123
PILE FOUNDATION Session 17 – 26 Course : S0825/Foundation Engineering Year : 2009

PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Embed Size (px)

Citation preview

Page 1: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

PILE FOUNDATIONSession 17 – 26

Course : S0825/Foundation EngineeringYear : 2009

Page 2: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE FOUNDATIONS

Topic:• Types of pile foundation• Point bearing capacity of single pile• Friction bearing capacity of single pile• Allowable bearing capacity of single pile

SESSION 17 – 20

Page 3: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

INTRODUCTION

Page 4: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

TYPES OF PILE FOUNDATION

STEEL PILE

Page 5: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

TYPES OF PILE FOUNDATION

CONCRETE PILE

Page 6: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

TYPES OF PILE FOUNDATION

CONCRETE PILE

Page 7: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

TYPES OF PILE FOUNDATION

Page 8: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

TYPES OF PILE FOUNDATION

WOODEN PILE

Page 9: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

TYPES OF PILE FOUNDATION

COMPOSITE PILE

COMBINATION OF:

- STEEL AND CONCRETE

- WOODEN AND CONCRETE

- ETC

Page 10: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE CATEGORIES

Classification of pile with respect to load transmission and functional behaviour: 1. END BEARING PILES

These piles transfer their load on to a firm stratum located at a considerable depth below the base of the structure and they derive most of their carrying capacity from the penetration

resistance of the soil at the toe of the pile

2. FRICTION PILES

Carrying capacity is derived mainly from the adhesion or friction of the soil in contact with the

shaft of the pile

3. COMPACTION PILES

These piles transmit most of their load to the soil through skin friction. This process of driving such piles close to each other in groups greatly reduces the porosity and compressibility of the

soil within and around the groups.

Page 11: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

END BEARING PILE

PILE CATEGORIES

Page 12: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE CATEGORIES

FRICTION PILE

Page 13: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE CATEGORIESClassification of pile with respect to effect on the soil

- Driven Pile

Driven piles are considered to be displacement piles. In the process of driving the pile into the ground, soil is moved radially as the pile shaft enters the ground. There may also be a

component of movement of the soil in the vertical direction.

Page 14: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE CATEGORIES

Classification of pile with respect to effect on the soil

- Bored PileBored piles(Replacement piles) are generally considered to be non-displacement piles a void is formed by boring or excavation before piles is produced.

There are three non-displacement methods: bored cast- in - place piles, particularly pre-formed piles and grout or concrete intruded piles.

Page 15: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE CATEGORIES

Page 16: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

DETERMINATION OF PILE LENGTH

Page 17: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

BEARING CAPACITY OF PILE

Two components of pile bearing capacity:

1. Point bearing capacity (QP)

2. Friction bearing capacity (QS)

SPU QQQ

Page 18: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

BEARING CAPACITY OF PILE

Page 19: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

POINT BEARING CAPACITY

SQUARE FOUNDATIONqu = 1,3.c.Nc + q.Nq + 0,4..B.N

CIRCULAR FOUNDATIONqu = 1,3.c.Nc + q.Nq + 0,3..B.N

For Shallow Foundation- TERZAGHI

- GENERAL EQUATIONidsqiqdqscicdcsu F.F.F.N.B..5,0F.F.F.Nq.qF.F.F.Nc.cq

Deep Foundationqu = qP = c.Nc* + q.Nq* + .D.N*

Where D is pile diameter, the 3rd term of equation is neglected due to its small contribution

qu = qP = c.Nc* + q’.Nq* ; QP = Ap .qp = Ap (c.Nc* + q’.Nq*)

Nc* & Nq* : bearing capacity factor by Meyerhof, Vesic and Janbu

Ap : section area of pile

Page 20: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

POINT BEARING CAPACITYMEYERHOF

PILE FOUNDATION AT UNIFORM SAND LAYER (c = 0)

QP = Ap .qP = Ap.q’.Nq* Ap.ql

ql = 50 . Nq* . tan (kN/m2)

Base on the value of N-SPT :

qP = 40NL/D 400N (kN/m2)

Where:N = the average value of N-SPT near the pile point (about 10D above and 4D below the pile point)

Page 21: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

POINT BEARING CAPACITYMEYERHOF

Page 22: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE FOUNDATION AT MULTIPLE SAND LAYER (c = 0)

QP = Ap .qP

dlblldl

llP qD

Lqqqq

10Where:

ql(l) : point bearing at loose sand layer (use loose sand parameter)

ql(d) : point bearing at dense sand layer (use dense sand parameter)

Lb = depth of penetration pile on dense sand layer

ql(l) = ql(d) = 50 . Nq* . tan (kN/m2)

POINT BEARING CAPACITYMEYERHOF

Page 23: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

QP = Ap (c.Nc* + q’.Nq*)For saturated clay ( = 0), from the curve we get:

Nq* = 0.0

Nc* = 9.0

and

QP = 9 . cu . Ap

POINT BEARING CAPACITYMEYERHOF

PILE FOUNDATION AT SATURATED CLAY LAYER (c 0)

Page 24: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

'3

21' q

Koo

• BASE ON THEORY OF VOID/SPACE EXPANSION• PARAMETER DESIGN IS EFFECTIVE CONDITION

QP = Ap .qP = Ap (c.Nc* + o’.N*)

Where:o’ = effective stress of soil at pile point

Ko = soil lateral coefficient at rest = 1 – sin Nc*, N* = bearing capacity factors

oKNq

N

NqNc

21

*3*

cot1**

POINT BEARING CAPACITYVESIC

Page 25: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

POINT BEARING CAPACITYVESIC

r

rrr I

II

1

According to Vesic’s theory

N* = f (Irr)

where

Irr = Reduced rigidity index for the soil

Ir = Rigidity index

Es = Modulus of elasticity of soil

s = Poisson’s ratio of soil

Gs = Shear modulus of soil

= Average volumetric strain in the plastic zone below the pile point

tan'tan'12 qc

G

qc

EI s

s

sr

Page 26: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

POINT BEARING CAPACITYVESIC

12

1ln3

4*

rrINc

For condition of no volume change (dense sand or saturated clay):

= 0 Ir = Irr

For undrained conditon, = 0

The value of Ir could be estimated from laboratory tests i.e.: consolidation and triaxial

Initial estimation for several type of soil as follow:

Type of soil Ir

Sand 70 – 150

Silt and clay (drained) 50 – 100

Clay (undrained) 100 – 200

Page 27: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

POINT BEARING CAPACITYJANBU

QP = Ap (c.Nc* + q’.Nq*)

cot1**

.tan1tan* tan'22

2

NqNc

eNq

Page 28: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

POINT BEARING CAPACITYBORED PILE

QP = . Ap . Nc . Cp

Where: = correction factor = 0.8 for D ≤ 1m = 0.75 for D > 1mAp = section area of pilecp = undrained cohesion at pile pointNc = bearing capacity factor (Nc = 9)

Page 29: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

FRICTION RESISTANCE

fLpQs ..Where:

p = pile perimeterL = incremental pile length over which p and f are taken constantf = unit friction resistance at any depth z

Page 30: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

FRICTION RESISTANCESAND

fLpQs ..

tan'.. vKf

Where:K = effective earth coefficient = Ko = 1 – sin (bored pile) = Ko to 1.4Ko (low displacement driven pile) = Ko to 1.8Ko (high displacement driven pile)v’ = effective vertical stress at the depth under consideration = soil-pile friction angle = (0.5 – 0.8)

Page 31: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

FRICTION RESISTANCECLAY

Three of the presently accepted procedures are:

1. methodThis method was proposed by Vijayvergiya and Focht (1972), based on the assumption that the displacement of soil caused by pile driving results in a passive lateral pressure at any depth.

2. method (Tomlinson)

3. method

Page 32: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

FRICTION RESISTANCECLAY - METHOD

avs fLpQ ..

uvav cf 2' Where:v’= mean effective vertical stress for the entire embedment lengthcu = mean undrained shear strength ( = 0)

VALID ONLY FOR ONE LAYER OF HOMOGEN CLAY

Page 33: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

FRICTION RESISTANCECLAY - METHOD

L

LcLcc uuu

..... 22,11,

FOR LAYERED SOIL

L

AAAv

...' 321

Page 34: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

FRICTION RESISTANCECLAY - METHOD

fLpQs ..

ucf .

For cu 50 kN/m2 = 1

Page 35: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

FRICTION RESISTANCECLAY - METHOD

fLpQs ..

'. vf Where:

v’= vertical effective stress

= K.tanR

R = drained friction angle of remolded clay

K = earth pressure coefficient at rest

= 1 – sin R (for normally consolidated clays)

= (1 – sin R) . OCR (for overconsolidated clays)

Page 36: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

FRICTION RESISTANCEBORED PILE

LpcQ us 45.0

Where:

cu = mean undrained shear strengthp = pile perimeterL = incremental pile length over which p is taken constant

Page 37: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

ULTIMATE AND ALLOWABLE BEARING CAPACITY

SPU QQQ

FS

QQ Uall

5.13SP

all

QQQ

FS= 2.5 - 4

DRIVEN PILE

BORED PILE

2U

all

QQ

5.2U

all

QQ D < 2 m and with expanded at pile point

no expanded at pile point

Page 38: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

EXAMPLEA pile with 50 cm diameter is penetrated into clay soil as shown in the following figure:

GWL5 m

5 m

20 m

NC clay = 18 kN/m3

cu = 30 kN/m2

R = 30o

OC clay (OCR = 2) = 19.6 kN/m3

cu = 100 kN/m2

R = 30o

Determine:1. End bearing of pile2. Friction resistance by , , and methods3. Allowable bearing capacity of pile (use FS = 4)

Page 39: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE FOUNDATIONS

Topic:• Settlement of Piles• Laterally Loaded Piles• Pull Out Resistance of Piles• Pile Driving Formula• Negative Skin Friction

SESSION 21 – 22

Page 40: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

SETTLEMENT OF PILES

S = S1 + S2 + S3

Where:

S = total pile settlement

S1 = elastic settlement of pile

S2 = settlement of pile caused by the load at the pile tip

S3 = settlement of pile caused by the load transmitted along the pile shaft

Page 41: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

SETTLEMENT OF PILES

pp

wswp

EA

LQQS

.

.1

Where:

Qwp = load carried at the pile point under working load condition

Qws = load carried by frictional (skin) resistance under working load condition

Ap = area of pile cross section

Ep = modulus of elasticity of the pile material

L = length of pile

= the magnitude which depend on the nature of unit friction (skin) resistance distribution along the pile shaft.

Page 42: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

SETTLEMENT OF PILES

wpss

wp IE

DqS .1

. 22

Where:qwp = point load per unit area at the pile point = Qwp/Ap

D = width or diameter of pileEs = modulus of elasticity of soil at or below the pile points = poisson’s ratio of soilIwp = influence factor = r

Page 43: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

SETTLEMENT OF PILES

wsss

ws IE

D

pL

QS .1 23

Where:

Qws = friction resistance of pile

L = embedment length of pile

p = perimeter of the pile

Iws = influence factor

D

LIws 35.02

Page 44: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

EXAMPLE

The allowable working load on a prestressed concrete pile 21 m long that has been driven into sand is 502 kN. The pile data are as follow:

- Diameter (D) = 356 mm

- The area of cross section (Ap) = 1045 cm2

- Perimeter (p) = 1.168 m

Skin resistance carries 350 kN of the allowable load, and point bearing carries the rest. Use Ep = 21 x 106 kN/m2

, Es = 25,000 kN/m2, s = 0.35 and = 0.62)

Determine the settlement of the pile.

Page 45: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

EXAMPLE

mm35.3m00353.0

10x211045.0

2135062.0152

E.A

LQ.QS

6pp

wswp1

mm5.15m0155.085.035.01000,25

356.0

1045.0

152I.1

E

D.qS 2

wp2s

s

wp2

mm84.0m00084.069.435.01000,25

356.0

21168.1

350I.1

E

D

pL

QS 2

ws2s

s

ws3

69.4356.0

2135.02

D

L35.02Iws

S = S1 + S2 + S3 = 3.35 + 15.5 + 0.84 = 19.69 mm

Page 46: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

LATERALLY LOADED PILE

Page 47: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

LATERALLY LOADED PILE

ELASTIC SOLUTION – EMBEDDED IN GRANULAR SOIL

Page 48: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

LATERALLY LOADED PILE

Page 49: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

LATERALLY LOADED PILEFor L/T 5

Page 50: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

LATERALLY LOADED PILE

Page 51: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

LATERALLY LOADED PILE

Page 52: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

LATERALLY LOADED PILE

ELASTIC SOLUTION – EMBEDDED IN COHESIVE SOIL

Page 53: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

LATERALLY LOADED PILE

Page 54: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

LATERALLY LOADED PILE

ULTIMATE LOAD ANALYSIS – MEYERHOF – PILES IN SAND

ULTIMATE LOAD RESISTANCE (Qu(g))

Page 55: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

LATERALLY LOADED PILEMAXIMUM MOMENT, Mmax DUE TO THE LATERAL LOAD Qu(g)

MAXIMUM MOMENT, Mmax DUE TO THE LATERAL LOAD Qg

For long (flexible) piles in sand

Page 56: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

LATERALLY LOADED PILE

ULTIMATE LOAD ANALYSIS – MEYERHOF – PILES IN CLAY

ULTIMATE LOAD RESISTANCE (Qu(g))

Page 57: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

LATERALLY LOADED PILE

MAXIMUM MOMENT, Mmax DUE TO THE LATERAL LOAD Qu(g)

MAXIMUM MOMENT, Mmax DUE TO THE LATERAL LOAD Qg

For long (flexible) piles

Page 58: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PULL OUT RESISTANCE OF PILES

Page 59: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PULL OUT RESISTANCE OF PILES

Page 60: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PULL OUT RESISTANCE OF PILES

EXAMPLE:

A concrete pile 50 long is embedded in a saturated clay with cu = 850 lb/ft2. The pile is 12 in. x 12 in. in cross section. Use FS = 4 and determine the allowable pullout capacity of the pileSolution

Given cu = 850 lb/ft2 40.73 kN/m2

’ = 0.9 – 0.00625cu = 0.9 – (0.00625)(40.73) = 0.645

kip4.274

7.109

FS

TT

kip7.1091000

)850)(645.0)(1x4)(50(c'..p.LT

un)all(un

uun

Page 61: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PULL OUT RESISTANCE OF PILES

Page 62: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PULL OUT RESISTANCE OF PILES

For dry soils, the equation simplifies to

Determine the value of Ku and from figure 9.36b and 9.36c.

tan.....tan.....2

1 2crucrucrun LLKLpKLpT

FS

TT un

allun )(

Where Tun(all) = allowable uplift capacity and FS is Factor of Safety (a value of 2 – 3 is recommended)

Page 63: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PULL OUT RESISTANCE OF PILES

EXAMPLE:

a precast concrete pile with a cross section 350 mm x 350 mm is embedded in sand. The length of pile is 15 m. Assume that sand = 15.8 kN/m3, sand = 35o, and the relative density of sand = 70%. Estimate the allowable pullout capacity of the pile (FS = 4)

Solution

From figure 9.36, for = 35o and relative density = 70%

kNFS

TT

kNT

LLKLpKLpT

K

mmLD

L

unallun

un

crucrucrun

u

o

crcr

4904

1961

1961

tan.....tan.....2

1

2

35351;1

08.5)35.0)(5.14(;5.14

)(

2

Page 64: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE DRIVING FORMULA

Page 65: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

NEGATIVE SKIN FRICTION

Can occur under condition such as:

- If a fill of clay soil is placed over a granular soil layer into which a pile is driven, the fill will gradually consolidate. This consolidation process will exert a downward drag force on the pile during a period of consolidation

- If a fill of granular soil is placed over a layer of soft clay. It will induce the process of consolidation in the clay layer and thus exert a downward drag on the pile

Page 66: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

NEGATIVE SKIN FRICTION

CLAY FILL OVER GRANULAR SOIL

Page 67: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

NEGATIVE SKIN FRICTIONGRANULAR SOIL FILL OVER CLAY

THE UNIT NEGATIVE SKIN FRICTION AT ANY DEPTH FROM z = 0 TO z = L1

Page 68: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

NEGATIVE SKIN FRICTION

Page 69: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

GROUP PILES

Topic:• Bearing Capacity of Group Piles• Group Efficiency• Piles in Rock• Consolidation settlement of Group Piles

SESSION 23 – 24

Page 70: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

GROUP PILES

Lg = (n1 – 1)d + 2(D/2)

Bg = (n2 – 1)d + 2(D/2)

Where:

D = pile diameter

d = spacing of pile (center to center)

Page 71: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

GROUP PILES

Page 72: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

GROUP EFFICIENCY

u

ug

Q

Q )(

Where:

= group efficiency

Qg(u) = ultimate load bearing capacity of the group pile

Qu = ultimate load bearing capacity of each pile without the group effect

Page 73: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

GROUP PILES IN SAND

uug Qnnp

DdnnQ

nnp

Ddnn

...

422

..

422

21

21)(

21

21

If < 1 Qg(u) = .Qu

If 1 Qg(u) = Qu

Page 74: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

GROUP PILES IN SAND

Page 75: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

GROUP PILES IN SAND

Page 76: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

GROUP PILES IN SAND

Page 77: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

GROUP PILES IN SAND

Summary:

1.For driven group piles in sand with d 3D, Qu(g) may be taken to be Qu, which includes the frictional and the point bearing capacities of individual piles.

2.For bored group piles in sand at conventional spacings (d 3D), Qg(u) may be taken to be 2/3 to 3/4 times Qu (frictional and point bearing capacities of individual piles)

Page 78: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

GROUP PILES IN SATURATED CLAY

Page 79: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

GROUP PILES IN SATURATED CLAYCalculation steps:1. Determine Qu = n1.n2 (Qp + Qs)

where:QP = 9 . cu . Ap (ultimate end bearing capacity of single pile)

QS = (.p.cu.L) (skin resistance of single pile)

2. Determine the ultimate capacity by assuming that the piles in the group act as a block with dimensional Lg x Bg x L as follow :- end bearing capacity of the block

QP’ = Ap . qp = Ap . cu . Nc* with Ap = Lg . Bg

- Skin resistance of the blockQS’= (pg.cu.L) = 2.(Lg+Bg).cu.L

- Ultimate bearing capacity o pile groupQu = QP’ + QS’ Qu = (Lg . Bg) . cu . Nc* + 2.(Lg+Bg).cu.L

3. Compare the values obtained in step 1 and 2 the lower of the two values is Qg(u)

Page 80: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

GROUP PILES IN SATURATED CLAY

Page 81: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

GROUP PILES IN SATURATED CLAY

Problem:

The section of a 3 x 4 group pile layered saturated clay. The piles are square in cross section (14 in. x 14 in.). The center to center spacing, d, of the piles is 35 in. Determine the allowable load bearing capacity of the pile group. USE FS = 4

Page 82: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

GROUP PILES IN SATURATED CLAY

Page 83: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILES IN ROCK

For point bearing piles resting on rock, most building codes specify that Qq(u) = Qu, provided that the minimum center to center spacing of piles is D + 300 mm. For H-Piles and piles with square cross sections, the magnitude of D is equal to the diagonal dimension of the pile cross section.

Page 84: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

CONSOLIDATION SETTLEMENT OF GROUP PILES

The Terzaghi formula is valid with some rules:

1.The consolidation settlement is occurred from the depth of 2/3 of pile length.

2.The stress increase caused at the middle of each soil layer by using 2:1 method

igig

gi zLzB

Qp

Page 85: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

sat = 18,9 kN/m3

Cc = 0,2

eo = 0,7sat = 19 kN/m3

Cc = 0,25

eo = 0,75

Problem:

A group pile with Lg = 3.3 m and Bg = 2.2 m as shown in the figure. Determine the consolidation settlement of the pile groups. All clays are normally consolidated.

CONSOLIDATION SETTLEMENT OF GROUP PILES

sat = 18 kN/m3

Cc = 0,3

eo = 0,82

Page 86: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

ELASTIC SETTLEMENT OF GROUP PILES

• VESIC

Page 87: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

ELASTIC SETTLEMENT OF GROUP PILES

• MEYERHOF (Pile groups in sand and gravel)

Page 88: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

ELASTIC SETTLEMENT OF GROUP PILES

• PILE GROUP SETTLEMENT RELATED TO THE CONE PENETRATION RESISTANCE

Page 89: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

UPLIFT CAPACITY OF GROUP PILES

Page 90: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

UPLIFT CAPACITY OF GROUP PILES

Page 91: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE INSTALLATION AND LOADING TEST

Topic:• Installation Method of Driven Pile• Installation Method of Bored Pile• Loading Test by Static Method• Loading Test by Dynamic Method

SESSION 25 – 26

Page 92: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

INSTALLATION METHOD

Pile Installation Equipment

The primary tools used in the actual driving(installing) of piles are :

• Impact Hammers,• Vibrator Driver / Extractors• Special Hydraulic Presses• Supporting Equipment – power sources, hoisting & material handling equipment, etc.

Page 93: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE INSTALLATION EQUIPMENTS

Types of Impact Hammers

Impact Hammers are identified by their method of operation or the motive force employed. They are generally identified as :• Drop Hammers• Air or Steam Hammers• Diesel Hammers• Hydraulic Impact Hammers

Page 94: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE INSTALLATION EQUIPMENTS

Drop Hammers

Page 95: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

Air (or Steam) Hammers

PILE INSTALLATION EQUIPMENTS

Page 96: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

Air (or Steam) Hammers

PILE INSTALLATION EQUIPMENTS

Page 97: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

Diesel Hammers

PILE INSTALLATION EQUIPMENTS

Page 98: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

Diesel Hammers

PILE INSTALLATION EQUIPMENTS

Page 99: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

Hydraulic Impact Hammers

PILE INSTALLATION EQUIPMENTS

Page 100: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE INSTALLATION EQUIPMENTS

Hydraulic Impact Hammers

Page 101: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE INSTALLATION EQUIPMENTS

Vibro Driver/Extractors

Page 102: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE INSTALLATION EQUIPMENTS

Vibro Driver/Extractors

Page 103: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE INSTALLATION EQUIPMENTS

Hydraulic Press Installer

Page 104: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE INSTALLATION EQUIPMENTS

Hydraulic Press Installer

Page 105: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE INSTALLATION EQUIPMENTS

Land Based RigsCantilever Fixed Lead

(With Fixed Bottom Brace) (With Spotter)

Page 106: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE INSTALLATION EQUIPMENTS

Land Based Rigs

Under slung Swinging Lead

(With Fixed Bottom Brace) (With stabbing points)

Page 107: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE INSTALLATION EQUIPMENTS

Land Based RigsEuropean Style, Fixed Lead with Fixed Bottom Brace

(Driving Aft Batter with Hydraulic Hammer)

Page 108: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE INSTALLATION EQUIPMENTS

Land Based RigsEuropean Style, Fixed Lead on Crawler Lower

Page 109: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

DRIVEN PILE INSTALLATION

Page 110: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

BORED PILE INSTALLATION

Page 111: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE QUALITY

Two aspects of final quality of pile:– Structural integrity of pile.– Pile ability to support external load, consist of strength

of structure element and relationship load-settlement between pile and soil support

Page 112: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

STATIC LOADING TEST

TEST METHODS– Use Static Load– The load is 200% of working load– Preparation before testing– Loading– Measurement of pile movement– Instrumentation

Page 113: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

STATIC LOADING TEST

• Loading Methods– Standard Method of Loading‑SML, Monotonic– Standard Method of Loading‑SML, cyclic– Quick Load Test (Quick ML)– Constant Rate of Penetration Method (CRP)

Sumber : Manual Pondasi Tiang, GEC

Page 114: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

Anchor Pile

Typical arrangements for axial compressive

load test

Dead Load

Page 115: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

STATIC LOADING TEST

Page 116: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

STATIC LOADING TEST

Test load arrangement using kentledge

Page 117: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

DYNAMIC LOADING TEST

• PDA (Pile Driving Analyzer) • DLT (Dynamic Load Test), TNO• Theory of wave propagation

Sumber : Manual Pondasi Tiang, GEC

Page 118: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

Strain gauge and accelerometerPDA computer

Interpretation of PDA

result

Page 119: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PULL OUT TESTS

Sumber : Manual Pondasi Tiang, GEC

Pullout load by using hydraulic jack between beam and reaction frame (ASTM D 3689-83, 1989)

Page 120: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PULL OUT TESTS

Pullout load by using hydraulic jack, one at each end of the beam (ASTM D 3689-83, 1989)

Page 121: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

LATERAL LOADING TEST

Sumber : Manual Pondasi Tiang, GEC

Page 122: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

LATERAL LOADING TEST

Page 123: PILE FOUNDATION Session 17 – 26 Course: S0825/Foundation Engineering Year: 2009

Bina Nusantara

PILE INTEGRITY TEST

• This test is needed to check the integrity of bored pile or driven pile.

• Some methods generally adopted is by using the principle of wave propagation. The test is carried out by applying vibration and evaluating its reflection.

• Through this test, the defect on pile will be able to detect.

Sumber : Manual Pondasi Tiang, GEC