolling average is 3.74

Surface metal mining average is approximately 2.5

Objective to improve safety training, hazard identification and conduct quality incident investigations resulting in clear action items

Freq

uen

cy (

/20

0k

ho

urs

)

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

Page 51: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

5151

Environmental Program – Non-Reportable Incidents

2014 Environmental Targets

Provide environmental awareness training to all employees during Annual Refresher training

Increase the reporting for minor spills to create a non-reportable spill baseline

2014 Environmental Performance

38 Environmental Incidents

35 Non-Reportable

3 Reportable

Prior to Capstone ownership, Pinto Valley did not capture the number of minor or non-reportable spills. Using the data we collected in 2014 we are creating targets for the reduction of non-reportable spills in future years.

Pinto Valley Environmental Performance - 2014

0

1

2

3

4

5

6

7

8

9

10

0

50

100

150

200

250

# o

f re

po

rtab

le e

ven

ts

# of n

on

-repo

rtable even

ts

Page 52: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

5252

Permit Function Status Expiration

Aquifer Protection

Permit (APP)

Authorizes operation of facilities that discharge ground water

Most recent update approved October 2013

Valid for the life of the mine (including (closure & post-closure)

Mined Land Reclamation Plan (MLRP)

Approved plan to enable productive post-mining land use

Initial MLRP approved in June 1998; update completed October 2013

Life of mine

AZPDES Discharge

Permit

Allows discharge of mine process water, mine drainage and stormwater from certain point source outfalls to surface waters

Approved March 2019 renewable with timely application submission

Air PermitAuthorizes emission of regulated pollutants

Approved May 8, 2017 renewable with timely application submission

Pinto Valley Environmental Permits

Local regulatory and community support demonstrated during prior operationsand no public comments received on restart or transfer of permits to Capstone.

Page 53: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

5353

Permitting – Next Steps

Existing

Capstone proponent on Plan of Operations submitted by BHPB in September 2009

PV2

Optimized operational plan will require permit amendments, initial approach to regulators received positively

PV3

Scoping studies completed and PV3 PFS now underway - EIS will be submitted accordingly

Capstone’s PV2 optimized mine plan contemplates some modifications.

Page 54: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

5454

Unless otherwise indicated, Capstone has prepared the technical information in this presentation (“Technical Information”) based on information contained in the

technical reports and news releases (collectively the “Disclosure Documents”) available under Capstone Mining Corp.’s company profile on SEDAR at www.sedar.com. Each

Disclosure Document was prepared by or under the supervision of a qualified person (a “Qualified Person”) as defined in National Instrument 43-101 – Standards of

Disclosure for Mineral Projects of the Canadian Securities Administrators (“NI 43-101”). For readers to fully understand the information in this presentation, they should

read the Technical Reports (available on www.sedar.com) in their entirety, including all qualifications, assumptions and exclusions that relate to the information set out in

this presentation which qualifies the Technical Information. Readers are advised that mineral resources that are not mineral reserves do not have demonstrated economic

viability. The Disclosure Documents are each intended to be read as a whole, and sections should not be read or relied upon out of context. The Technical Information is

subject to the assumptions and qualifications contained in the Disclosure Documents.

The technical information in this presentation has been prepared in accordance with Canadian regulatory requirements set out in National Instrument 43-101 Standards of

Disclosure for Mineral Projects of the Canadian Securities Administrators ("NI 43-101") and reviewed by Brad Skeeles, P.Eng. VP of North American Operations (Technical

Information related to mining and production) and Brad Mercer, P. Geol., Senior Vice President, Exploration (Technical Information related to mineral exploration

activities), and reviewed and approved by Gregg Bush, P. Eng., Senior Vice President and Chief Operating Officer for Capstone Mining, all "Qualified Persons" under NI 43-

101.

The PV2 PFS project was directed by Capstone with contributions from Kirkham Geosystems Ltd. (geology, Resource estimation), Independent Mining Consultants Inc.

(reserve, geotechnical, mine design and schedule, equipment selection), KWM Consulting Inc. (metallurgy, mill operation), AMEC Environment & Infrastructure Inc.

(tailings), Stantec (Infrastructure and PFS report compilation), SRK (US), Inc. (environmental), and Adam M Consulting Inc. (financial modelling). Personnel from each of

these companies will be signing off as a QP as defined in NI 43-101 for their specific responsibilities. The following QP’s will author the technical report: Mel Lawson, P.E. of

Stantec, Garth Kirkham, P.Geo. of Kirkham Geosystems Ltd., John Marek P.E. of Independent Mining Consultants, Inc., Ken Majors P.Eng. of KWM Consulting Inc, Tony

Freiman, P.E. of AMEC Inc., Adam Majorkiewicz, P.Eng of Adam M Consulting Inc. and Cori Hoag C.P.G. of SRK.

The March 2014 Mineral Resource estimate reported herein for the Pinto Valley property was prepared by Garth Kirkham, P. Geo, Kirkham Geosystems Ltd., an

independent QP. Based on the Mineral Resource Estimate, a standard methodology for pit limit analysis, mining sequence, and cut-off grade optimization, including

application of mining dilution, process recovery, economic criteria and physical mine and plant operating constraints, has been followed to design the Pinto Valley pit and

determine the Mineral Reserve Estimate.

Compliance with NI 43-101

Page 55: Pinto Valley Mines2.q4cdn.com/231101920/files/doc_presentations/2015/Pinto-Valley... · 129 km from Phoenix to Pinto Valley via US Highway 60 ... 1.Source BHP Copper. 2. The cost

55

For additional information, please visit capstonemining.com or contact us at:

Phone: +1-604-684-8894

Toll Free: 1-866-684-8894

Email: [email protected]

Last updated February 24, 2015