Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Organisational Response to Major Investigations Peter Connelly
Deputy Secretary, Organisational Performance and Operations 10 November 2016
Department of Justice
Our context Creating a single Department of Justice
• Department of Justice established after various machinery of government changes.
• Formerly separate agencies brought together.
• Back office systems being consolidated - 7 ERP systems.
• 16/17 Budget $6.8 bil • 14,000 FTE
Organisational Responses to Major Investigations 2
Attorney General’s
Corrective Services
Juvenile Justice
MPES
OLGR/ ILGA
Arts NSW
Justice corporate functions
2011 2015
Department of Justice 3 Organisational Responses to Major Investigations
Department of Justice
Fatima Hammoud
Shadi Chacra (Saff Projects/Triton)
Anthony Andjic
Key characters
4 $1.3m
Hunter Courthouse
Gunnedah Courthouse
Tamworth Courthouse
Organisational Responses to Major Investigations
Fay Rouze a.k.a. Fayrouz
Hammoud/ Chacra
Department of Justice
Operation “Yancey”
5
The Public Inquiry
Organisational Responses to Major Investigations
Department of Justice
Operation “Yancey”
6 Organisational Responses to Major Investigations
Department of Justice
Operation “Yancey”
7
The Public Inquiry
Organisational Responses to Major Investigations
Department of Justice
Operation “Yancey”
8
The Public Inquiry
Organisational Responses to Major Investigations
Department of Justice
Time line Illustrative dates
Organisational Responses to Major Investigations 9
2012 2014 2015 2013
Note: ICAC is yet to release the final report on Operation Yancey
Projects managed by Andjic (December 2012 – September 2013)
Andjic Resignation (9 October 2014)
Hammoud Resignation
(17 March 2014) Initial Public
Works Review (September 2013)
First ICAC Notification
(31 October 2013)
Second ICAC Notification
(25 March 2014)
ICAC Inquiry (June-July
2015)
Andjic Suspended (7 March 2014)
Yancey Steering Committee
(6 November 2014)
ICAC Activity
Suspension
Resignation
Improvement Action
Public Works and PwC Reviews (November 2014 –
May 2015)
Key
2016
Dawson Review (March 2015 – September 2015)
Department of Justice
Operation “Yancey” Prior to the commencement of the Public Inquiry
External agency referrals • Referral to ICAC and liaison regarding scope of investigations. • Referral to NSW Police Force and Auditor-General of NSW. • Respond to ICAC’s requests for information.
Initial investigations and assessments • NSW Public Works engaged to conduct an initial review of the processes and
governance arrangements. • External investigator conducts preliminary investigation of allegations. • Concerns identified in relation to
• Breach of Departmental policy and procedures • Failure to maintain appropriate records • Failure to minimise risk profile for the Department.
10 Organisational Responses to Major Investigations
Department of Justice
Immediate tasks Internal taskforce to manage investigations and responses • Taskforce, chaired by the Secretary, established • Asset Management Services, Strategic HR, Office of the General Counsel,
and Organisational Performance and Operations Division. • Provide oversight management of allegations of corrupt conduct • Develop strategy for mitigating risk relating to fraud and unethical practices • Coordinated external investigations.
Initial tasks • Established a secure room in a restricted area • Preservation of evidence (copy drives and email accounts) • Secure all hard/ soft copy files • Data retention strategy • Defining the review population • Develop a risk profile matrix to inform further investigation and sampling • Review of files (sample basis)
Organisational Responses to Major Investigations 11
Department of Justice
How extensive was the problem? How do we know?
Organisational Responses to Major Investigations 12
A = Known matters referred to ICAC
B = Known matters being internally investigated
D = No File, Known Officers (Known unknowns)
C = Other files assessed (sample based) (Potentially known)
E = No File, Officers unknown (Unknown unknowns)
Examine all projects between January 2011 – December 2012 (number ~ 430)
Department of Justice
Assessing other projects NSW Public Works undertook a further assessment
Develop a sampling/verification approach to include: • Compliance with policy and procedures • Procurement selection process
• Tender Selection • Tendering Procedures • Delegations and approvals
• Extensions and variations • Completion of works (to specification) • Value of works undertaken • Matching with approvals – scope and expenditure • Compliance with contract terms • Value for money
Organisational Responses to Major Investigations 13
Department of Justice
Due diligence Forensic accountants
Fraud focussed data analysis/ risk profiling (via internal audit partner):
• Payment profiling by vendor / project
• Analytics eg payments within delegations, duplicate payments
• Data mining across population, eg, suppliers, contractors, ABN, GST details
• Review of prior audit and investigation reports
Organisational Responses to Major Investigations 14
Department of Justice
How did we respond to the challenges 1. Addressing the ICAC information requests/ inquiry
2. Developing Governance processes
3. Preparing a 20 Point plan • Ethical Behaviour
• Enterprise risk
• Fraud Control
• Financial and procurement delegations
• Consolidation of corporate functions
• Asset Management Service Review
4. Providing support to staff
5. Developing a communication strategy
Organisational Responses to Major Investigations 15
Department of Justice
Developing organisational resilience 20-Point Plan
Organisational Responses to Major Investigations 16
Issue Actions
Department-wide Initiative
1. Fraud Control
Remediation Process
• A Department-wide Fraud Control Remediation Process was
approved January 2015.
• A Fraud Control Steering Group to oversee the Fraud Control
Remediation Process.
• A fraud risk questionnaire distributed to all Division heads, to assess
‘as is’ state of Fraud Control within the Department.
2. Fraud Control Policy • A ‘Secretary’s Directive’ on Fraud Control released.
• Re-issued the Fraud Control Policy reminding all staff of their
responsibilities under the Department of Justice Fraud Control
Policy (which was originally released in June 2013).
Department of Justice
Developing organisational resilience 20-Point Plan
Organisational Responses to Major Investigations 17
Issue Action
3. Behaving Ethically
• Implemented Behaving Ethically guidelines issued by PSC.
• A new code of conduct and relevant policies developed and
implemented
• Education strategy promote awareness of new and existing staff.
4. Enterprise Risk
Framework
• An Enterprise Risk Framework developed
• Senior Executives nominated as ‘risk champions’
• Enterprise risk champions developing risk mitigation plans for each
enterprise risk.
5. Delegations • Financial and Procurement Delegations reviewed
• Single, consolidated delegations instrument for whole department
Department of Justice
Developing organisational resilience 20-Point Plan
Organisational Responses to Major Investigations 18
Issue Actions
6. Procurement • Review to standardise procurement processes.
• Provision of training to staff on procurement processes.
7. Governance
Framework
• A framework for the Department developed.
8. Development of
consolidated corporate
service functions
• Restructure of DJ consolidated key corporate service functions.
• Consolidation and standardisation of corporate policies and systems
• Improve the control environment across the department.
9. Internal Audit and Risk
• Single Audit and Risk function established.
• Regular fraud risk reporting to Audit and Risk Committee and
Executive.
Department of Justice
Developing organisational resilience 20-Point Plan
Organisational Responses to Major Investigations 19
Issue Actions
10. Legislative Policy and Compliance
• Compliance with legislative and policy requirements part of the Internal Audit Program.
11. Single Enterprise Resource Planning System
• SAP as a service – is being rolled out • Reducing 7 ERP systems to a target state of 1 ERP. • Significantly improve the control environment.
12. ICT Infrastructure • ICT CORE program is establishing common platforms for key business systems eg email, electronic records management.
• Improve the control environment.
13. Enterprise-wide Business Analytics and Reporting System
• Enterprise-wide business analytics and reporting system to be integrated with the new SAP system.
• Management and Project reporting at Departmental and Divisional/branch level.
• Improve the control environment
Department of Justice
Developing organisational resilience 20-Point Plan
Organisational Responses to Major Investigations 20
Issue Actions
Asset Management Services Initiatives
14. Governance and
Structure
• Review governance and structure of Asset Management Branch.
• Recruitment action underway, consistent with Government Sector
Employment Act.
15. Project Governance
strengthened in AMS
• Project Governance oversight group involving relevant senior
executives to review all projects.
• Improve the control environment.
16. Delegations • Revised delegations relating to Asset Management instituted.
• Delegations removed from junior staff with accountability at an
executive level.
• Improve the control environment.
Department of Justice
Developing organisational resilience 20-Point Plan
Organisational Responses to Major Investigations 21
Issue Actions
17. Review of Capital Procurement Compliance
• A review of compliance with NSW Government Capital/Construction
Procurement requirements was undertaken
18. Processes and Systems
• Institute project and contract management processes compliant with
Construction Procurement/ PFAA requirements.
• Improve the control environment.
19. Review of Accounting Practices
• Review of financial records over the period 2011-14 to identify any
aberrant accounting practices.
20. Planning and Environment Compliance Review
• Review compliance with Planning and Environment legislation and
related requirements.
Department of Justice
Operation “Yancey” After announcement of the Public Inquiry
Public Inquiry Public inquiry announced 12 June 2015 under section 31 of the Independent Commission Against Corruption Act 1988. Action • Briefing of legal representatives • Preparation of witness statements • Issue of media statements and management of media enquiries • Internal staff briefings, advice and assistance in relation to:
o What to do if summoned to the ICAC; o Access to legal representation; and o Access to the Employee Assistance Program.
22 Organisational Responses to Major Investigations
Department of Justice
Operation “Yancey” 7 Lessons 1. Tone from the top: Strong leadership to signify the identified issues were
being taken seriously. 2. Multi-faceted approach: Rapidly mobilising an integrated response –
addressing the immediate issues, undertaking due diligence, independent expert reviews, responding to investigations, supporting staff, legal advice.
3. Open book approach: Work openly with investigators and legal teams. 4. Maintaining business as usual: Instituting new expectations, processes
and systems while continuing to deliver services. 5. Creating a corruption resistant culture: Visibility to prevention and
detection of fraud, procurement processes and record keeping; staff ‘town halls’ to reinforce expectations and departmental Values
6. Investment in systems: Creating common policies, processes and systems (ERP, email, EDRMS).
7. Creating the future structure: Developing new structure and recruiting executive and staff positions. 23 Organisational Responses to Major Investigations
Organisational Response to Major Investigations� Our context Slide Number 3Key charactersOperation “Yancey”Operation “Yancey”Operation “Yancey”Operation “Yancey”Time line Operation “Yancey”Immediate tasksHow extensive was the problem?Assessing other projectsDue diligenceHow did we respond to the challengesDeveloping organisational resilienceDeveloping organisational resilienceDeveloping organisational resilienceDeveloping organisational resilienceDeveloping organisational resilienceDeveloping organisational resilienceOperation “Yancey”Operation “Yancey”