Upload
volien
View
222
Download
0
Embed Size (px)
Citation preview
PECDEMO is a Collaborative Project co-funded by FCH JU under the call SP1-JTI-FCH.2013.2.5.
GA n°: 621252. Start date: April 1st, 2014. Duration: 36 months.
Deliverable title: Final Assessment Report
Deliverable nature: Report
Dissemination level: Public
Lead beneficiary: HZB
Contracted date of delivery: Mar-17
Actual date of delivery: Mar-17
Author(s): Daniela Kaden, Roel van de Krol
Photoelectrochemical
Demonstrator Device
for Solar Hydrogen
Generation
Project Deliverable Report −
D7.2
PECDEMO Mid-term Assessment Report
TABLE OF CONTENTS
1. Executive Summary ............................................................................................................ 1
2. Core of the Report .............................................................................................................. 2
2.1. Background and Objectives for the reporting period ....................................................... 2
2.2. Work progress and achievements during the reporting period ........................................ 2
2.2.1. General Management (Task 7.1) .............................................................................. 2
2.2.2. General Assembly (Task 7.2) .................................................................................... 5
2.2.2.1. Project amendment and budget adjustments........................................................ 5
2.2.3. Executive Board (Task 7.3) ....................................................................................... 6
2.2.4. Establishment of an Industrial Review Panel (Task 7.4) .............................................. 7
3. Appendices ......................................................................................................................... 9
PECDEMO Final Assessment Report
WP7 - Page 1
1. EXECUTIVE SUMMARY
The aim of this report is to summarise the second 18 months of activity of
PECDEMO’s Management work package WP7. Efforts of WP7 have thus far involved
common management and assistance to the project partners with regard to daily
administrative processes and activities, i.e., monitoring the progress of the project,
organisation, preparation and follow-up of project meetings, coordination of regular
scientific and financial reports as well as establishing the formal link between the
Consortium and the FCH JU Programme Office.
Moreover, the Coordinator supported by the Management Support Team has
helped ensuring the project communication both internally and externally .
PECDEMO Final Assessment Report
WP7 - Page 2
2. CORE OF THE REPORT
2.1. Background and Objectives for the reporting period
The objective for WP7 was to establish a general management infrastructure for
the proposed work and to provide coordination activities during the course of the
project. It monitors and controls the progress of the project and establishes the formal
link between the Consortium and the FCH JU Programme Office by handling all
general financing and reporting matters. In the framework of WP7, the Management
Support Team organises and facilitates the meetings of the Consortium bodies.
Additionally, this WP coordinates internal communication activities between all
participating project partners.
2.2. Work progress and achievements during the reporting period
2.2.1. General Management (Task 7.1)
The general organisation of the project has been put in place in the early
phases of the project, with a Coordinator, a Management Support Team, Leaders for
each WP and a strong collaborative spirit (for details see D7.1). In order to establish
and provide effective project management, several management activities and
services have been undertaken. These include the following:
Project Meetings and Reporting:
During the second 18 months, three physical meetings and five technical
conference calls have been initiated and held at regular intervals in order to oversee
and assess the progress of each WP, to discuss critical aspects and to address any
problems or deviations from the proposal. Following is a list of project meetings held
during the course of the project:
Conference call, 15/10/2015, via Adobe Connect
Conference call, 16/02/2016, via Adobe Connect
5th PECDEMO GA and EB meeting, 07/03/2016, at Technion, Haifa, Israel
Conference call, 23/05/2016, via Adobe Connect
Conference call, 23/08/2016, via Adobe Connect
6th PECDEMO GA and EB meeting, 07/10/2016, at UPorto in Porto, Portugal
Conference call, 09/12/2016, via Adobe Connect
PECDEMO Final Assessment Report
WP7 - Page 3
7th PECDEMO GA and EB meeting, 07/02/2017, at DLR in Cologne, Germany
Conference call, 13/03/2017, via Adobe Connect
The Members of the GA and EB have been invited to all the meetings. The Coordinator
and its Management Support Team were responsible for preparing the agenda,
chairing the meetings, providing the summarized minutes and monitoring the
implementation of decisions taken at these meetings. All documents were shared with
the PECDEMO Consortium and a final copy was stored in the restricted file-sharing
area at my.epfl.ch. All partners have hosted at least one PECDEMO meeting, with only
one exception. In the 6th PECDEMO meeting it was unanimously decided to hold the
final PECDEMO meeting at the demonstrator site DLR in Cologne, instead of the Evonik
partner site. The demonstrator was presented and introduced by DLR. In addition, DLR
also intends to make a video of the working demonstrator and disseminate it publicly
via the PECDEMO website.
In addition to the regular conference calls and project meetings, we organized two
additional conference calls on 30/11/2015 and 03/12/2015 to prepare for the Mid-term
review in Brussels on 10/12/2015. At the mid-term review in Brussels the coordinator,
Prof. Roel van de Krol as well as all work package leaders presented the current status
of the project and the individual work packages. The project officer and reviewer
gave us constructive and useful suggestions for continuing the second period and as
far as possible these suggestions were implemented in this second period.
The Coordinator and the Management Support Team have maintained regular
contacts with all the project partners, closely following their financial status and
providing all the necessary information and administrative support, including the
coordination of periodic reporting. The second Annual Project Status Report was
delivered to the Coordinator in September 2016. Those reports were originally planned
for March 2016, but since there were only small changes to the results presented in the
mid-term data report, we decided to postpone it to September, because more data
could be included this way. In addition, these reports serve as a good base for the
final data report. These annual reports are detailed internal project reviews and
include all the work performed within the respected WP up to date. The WP Leaders
reported not only on achievements but also on problems, critical points and risks, as
well as corrective actions. All Annual Project Status Reports were submitted to the
Coordinator and then distributed to the Consortium and are accessible to all partners
on the restricted file-sharing area at http://my.epfl.ch. Since at project end a second
PECDEMO Final Assessment Report
WP7 - Page 4
periodic report will be submitted, there will be no additional Annual Project Status
Report for the final phase.
Communication between the Management Support Team and FCH JU has
been regular throughout the course of project. In the second period, 20 reports on
deliverables, have been provided. The deliverables D4.2 (Delivery date: Nov 2015,
Deliverable Nature: Report), D4.3 (Delivery date: Jan 2016, Deliverable Nature:
Report), D1.4, D3.2 and D5.1 incl. MS5 (Delivery date: Mar 2016, Deliverable Nature:
Report), D3.3 (Delivery date: May 2016, Deliverable Nature: Report), D8.2 (Delivery
date: Jul 2016, Deliverable Nature: Other), D3.4 (Delivery date: Sep 2016, Deliverable
Nature: Prototype), D6.1 incl. MS7 (Delivery date: Nov 2016, Deliverable Nature:
Prototype), D1.5 incl. MS8, D5.3 and D7.2 (Delivery date: Mar 2017, Deliverable Nature:
Demonstrator (D1.5) and Report) were delivered in time. The Deliverables D7.1
(Delivery date: Nov 2015, Deliverable Nature: Report), D2.2 incl. MS4 (Delivery date:
Mar 2016, Deliverable Nature: Report), D4.4 incl. MS6 (Delivery date: Jul 2016,
Deliverable Nature: Prototype), D5.2 (Delivery date: Sep 2016, Deliverable Nature:
Report), D2.3 (Delivery date: Dec 2016, Deliverable Nature: Report), D6.2 (Delivery
date: Jan 2017, Deliverable Nature: Report) and D6.3 (Delivery date: Feb 2017,
Deliverable Nature: Report) were delivered with short delays. However, delays were
always announced and justified to and accepted by the responsible FCH JU project
officer Nikolaos Lymperopoulos. Due to some technical problems and weather
conditions, WP6 was slightly delayed beginning with D6.2. Therefore, also the final
Deliverable D6.4 (Delivery date: Mar 2017, Deliverable Nature: Report) will be delayed
to be able to present the latest data.
In summary, apart from some minor delays, all deliverables and milestones
foreseen in the Grant Agreement for the second period have thus far been attained
by the Consortium.
In addition, the PECDEMO project was represented by the Management
Support Team at the FCH JU Programme Review Days 2015 and 2016 which took place
in Brussels. Key objectives and so far achievements were presented during manned
poster sessions. The poster templates were provided by the FCH JU. In 2015, Fatwa
Abdi, the Leader of work package 1 presented the PECDEMO poster in a manned
poster session in Brussels on 18/11/2015 (Fig. 1 in the Appendix). In 2016, Roel van de
Krol gave an oral presentation and presented the PECDEMO poster in a manned
poster session on 22/11/2016 (Fig. 2 in the Appendix).
PECDEMO Final Assessment Report
WP7 - Page 5
2.2.2. General Assembly (Task 7.2)
The General Assembly (GA) is the top decisional body, primarily responsible to carry
out the strategic plans and policies as established in the Grant Agreement and
Consortium Agreement. It includes at least one representative from each Consortium
partner. These representatives should be able to decide on behalf of their
organisations. The GA meets twice a year. In the second period of the project no more
changes in the GA occurred.
Members of the GA are to date:
Roel van de Krol [HZB, E-IF] as Coordinator and chairperson
Daniela Kaden [HZB, E-IF] as project manager share one vote
Matthew Mayer [EPFL, LPI]
Avner Rothschild [IIT]
Michael Wullenkord [DLR]
Adélio Mendes [University of Porto]
Artjom Maljusch [Evonik Industries AG]
Frédéric Oswald [Solaronix SA]
If both HZB representatives are present at a GA meeting they shall share one vote on
decisions, according to the Consortium Agreement.
2.2.2.1. Project amendment and budget adjustments
After the end of the first project period, Evonik requested a shift of person month from
work package 1. Therefore we submitted a project amendment.
The main scope of WP1 was focused on the development of metal oxide
photoelectrodes and optically transparent counter electrodes at small scale, as we ll
as on the evaluation of their performance. As Evonik is not an expert in metal oxide
deposition techniques, their contribution in WP1 was meant to support the
cooperation partners with the evaluation of the performance of prepared electrodes.
Within the project, the consortium partners had successfully developed
photoelectrodes according to project targets in WP 1 and were able to evaluate
performance directly by themselves due to availability of highly qualified personnel
and appropriate equipment. Thus, additional contribution from Evonik was not really
needed and would not have enabled faster reaching of milestones in WP1.
PECDEMO Final Assessment Report
WP7 - Page 6
During the Midterm Review in Brussels on 10/12/2015, the reviewers recommended to
strengthen the scale-up activities in the second half of the project. Therefore, in
agreement with all the consortium partners, we proposed to reallocate a small part of
the 13.59 person-months still available for Evonik in WP1 (Cell Development) to HZB,
and the rest to EPFL and HZB for the activities in WP3 (Large Area Technology
Development) and WP4 (Device design and testing). This leveraged remaining
resources on topics which are essential to meet upcoming deliverables and therefore
increased the probability to reach the main goal of the PECDEMO project (8% efficient
PEC device with an active area > 50 cm2 and stability > 1000 hours).
In detail, the PECDEMO management team proposed to shift the 13,59 remaining
person months of Evonik WP1 to HZB and EPFL. This shift enabled eight additional
person months for WP1 and WP3 for HZB and four additional person months for WP3
and WP4 for EPFL. The GA and their legal entities formally agreed to this amendment.
Therefore, it was submitted in July 2016 and finally accepted in September 2016. The
changed Annex I and DoW is dated 07/07/2016 and was sent to all partners and was
uploaded on myEPFL.
In addition, we had two formal requests of budget adjustments.
First, DLR requested to shift consumables and travel costs to personnel for WP4 and
WP6. Second, Technion (IIT) requested to shift consumables to personnel, in order to
cover additional salary. We discussed both requests with our FCH JU project officer.
Both mentioned changes were well within the tolerance of shifting funds and effort
between WPs and cost categories. That means, that it was not necessary to submit an
additional amendment. As coordinator we agreed to both budget adjustments and
confirmed this by sending a formal letter to the partners.
2.2.3. Executive Board (Task 7.3)
The Coordinator and all of the WP Leaders make up the Executive Board (EB). The
main responsibility of the EB is the high quality preparation and execution of the
project. The EB meets on a need-to-meet basis but at least quarterly either at physical
meetings or via conference call (For a detailed list of meetings, please go to point
2.2.1.). In the second period of the project no more changes in the EB occurred.
Members of the EB are to date:
PECDEMO Final Assessment Report
WP7 - Page 7
Roel van de Krol [HZB, E-IF]
WP1: Fatwa Abdi [HZB, E-IF]
WP2: Avner Rothschild [Technion/IIT]
WP3: Bernd Stannowski [HZB, PVcomB]
WP4: Adelio Mendes [University of Porto]
WP5: Artjom Maljusch [Evonik Industries AG]
WP6: Michael Wullenkord [DLR]
WP7: Daniela Kaden [HZB, E-IF]
WP8: Matthew Mayer [EPFL, LPI]
2.2.4. Establishment of an Industrial Review Panel (Task 7.4)
The first milestone of the PECDEMO project has been to set up an Industrial
Review Panel (IRP) within the framework of WP7. This was established to enhance the
economic impact of scientific and technological results obtained within PECDEMO.
The main objectives of this panel are (i) to evaluate the economic potential of the
obtained results, (ii) to provide a gateway for regular communication with potentia l
industrial partners and (iii) to provide scientific feedback.
Composition of the IRP:
The following persons were named for the IRP originally:
Dr. Günter Schmid / Siemens AG
Dr. Jens Busse / Evonik Industries AG – CREAVIS
Max von Romatowski / SolarWorld Asia Pacific Pte Ltd
Since Dr. Jens Busse changed the position inside Evonik, another coworker from
Evonik was asked to overtake the task. Although he accepted, we unfortunately
never received the requested CV as a basis for making a decision in the GA. That
means, the position was not filled anymore after the mid-term report.
Tasks of the IRP:
The IRP was timely informed about the Mid-term Assessment Report and two of
the three members reviewed the preliminary reports. Max von Romatoswki apologized
due to time constraints. Dr. Jens Busse and Dr. Günter Schmid both emphasized the
progress that has been made in all aspects of the project and gave us detailed
PECDEMO Final Assessment Report
WP7 - Page 8
questions and comments to the individual work packages and to the report as a
whole. Günter Schmid concluded: “Here I have seen great work, best engagement
and tremendous creativity .”
The IRP was further invited to take part in the physical meetings taking place in
Porto, Portugal on 07/10/2016 and Cologne on 07/02/2017. Only Günter Schmid
accepted the invitations and planned to come, but unfortunately had to cancel both
meetings due to severe illness.
The PECDEMO management team and the project partners highly
appreciated the efforts made by the IRP. We especially appreciated the contributions
of Günter Schmid and Jens Busse, who were present at the first meeting and both
gave us precious input for the mid-term report. Günter Schmid also already agreed to
review the second periodic report as well as the final report. We regret that Max von
Romatowski was unable to attend any meetings due to time constraints and
geographical challenges (he is located in Singapore), but we highly appreciated it
that he could be represented by Mr. Holger Neuhaus at the 3rd PECDEMO meeting in
Cologne.
PECDEMO Final Assessment Report
WP7 - Page 9
3. APPENDICES
Figure 1– Poster presentation at the FCH JU Programme Review Days 2015 in Brussels.
PECDEMO Final Assessment Report
WP7 - Page 10
Figure 2– Poster presentation at the FCH JU Programme Review Days 2016 in Brussels.