23
PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto, PE; Manager, Transmission & Distribution Automation i-PCGRID, March 26-28, 2013

PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

PHI’s Distribution Automation Projects

Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto, PE; Manager, Transmission & Distribution Automation i-PCGRID, March 26-28, 2013

Page 2: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

2

Acknowledgement

"This material is based upon work supported by the Department of Energy under Award Numbers: DE-OE000300, DE-OE0000301, DE-OE0000204”

Disclaimer: "This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof.

The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof."

Page 3: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

3

Presentation Topics

Automation Technologies ASR Overview and Demonstration Estimated Impacts On Reliability Learnings from ASR pilot project and initial SGIG

projects. ASR implementation timeline Summary of Benefits Q&A

Page 4: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

4

About Pepco Holdings, Inc.

Approximately 2 million customers in Delaware, the District of Columbia, Maryland and New Jersey • Atlantic City Electric, Delmarva

Power and Pepco provide regulated electricity service – Delmarva Power also provides

natural gas service • Pepco Energy Services is a

non-regulated subsidiary that provides energy efficiency and renewable energy services

Regulated transmission and distribution is PHI’s core business

Page 5: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

5

Pepco Holdings, Inc. Quick Facts

Incorporated in 2002 Service territory:

8,340 square miles Customers served

• Atlantic City Electric: – 545,000 – electric

• Delmarva Power: – 503,000 – electric – 125,000 – natural gas

• Pepco: – 793,000 – electric

Total Population Served: 5.6 million

Page 6: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

6

PHI SGIG Awards Summary

Company/Regions AMI DLC DA CI Total

Project Costs

DOE Funding

Pepco Maryland $137.7 $51.4 $15.0 $ 5.5 $209.6 $104.8

Pepco DC $ 68.2 $ 7.1 $ 9.1 $ 4.8 $ 89.2 $ 44.6

ACE NA $13.4 $17.0 $ 7.0 $ 37.4 $ 18.7

Smart Grid Workforce Training

Grant NA NA NA NA NA $ 4.4

Total $205.9 $71.9 $41.1 $17.3 $336.2 $173.5

PJM Syncrophasor $ 1.4 $ 0.7

•$ Are in millions

Page 7: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

7

5 evolutionary steps to achieving the Smart Grid Smart Grid Investment Grant (SGIG) funding accelerated this process

Page 8: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

8

Smart Grid Devices and Technologies

Page 9: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

9

PHI’s Smart Grid Domains and Integrated Communications Infrastructure

Page 10: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

10

Distribution Automation (DA) Project Types

Automatic Sectionalizing & Restoration (ASR) Schemes • DA ASR entails the installation of certain devices that are intended to work together to

identify distribution feeder faults, automatically isolate identified faulted area, and reroute electricity supply to segments of the outage feeder un-impacted by the fault. This will to reduce the number and length of electric system outages, resulting in increased reliability and customer satisfaction.

Dissolved Gas Analysis (DGA) monitors on substation transformers • This on-line system will continuously monitor eight critical fault gases and other

transformer insulating oil key parameters for a timely assessment of transformer conditions to schedule maintenance and help prevent failures.

URD Fault Detectors System –FDS (Pepco MD) • This system will identify the location of faulted URD transformers by conveying a signal

back to the control center in order to reduce time spent by crews in locating faults. Network Transformer Protector Remote Monitoring System - RMS

(Pepco DC) • This system will provide real time remote control/monitoring capability as well as power

quality information such as phase currents, transformer loading, power factor, etc. to network transformers through implementation of two way communication and installation of intelligent sensors for an enhanced reliability of the network system.

Capacitor Bank Automation • This project will add feeder capacitors that have supervisory controlled capability and

visibility. This will allow remote control of feeder reactive power (VAr) and resolution of high/low voltage issues.

Page 11: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

11

ASR Overview – Building Blocks

Page 12: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

12

PHI’s ASR System

Protects customers from sustained outages caused by feeder lock-outs

Segments feeders into 2, 3, or 4 sections using closed remote controlled SF6 switches or Automatic Circuit Reclosers (ACR’s) in the field

For an fault in any one section, ASR opens closed switches to isolate the section

ASR restores the other sections by reclosing the feeder breaker and/or closing open tie switches to other feeders

Generally ASR operates in less than a minute

Page 13: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

13

PHI’s ASR System, Continued.

ASR Program runs on a hardened PC in the substation Communicates with substation breakers, field switches, and

field ACR’s – receives field intelligence and sends commands through packet radio network

When the breaker opens, the ASR Program automatically reviews field intelligence and sends commands to restore as many customers as possible

Communicates with other substations to use their feeders to restore load, if necessary

Uses pre-fault loads to insure that switching won’t cause overloads

Tells the Distribution System Operators the configuration changes that it commanded

Page 14: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

14

PHI’s ASR System - Demonstration

Substation

Fault Occurs on Feeder 001

Feeder 001 Locks out

1008 Customers out

ASR verifies switch status and fault location

Open Switch

Open Switch

Close Switch

270 Customers out

Total Time: 51 Seconds

Close Breaker

Page 15: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

15

Pilot Results – ASR Minimizes Outage Impact

Page 16: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

16

Outage Impact Reductions (DOE Scheme 1)

Page 17: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

17

Reliability Impacts: DOE Scheme 1

11,439

4,985 6,454

-

2,000

4,000

6,000

8,000

10,000

12,000

14,000

Sustained CI w/o operation of DAswitches

Sustained CI w/ operation of DAswitches

Sustained CIReduction

Change in Customer Interruptions (CI)

1,908,333

876,705 1,031,628

-

500,000

1,000,000

1,500,000

2,000,000

2,500,000

CMI w/o operation of DA switches CMI w/ operation of DA switchesCMI

Reduction

Change in Customer Minutes Interrupted (CMI)

Results from 11 successful operations.

These reductions resulted in a 24% improvement in feeder group SAIFI/SAIDI.

Page 18: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

18

DOE Scheme 1: Troubleshooting

Operation Category

Number Cause Correction Status

Completed operations

11 N/A N/A N/A

As designed non-ops

1 4 3 1

High Mag Fault Maintenance Out Disabled by CC Downed conductor

Condition removed None Process review None

Completed N/A Completed N/A

Other Non-Operations

6 3

Equipment Failure Telecom failure

Repair/replace Investigation

Completed Ongoing

Protection 2 1

Multi-fault/Coord False targets

Fault Study Alt. target algorithm

Ongoing Ongoing

Page 19: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

19

Some other Key Learnings

Continued maintenance is critical – can’t just set it and forget it! • Battery failure most common maintenance issue; added dual power

sources to the control. • Communication system needs to stay continuous; NOC plays a key

role. • ASR Model needs to stay up to date; stake holders identified and

trained. These issues, if not addressed, will diminish the potential

benefits of ASR by: • Reducing reliability improvement benefits by half+ • Reducing the confidence that control center and field personnel

have on the technology.

Page 20: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

20

ASR Commissioning Timeline:

First four schemes encompassing 41 feeders and 14 substations activated Total of 41 substations and 118 feeders under the SGIG program. An additional 30-50 feeders in the DPL service area between 2011-2014.

Page 21: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

21

Summary of DA/ASR expected benefits:

Distribution Automation will help PHI achieve its smart grid vision.

It will result in key benefits to customers and the company: • Improved feeder and system reliability increased

customer satisfaction • Increased visibility, control, and optimization of the

distribution system. • Operational savings from reduced field trips and

restoration times. • Increased knowledge of transformer health resulting in

better maintenance and asset end of life control.

Page 22: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

22

Next Steps for PHI

Continue to execute Smart Grid programs and realize Smart Grid vision

Continue to engage and educate customers to maximize benefits of smart grid implementation

Continue to support development of a secure grid by working with industry and federal consortiums to develop industry standards

Continue to encourage innovation in the marketplace through new capabilities of the smart grid, including renewable integration and electric vehicle grid infrastructure

Success will be measured in the eyes of the customer!

Page 23: PHI’s Distribution Automation Projects · 2016-01-20 · PHI’s Distribution Automation Projects Early Impacts On Reliability and Lessons Learned Presented by: Joseph M. LoPorto,

23

Questions