Facilities Subcommittee MeetingApril 18, 2017
Pinole Valley High School (PVHS) Project Update
PVHS New CampusProject Update
Construction Activities in March• The delivery, erection, and welding of structural steel of the
Classroom building has continued, as well as metal decking on the second, third, and roof levels
• A second set of concrete walls have been poured in the Performing Arts building and preparations were made for waterproofing and a major footing pour
• Rebar, electrical conduit, and the brick veneer have been placed in the tilt-up panel walls for the Gymnasium and the first 17 panels were poured
• Additional casting slabs for the tilt-up panels of the Performing Arts building have been poured and panel layout began
Facilities Subcommittee Meeting – April 18, 2017
Classroom Building C Steel and DeckingFacilities Subcommittee Meeting – April 18, 2017
PVHS New CampusProject Update
Gymnasium Wall FormsFacilities Subcommittee Meeting – April 18, 2017
PVHS New CampusProject Update
Performing Arts Footings and Walls
Facilities Subcommittee Meeting – April 18, 2017
PVHS New CampusProject Update
Earl Combs
Facilities Subcommittee Meeting – April 18, 2017
PVHS New CampusProject Update
SCHEDULE SUMMARY
NTP June 16, 2016
Total Contract Duration 981 Days
Original Contract Completion Date December 14, 2018
Change Order Time Extension 69 Days
Revised Contract Completion Date February 21, 2019
Current Projected Completion Date February 21, 2019
WEATHER IMPACT
October 7 Non-compensable Days
December 5 Non-compensable Days
January 14 Non-compensable Days
February 17 Non-compensable Days
March (pending) 3 Non-compensable Days
Project Extension (Unforeseen Conditions) 26 Non-compensable days
Facilities Subcommittee Meeting – April 18, 2017
April Construction Activities
• Continued delivery and erection of structural steel at the Classroom building
• Pouring concrete walls of Performing Arts building• Forming and pouring tilt-up walls of Gymnasium• Underslab electrical and plumbing of Classroom and
Performing Arts buildings
PVHS New CampusProject Update
Facilities Subcommittee Meeting – April 18, 2017
PVHS New CampusProject Update
Construction Budget
Lathrop Construction Contract Amount $129,894,002
Change Orders $112,735.14
Amended Contract Total $130,006,737.14
Paid to Date $21,084,811.16
Balance to Finish $108,921,925.98
PVHS New CampusProject Update
Community Communication Plan• City Council and Staff Updates
– Kickoff meeting in June 2016– Council - August 2016– Council - January 2017– Public Works staff invited to
weekly project meetings• TV format of Newsletters 1-9
provided to the City of Pinole• Newsletters 1-9, mailed to
community, City of Pinole, PVHS, CBOC
Facilities Subcommittee Meeting – April 18, 2017