Upload
camron-hodges
View
218
Download
1
Embed Size (px)
Citation preview
Phoenix Convention Center • Phoenix, Arizona
Lessons Learned from ARRA Projects
Solution Showcase Lessions Learned from ARRA Projects
Walter Tersch, LEED AP (BD + C)US General Services Administration
August 13, 2015
Energy Exchange: Federal Sustainability for the Next Decade2
Lessons Learned from ARRA Projects
Overview• What worked: process• What worked: technology and project case
studies• What worked less-well than planned
Energy Exchange: Federal Sustainability for the Next Decade3
What worked: process
Methodical selection criteria
• GSA selected projects that met the American Recovery and Reinvestment Act’s criteria based on two overarching criteria: Ability of the project to put people back to work quickly, and transforming Federal buildings into high-performance green buildings.
• The complete list of selection criteria, in descending priority order is: – High-performance features concentrating on energy conservation and renewable energy generation. – Speed of construction start (creating jobs), with an emphasis on those projects that could begin within
120 days. – Execution Risk (ensuring that the projects will not fail due to unforeseen conditions) – Facility Condition. The Facility Condition Index is a standard real estate industry index that reflects the
cost of the repair and alteration backlog of a particular building relative to the building's replacement value.
– Improving Asset Utilization – Return on Investment – Avoiding Lease Costs – Historic Significance
• In any construction or modernization project, objectives go far beyond just saving energy. GSA has carefully implemented the objectives of the Recovery Act, and continues to deliver projects that combine different types of work to yield sound overall value.
Energy Exchange: Federal Sustainability for the Next Decade4
What worked: process
Systematic data gathering
• GSA’s gBUILD project tracking tool – Collect and review high performance green building
project information, including scope details and performance projections
– Verify compliance with the Guiding Principles• “On Green” performance measure– GSA’s Minimum Performance Criteria
• Recurring dashboards and reports for unprecedented transparency
Energy Exchange: Federal Sustainability for the Next Decade5
What worked: technologies and project case studies
• Dayton Federal Building & U.S. Courthouse • Completion Date: FY2012 • Project Cost: $4,701,240 • Actual Energy Reduction: 32%• The Dayton Federal Building & U.S. Courthouse in
Dayton, OH, invested Recovery Act funding for daylight harvesting and occupancy sensors, the installation of high performance heating ventilation and air conditioning components, a new rooftop air handling unit, building pressurization, and low-flow restroom fixtures with lavatory sensors.
Energy Exchange: Federal Sustainability for the Next Decade6
What worked: technologies and project case studies
• Thomas S. Foley U.S. Courthouse • Completion Date: FY2013 • Project Cost: $43,743,451 • Actual Energy Reduction: 47% • The Thomas S. Foley U.S. Courthouse in Spokane, Washington used
Recovery Act funding to turn an aging building into a modernized and operationally efficient high-performance green building. The project focused on upgrades and replacements of building systems including electrical, HVAC, and lighting systems. Resource efficiency improvements include system level submetering of lighting and plug loads, indoor lighting retrofits with LED lamps, occupant sensors, time scheduling and integration with building automation system (BAS), and outdoor lighting retrofits. Indoor environmental quality was also improved through task ambient conditioning systems that allow occupants to control thermal conditions in small, localized zones. Indoor water conservation measures include installation of new low-flow, sensor-controlled lavatory fixtures. This renovated U.S. Courthouse earned LEED Silver certification.
Energy Exchange: Federal Sustainability for the Next Decade7
What worked less-well than planned
– Energy models can make unrealistic assumptions– Faulty commissioning– Insufficient training– Buildings with old, poorly-designed systems
(thermal loops upon loops, single-pane glass, etc.)– Insufficient recirculation of conditioned air
• Difficulty parsing out HPGB-specific cost• Burden of data gathering upon PMs
Energy Exchange: Federal Sustainability for the Next Decade8
Next Steps
• Continue Light-Touch Measurement & Verification Review
• Implementation strategy for achieving 2025 goals set out in EO 13693
• Assessing performance of buildings meeting the Guiding Principles – Follow on to GSA’s post occupancy evaluation and
Green Building Performance reports