20
Phase 2 Phase 2 Overview Factsheet Spring 2013 Phase 2 Overview In February 2002, the EPA issued a Record of Decision (ROD) for the Hudson River PCBs Superfund site that calls for targeted environmental dredging of approximately 2.65 million cubic yards of PCB- contaminated sediment from a 40-mile section of the Upper Hudson River. PCBs, or polychlorinated biphenyls, are considered probable human carcinogens and are linked to other adverse health effects. The primary goal of the Hudson River PCBs cleanup is to protect people and the environment from unacceptable risks due to PCB- contaminated sediments in the Upper Hudson River. The cleanup of the Hudson River is occurring in two phases. Phase 1 of the project was conducted by General Electric Co (GE) with oversight by the EPA from May to November 2009. During this phase, approximately 283,000 cubic yards of PCB- contaminated sediment was removed from a six- mile stretch of the Upper Hudson River near Fort Edward, New York. After an extensive evaluation by an independent panel of scientists and input from a broad range of stakeholders, the EPA developed plans for the second part of the cleanup. Phase 2 is being conducted at full production to remove the remainder of the contaminated river sediment targeted for dredging. Phase 2, Year 1 was conducted from June to November 2011 along a one and one-half mile section of the Hudson River south of Ford Edward. Approximately 363,000 cubic yards of contaminated sediment were removed. In 2012 (Phase 2, Year 2), dredging continued south of the village of Fort Edward. The volume dredged exceeded original expectations; approximately 663,000 cubic yards of PCB-contaminated sediment were removed from a three-mile section of the Hudson River. The remainder of the cleanup is expected to take three to five more years to complete. River Section 1 River Section 2 River Section 3 Dewatering Facility Tomhannock Reservoir Saratoga Lake RN87 Fort Miller Dam Lock 6 Lock 5 Thompson Island Dam Former Fort Edward Dam Lock 4 Stillwater Dam Lock 8 Northumberland Dam Federal Dam at Troy Lock 7 Lock 3 Lock 1 Lock 2 7 2 1 4 3 6 5 8 9 11 12 15 14 13 10 Easton Argyle Pittstown Saratoga Stillwater Wilton Grafton Schaghticoke Brunswick Greenwich Halfmoon Cambridge Fort Edward Northumberland Colonie Troy Waterford Saratoga Springs Cohoes Watervliet Green Island Mechanicville SARATOGA COUNTY WASHINGTON COUNTY RENSSELAER COUNTY ALBANY COUNTY Map Index Phase 1 & 2 Dredging Areas Upper Hudson River 0 2 4 1 Miles New York Index Frame Hudson River Phase 1 Dredging Areas Phase 2 Dredging Areas Municipality Boundary Lock/Dam Upper Hudson River Sections

Phase 2 Phase 2 Overview Factsheet - US EPA · Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Phase 2 Phase 2 Overview Factsheet - US EPA · Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including

Phase 2Phase 2 OverviewFactsheetSpring 2013

Phase 2 OverviewIn February 2002, the EPA issued a Record of Decision (ROD) for the Hudson River PCBs Superfund site that calls for targeted environmental dredging of approximately 2.65 million cubic yards of PCB-contaminated sediment from a 40-mile section of the Upper Hudson River. PCBs, or polychlorinated biphenyls, are considered probable human carcinogens and are linked to other adverse health effects. The primary goal of the Hudson River PCBs cleanup is to protect people and the environment from unacceptable risks due to PCB-contaminated sediments in the Upper Hudson River.

The cleanup of the Hudson River is occurring in two phases. Phase 1 of the project was conducted by General Electric Co (GE) with oversight by the EPA from May to November 2009. During this phase, approximately 283,000 cubic yards of PCB-contaminated sediment was removed from a six-mile stretch of the Upper Hudson River near Fort Edward, New York. After an extensive evaluation by an independent panel of scientists and input from a broad range of stakeholders, the EPA developed plans for the second part of the cleanup. Phase 2 is being conducted at full production to remove the remainder of the contaminated river sediment targeted for dredging. Phase 2, Year 1 was conducted from June to November 2011 along a one and one-half mile section of the Hudson River south of Ford Edward. Approximately 363,000 cubic yards of contaminated sediment were removed.

In 2012 (Phase 2, Year 2), dredging continued south of the village of Fort Edward. The volume dredged exceeded original expectations; approximately 663,000 cubic yards of PCB-contaminated sediment were removed from a three-mile section of the Hudson River.

The remainder of the cleanup is expected to take three to five more years to complete.

Qu ee nsb uryGl ens Fa l ls

River Section 1

River Section 2

River Section 3

Dewatering Facility

Tomhannock Reservoir

Saratoga Lake

WARRENCOUNTY

WARRENCOUNTY

87 F o r t M i l l e r D a mL o c k 6

L o c k 5

T h o m p s o n I s l a n d D a m

F o r m e r F o r t E d w a r d D a m

L o c k 4 S t i l l w a t e r D a m

L o c k 8

N o r t h u m b e r l a n d D a m

F e d e r a l D a m a t T r o y

L o c k 7

L o c k 3

L o c k 1

L o c k 2

7

2

1

4

3

6

5

8

9

11

12

15

14

13

10

Ea s to n

Argy le

Pi t ts t ow n

More a u

Sa ra to ga

St i l lw at e r

Wi l to n

Gra f to n

Sc ha ght ic ok e

Bruns w ic k

Gre e nw ic h

Ha l fm oo n

Ca m br idge

For t Ed w ard

Nor t hum be r la nd

Colon ie

Tro y

Wa te r f ord

Sa ra to ga Sp r ings

Coho es

Qu ee ns bur y

Lak e Luz ern e

Wa te rv l iet

Po es t enk i l l

Gre e n Is la nd

Me ch an icv i l le

Gle ns Fa l ls

SARATOGACOUNTY

WASHINGTONCOUNTY

RENSSELAERCOUNTY

ALBANYCOUNTY

WARRENCOUNTY

Map IndexPhase 1 & 2 Dredging Areas

Upper Hudson River

0 2 41Miles

New York

Index FrameHudson River

Phase 1 Dredging Areas

Phase 2 Dredging Areas

Municipality Boundary

Lock/DamUpper Hudson River Sections

Page 2: Phase 2 Phase 2 Overview Factsheet - US EPA · Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including

2

Where will the dredging be done?The ROD covers three sections of the Upper Hudson River: River Section 1 (from the former Fort Edward Dam to the Thompson Island Dam); River Section 2 (from the Thompson Island Dam to the Northumberland Dam); and River Section 3 (from the Northumberland Dam to the Federal Dam at Troy). Within the River Sections (see Map Index on page 4), dredging is conducted in areas of approximately five acres each, called “certification units” (CUs).

Phase 1 dredging was conducted in portions of River Section 1. Phase 2 dredging began with the areas that were not completed in Phase 1 and will continue downstream through River Sections 2 and 3.

In 2011, dredging took place in CUs 9 – 16 and 19 – 25 (see Map 1). In 2012, dredging occurred in CUs 26 – 48 (See Map 1 & 2).

During the initial years of the project, the areas targeted for dredging were close together and generally extended from shoreline to shoreline. In future years, as the project continues to move southward toward Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including those near dams, shallow areas behind islands and the landlocked section of river located between the Thompson Island Dam and Fort Miller Dam.

In 2013, dredging operations will resume around Griffin Island (CU 49) and will continue south to the Thompson Island Dam (CU 60), completing dredging in River Section 1. Additional dredging is expected to occur in sections of river near the towns of Northumberland and Schuylerville, New York (CUs 67-78).

How were the dredge areas selected?The dredge areas were identified using the results of a multi-year sediment sampling program conducted by GE that began in 2002 and generated more than 50,000 sediment samples taken from the bottom of the Upper Hudson River. The sampling data allowed the EPA and GE to determine the distribution of the PCBs in the sediment, refine estimates of the amount of PCBs in the sediment, and establish river sediment characteristics (e.g., silt, sand, gravel). Phase 2 of the project was designed using the Phase 2 Dredge Area Delineation report (including the Phase 2 Intermediate and Final Design reports) and knowledge gained during Phase 1. In addition, before the start of the 2011 dredge season, 3,900 additional samples were taken from the river bottom in River Section 1 to more accurately determine the depth and location of PCBs. Some additional sediment sampling will occur in River Sections 2 and 3 as the project continues. Various project design reports are available on the project Web site at www.epa.gov/hudson.

How is PCB-contaminated sediment removed, processed and disposed of? Mechanical dredges are used to remove sediment from the river bottom. Dredges mounted on deck barges use environmental clamshell buckets to place dredged sediments into barges. Tugboats then push the filled barges to a dewatering and sediment-processing facility located on the Champlain Canal in Fort Edward, New York. Once there, the most contaminated sediment is processed first. Debris is removed and sediment is mechanically dewatered; the water is treated on-site before being returned to the Champlain Canal. The dewatered sediment and debris are loaded

Data and operations are constantly evaluated to ensure that the momentum of cleanup work in the river continues and that the biggest sources of ongoing contamination are addressed. After an extensive review of the first phase of dredging in 2010, the EPA modified a number of requirements for dredging. These refinements include:

• Improved sampling: Improved sampling methods provide more complete information on the extent of contamination in the targeted dredge areas.

• Improved dredge design and fewer dredge passes: By dredging deeper than the expect depth of contamination, fewer bucket bites or dredge “passes” are needed to remove PCBs. These refinements account for the high degree of variability in the sediment layer and help to minimize sediment re-deposition.

• Less capping: Capping is limited to 11% of the dredged area, excluding areas that must be capped due to considerations such as encountering bedrock. In some locations capping of the river sediments is necessary to isolate small amounts of PCBs remaining after dredging.

Page 3: Phase 2 Phase 2 Overview Factsheet - US EPA · Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including

3

onto railcars for transport to a PCB-approved landfill. Dredging and processing operations are continually monitored and evaluated to determine if changes are needed to improve operations. Prior to the 2012 season, improvements were made at the processing facility to support operations and increase productivity (see Figure 1).

Performance StandardsThe performance standards were designed to ensure dredging operations are done safely and public health is protected. Three engineering performance standards were created to protect water intakes and the environment: resuspension (transport of PCBs down river); residuals (PCBs left behind); and productivity (complete the project efficiently). Five quality of life performance standards were developed (air quality, noise, lighting, odor, and navigation) for the purpose of minimizing the effects of dredging on people, businesses, and communities. These standards are re-evaluated and may be adjusted,

as needed, as dredging operations move from the uppermost portions of the river into areas much further downstream.

In-River MonitoringThe Federal Safe Drinking Water Act standard of 500 parts per trillion (ppt) is used as the resuspension standard for the project. Compliance with this standard is monitored through an extensive river quality monitoring program at upstream, near-field (within 300 meters downstream of dredging), mid-field (approximately 1-2 miles downstream), and at far-field (greater than 2 miles downstream) locations. When resuspension or other performance standards are not met, GE will be required to conduct evaluations and adjust dredging operations. Air monitoring also occurs 24/7 during dredging operations. For quality of life issues such as odor, noise, or lighting, monitoring will occur regularly, as well as in response to complaints; and GE will be required to take action to address the issue.

Performance standard monitoring data is available on the EPA’s Hudson Dredging Data web site: www.hudsondredgingdata.com

Figure 1: Prior to the 2012 season, improvements were made at the Processing Facility which included expansion of the coarse material staging area and construction of a second barge unloading station, additional size separation equipment, and a second gravity thickener.

Page 4: Phase 2 Phase 2 Overview Factsheet - US EPA · Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including

4

Queensbury

River Section 1

River Section 2

Dewatering Facility

River Section 3

Ca mb ridg e

Sa ra toga Sp ring s

Colo nie

WARRENCOUNTY

87 F o r t M i l l e r D a mL o c k 6

L o c k 5

T h o m p s o n I s l a n d D a m

F o r m e r F o r t E d w a r d D a m

L o c k 4 S t i l l w a t e r D a m

L o c k 8

N o r t h u m b e r l a n d D a m

F e d e r a l D a m a t T r o y

L o c k 7

L o c k 3

L o c k 1

L o c k 2

Ea s to n

Ar gyle

Pi t ts to wn

Mo re au

Sa ra toga

St i l lw ate r

Wi l to n

Gra f to n

Sc ha ght ic oke

Br uns wick

Gre en wic h

Ha l fm oo n

Fort Edw ar d

Nor thum ber la nd

Tr oy

Wate rfor d

Coh oes

Ma l ta

Ja ck son

Wate rv l iet

Po es tenk i l l

Gre en Is la nd

Me c han icv i l le

SARATOGACOUNTY

WASHINGTONCOUNTY

RENSSELAERCOUNTY

ALBANYCOUNTY

7

2

1

4

3

6

5

8

9

11

12

15

14

13

10

0 2 41Miles

LEGENDIndex Frame

Hudson RiverPhase 1 Dredging AreasPhase 2 Dredging AreasMunicipality Boundary

Lock/DamUpper Hudson River Sections

Page 5: Phase 2 Phase 2 Overview Factsheet - US EPA · Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including

5

Page 6: Phase 2 Phase 2 Overview Factsheet - US EPA · Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including

6

Page 7: Phase 2 Phase 2 Overview Factsheet - US EPA · Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including

7

Page 8: Phase 2 Phase 2 Overview Factsheet - US EPA · Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including

8

Page 9: Phase 2 Phase 2 Overview Factsheet - US EPA · Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including

9

Page 10: Phase 2 Phase 2 Overview Factsheet - US EPA · Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including

10

Page 11: Phase 2 Phase 2 Overview Factsheet - US EPA · Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including

11

Page 12: Phase 2 Phase 2 Overview Factsheet - US EPA · Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including

12

Page 13: Phase 2 Phase 2 Overview Factsheet - US EPA · Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including

13

Page 14: Phase 2 Phase 2 Overview Factsheet - US EPA · Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including

14

Page 15: Phase 2 Phase 2 Overview Factsheet - US EPA · Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including

15

Page 16: Phase 2 Phase 2 Overview Factsheet - US EPA · Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including

16

Page 17: Phase 2 Phase 2 Overview Factsheet - US EPA · Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including

17

Page 18: Phase 2 Phase 2 Overview Factsheet - US EPA · Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including

18

Page 19: Phase 2 Phase 2 Overview Factsheet - US EPA · Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including

19

Page 20: Phase 2 Phase 2 Overview Factsheet - US EPA · Troy, the dredging areas will be further apart. Several areas will also need to be dredged that are logistically challenging, including

20

For More Information The EPA will continue the public outreach program for this project. The program includes maintaining the Hudson River Field Office, providing project information and meeting with riverfront residents living near the dredging areas. Visit*, call toll-free, or write to the Hudson River Field Office at the address below for more information.

EPA Contacts:Larisa Romanowski, Community Involvement CoordinatorHudson River Field Office421 Lower Main StreetHudson Falls, NY 12839(518) 747-4389 or (866) 615-6490 [email protected]

Gary Klawinski, Remedial Project ManagerHudson River Field Office421 Lower Main StreetHudson Falls, NY 12839(518) 747-4389 or (866) 615-6490 [email protected]

*The Field Office hours are Monday - Friday, 8:00 am - 4:30 pm, with evening hours by appointment.

EPA Regional Public LiaisonEPA Region 2 has designated a public liaison as a point-of-contact for community concerns and questions about the federal Superfund program in New York, New Jersey, Puerto Rico, and the U.S. Virgin Is-lands. To support this effort, the Agency has established a 24-hour, toll-free number that the public can call to request information, express concerns, or register complaints about Superfund. The public liaison for EPA’s Region 2 office is: George H. Zachos, U.S. EPA, Region 2, 2890 Woodbridge Avenue MS-211, Edison, New Jersey 08837, (732) 321-6621, Toll-free (888) 283-7626.