Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Kangaroo Resources Limited
ABN: 38 120 284 040
ASX Code: KRL
Perth Office
Suite B, 150 Hay Street
Subiaco
Western Australia, 6008
Telephone +61 8 6102 6990
Facsimile +61 8 6102 6993
Jakarta Office
Graha Irama Building 12th Floor
Jl. HR Rasuna Said Blok X-1
Kav.1&2
Jakarta Selatan 12950, Indonesia
Telephone +62 21 526 9868
Facsimile +62 21 526 9866
30 July 2013
JUNE 2013 QUARTERLY ACTIVITIES REPORT
HIGHLIGHTS COAL PROJECTS – INDONESIA
Mamahak Coal Project:
Production at MCM remains suspended pending identification of additional
mineable reserves, construction of new road and port and improvement in
market conditions.
MCM coal sales of 61,758 tonnes, reduction in coal stockpile inventory down to
71,940 tonnes.
Exploration Program now commenced at MEL. MEL is the second concession out
of the four Mamahak mining concessions.
159 Drill holes completed totalling 7,389m of exploration drilling completed at
primarily at MCM and a small proportion at MEL.
Pakar Coal Project:
Continuation of the regulatory process required to obtain Government sign-off for
the transfer of outstanding equity in the Pakar Project to the remaining 4
concessions to be transferred to the Company.
Corporate:
Cash reserves of AU$3.825M at Quarter-end with US$10.5M due to be transferred
once the project equity component of the Pakar transaction is completed.
Legal Action has been commenced in the Supreme Court of Victoria against the
Company by former advisors, Chimaera and Empire, relating to an engagement
in 2010. The Company has engaged legal firm Clayton Utz to defend the case.
A Freezing Order against Kangaroo which was issued in April 2012 has now been
discharged following a ruling by the Supreme Court of Western Australia on 26
June 2013.
MAMAHAK COAL PROJECT (four concessions MCM, BKL, MEL & MBE)
Mamahak project contains 4 individual mining concessions which are now located in
the newly formed Mahakam Hulu regency in East Kalimantan, Indonesia (formerly Kutai
Barat).
For
per
sona
l use
onl
y
2
Production at MCM remains suspended pending identification of additional mineable
reserves from MCM, MEL, MBE and BKL, construction of new road and port along with
improvements in the international coal market. A work program is in place to identify
additional coal reserves. Coal stockpiles will be sold down as soon as river levels allow
barging from the existing port location.
During the March 2013 Quarter mining operations were suspended at the Mamahak
Coal project in Indonesia. This decision was taken to enable the completion of an
operational review and also to await an improvement in international coal market
conditions.
During the June 2013 Quarter - the suspension was continued and no mining production
activity was carried out, however coal crushing and coal hauling activity was continued
to build up coal product stockpiles at the Long Hubung port area on the Mahakam
River.
The MCM mining agreement established in the March 2013 Quarter with mining
contractor PT Hero Krida Utama (HKU), under which Kangaroo will notify HKU three
months before the date it wishes to start the new mining contract is still in place. The
deadline for initiating mobilization is 30 September 2013.
During the June Quarter – Coal Barging re-commenced and a total of 61,758 tonnes
was barged to Balikpapan Coal Terminal utilising a 2 stage barging process. Barging
throughout the June 2013 Quarter was intermittent due to seasonal variations to the river
levels. Barging form Long Hubung port was eventually halted in June due to the onset of
a prolonged dry weather period which reduced river levels to below the minimum
required for barging.
All coal barged to Balikpapan Coal Terminal during the June 2013 Quarter has been sold
for export markets and revenues used to offset project debt. Coal Sales were all to
Bayan using a pro-rata index linked contract based on the Indonesian coal price index.
Site investigation & exploration activities were also continued and expanded during the
June 2013 Quarter. A total of 4 exploration drill rigs were in operation at MCM and MEL
for resource definition and exploration. In the September 2013 Quarter, the Company
will continue its exploration drilling programme to increase the coal resources & reserves
at Mamahak. During the June 2013 Quarter, a total of 159 boreholes were drilled for an
aggregate total of 7,389 linear metres. (drilling for MCM & MEL combined)
The MEL concession which covers an area of 5,000 hectares is within an area designated
for Production Forestry. A forestry usage permit known locally as “Pinjam Pakai” was
obtained for MEL on 30 October 2012 for a total area of 1,516 Hectares which covers the
Western and Eastern areas of the MEL concession area. The remaining Central area of
the MEL concession area is still pending submission of a revised forestry usage permit
application, due to the existence of a former forestry logging licence held by others.
During the June 2013 Quarter, physical access was established to the Western “Pinjam
Pakai” area and 1 drilling rig was able to commence initial exploration drilling on 16 June
2013. A total of 6 holes equating to 297 linear metres of drilling were completed at MEL
concession area during the June 2013 Quarter.
For
per
sona
l use
onl
y
3
Access to MBE for exploration is subject to establishing a new road access. A forestry
usage permit for MBE is already in place since 6 March 2013 covering 1,420 Hectares of
the 5,000 Hectare mining concession. As with MEL, the approved area covers a Western
and an Eastern area only – the remaining Central area will require a further submission to
be made due to the existence of a former forestry logging permit held by others.
An application for forestry usage permit “Pinjam Pakai” for BKL is also being prepared by
the Company for submission. The “Pinjam Pakai” process requires the company to
obtain a number of other supporting documents and recommendation letters from
other government departments prior to submission of an application.
The Company’s focus at Mamahak for the remainder of 2013 will be in continuing
ongoing exploration in MCM & MEL concession areas and also in establishing new
vehicular access to the eastern areas of MEL and also to the easternmost MBE
concession to allow access for drilling rigs to commence exploration drilling.
The Company’s primary objective is to increase the current Mamahak Coal Resource
and provide the basis for the definition of a Coal Reserve to justify the additional capital
expenditure required to overcome the barging issues caused by the seasonal river level
variations at the current Long Hubung port location.
PAKAR COAL PROJECT
Pakar project contains 9 individual coal mining concessions which are located in the
Kutai Kartanegara (Kukar) regency in East Kalimantan, Indonesia.
Pakar North has 3 projects (TA, TJ and DE) while Pakar South has 6 projects (OM, SA, CA,
BS, AU, SK). There is also one other asset-holding company associated with the 9 Pakar
mining concessions (SAU).
The Company has previously announced the execution of direct foreign ownership of
five separate concessions and one asset-holding company at the Pakar Project. These
are TJ and DE from Pakar North, OM, SA and SK from Pakar South and the separate asset
company SAU.
The remaining 4 projects (TA, AU, BS and CA) are now in the process of legal hand over
between BAYAN and the Company. Previous legal issues which prevented these
projects from being transferred from the original vendors to BAYAN have now been
resolved and (as of the date of this update) the 4 projects are in the hands of BAYAN
who have now commenced the various legal processes necessary to have these
transferred to the Company.
The Pakar Coal Project is a cornerstone asset in the Company’s Indonesian coal
production strategy, and the transfer of outstanding equity for direct ownership will
secure the Company’s exposure to future cash flows to be generated by the Project,
complementing its existing portfolio of thermal and coking coal projects in Indonesia.
A new exploration strategy and individual exploration programs for each concession are
being prepared along with budget estimates in readiness for access to the Pakar areas.
For
per
sona
l use
onl
y
4
In addition, the Company is continuing the preparation of feasibility studies and
environmental impact studies (based on site investigation data obtained previously) to
submit to the regulatory authority to convert all the Pakar concessions from exploration
status to exploitation status.
The Company must also wait on receipt of several forestry usage permits, “Pinjam
Pakai”, before any on-site works can proceed at the Pakar Project concessions.
Pakar Infrastructure (SAU)
BAYAN currently has two coal mining concessions in production adjoining the northern
boundary of the Company’s Pakar (North) concessions. BAYAN is currently barging coal
from these concessions to the Gunung Sari port to the west on the Belayan River. BAYAN
is planning to construct a new road from these concessions to a new port location on
the larger capacity Kedang Kepala River to enable a major expansion in production
capacity from these mines.
Discussions were held with Bayan during the June 2013 Quarter to enable the
Company’s Pakar projects to also access the proposed new haul road, conveyor and
barge loading facilities once constructed. These facilities will connect all 9 Pakar coal
projects to a new large scale port area on the Senyiur River.
BAYAN and the Company have identified an opportunity to utilise some currently
unused SAU infrastructure, including haul roads, buildings and land in the establishment
of the proposed new Infrastructure.
Such an arrangement would enable the Company to:-
recover capital cost already expended on infrastructure that will not be utilised in
the immediate future
progressively develop and exploit the Pakar concessions and get coal to market
without any major upfront capital expenditure thereby giving a significant
advantage to improve economic outcomes for the Company.
Further discussion between the Company and BAYAN will continue in the September
2013 Quarter to establish a cooperation framework and commercial agreements under
which cooperation can be formalized for the long term benefit of both parties.
GRAHA PANCA KARSA COAL PROJECT (GPK)
GPK is located near Long Hiram, in the Kutai Barat regency, East Kalimantan, Indonesia.
During the June 2013 Quarter, the Company continued to progress the “Pinjam Pakai”
permitting process required to enable it to carry out further exploration activities at the
GPK Project. The Company is required to secure the necessary forestry usage permits
which will enable additional confirmation exploration to be carried out prior to the
selection of a mining contractor and award of a mining contract. In-principle approval
has been given, however activity cannot be commenced until the formal permit
documentation has been issued.
For
per
sona
l use
onl
y
5
The Company remains firmly committed to the development of the GPK project but, in
light of current coal markets, the Company is currently evaluating the timing of the
development of this project.
To enhance tenure, the Company is also continuing the legal process of acquiring direct
foreign ownership of the GPK asset by converting GPK into an Indonesian PMA company
(a foreign investment company) and transferring approximately 84.82 per cent of the
shares in GPK directly to the Company.
Under the terms on an existing commercial agreement with KAL Energy dating back to
April 2010, upon receipt of the shares in GPK, the Company will issue approximately 8 per
cent of its shares in GPK to KAL Energy leaving its total direct ownership at 76.82 per
cent.
MT RUBY PROJECT
Mt Ruby tenement lies approximately 90km SW of Cairns and is around 120km from the
Mourilyan Bulk Loading Terminal at Innisfail, in Queensland.
An application to renew the Mt Ruby tenement was submitted in the March 2013
Quarter. The tenement is held by a subsidiary KML. The Company has applied for an
extension of the exploration permit and is awaiting formal documentation being
processed.
Further discussions were held in the June 2013 Quarter with other tenement lease holders
in the area of Mt Ruby with a view to assessing joint development opportunities.
The Company is currently arranging for the engagement of an independent Geological
consultant to review existing data and conduct an appraisal of the tenement to assist
the Board of Directors in reviewing development options and determining the best
strategy.
CORPORATE
During the June 2013 Quarter three Board Directors resigned and were replaced by
three new Directors on 1 May 2013. These changes were ratified at the Company’s AGM
held in Perth on 31 May 2013. The Company also relocated the Perth Head Office to 14
Emerald Terrace in West Perth and engaged 2 new individuals as joint Company
Secretary.
During the June 2013 Quarter, the Company continued to monitor the Supreme Court of
Western Australia proceedings initiated by a subsidiary of WEC (BCBC Singapore Pte Ltd)
against BAYAN for freezing orders. Freezing orders against BAYAN and the Company
were made by the Court on 5 April 2012. The Company had only been joined as a third
party to these proceedings to enable the freezing orders against BAYAN to be made.
The freezing orders made against the Company were discharged following an order by
the Supreme Court of Western Australia judgment which was delivered on 26 June 2013.
The Court held that this was not a case in which the Court should have made a freezing
order against a third party, such as the Company. The Company received its costs of
this proceeding and has liberty to make an application to ask for an inquiry as to
damages that it has sustained by reason of the freezing orders being granted on 5 April
2012.
For
per
sona
l use
onl
y
6
During the June 2013 Quarter, legal action was commenced against the Company by
former advisors, Chimaera Capital Markets Pte Ltd and Empire Equity Limited in the
Supreme Court of Victoria. The proceedings relate to payment for an engagement
commenced on 17 November 2010 and terminated on 8 February 2011. The former
advisors are seeking relief in the quantum of AU$28 million plus Company shares &
warrants for services allegedly provided over the three month period. The Company has
engaged legal firm Clayton Utz to defend the case on its behalf.
Cash at bank at the end of the March Quarter was ~AU$3.825 million, with a total of up
to US$10.5 million due to be received once the complete project equity component of
the Pakar transaction has been finalised.
KEY OBJECTIVES FOR SEPTEMBER 2013 QUARTER
Commercial – Sale of remaining coal stockpiles at Mamahak
Exploration 1 - Monitor progress on existing exploration program at the 4 Mamahak
concessions, including increasing areas of existing forestry usage permits to widen
the overall exploration footprint.
Exploration 2 - Develop additional exploration programs, work plans and budgets for
Pakar Projects, along with a new confirmation drilling program for GPK.
Legal - Continue the regulatory process and obtain Government sign-off for the
transfer equity of the 4 outstanding Pakar projects to the Company.
Licensing & Permitting 1 - Continue the process of acquiring “Pinjam Pakai” for GPK
and also of acquiring direct foreign ownership of the GPK Project.
Licensing & Permitting 2 - Commence “Pinjam Pakai” process for the Pakar projects.
Business Development 1 - Establish any necessary legal and commercial agreements
to enable the Company’s Pakar projects to enable access to and use of the new
haul road, conveyor and barge loading facility to be constructed by BAYAN.
Business Development 2 – Identify opportunity and optimal timing to bring GPK
concession into production.
Business Development 3 – Formalise a new business strategy and market the
Company as a long term Investment opportunity.
ENDS
For
per
sona
l use
onl
y
7
GLOSSARY
CORPORATE
Company – Kangaroo Resources Limited (ASX – KRL)
BAYAN – PT Bayan Resources Tbk
KML – Kangaroo Minerals Pty Limited
WEC – White Energy Company Limited (ASX – WEC)
PMA – Perusahaan Model Asing (local term used for a foreign investment company)
MAMAHAK
MCM – PT Mamahak Coal Mining
BKL – PT Bara Karsa Lestari
MEL – Mahakam Energi Lestari
MBE – Mahakam Bara Energi
Long Hubung – Current Port location on Mahakam River for MAMAHAK projects
PAKAR (NORTH)
TA – PT Tiwi Abadi (currently pending share transfer from BAYAN to KRL)
TJ – PT Tanur Jaya
DE – PT Dermaga Energi
PAKAR (SOUTH)
OM – PT Orkida Makmur
SA – PT Sumber Api
CA – PT Cahaya Alam (currently pending share transfer from BAYAN to KRL)
BS – PT Bara Sejati (currently pending share transfer from BAYAN to KRL)
AU – PT Apira Utama (currently pending share transfer from BAYAN to KRL)
SK – PT Silau Kencana
PAKAR (NORTH & SOUTH)
SAU – PT Sumber Aset Utama
Senyuir – Proposed port location on Kedang Kepala River for PAKAR projects
GRAHA PANCA
GPK – PT Graha Panca Karsa
Further information:
Ian Ogilvie
Managing Director
T | +61 8 9322 4994
W| www.kangarooresources.com
For
per
sona
l use
onl
y
8
DISCLAIMER: The information concerning production targets in this announcement are not intended to be forecasts. They
are internally generated goals set by the board of directors of Kangaroo Resources Limited. The ability of the company to
achieve these targets will be largely determined by the company’s ability to secure adequate funding, implement mining
plans, resolve logistical & permitting issues associated with mining and enter into off take arrangements with reputable third
parties.
It is common practice for a company to comment on and discuss its exploration in terms of target size and type. The
information above relating to the exploration target should not be misunderstood or misconstrued as an estimate of Mineral
Resources or Ore Reserves. Hence the terms Resource(s) or Reserve(s) have not been used in this context. The potential
quantity and grade is conceptual in nature, since there has been insufficient exploration to define a Mineral Resource. It is
uncertain if further exploration will result in the determination of a Mineral Resource.
ABOUT KANGAROO RESOURCES
Kangaroo Resources Limited (ASX: KRL) is an emerging international mining Company with a portfolio of 14* coal
projects in the East Kalimantan province of Indonesia and one Mineral exploration project in Queensland Australia
The Company’s Indonesian projects host significant thermal coal resources, some with coking coal properties, which
will see the Company emerge as a significant Indonesian coal producer.
The Company is committed to building a sustainable mid-tier mining house, focusing on Indonesian coal and using
the considerable experience and expertise of its exceptional in-country majority shareholder to enable it to fast
track development and production.
The Company’s strategy entails continuing to develop its resources and reserves and progressively build production
in the short term from within its current portfolio of 14* existing Indonesian projects.
* assumes successful transfer of the remaining 4 Pakar concessions
ABOUT BAYAN RESOURCES
Bayan Resources
PT. Bayan Resources Tbk is a leading Indonesian coal producer which has integrated coal mining, processing and
logistics operations. The Group is engaged in the business of surface open cut mining of thermal coal located
primarily in East and South Kalimantan.
Bayan has a total of 22 concessions which have a JORC certified reserves of 0.87 billion tonnes and JORC resources
of 4.10 billion tonnes. Coal production also includes other grades of coal which comprise of environmentally-
friendly, low sulfur, sub-bituminous coal and semi-soft coking coal. Having diverse coal quality, the Group is able to
blend its products to meet various customers’ specifications.
In addition, Bayan has access to cost effective and superior logistics with significant expansion possibility; ownership
of port loading infrastructure is a key strategy. The Group owns and operates port loading facilities such as the
Balikpapan Coal Terminal (BCT) which is one of the largest coal terminals in East Kalimantan with a handling
throughput capacity of 15.0 million tonnes per annum.
The BCT is able to blend from up to four stockpiles to desired specification and can fully load large scale Panamax
vessels. It also owns and operates two Floating Transfer Stations (KFT) which can accept up to Capesize vessels as
well as barge loading facilities in the various mine sites.
Bayan has the necessary resources, experience and expertise to help Kangaroo manage issues on the ground and
drive forward its Indonesian coal strategy
For
per
sona
l use
onl
y
9
Appendix 1: Project Location Map – East Kalimantan, Indonesia
For
per
sona
l use
onl
y
Appendix 5B
Mining exploration entity quarterly report
+ See chapter 19 for defined terms.
30/9/2001 Appendix 5B Page 1
Rule 5.3
Appendix 5B
Mining exploration entity quarterly report Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001, 01/06/10.
Name of entity
KANGAROO RESOURCES LIMITED
ABN Quarter ended (“current quarter”)
38 120 284 040 30 June 2013
Consolidated statement of cash flows
Cash flows related to operating activities
Current quarter $A’000
Year to date (6 months) $A’000
1.1 Receipts from product sales and related debtors
4,913 4,913
1.2 Payments for (a) exploration & evaluation
(b) development
(c) production
(d) administration
(130)
-
(3,897)
(1,101)
(212)
-
(9,467)
(1,568)
1.3 Dividends received - -
1.4 Interest and other items of a similar nature
received
31 64
1.5 Interest and other costs of finance paid - -
1.6 Income taxes paid - -
1.7 Other (provide details if material) - -
Net Operating Cash Flows
(184) (6,270)
Cash flows related to investing activities
1.8 Payment for purchases of:
(a) prospects
(b) tenement acquisition
(c) other fixed assets
(d) equity investments
-
-
(651)
-
-
-
(767)
-
1.9 Proceeds from sale of:
(a) prospects
(b) equity investments
(c) other fixed assets
-
-
14
-
-
14
1.10 Loans to other entities - -
1.11 Loans repaid by other entities - -
1.12 Other (provide details if material) - -
Net investing cash flows
(637) (753)
1.13 Total operating and investing cash flows
(carried forward)
(821) (7,023)
For
per
sona
l use
onl
y
Appendix 5B
Mining exploration entity quarterly report
+ See chapter 19 for defined terms.
Appendix 5B Page 2 30/9/2001
1.13 Total operating and investing cash flows
(brought forward)
(821) (7,023)
Cash flows related to financing activities
1.14 Proceeds from issues of shares, options, etc. - -
1.15 Proceeds from sale of forfeited shares - -
1.16 Proceeds from borrowings 5,373 11,582
1.17 Repayment of borrowings (4,913) (4,913)
1.18 Dividends paid - -
1.19 Other (provide details if material) - -
Net financing cash flows
460 6,669
Net increase (decrease) in cash held
(361)
(354)
1.20 Cash at beginning of quarter/year to date 3,820 3,855
1.21 Exchange rate adjustments to item 1.20 366 324
1.22 Cash at end of quarter 3,825 3,825
Payments to directors of the entity and associates of the directors
Payments to related entities of the entity and associates of the related entities Current quarter
$A'000
1.23
Aggregate amount of payments to the parties included in item 1.2
208
1.24
Aggregate amount of loans to the parties included in item 1.10
NIL
1.25
Explanation necessary for an understanding of the transactions
The amount above includes payments to Directors and their associated companies.
Non-cash financing and investing activities
2.1 Details of financing and investing transactions which have had a material effect on consolidated
assets and liabilities but did not involve cash flows
NIL
2.2 Details of outlays made by other entities to establish or increase their share in projects in which the
reporting entity has an interest
NIL
For
per
sona
l use
onl
y
Appendix 5B
Mining exploration entity quarterly report
+ See chapter 19 for defined terms.
30/9/2001 Appendix 5B Page 3
Financing facilities available Add notes as necessary for an understanding of the position.
Amount available
$A’000
Amount used
$A’000
3.1 Loan facilities
- -
3.2 Credit standby arrangements
- -
Estimated cash outflows for next quarter $A’000 4.1 Exploration and evaluation
200
4.2 Development
-
4.3 Production
3,000
4.4 Administration
500
Total
3,700
Reconciliation of cash
Reconciliation of cash at the end of the quarter (as
shown in the consolidated statement of cash flows) to
the related items in the accounts is as follows.
Current quarter $A’000
Previous quarter $A’000
5.1 Cash on hand and at bank 3,825 3,820
5.2 Deposits at call - -
5.3 Bank overdraft
-
-
5.4 Other (provide details)
-
-
Total: cash at end of quarter (item 1.22) 3,825 3,820
Changes in interests in mining tenements Tenement
reference
Nature of interest
(note (2))
Interest at
beginning
of quarter
Interest at
end of
quarter
6.1 Interests in mining
tenements relinquished,
reduced or lapsed
6.2 Interests in mining
tenements acquired or
increased
For
per
sona
l use
onl
y
Appendix 5B
Mining exploration entity quarterly report
+ See chapter 19 for defined terms.
Appendix 5B Page 4 30/9/2001
Issued and quoted securities at end of current quarter Description includes rate of interest and any redemption or conversion rights together with prices and dates.
Total number Number quoted Issue price per
security (see note
3) (cents)
Amount paid up per
security (see note 3)
(cents)
7.1 Preference +securities (description)
7.2 Changes during
quarter
(a) Increases
through issues
(b) Decreases
through returns
of capital, buy-
backs,
redemptions
7.3 +Ordinary
securities
3,434,430,012 3,434,430,012 Fully Paid Fully Paid
7.4 Changes during
quarter
(a) Increases
through issues
(b) Decreases
through returns
of capital, buy-
backs
7.5 +Convertible
debt securities
(description)
7.6 Changes during
quarter
(a) Increases
through issues
(b) Decreases
through
securities
matured,
converted
7.7 Options (description and
conversion
factor)
128,103,448
-
Exercise Price
$0.133
Expiry Date
29 June 2015
7.8 Issued during
quarter
7.9 Exercised during
quarter
7.10 Expired during
quarter
7.11 Debentures (totals only)
7.12 Unsecured
notes (totals
only)
For
per
sona
l use
onl
y
Appendix 5B
Mining exploration entity quarterly report
+ See chapter 19 for defined terms.
30/9/2001 Appendix 5B Page 5
Compliance statement
1 This statement has been prepared under accounting policies which comply with
accounting standards as defined in the Corporations Act or other standards acceptable
to ASX (see note 4).
2 This statement does give a true and fair view of the matters disclosed.
Sign here: ............................................................ Date: 30 July 2013
Company secretary
Print name: Michael Loh
Notes
1 The quarterly report provides a basis for informing the market how the entity’s
activities have been financed for the past quarter and the effect on its cash position.
An entity wanting to disclose additional information is encouraged to do so, in a note
or notes attached to this report.
2 The “Nature of interest” (items 6.1 and 6.2) includes options in respect of interests in
mining tenements acquired, exercised or lapsed during the reporting period. If the
entity is involved in a joint venture agreement and there are conditions precedent
which will change its percentage interest in a mining tenement, it should disclose the
change of percentage interest and conditions precedent in the list required for items
6.1 and 6.2.
3 Issued and quoted securities The issue price and amount paid up is not required in
items 7.1 and 7.3 for fully paid securities.
4 The definitions in, and provisions of, AASB 1022: Accounting for Extractive
Industries and AASB 1026: Statement of Cash Flows apply to this report.
5 Accounting Standards ASX will accept, for example, the use of International
Accounting Standards for foreign entities. If the standards used do not address a topic,
the Australian standard on that topic (if any) must be complied with.
== == == == == For
per
sona
l use
onl
y