Upload
osdocs2012
View
223
Download
1
Embed Size (px)
Citation preview
8/3/2019 Perkin Expert Report
1/263
8/3/2019 Perkin Expert Report
2/263
GreggS.Perkin,P.E.EngineeringPartnersInternational
August26,2011 EXPERTREPORTMACONDO
2 |
TableofContents INTRODUCTION................................................................................................................................................. 3AUTHORQUALIFICATIONS................................................................................................................................... 5FINDINGS:........................................................................................................................................................ 6BACKGROUNDANDDISCUSSIONOFTHEMACONDOWELLANDHORIZONSBOP:................................................... 10OPINIONS
&
CONCLUSIONS:
..............................................................................................................................
14
CONCLUSION:................................................................................................................................................. 22
8/3/2019 Perkin Expert Report
3/263
GreggS.Perkin,P.E.EngineeringPartnersInternational
August26,2011 EXPERTREPORTMACONDO
3 Introduction|
INTRODUCTIONEngineering Partners International, L.L.C. (EPI) was retained by the Plaintiffs
Steering Committee (PSC) with respect to the DEEPWATER HORIZON Explosion in
the Gulf of Mexico on April 20, 2010. Specifically, you requested that Gregg S.
Perkin, P.E. of EPI review and analyze certain facts and issues concerning the
design, assembly, testing, installation, maintenance, repair, modifications and use
of the subsea blowout preventer (BOP) and its related control systems (CS)
which had been utilized on the mobile offshore drilling unit (MODU) DEEPWATERHORIZON (HORIZON). You also asked that I review and analyze issues related to
the BOP and its CSs role in the explosions and fire which occurred during the
evening of April 20, 2010 while the HORIZON was drilling and temporarily
abandoning BPs Macondo deepwater well (Macondo) in the Gulf of Mexico
(GoM). Further, what roles the BOP and its CS had in preventing the sinking of
the HORIZON two days later.
Each of the opinions I express herein are based upon my education, training,
knowledge and experience in the areas of mechanical engineering and the design,
application and use of oilfield equipment, such as BOPs and their CS, used in bothonshore and offshore oil and gas drilling and operations.
My opinions are based upon the information and materials which I have reviewed
which are set out in Appendix M and other appendices. They are also based upon
certain regulatory requirements governing offshore oil and gas exploration, drilling
and production activities as well as industry standards including normal and
customary practice for those operating companies (operators) pursuing these
activities. I am familiar with these particular regulations, standards and
recommended practices for the relevant time frame between 2001 to the present.
These materials are commonly and routinely relied upon by Operators in the GoM
when determining both the configuration and the utilization of their BOP and the CS
they choose when planning and conducting the drilling of deepwater wells, such as
Macondo. All of the materials cited herein in the both the endnotes and references
are materials that are relied upon in the ordinary course of business of Operators,
such as BP, and their working interest owners who drill deepwater wells in the GoM.
8/3/2019 Perkin Expert Report
4/263
GreggS.Perkin,P.E.EngineeringPartnersInternational
August26,2011 EXPERTREPORTMACONDO
4 Introduction|
I have not been asked to make any assumptions, nor have I presumed any facts
beyond those which are evidenced by the reliance materials identified in this Expert
Report, the endnotes and the appendices.
8/3/2019 Perkin Expert Report
5/263
GreggS.Perkin,P.E.EngineeringPartnersInternational
August26,2011 EXPERTREPORTMACONDO
5 AuthorQualifications|
AUTHORQUALIFICATIONS
Gregg Perkin has been involved in oil and gas drilling equipment
design and oilfield operations since 1968. He has authored
technical papers on equipment design, well control and oilfield
safety including having developed a number of equipment and
systems patents.
While in college, he was employed by a major oil and gas service
company. In 1973, he graduated with a Bachelor of Science in
Mechanical Engineering from California State University at Long
Beach. He became a registered Professional Engineer by
examination in the State of California in 1978 and is currently
registered as a Professional Engineer in good standing byexamination, experience & comity in thirteen (13) states
including Louisiana.
Mr. Perkins Oilfield Service Industry experience included working as a Design Engineer,
Engineering Manager, Manager of Technical Services, Chief Engineer, Vice President of
Engineering and also as a Director of Manufacturing. Mr. Perkin also worked as a
Roughneck or Floorman and Derrickman on an onshore drilling rig and as Serviceman and
Field Engineer in both offshore and onshore drilling and completion operations.
In mid-1987, Mr. Perkin began work as an independent professional mechanical engineering
consultant. In 1995, Mr. Perkin co-founded Engineering Partners International, L.L.C.
(EPI). Mr. Perkin is presently employed by EPI as its President and also as anindependent consultant and Professional Engineer in the areas of domestic and international
onshore and offshore Oil & Gas Drilling and Production operations including the design, use
and application of the equipment and systems used in oilfield exploration.
While at EPI, Mr. Perkin has been retained to conduct product design analysis, equipment
design, perform failure analysis, review claim elements of intellectual property and provide
other independent engineering consulting services related to mechanical equipment and
systems including the design, application, use, testing of BOPs and their related CS used
both onshore and offshore. Mr. Perkins full curriculum vitae and other biographical
materials are attached as Appendix L.
Respectfully Submitted -
Gregg S. Perkin, P.E.President and Principal EngineerEngineering Partners International, L.L.C
8/3/2019 Perkin Expert Report
6/263
GreggS.Perkin,P.E.EngineeringPartnersInternational
August26,2011 EXPERTREPORTMACONDO
6 Findings:|
Based on my education, training, knowledge and experience in oilfield equipment
design, application and use in oilfield operations, such as Deepwater drilling
operations, and based upon the information I have reviewed and the work I have
conducted, I presently have found the following to be true, supplemented and
explained in the remainder of this Expert Report and its appendices, regarding
HORIZONS BOP and its control systems including the subsequent explosion and fire
on the HORIZON on April 20, 2010, and major contributing factors leading thereto.
FINDINGS:
1. BP management controlled the configuration, testing, and safety profile ofHORIZONS BOP and its control systems (CS) under the well controlconditions being experienced on April 20, 2010 and before Macondo flowed
uncontrollably to the surface (blowout).
2. BP management knew all of the capabilities and the limitations of theHORIZONS BOP before the blowout on April 20, 2010.
3. BP management misrepresented data to the Minerals Management Service(MMS) regarding the well conditions which Macondo could produce.
4. BP management knew that a single BOP component used in HORIZONs BOP,its blind shear ram (BSR), was incapable of being successfully actuated
under the well control conditions being experienced on April 20, 2010 and
knew that Macondo could produce these actual well conditions.
5. Other BOP components used in HORIZONS BOP included two annular BOPs(annular), the single BSR, a casing shear ram (CSR), two variable bore
rams (VBR) and a test ram. On April 20, 2010, as the well control
emergency became greater in both size and proportion, both annulars and
the VBRs were closed. But the emergency continued to grow, exceeding the
operational envelope of the BOP. Due to known deficiencies pertaining to
both of HORIZONS annulars and its BSR, BP Management should not have
used this BOP as it was configured. The pressures that Macondo producedcould and did overwhelm the annulars and could and did overwhelm its BSR.
6. BP and Transocean management failed to competently train and supervisetheir employees pertaining to deepwater well control issues on the design,
use, assembly, testing, application and maintenance of HORIZONS BOP.
8/3/2019 Perkin Expert Report
7/263
GreggS.Perkin,P.E.EngineeringPartnersInternational
August26,2011 EXPERTREPORTMACONDO
7 Findings:|
7. BP and Transocean Management failed to adequately inspect, test, maintainand repair the BOP and keep it in proper working order.
8. BP management ignored safety concerns pertaining to the design, use,assembly, testing, application and maintenance of HORIZONS BOP and failed
to recognize its limitations as a well control device.
9. On April 20, 2010, BP management had a faulty well control policy in-placewhereby the annulars were to be closed first to shut-in and seal-off
Macondos wellbore. BP management should have known that bottom hole
pressures could be as high as 11,000 pounds per square inch ("psi") or more.
If the annulars could not shut-in and seal-off Macondos wellbore,
hydrocarbons could reach HORIZONS rig floor. In the event either/both
annulars could not shut-in and seal-off Macondos wellbore, the BSR below
the annulars would be subjected to shut-in wellbore pressures of up to
11,000 psi or more including the unknown flow conditions present within the
wellbore. BP management knew that closing the BSR under high flow rates
within Macondos wellbore could jeopardize its ability to shut-in and seal-off
Macondo. Under either well control scenario, BP Managements well control
policies placed the HORIZON and all of its personnel in grave danger. Had
BP management implemented realistic and competent well control policies,
Macondo should have been contained on April 20, 2010.
10.BP management failed to use the Best Available and Safest Technology("BAST") on the BOP system.
11.BP management failed to utilize audible and visual alarm systems with presetlimits regarding pressure, temperature, flow and other parameters, such as
sound, vibration, etc. within the BOP which would have alerted competent
and responsible personnel on the HORIZON that a potential well control
event was occurring;
12.BP management also failed to provide a realistic means to monitor, test andrecharge the batteries in the HORIZON BOPs control pods. The batteries
used were not rechargeable. They could discharge without any audible and
visual alarm at the surface. BP management needed to install a means tomonitor critical battery charges with preset limits. If battery charges went
into alarm modes sufficient charge would remain to activate critical systems
while they were being recharged and/or replaced.
13.The BOP had two (2) redundant and independent operator control systems.Each system utilized one set of Multiplex Electronic Control (MUX) cables.
The rigs MUX cables laid in close proximity to each other in the moon pool,
8/3/2019 Perkin Expert Report
8/263
GreggS.Perkin,P.E.EngineeringPartnersInternational
August26,2011 EXPERTREPORTMACONDO
8 Findings:|
an area which is classified as a hazardous area. The moon pool is the
entrance to the wellbore on the surface of the ocean. On April 20, 2010,
explosions knocked-out the MUX cables. Subsequently, there was no BOP
control from the rig. BP management failed to provide a backup control
system, such as an acoustic trigger, which was available from the BOPs
original equipment manufacturer (OEM); Cameron International
Corporation (Cameron). Utilizing an acoustic trigger would have been a
realistic and meaningful back-up to control the BOP if the MUX cables were
lost. Placing both of the MUX cables in the same hazardous area made it
such that a single event, could eliminate both systems. BP management
knew that the MUX cables could become a single point of failure (SPOF)
and they should have anticipated and guarded against not only this but all
SPOFs;14.BP management failed to identify all relevant SPOFs in the BOP assembly and
its control system. Since BP management failed to do so and because the
BOP had limited well control capabilities, other automatic BOP actuation
systems, such as the BOPs autoshear and Automatic Mode Function (AMF),
failed to shut-in and seal-off Macondo.
15.The BSR was the BOPs last resort to shut-it-in and seal-it-off should all elsefail to control it. As a result of the blowout, an assembly of pipe was in
Macondos wellbore and its BOP. If the BSR was called-upon with this pipe in
the wellbore, this single BSR had to shear this pipe in two, either centered
within the BSR or off-center, and then shut-in and seal-off Macondos
wellbore. BP management knew that Macondos BSR was incapable of
shearing certain sizes, weights and grades of pipe under certain and known
well control conditions. Further, BP management failed to provide the proper
cutting blades within the BSR to completely shear off-centered pipe including
having sufficient hydraulic energy available to actuate it.
16.BP management knew that ROV intervention to shut-in and seal-off Macondoin the event that an uncontrolled blowout occurred would be virtually useless
particularly of the BSR had not been activated or needed to be further
activated, i.e., had been partially closed but not completely closed.
17.BP management knew that an appropriate capping BOP was necessary andshould have been available on the HORIZON in the event that an
uncontrolled blowout occurred and the BOPs LMRP and the HORIZON was
successfully disengaged from the BOP. Even though Macondo would have
been blowing out uncontrollably, the capping stack could have been deployed
from the HORIZON, or another vessel, and placed atop the BOP. Activating
8/3/2019 Perkin Expert Report
9/263
GreggS.Perkin,P.E.EngineeringPartnersInternational
August26,2011 EXPERTREPORTMACONDO
9 Findings:|
the capping BOP should then have stopped the uncontrolled flow from
Macondo. Macondo would then have blown out of control for a considerably
less period of time than the 83 days which it did blow out.
18.BP management was aware of the catastrophic consequences that wouldfollow a failure of the BOP to contain a blowout, and had no plan to address
that eventuality.
19.The BSR failed because of a) the inability of the accumulator to providesufficient force; b) the inability of the BSR to shear off-center pipe; and c)
erosion washout as a result of dynamic conditions.
8/3/2019 Perkin Expert Report
10/263
8/3/2019 Perkin Expert Report
11/263
GreggS.Perkin,P.E.EngineeringPartnersInternational
August26,2011 EXPERTREPORTMACONDO
11 BackgroundandDiscussionoftheMacondoWellandHORIZONsBOP:|
ImageSource:EngineeringPartnersInternational,LLC9. Cameron International Corporation (Cameron) designed, manufactured and
sold the BOP system. However, Vastar Resources Incorporated, and its
corporate successor BP, were heavily involved in the design, choice of
components and control systems and the configuration of the BOP system.
Among the decisions made by BPs predecessor in the design andconfiguration of the BOP, Vastar:
a. Specified a 5 cavity BOP;b. Specified a 30 second LMRP disconnect with the lower BOP Stack in
connection with its Automatic Mode Function (AMF) or Deadmansystem;
UpperAnnular
LowerAnnular
CSRVBRVBR
TestRam
BSR
LMRP
LowerBOPStack
8/3/2019 Perkin Expert Report
12/263
GreggS.Perkin,P.E.EngineeringPartnersInternational
August26,2011 EXPERTREPORTMACONDO
12 BackgroundandDiscussionoftheMacondoWellandHORIZONsBOP:|
c. Decided against equipping the BOP with an acoustic trigger, i.e.,remote control;
d.Required certain adjustments to be made by Cameron beforeaccepting the BOP into service after the factory acceptance test;
e. Specified the location of the MUX cables in a hazardous area;f. Specified Emergency Disconnect System 1 (EDS-1) which activates
only the BSR instead of EDS-2 which activates of the CSR first,
followed by the BSR to shut-in and seal-off the well in primaryemergency LMRP disconnect mode.1
10.BP exercised operational control over the drilling activities conducted on theHORIZON through the leadership of BPs Well-Site Leaders (WSL) and other
BP employees on board the HORIZON, and a team of BP employees in BPs
Houston office;11.BP made all the significant and key decisions regarding HORIZONs BOP on
Macondo. With respect to the BOP and its control system, while theHORIZON was under charter to BP, its testing protocol was determined by
BP, not Transocean;2
12.During the course of the operations of the HORIZON, BP management made
modifications to the BOP;
13.Deepwater wells in the GoM present specific risks which are relevant to the
requirement for a properly chosen, properly designed and properly
functioning BOP and control system. The Macondo well was a deepwater well
located in over 5,000 feet of water;
14.In an Application for Permit to Drill (APD) submitted by BP to the United
States Minerals Management Service (MMS), BP misrepresented the
characteristics of Macondo which were relevant to the kind of BOP system
that would be necessary to control the well.
15.BP management sought and subsequently gained their permission to exempt
HORIZONS BOP from certain required tests and testing;
16.BP began drilling the Macondo well in in October of 2009 using the
Transoceans MODU MARIANAS, which was another semisubmersible.
Because of damage done to the MARIANAS by Hurricane Ida, BP
management replaced the MARIANAS with the HORIZON to complete
Macondo. HORIZON began its drilling of Macondo on February 6, 2010;
1ForamorecompletediscussionofBPsroleinthedesignandconfigurationoftheBOPsystem,seeAppendixF.2ForamorecompletediscussionofBPsroleintesting,maintenanceanddecisionsregardingtheBOP,seeAppendixG.
8/3/2019 Perkin Expert Report
13/263
GreggS.Perkin,P.E.EngineeringPartnersInternational
August26,2011 EXPERTREPORTMACONDO
13 BackgroundandDiscussionoftheMacondoWellandHORIZONsBOP:|
17.Macondo suffered a number of well control events during drilling operations.
For deepwater drilling operations, well control efforts are intended to be
competent and preventative measures taken to avoid an offshore blowout
catastrophe. These measures entail the prevention of fluids, i.e., formation
liquids and gas, from entering the wellbore. The entrance of formation fluids
and gas into the wellbore is referred to as a kick. Kicks must first be
recognized and then controlled. Conversely, a well control event can occur
from the loss of drilling fluids in the wellbore. Wellbore kicks and circulation
losses are discussed in more detail in attached Appendices.
18.On April 9, 2010, Macondo had been drilled to a total depth of 18,360 feet
where another kick was experienced. At this time, the well was months
behind and well over budget.
19.On April 20, 2010, BP management had already decided to temporarily
abandon Macondo. During this process, Macondo went out of control.
Despite efforts to activate the BOP, the well suffered a blowout followed by
explosions and fires and the ultimate sinking of the HORIZON and release of
oil into the GoM.3
20.The explosions disabled the MUX communication cables, the means by which
the crew would otherwise have been able to activate the BOPs EDS from
various locations on the HORIZON. The Autoshear Function, part of the
BOPs CS, should have activated the BSR and released the LMRP allowing the
HORIZON to drift off site. This did not occur and, as a result, the HORIZONremained connected to Macondo until it sank. The piping which connected
the LMRP (Riser) bent and broke.
21.After the HORIZON sank, efforts were made to activate the BOP using an
ROV. These efforts failed for reasons which are stated in more detail at
Appendix J.
3Foramorecompletediscussionoftheeventsleadinguptoandfollowingtheexplosion,seeAppendixI&J.
8/3/2019 Perkin Expert Report
14/263
GreggS.Perkin,P.E.EngineeringPartnersInternational
August26,2011 EXPERTREPORTMACONDO
14 Opinions&Conclusions:|
OPINIONS&CONCLUSIONS:OPINION 1: HORIZONS BOP AND ITS CONTROL SYSTEM FAILED TO PERFORM ITS INTENDEDFUNCTIONOFPREVENTINGABLOWOUT.
A. The HORIZON BOP failed to prevent the blowout despite efforts to activatethe various BOP components;
B. Attempts after the explosions to use the ROV to activate the BOP werelikewise unsuccessful;
1. Many ROV used post blowout were not working and the others lackedsufficient hydraulic power to be effective.
2. ROVs are not effective when a well is flowing through the BOP.OPINION 2: BP MANAGEMENT DID NOTADEQUATELY PERFORM ITS RISKASSESSMENT REGARDINGMACONDOSWELLCONTROLANDITSBOPANDCONTROLSYSTEM.
A. BP managements own guidelines required that the risks associated with thedrilling of a specific well be identified, evaluated, addressed and mitigated.
Even without written guidelines, a prudent operator should, prior to
commencing a drilling operation, identify, assess, and manage risks of the
operation;
B. BP management did not consider the safety and functionality risks associatedwith the BOP and its control system in its Risk Register, instead focused on
the financial impact of non-productive time. The only risk BP management
identified with respect to its BOP and its control system was non-productive
time;
C. BP managements risk assessment violated industry standards by failing toconsider the risks associated with the hazards of well control, uncontrolled
blowout, personal injury, death and environmental damage caused by a
blowout;
D. If BP had performed an industry standard risk assessment, the assessmentwould have identified, assessed and managed at least the following issues;
1. The adequacy of the design and configuration of the BOP system;2. The appropriateness of the HORIZONs BOP for the Macondo well
given the characteristics of that well;
8/3/2019 Perkin Expert Report
15/263
GreggS.Perkin,P.E.EngineeringPartnersInternational
August26,2011 EXPERTREPORTMACONDO
15 Opinions&Conclusions:|
E. Had these risks been adequately addressed and managed, the April 20, 2010blowout of Macondo would have been averted or significantly reduced.
Had these risks been adequately assessed and managed, the BOPwould have been upgraded and the blowout would have never
happenedOPINION3:BPMANAGEMENTKNEWORREASONABLYSHOULDHAVEKNOWNTHATHORIZONSBOPANDCONTROLSYSTEMWASNOTSUITABLEANDSAFEFORUSEINALLFORESEEABLEWELLCONTROLANDBLOWOUT CONDITIONS. BP MANAGEMENT SHOULD HAVE UPGRADED MACONDOS BOP WITH BASTFROMCAMERONBEFOREITWASPLACEDONITSWELLHEADONTHEOCEANFLOOR.
A. BP management failed in its responsibility to accurately determine criticalwell conditions and to ensure that the equipment being used, i.e.,
HORIZONS BOP and its control system was fit for its intended purpose.
B. As a part of insuring that Macondo could be drilled safely, an operator suchas BP must insure that the equipment it is going to use in connection with
drilling and well control operations is suitable and safe for the purpose for
which it will be used. If it is not suitable to a specific well, the BOP should not
be assigned to that well. This requires that the operator determine the
conditions of the well to be drilled and given those conditions, choose
equipment which is suitable and safe to use;
C. BP management failed to design, assemble, install, test, use and maintain insuch a way as to ensure well control under all predictable circumstances. Themaximum allowable or operating pressure ratings for each BOP component
must be greater the maximum allowable and/or anticipated surface pressure
(MASP), i.e. the maximum pressure that the well can produce at the
wellhead;
D. BP management failed to competently calculate and provide the MMS withMacondos MASP at the mud line as required by the MMS for permission to
drill the Macondo well;
E. BP misrepresented Macondos MASP to the MMS. BP managementrepresented that the worst-case MASP was 8,904 psi at the mud line. BPknew, from information available, it misrepresented the MASP because the
Macondo well was capable of producing pressures in the wellhead in excess
of 11,000 psi, or greater;
F. BP management knew that it was probable that the annulars would becomeless capable of sealing Macondo with wellhead pressures in excess of 10,000
psi;
8/3/2019 Perkin Expert Report
16/263
GreggS.Perkin,P.E.EngineeringPartnersInternational
August26,2011 EXPERTREPORTMACONDO
16 Opinions&Conclusions:|
G. BP management knew that it was probable and highly likely that the BSRwould be incapable of cutting the DP in two, shutting-in and sealing-off
Macondo, given the drill pipe (DP) inside the BSR on April 20, 2010, i.e.
5 outside diameter (OD), 21.9 lbs/ft, Grade S135, wellhead pressure in
excess in 10,000 psi, and flow;
H. As an operator, BP management was required to determine whether the DPacross the BSR, at any time, could be sheared;
I. BP management failed to take reasonable steps to determine the shearabilityof the DP being utilized on the HORIZON prior to and on April 20, 2010. The
following are examples supporting this opinion:
1. BP management never conducted shear tests on the assemblies of DP,i.e. drill string, being utilized on Macondo even though such tests are arecommended practice and that BP changed from 5 DP to stronger
6 DP to conduct drilling operations;
2. BP used an obsolete shearing chart to determine whether the DP wasshearable;
3. The shearing chart employed incorrect calculations. The shearingchart analysis referred to the use of a 5,000 psi accumulator system
(accumulators). Accumulators provide the hydraulic pressure and
flow to actuate all of the BOP components in the BOP. HORIZONs
accumulators to actuate the BSR had only 4,000 psi available, perhapsless;
4. BP Management had to request information, after the explosion, aboutthe shearability of the DP that was being used in Macondo;
5. BP never investigated the shearability of 6 DP by the HORIZONBOP. 6 DP was specifically requested by BP to be placed on the
HORIZON and was the DP primarily used in Macondos drilling
operation.
J. Transocean Management should have verified the shearability of all DP sizes,weights and grades using the BSR in HORIZONs BOP;
K. If BP management would have taken reasonable steps to determine theshearability of its DP, it would have discovered that, given the limitations of
the BOPs accumulators and its BSR, and given the wellbore conditions that
Macondo could and would produce as it was being drilled, BP management
would have reached the conclusion that HORIZONS BOP could not reliably
8/3/2019 Perkin Expert Report
17/263
GreggS.Perkin,P.E.EngineeringPartnersInternational
August26,2011 EXPERTREPORTMACONDO
17 Opinions&Conclusions:|
shear the DP being used. Therefore, HORIZONS BOP was not suitable and
safe for its intended use;
L. BP management should have upgraded the BOP. The following are specificexamples of options which were available to BP from Cameron to upgrade it:
1. Add tandem boosters, which would have effectively doubled theshearing capacity of the blind shear ram. Tandem Boosters which
would increase the shearing capability of the BSR and allow for higher
forces to shear DP;
2. Add another BSR, a preferable configuration;3. Install more efficient ram blocks in the BSR, such as Double V Shear
(DVS or CDVS) ram blocks. Double V Shear Rams shear DP with
greater efficiency and can cover the entire 18 BSR cavity in the
event that DP was off-center;
4. Install a larger subsea Accumulator system thereby giving greaterregulated flows and pressures to actuate critical BOP components;
5. Use EDS-2 instead of EDS-1. This modification would have cost BPmanagement nothing. It would also have protected the BSR by closing
the CSR first;
6. Install an Acoustic Control System (ACS) which could haveautomatically actuated the LMRP disconnect sequence from the
HORIZON;
7. Install monitoring systems on the BOP. Install instrumented audibleand visual preset alarms;
8. A 5,000 psi subsea accumulator;OPINION4:HORIZONSBOPASORIGINALLYDESIGNEDANDCONFIGUREDONAPRIL20,2010WASDEFECTIVE. THESEDEFECTSWERESIGNIFICANTANDCONTRIBUTINGCAUSESTOTHEBOPANDITSCSTOPERFORMITSINTENDEDFUNCTION:
A. The failure of the BOP to have cutting blades that extend across the wellbore;
1. Both BP and Cameron knew that off-center pipe within the cavity of aBOP component, such as the BSR, is a common occurrence in offshore
drilling. Therefore, Cameron and BP knew or reasonably should have
known that it is when pipe is off-center inside the BOP, HORIZONS
BSR would likely not completely shear the pipe and thus not seal the
8/3/2019 Perkin Expert Report
18/263
GreggS.Perkin,P.E.EngineeringPartnersInternational
August26,2011 EXPERTREPORTMACONDO
18 Opinions&Conclusions:|
well. Thus, the failure of the BSR to have cutting blades that do not
fully cover and extend across the wellbore was a design flaw rendering
the BOP not reasonably safe. The risk of occurrence could have been
avoided or significantly reduced by a reasonable alternative design,
namely providing a set of BSR cutting blades which extended across
the 18 opening;
B. The failure of HORIZONS BOP to have an adequate system for conveyingpressure, flow, temperature, vibration, battery charge, critical equipment
operational status information, etc. data to the rig;
1. Both Cameron and BP knew or reasonably should have known of theimportance and need for pressure, flow, temperature, vibration data
which may audibly and/or visually dictate the activation of the BOP to
rig personnel. The failure of the BOP to have a mechanism for the
transmission of such data to the rig floor and bridge it with adequate
alarms constitutes a design flaw rendering the BOP not reasonably
safe. Reasonable alternative designs existed that would have allowed
for the transmission of this data to rig personnel during a well control
event which would have avoided or reduced the risk of the BOP system
not being activated in a timely fashion.
C. The failure to properly segregate and/or otherwise protect the MUX cableswhich provide power to BOP controls so as to preserve the integrity and
redundancy of the BOP controls in case of an explosion;
1. HORIZONS BOP had two independent BOP operating systems. Theprimary system to operate HORIZONS BOP on the seafloor was
through the use of a multiplex electronic control (MUX) system. The
HORIZON had three separate panels from which personnel could
activate certain BOP controls. When activated, the command was
transmitted from the panel to a junction box, onto a MUX cable reel
and then through MUX cables to two separate control pods on the
LMRP; i.e. the yellow and blue pods. Electronic signals were then
converted to hydraulic signals which would activate components of
HORIZONS BOP. The separate panels and pods were provided so as to
give redundancy to the controls such that the BOP could continue to be
operated in the event one of the panels or pods became disabled.
2. However, the MUX cables which transmitted the commands from eachof the three panels to the blue and yellow pods were strung through a
single and classified hazardous area called the moon pool. The moon
8/3/2019 Perkin Expert Report
19/263
GreggS.Perkin,P.E.EngineeringPartnersInternational
August26,2011 EXPERTREPORTMACONDO
19 Opinions&Conclusions:|
pool is an area at the top of the well above the surface of the ocean, a
direct conduit from the well bore and thus an area which is subject to
explosion and fire. The design and construction of the system so as to
route both the yellow and blue MUX cables through the moon pool
created a SPOF. By running both blue and yellow MUX cables through
the same hazardous area, both cables are subjected to loss or
compromise in the event of an explosion in the moon pool, thus
defeating the purpose of these dual and redundant controls. As
designed and configured, the BOP and its CS was unreasonably safe.
The decision of BP, Transocean and Cameron to place the MUX cablesin the moon pool without protection from explosion and fire was
unreasonably dangerous
4. The possibility of an explosion in the moon pool was entirelyforeseeable and there were reasonable alternative designs which
would have eliminated or significantly reduced the risk of losing the
control of HORIZONS BOP included:
a. The consideration of routing one of the MUX cables through anon-hazardous area;
b. Providing exterior protection to both MUX cables thus increasingtheir ability to reliably function in a classified hazardous area
and;
c. Providing ACS (Acoustic Trigger) as a means of activating theBOP wirelessly.
D. The failure to have a wireless method to activate and control emergencyfunctions;
1. As explained above, there was a need for a remote control wirelessmethod of activating BOP controls in the event the MUX cables or
other elements within the BOP system were disabled or destroyed.
Such a method, i.e. an ACS (Acoustic Trigger) was available in 2001,
Such a device should have been a part of HORIZONS BOP and its CS.
E. The inability to monitor, test, charge, and/or change the batteries whichpowered certain Blue and Yellow Pods while HORIZONS BOP was on the
seafloor;
1. HORIZONS BOP had batteries in its blue and yellow pods which werenecessary for the activation of the BOPs AMF/Deadman systems and
were a critical component of the BOPs CS;
8/3/2019 Perkin Expert Report
20/263
GreggS.Perkin,P.E.EngineeringPartnersInternational
August26,2011 EXPERTREPORTMACONDO
20 Opinions&Conclusions:|
2. As designed and manufactured, the batteries in the subsea pods couldnot be monitored, tested, charged, and/or changed while HORIZONS
BOP was on the ocean floor creating a risk that the batteries would
have insufficient charge and quit functioning. Such a condition would
go undetected. This represented a design flaw which rendered
HORIZONS BOP not reasonably safe;
3. There were reasonable alternative designs that would have eliminatedthis risk or have significantly reduced it.
4. BP, Cameron and Transocean knew or reasonably should have knownof this hazard pertaining to the blue and yellow pod batteries.
However, nothing was done to address this deficiency. Such conduct
falls below the standard of care of a reasonably prudent operator, BOP
Equipment Provider and Drilling Contractor in the GoM.
F. The failure to have redundancy in the emergency activation systems byrelying on a single component for all pipe shearing and well bore shutting-in
and sealing functions, namely the single BSR. There were five emergency
activation systems on HORIZONS BOP. Each system utilized the same BOP
component to seal it, namely the BSR and the accumulator necessary to
energize it. If the BSR failed to function, for whatever reason, it essentially
disables every emergency function of the BOP.OPINION5:BPMANAGEMENTFAILEDTOHAVEANADEQUATEWELLCONTROLPOLICYPERTAININGTOHORIZONSBOP.
A. BP management had a faulty well control policy in-place whereby HORIZONSannulars were to be closed first to shut-in and seal-off the wellbore;
B. BP management knew that closing the BSR under high flow rates withinMacondos wellbore could jeopardize its ability to shut-in and seal-off the
wellbore.
C. By regulation, BP was responsible for competently calculating MASP, aregulatory requirement relating to the BOP per 30 CFR 250.446;
D. By making the lower ram a test ram, BP management violated its own wellcontrol policy which stated that: "the lowermost ram be preserved as a
master component and only used to close in the well when no other ram is
available for this purpose."
E. BP failed to adequately supervise and oversee Transocean with regards toBOP operations.
8/3/2019 Perkin Expert Report
21/263
8/3/2019 Perkin Expert Report
22/263
GreggS.Perkin,P.E.EngineeringPartnersInternational
August26,2011 EXPERTREPORTMACONDO
22 Conclusion:|
Instead of dry dock, Transocean performed Underwater Inspections in Lieu of
Dry-docking ("UWILD") and other at-sea inspections;
1. Both the three (3) and five (5) year certifications of the Ram-Type BOPbonnets were identified in the BP's September 2009 audit as never
having been completed.
D. The HORIZON had been under continuous contract to BP and had never beento dry dock for shore-based repairs in the nine years since it was built.
OPINION8:THEACCIDENTOFAPRIL20,2010WASENTIRELYFORESEEABLEANDPREVENTABLE,ANDWASCAUSEDBYTHEFAILURESDETAILEDABOVE.
CONCLUSION
:
These are my opinions within a reasonable degree of probability, based upon the
materials referenced in Appendix M, as well as the other appendices. Further
elaboration of my opinions can be found in the chart located at Appendix K and
other attached Appendices.
8/3/2019 Perkin Expert Report
23/263
8/3/2019 Perkin Expert Report
24/263
GreggS.Perkin,P.E.
EngineeringPartnersInternational
August26,2011 BLOWOUTPREVENTERMACONDO
2 AppendixA: AbbreviationsandAcronyms|
TableofContents
AppendixA: AbbreviationsandAcronyms.............................................................................................. 3
AppendixB: DeepwaterDrilling.............................................................................................................. 6
AppendixC: WellControl........................................................................................................................ 8
AppendixD: BlowoutPreventers&Systems......................................................................................... 13
AppendixE: BOPRegulatoryCompliance............................................................................................. 20
AppendixF: ResponsibilityforBOPConfiguration............................................................................... 27
AppendixG: DEEPWATERHORIZON'SSubseaBOP............................................................................... 32
G.1 Modifications.................................................................................................................... 47
G.2 Testing............................................................................................................................... 48
G.3 Training............................................................................................................................. 52
G.4 BOPMaintenance............................................................................................................. 57
G.5 BestAvailableandSafestTechnology("BAST")................................................................ 59
AppendixH: BP'sMacondoWell........................................................................................................... 67
H.1 ApplicationforPermittoDrill........................................................................................... 67
H.2 MaximumAllowableSurfacePressure(MASP):............................................................ 71
H.3 WellControlResponsibilities............................................................................................ 81
AppendixI: EventsLeadingUptoBPsMacondoBlowout.................................................................. 86
AppendixJ: PostBlowout.................................................................................................................... 95
AppendixK: MacondoDesignandImplementationFailures................................................................ 97
AppendixL: Mr.GreggS.Perkin,C.V.andrelatedinformation....................................................... 104
AppendixM:SourcesandInformation.................................................................................................. 114
EndNotes ........................................................................................................................................ 223
8/3/2019 Perkin Expert Report
25/263
8/3/2019 Perkin Expert Report
26/263
GreggS.Perkin,P.E.
EngineeringPartnersInternational
August26,2011 BLOWOUTPREVENTERMACONDO
4 AppendixA: AbbreviationsandAcronyms|
HORIZON ................ DEEPWATER
HORIZON
HP ......................... High Pressure
HPU ....................... Hydraulic Power Unit
Hydrocarbons .......... Deposits beneath the
earths surface such
as oil and gas
IADC ...................... International
Association of Drilling
Contractors
In .......................... Inch or inches
ID .......................... Inside diameter
Joints ..................... Individual sections of
drill pipe
Kick ....................... Unexpected flow of
hydrocarbons into the
wellbore
LDS ....................... Lock Down Sleeve
LIT ........................ Lead Impression Tool
LMRP ..................... Lower Marine Riser
Package
Long String ............. Long String of
Production Casing
MASP ..................... Maximum Anticipated
Surface Pressure
MAWP .................... Maximum Allowable
Working Pressure
MC252 ................... Mississippi Canyon
Block #252 location
of the Macondo well
MD ........................ Measured depth
MGS ....................... Mud-gas separator
MMS ...................... Minerals Management
Service, now BOEMRE
MODU .................... Mobile Offshore
Drilling Unit
Mud ....................... Drilling mud
MUX ...................... Multiplex
MW ........................ Mud Weight
NDT ....................... Non-Destructive
Testing
NPT ....................... Non-Productive Time
OCS ....................... Outer Continental
Shelf
OD ........................ Outside diameter
OEM ...................... Original Equipment
Manufacturer
OIM ....................... Offshore Installation
Manager
PLC........................ Programmable LogicController
ppf ........................ Pounds per foot
ppg ....................... pounds per gallon
psi ......................... Pounds per square
inch
Riser ...................... Marine Riser System
RMS ....................... Rig Maintenance
System
ROV ....................... Remotely operated
vehicle
RP ......................... Recommended
Practice
8/3/2019 Perkin Expert Report
27/263
GreggS.Perkin,P.E.
EngineeringPartnersInternational
August26,2011 BLOWOUTPREVENTERMACONDO
5 |
SEM ....................... Subsea Electronic
Module
SPOF ...................... Single Point of Failure
ST Lock .................. Hydro-mechanical ram
locking mechanism
TA ......................... Temporary Abandon
TD ......................... Total Depth
TVD ....................... Total Vertical depth
UMRP ..................... Upper Marine Riser
Package
UWILD ................... Underwater Inspection
in Lieu of Dry-Dock
V ........................... Volt
VBR ....................... Variable Bore Ram
8/3/2019 Perkin Expert Report
28/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
6 AppendixB: DeepwaterDrilling|
AppendixB: DeepwaterDrilling1
Deepwater drilling has been commonly known historically as the process of
conducting oil & gas exploration and production operations in seawater
depths of more than 500 feet (ft). Using this definition, there have been
approximately 600 Deepwater wells drilled in the GoM.2
Oil production in water depths exceeding 6,000 ft is currently taking place in
different parts of the world.3 New explorations in ultra-Deepwater drilling
operations are being performed in water depths exceeding 9,000 ft.4
Deepwater drilling presents unique technical and safety challenges, especially
for the BOP. At these depths, the BOP equipment, hoses, and connectionscannot be reached, except by Remote Operated Vehicle (ROV). ROV
operations are difficult due to water pressure, lack of visibility, depth
perception and color (everything is monochromatic), lack of appropriate tools
and the limitations of remote control. In addition, the BOP cannot easily be
brought to the surface even when the well is shut in, especially when the well
is flowing. When the BOP malfunctions, repair or replacement becomes
difficult, if not impossible. Accordingly, planning for Deepwater drilling BOP
strategies must be undertaken with the utmost care and prudence.
SINTEF published a reliability study on behalf of the MMS, to review subseaBOP performance, entitled Deepwater Kicks and BOP Performance dated July
24, 2001.5 The study reported a total of 117 BOP failures and 48 well kicks
were recorded in the 83 wells observed between 1997 and 1998.6 Of the 83
wells, 58 wells were deemed exploratory drilling, defined as drilling in less
well known formations. Macondo was an exploratory well.7
The report indicated that many of the GoM Deepwater wells were high
pressure/high temperature wells.8 The frequency of Deepwater kicks where
a BOP was necessary to control the event was high when there was a low
limit between the pore pressure and fracture pressure, such as on the
Macondo.9 During the kick control operations, BOP failures were observed
that were probably caused by the kick killing operations.10
Macondo experienced numerous lost circulation events, and three kicks
between February and April 2010, including one which resulted in reducing
the total depth of the well.11 The kicks were circulated out while the annular
was engaged. Refer to Figure B.1 on the following page.
8/3/2019 Perkin Expert Report
29/263
8/3/2019 Perkin Expert Report
30/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
8 AppendixC: WellControl|
AppendixC: WellControl
Well Control or blowout prevention is a critical part of drilling,
completing, and working over wells. Blowout equipment is the final
line of defense against a catastrophic event which may include
fatalities, uncontrollable release of oil and gas, and evacuation of
entire communities.
Blowout prevention is much more than blowout preventers. It is an
integral system that not only includes equipment but training and
stringent policies adhered to by the entire team. BPs publication BP-
Wells Engineer OJT Module #716
For deepwater drilling operations, well control efforts must be competently
performed and all reasonable preventative measures taken to avoid an
offshore blowout catastrophe. These measures entail the prevention of
fluids, i.e., formation liquids and gases, from entering the wellbore. The
entrance of formation fluids and gases into the wellbore are referred to as a
kick.17 Kicks must first be recognized and then controlled.
There are multiple barriers, or layers of prevention, which are relied upon to
maintain the control of fluids, both produced and injected. The design,
installation and/or use of these barriers is critical. Good well control
procedures normally consist of installing barriers to uncontrolled flow. Kicks
occur because a barrier has failed to control fluid pressure in the formation.
For example, some barriers are:
Hydrostatic Fluid Pressure;
Downhole Casing;
Annular Cement and;
Mechanical Barriers.
The primary barrier is the fluid column, which BP recognized.18
Hydrostatic fluid pressure is the pressure exerted against the formation by a
fluid at equilibrium due to the force of gravity.19 In oil and gas well drilling
operations, the engineered fluids used in the Rotary Drilling Rigs Circulating
System are commonly referred to as drilling mud (Mud). Refer to Figure
C.1 on the following page.
8/3/2019 Perkin Expert Report
31/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
9 AppendixC: WellControl|
Figure C.1. Hydrostatic Pressure exerted by a Column of Fluid. Shape is
insignificant.
8/3/2019 Perkin Expert Report
32/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
10 AppendixC: WellControl|
Pressure is defined as the force distributed over an area.
P = F/A where:
P is pressure in pounds per square inch (psi)
F is the force normal or perpendicular to the area in pounds (lbs)
A is the area in square inches (in)
The pressure gradient can be used to calculate the pressure exerted by a
column of fluid vs. depth. Referring to Figure 6.1, the pressure gradient of
fresh water is 0.433 psi per foot of depth. Therefore, at a depth of 1 foot,
the hydrostatic pressure is equal to 0.433 x 1 ft = 0.433 psi. At a depth of
50 ft, the hydrostatic pressure is equal to 0.433 x 50 ft = 21.65 psi20
Refer to Figure C.2 below with regard to calculating the pressure gradient of
water.
Figure C.2. Pressure Gradient of Fresh Water
8/3/2019 Perkin Expert Report
33/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
11 AppendixC: WellControl|
If a heavier or denser fluid is used, such as salt water or an engineered fluid
such as mud, the calculation of the pressure gradient is determined by
dividing the weight of 1 cubic foot of the fluid by 144.
Drilling mud weights in the English system can be expressed in pounds per
cubic foot (lbs/ft) or pounds per gallon (lbs/gal). There are 7.48 gallons
per cubic foot. Dividing 7.48 gallons by 1 square foot equals 0.052 gallons
per foot (gal/ft). If the muds weight (MW) is known in lbs/gal and the
true vertical depth of the well is known in feet, then the hydrostatic pressure
in the wellbore at its true vertical depth (TVD) is equal to the MW (lbs/gal)
x 0.052 x TVD (ft) = hydrostatic pressure (psi). For example, at a TVD of
10,500 ft and drilling with a 14.1 lbs/gal drilling mud, the hydrostatic
pressure of the column of fluid at the bottom of the well would be calculated
as 10,500 ft x 0.052 x 14.1 = 7,698.6 psi.
When drilling an oil & gas well, the hydrostatic pressure of the fluid column in
the well should hold back formation fluids and gases.21 If formation pressure
exceeds the hydrostatic pressure, the well could kick. A kick may be a
combination of water, gas, and/or oil, alone and/or in combination. Refer to
Figure C.3 below.
8/3/2019 Perkin Expert Report
34/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
12 AppendixC: WellControl|
Figure C.3. Well Control
Because gas is compressible and liquid is generally considered not to be
compressible, if a well kick is believed to have occurred, it should be treated
as a gas kick.22
Formation pressure can become greater than hydrostatic pressure undercertain circumstances. For example:
1. Insufficient mud weight;23
2. Lost circulation from the wellbore;24
3. Cementing operations;254. Drilling operations where:
Excessive rates of penetration are employed;
Pressure charged formations are encountered; Underbalanced drilling operations are underway or;
Shallow gas is encountered.
All competent Operators regard the management of hydrostatic pressure as
the primary means of well control.26 Engineering, controlling, managing and
monitoring the mud used in the wellbore is the Operators primary means of
preventing a blowout.27 Well control equipment, including BOPs, is
considered a secondary means of well control.28
At the first sign of a kick, the wells operator and the drilling rigs crew mustfirst detect it, then stop it from progressing through the use of one or more
of the barriers.29 The influx is then circulated out of the wellbore. BP's well
control policies dictated which well control equipment (such as an annular or
ram-type BOP) was used to prevent the influx from escalating and flowing to
the surface in an uncontrolled manner, or a blowout.30
The BP well site leader ("WSL") had the responsibility for overseeing all
operations on the well. That responsibility included the delegation and
oversight of the minute-to-minute monitoring of data, and the review and
approval of the drilling contractor's well control procedures.31
BPs Macondo well was an example of a blowout which should have been
avoided, and, after occurring, managed and controlled.
8/3/2019 Perkin Expert Report
35/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
13 AppendixD: BlowoutPreventers&Systems|
AppendixD: BlowoutPreventers&Systems
A BOP is basically a pressure vessel. It can have multiple configurations
based upon the drilling and completion operations being conducted.
A BOP is also a valve. When actuated, a BOP is intended to seal-off (1) the
annular space or (2) the wellbore from below in order to contain formation
pressures, i.e., the kick, downhole. The annulus or annular space is the area
which surrounds a cylindrical object within a larger cylinder. In the oilfield, it
is the donut-shaped space between the outside diameter (OD) of the pipe
in the wellbore and the inside diameter (ID) of either the wellbore or
casing. Refer to Figure D.1.
The BOP provides a means of containing wellbore flows and pressures during
a kick. The design of the BOP permits drilling mud to be circulated into and
out of the wellbore so that the kick can be circulated out and the well can be
returned to its controlled, i.e., non-flowing condition.The BOP is also capable
of suspending the drill string.
Figure D.1. The Wellbore Annulus
8/3/2019 Perkin Expert Report
36/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
14 AppendixD: BlowoutPreventers&Systems|
Once a BOP is actuated and seals, it contains the wellbore fluids and the
wellbore pressures beneath it.
BOP original equipment manufacturers (OEM) provide their BOPs with
maximum allowable working pressure (MAWP) ratings such as 2,000 psi,
3,000 psi, 5,000 psi, 10,000 psi and 15,000 psi. MAWP is provided for static
and not dynamic flow conditions. Regardless of the BOP stacks overall
pressure rating, the MAWP of the downhole casing which lines the wellbore
(Casing) limits the wells MAWP.
There are 2 types of BOPs; annular and ram-type. Refer to Figures D.2 and
D.3 below.
Figure D.2. Exemplar: Hydril Annular BOP
Figure D.3. Exemplar: Cameron Ram-Type BOP
8/3/2019 Perkin Expert Report
37/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
15 AppendixD: BlowoutPreventers&Systems|
When the drill string is in the wellbore, a subsea BOP must have the
capability of shearing the drill string, shutting-in the wellbore and sealing it
off from the surface. Shearing the drill string is accomplished by installingShear rams into the body of a ram-type BOP.
All subsea BOPs are required to have a shearing/sealing ram (a BSR). A
blind ram seals, a shearing ram shears, a blind-shear ram does both. When
the BSR was developed, it was the first time there was the ability to shear
and seal simultaneously with one (1) movement of the rams through the
opening of the wellbore. Prior, all rams had to seal around the pipe and then
attempt to shear with another stroke. Because of dynamic flow conditions,
this was often a failure.
After the drill string is severed by the Shear rams, the LMRP should be
capable of being disconnected from the lower BOP stack.
Refer to Figure D.4 on the following page of a subsea BOP connected to its
MODU.
8/3/2019 Perkin Expert Report
38/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
16 AppendixD: BlowoutPreventers&Systems|
(1) Conductor Pipe and
Subsurface Casing
(2) Wellhead and Casing
Hanger Systems
(3) BOP
Connector
(4) BOP (LMRP and Lower BOP
Stack) & Flex Joint
(5) Marine Riser
System
(6) Telescopic Joint
Assembly
Motion CompensationSystem to include:
Drill String MotionCompensator
Riser and GuidelineTension Systems
Upper Marine Riser
Package(UMRP)
Waterlevel
SeaFloor
Figure D.4. Subsea BOPs hooked-up to aMobile Offshore Drilling Unit (MODU)(from the 1896-1987 Oilfield Composite
Catalogue, Vetco Gray)
8/3/2019 Perkin Expert Report
39/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
17 AppendixD: BlowoutPreventers&Systems|
Because the BOP is placed on the oceans floor, it must be operated from the
surface. Electrical and hydraulic lines, control pods, hydraulic accumulators,
valves, choke and kill lines, a riser connector, a wellhead connector and asupport frame are connected to, and are part of, a BOP. Acoustic devices
were available that would allow for the remote actuation of subsea BOPs.
The BOP on the HORIZON was a five (5) cavity stack which attached to the
wellhead. The lower BOP stack sits on the wellhead. The Lower BOP Stack is
connected to the Lower Marine Riser Package (LMRP). The LMRP contained
the annular BOPs. The LMRP had two (2) control pods, designated blue and
yellow. A Multiplex Electronic Control (MUX) cable connected the pods to
the HORIZON. Electronic signals were transmitted from the rig through the
MUX cables to the electronic packages within the pods. Then the signals
were decoded to deliver certain commands to solenoid valves using battery
power.
Figure D.7. MUX Cables & Hydraulic Conduits connected to the Blue & Yellow Pods
8/3/2019 Perkin Expert Report
40/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
18 AppendixD: BlowoutPreventers&Systems|
Solenoid valves are flow control devices in each pod. When energized by an
electronic signal, a solenoid valve generates a hydraulic signal to operate a
hydraulic component on the BOP.
At the bottom of the HORIZON LMRP was
a hydraulically actuated connector. This
connector attached the LMRP to the top of
the lower BOP stack. This connector was
similar to the wellhead connector which
locked the lower BOP stack onto the
wellhead.
The LMRP could be disconnected from the
lower BOP stack, remotely by operator
controls on the rig. Then, the HORIZON
could move-off, if necessary, while the
Lower BOP stack remained on the subsea
wellhead. Refer to Figure D.6.
Auxiliary lines include (a) choke and kill lines (b) mud booster lines and (c)
hydraulic conduit lines. They are normally spaced asymmetrically around the
Riser.
(a) choke and kill lines extend from the wellbore at the seafloor up tothe MODU when the BOP has been shut-in and the wellbore sealed.
Mud can be pumped down the kill line into the wellbore. Mud andwellbore fluids are circulated out of the wellbore through the choke
Line. A Drilling choke, i.e., variable opening valve, is connected at
the end of the choke Line in order to control the flow and pressure
of the displaced wellbore fluids and mud.
Figure D.6. Example of Disconnect LMRP
from Lower BOP Stack with HORIZON
moving-off
(from the cover of Camerons
Emergency, Back-up and DeepwaterSafety Systems)
8/3/2019 Perkin Expert Report
41/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
19 AppendixD: BlowoutPreventers&Systems|
The BOP and its control systems (CS) must also have emergency closure
systems available to the MODU on the surface.
Failures of BOPs have been well documented throughout the industry.
Several reports studying BOP failures and several reviews show a long
history of BOP failure upon emergency activation. Well control policies that
rely solely on the BOP as the only barrier are reckless and below the
minimum standard of care. BPs own policy requires a minimum of two (2)
barriers and the BOP is not considered one of those barriers.
8/3/2019 Perkin Expert Report
42/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
20 AppendixE: BOPRegulatoryCompliance|
AppendixE: BOPRegulatoryCompliance
The regulatory requirements for the BOP are detailed and thorough.
In 1938, the United States Federal Government, through the Office of
Federal Register, established a written Code of Federal Regulations (CFR).
In 2010, the MMS was the Federal Governments agency that governed Title
30 Part 250 Oil and Gas and Sulphur Operations in the Outer
Continental Shelf. Included in 30 CFR 250:440, 442, 443 and 445 are the
regulations which mandate the use of a subsea BOP and set forth minimum
requirements.
The regulations mandate, among other things, that: 1) a description of theBOP to be used on the well be given to MMS [CFR 250:415], 2) the BOP be
maintained and inspected [30 CFR 250:446], and tested [30 CFR 250:447-
449], and 3) personnel be trained in its use [30 CFR 250:1500-1506].
BP did not comply with many of the regulations and violated more than one
of them.
Some of the regulations that the MMS requires an Operator such as BP to
comply with include: (Emphasis Added)
250.107 Protect health, safety, property, and the environment
by:
(c) Us[ing] the best available and safest technology ("BAST")
whenever practical on all exploration, development, and production
operations;
(d)(1) Avoiding the failure of equipment that would have a significant
effect on safety, health, or environment;
250.213 Provide general information with the Exploration
Plan including:
(g) Blowout scenario. A scenario for the potential blowout of the
proposed well in your EP that you expect will have the highest volumeof liquid hydrocarbons. Include the estimated flow rate, total volume,
and maximum duration of the potential blowout. Also, discuss the
potential for the well to bridge over, the likelihood for surface
intervention to stop the blowout, the availability of a rig to drill a relief
well, and rig package constraints. Estimate the time it would take to
drill a relief well.
8/3/2019 Perkin Expert Report
43/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
21 AppendixE: BOPRegulatoryCompliance|
250.401 Keep wells under control at all times by:
(a) Us[ing] the best available and safest (BAST) drilling
technology to monitor and evaluate well conditions and to minimizethe potential for the well to flow or kick;
(c) Ensur[ing] that the Toolpusher, Operator's representative, or a
member of the drilling crew maintains continuous surveillance on
the rig floor from the beginning of drilling operations until the well is
completed or abandoned, unless you have secured the well with
blowout preventers (BOPs), bridge plugs, cement plugs, or packers;
(d) Use personnel trained according to the provisions of subpart O;
(e) Us[ing] and maintain[ing] equipment and materials
necessary to ensure the safety and protection of personnel,equipment, natural resources, and the environment.
250.407 Conduct tests to determine reservoir characteristics
to:
determine the presence, quantity, quality, and reservoir
characteristics of oil, gas, sulphur, and water in the formations
penetrated by logging, formation sampling, or well testing.
250.413 What must my description of well drilling design
criteria address:
(f) Maximum anticipated surface pressures. For this section,maximum anticipated surface pressures are the pressures that you
reasonably expect to be exerted upon a casing string and its related
wellhead equipment. In calculating maximum anticipated surface
pressures, you must consider: drilling, completion, and producing
conditions; casing setting depths; total well depth; formation fluid
types; safety margins; and other pertinent conditions. You must
include the calculations used to determine the pressures for the
drilling and the completion phases, including the anticipated surface
pressure used for designing the production string;
250.416 Describe the diverter and BOP Systems to:
(e) Show the blind-shear rams installed in the BOP stack (both
surface and subsea stacks) are capable of shearing the DP in
the hole under maximum anticipated surface pressures
("MASP").
250.440 Provide general requirements for BOP systems
components:
8/3/2019 Perkin Expert Report
44/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
22 AppendixE: BOPRegulatoryCompliance|
You must design, install, maintain, test, and use the BOP
system and system components to ensure well control. The
working-pressure rating of each BOP component must exceedmaximum anticipated surface pressures. The BOP system
includes the BOP stack and associated BOP systems and
equipment.
250.442 What are the requirements for a subsea BOP system:
When drilling with a subsea BOP system you must:
(b) Have an operable dual-pod control system to ensure proper and
independent operation of the BOP system.
(k) Before removing the marine riser, displace the fluid in the riser
with seawater. Additionally, you must maintain sufficient hydrostatic
pressure or take other suitable precautions to compensate for the
reduction in pressure and to maintain a safe and controlled well
condition.
250.443 What associated systems and related equipment must
all BOP systems include:
All BOP systems must include the following associated systems and
related equipment:
(a) An automatic backup to the primary accumulator-charging
system.
(g) A wellhead assembly with a rated working pressure that exceedsthe maximum anticipated surface pressure.
250.446 Maintain and Inspect the BOP System to:
(a) Ensure that the equipment functions properly. BOP
maintenance must meet or exceed the provisions of Sections 17.10
and 18.10, Inspections; Sections 17.11 and 18.11, Maintenance; and
Sections 17.12 and 18.12, Quality Management, described in API RP
53, Recommended Practices for Blowout Prevention Equipment
Systems for Drilling Wells (incorporated by reference as specified in
Sec. 250.198).
250.447 Pressure test the BOP System on a consistent basis:
(b) Before 14 days have elapsed since your last BOP pressure test.
You must begin to test your BOP system before midnight on the 14th
day following the conclusion of the previous test. However, the
District Manager may require more frequent testing if conditions or
BOP performance warrant (this includes the choke manifold, Kelly
valves, inside BOP, and drill-string safety valve).
8/3/2019 Perkin Expert Report
45/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
23 AppendixE: BOPRegulatoryCompliance|
250.448 Pressure test the BOP System to prescribed levels:
Conduct a low-pressure and a high-pressure test for each BOP
component. Conduct the low-pressure test before the high-pressuretest. Each individual pressure test must hold pressure long enough to
demonstrate that the tested component(s) holds the required
pressure. Required test pressures are as follows:
(a) Low-pressure test. All low-pressure tests must be between 200
and 300 psi. Any initial pressure above 300 psi must be bled back to a
pressure between 200 and 300 psi before starting the test. If the
initial pressure exceeds 500 psi, you must bleed back to zero and
reinitiate the test.
(b)High-pressure test for ram-type BOPs, the choke manifold, and
other BOP components. The high-pressure test must equal the rated
working pressure of the equipment or be 500 psi greater than your
calculated maximum anticipated surface pressure (MASP) for the
applicable section of hole. Before you may test BOP equipment to the
MASP plus 500 psi, the District Manager must have approved those
test pressures in your APD.
(c) High pressure test for annular-type BOPs. The high pressure test
must equal 70 percent of the rated working pressure of the
equipment or to a pressure approved in your APD.
(d)Duration of pressure test. Each test must hold the requiredpressure for 5 minutes. However, for surface BOP systems and
surface equipment of a subsea BOP system, a 3-minute test duration
is acceptable if you record your test pressures on the outermost half
of a 4-hour chard, on a 1-hour chart, or on a digital recorder. If the
equipment does not hold the required pressure during a test, you
must correct the problem and retest the affected component(s).
250.449Perform additional testing:
(d) Pressure test the blind or blind shear ram BOP during stump tests
and at all casing points;
(e) The interval between any blind or blind-shear ram BOP pressuretests may not exceed 30 days;
(h) Function test annular and ram BOPs every 7 days between
pressure tests;
(j) Test all ROV intervention functions on your subsea BOP
stack during the stump test. You must also test at least one set of
8/3/2019 Perkin Expert Report
46/263
8/3/2019 Perkin Expert Report
47/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
25 AppendixE: BOPRegulatoryCompliance|
In addition to the 30 CFR Part 250, the MMS requires operators to comply
with specific portions of API Recommended Practice No. 53 (API RP 53),
Blowout Prevention Equipment Systems for Drilling Wells.
Also, API RP 53 recommends:
18.10.1 Between Wells:
After each well, the well control equipment should be cleaned, visually
inspected, preventative maintenance performed, and pressure test
before installation on the next well. The manufacturers test
procedures, as prescribed in their installation, operation, and
maintenance (IOM) manual, should be followed along with the test
recommendations. All leaks and malfunctions should be corrected
prior to placing the equipment in service.
18.10.3 Major Inspections:
After every 3-5 years of service, the BOP stack, choke manifold, and
diverter components should be disassembled and inspected in
accordance with the manufacturers guidelines.
Elastomeric components should be changed out and surface finishes
should be examined for wear and corrosion. Critical dimensions shouldbe checked against the manufacturers allowable wear limits.
Individual components can be inspected on a staggered schedule.
A full internal and external inspection of the flexible choke and kill lines
should be performed in accordance with the equipment manufacturers
guidelines.
18.11.3 Replacement Parts:
Spare parts should be designed for their intended use by industryapproved and accepted practices. After spare part installation, the
affected pressure-containing equipment shall be pressure tested.
Elastomeric components shall be stored in a manner recommended by
the equipment manufacturer.
8/3/2019 Perkin Expert Report
48/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
26 AppendixE: BOPRegulatoryCompliance|
The original equipment manufacturer should be consulted regarding
replacement parts. If replacement parts are acquired from a non-
original equipment manufacturer, the parts shall be equivalent to orsuperior to the original equipment and be fully tested, design verified,
and supported by traceable documentation.
18.12.1 Planned Maintenance Program:
A planned maintenance system, with equipment identified, tasks
specified, and the time intervals between tasks stated, should be
employed on each rig. Records of maintenance performed and repairs
made should be retained on file at the rig site or readily available.
8/3/2019 Perkin Expert Report
49/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
27 AppendixF: ResponsibilityforBOPConfiguration|
AppendixF: ResponsibilityforBOPConfiguration
Information reviewed showed that BP was responsible for, and exercised
control over, the configuration, management, monitoring, testing and usage
of this BOP.32 Between 2001 and 2010, even though the BOP is part of the
rig and owned by Transocean, BP was the dominant force in its
configuration.33
Vastar, and its successor, BP, specified the configuration of the BOP,
participated in its design, and chose its components and control systems.34
Vastar, BPs predecessor:
Configured a 5-cavity BOP;
Specified a 30 second disconnect in connection with the Deadman
system; 35
Decided against equipping the HORIZON with an acoustic trigger, i.e.,
a remote control;36
Required certain adjustments be made by Cameron before accepting
the BOP into service after the Factory Acceptance Test37;
Specified the location of the MUX cables;38
Selected EDS-1 (activation of the BSRs only) instead of EDS-2
(activation of the CSR first, followed by the BSR) as the primary
emergency disconnect mode.39
The original contract with Transocean, specified the configuration of the BOP;
ten (10) years later, in September 2009, Amendment #38 to the contract,
BP again specified the BOP configuration.40 By Federal regulations and
industry standards, BP was responsible for the BOP. Under the CFRs, BP
was obligated to ensure proper configuration, testing, training and use of the
Subsea BOP equipment. See 30 CFR 250 400 et seq., cited; American
Petroleum Institute (API) Recommended Practices (RP) No. 53 or API RP
53.41 BP knew the importance of the BOP. BP repeatedly, post-blowout, said
that their well control plan was to rely on the BOP.42
With only one BSR, BP's Management knew that it was difficult to remove all
of the single points of failure ("SPOF"). In a Risk Assessment performed on
the HORIZON's BOP CS, in 2001, there was an indication that the final
shuttle valve, supplying the BSR with pressurized hydraulics, as well as the
BSR itself, represented a single point failure that accounted for 56% of the
8/3/2019 Perkin Expert Report
50/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
28 |
likelihood of the system to fail to perform an EDS.43 Studies had shown that
with the addition of a second BSR in the upper pipe ram cavity, the
probability of a blowout would be reduced in comparison to the three VBRspresent in most BOP configurations. Even knowing that, and knowing that
other rigs in the GoM had 2 BSRs,44 BP left only one BSR in HORIZONs BOP
configuration.
BP was responsible for calculating the Maximum Anticipated (Allowable)
Surface Pressure (MASP), a regulatory requirement relating to the BOP (30
CFR 250.446)45. Inexplicably, BP never properly utilized MASP in setting well
control policy or to determine safety risks (MASP is discussed in more detail
below).46
BPs Management did not adequately address the safety aspects of the BOP
configuration for the inherent risks associated with the Macondo well
design.47 In fact, according to BPs Risk Register for Macondo, non-
productive time (NPT) was the only risk associated with Macondos BOP.48
In addition, BPs Management spent considerable time/money to invent,
install, test and patent a digital BOP testing system.49 This proprietary
system had no effect on safety, but was designed solely to save money by
reducing non-productive time.50
In 2004, BPs Management decided to convert the BOP lower VBR to a Testram.51 A test ram will sustain pressures from above, i.e., during BOP
pressure testing, but not from the wellbore below the test ram. BP
spearheaded the decision and paid for the test ram conversion.52
...we (BP) drove the decision to install test rams
BPs Management also talked about the savings that this test ram conversion
would bring53, while simultaneously admitting that the decision reduces the
safety margin of the BOP.54 The test ram reduced redundancy, i.e., the
lower BOP stack went from three VBRs to two. By making the lower ram atest ram, BP violated its own well control policy which stated the "the
lowermost ram be preserved as a master component and only used to close
in the well when no other ram is available for this purpose."55 On the test
ram decision, BP analyzed the risks and concluded that lowering safety was
justified because of the monetary savings.56 Again, in 2008, BP recognized
that the test ram conversion would lower the safety profile.
8/3/2019 Perkin Expert Report
51/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
29 |
BPs Management modified the lower annular from a 10,000 psi rated
component to a 5,000 psi stripping annular.57
Cameron specifically warnedthat this particular BOP component should not be put into a situation where it
was exposed to greater than 5,000 psi58. There was no evidence that BP
went through any risk assessment prior to the change order59.
BP wants [stripper packer] on DEEPWATER HORIZON at all times.
While on location in 2007, the HORIZONs VBRs failed while attempting to
shut-in and seal-off the wellbore annulus. BPs Management, independent of
Transocean, decided to retain Wild Well Control, a third party vendor, to
perform a risk assessment of the HORIZONs BOP.60
BP was consideringwhether to upgrade the BOP. If BP were not the entity making the decisions,
the assessment would have been superfluous.
BP also had actual control over the HORIZONs BOP. BPs own policy
manuals required a certain BOP configuration,61 required industry best
practices,62 and required bridging documents between BP and Transocean.63
BP manuals specified that BP personnel must ensure that BPs well control
policies were implemented and followed by Transocean64 Well control
included many areas (for example, using a fluid column as the primary
barrier), one of which was the proper and appropriate use of the BOP.
65
On Macondo, BPs Management consistently made decisions regarding the
BOP. For example, a leak was discovered in a shuttle valve on the yellow
pod, it was placed in vent, i.e., inactive.66 BPs Management decided not to
pull the LMRP to fix the yellow pod,67 despite MMS requirements to do so.68
During drilling, someone accidentally hit the Joystick and stripped DP through
the upper annular, a non-stripping annular.69 Stripping is moving DP and its
Tool Joints, located on the ends of the DP, through the annular while closed.
On April 5, 2010, a stripping operation occurred through the upper annular70.
Later, pieces of rubber were found in the shaker, from Macondos flow
returns.71 On April 20, 2010, an actuation pressure of 1,900 psi was required
to affect a seal on the upper annular, when the normal setting was 1,500
psi.72
BPs Management knew that the annular had been subjected to repeated
activation, and knew frequent use of either or both annulars would cause
8/3/2019 Perkin Expert Report
52/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
30 |
accelerated element wear.73 Even after all of this, BP decided not to pull the
BOP to inspect and/or repair it.
BPs Management exercised control over BOP decisions even in the area of
maintenance. For example, in September of 2009, a BP audit team from
London, audited the HORIZON. BPs Audit Team, headed by Mr. Kevan
Davies and Mr. Norman Wong, concluded that 3,545 hours of maintenance
was required. This included open items that had not been closed out from
previous audits going back as far as 2005.
Many hours of overdue maintenance on Macondos BOP had yet to be
completed. Some of the BOP ram bodies had exceeded their five year re-
certification period. API 53 RP 18.10.1, 18.10.3, and 18.11.3 recommended
that BP follow OEM configured equipment manufacturer specifications. In
this case, according to Cameron, it meant re-certification every five years.
In spite of Camerons five year recommendation, including the BP audit
teams recommendations, BPs Management returned the rig to service in
just five (5) days with absolutely no changes to this BOP.
Mr. John Guide, the HORIZONs Well Team Leader, rather than reacting
constructively to the suggestion that maintenance was needed, instead
claimed that Mr. Wong, who was head of BPs audit team, was:
throwing [HORIZON] under the bus.
Mr. Guide put the HORIZON back into service in five days, he even refused to
meet and discuss the findings with BPs audit team. Mr. Cocales, with BP
engineering, who a Transocean rig manager described as inexperienced,74 did
not let the BP auditors back on the HORIZON for any further inspection. Mr.
Wongs supervisor sent an email suggesting Mr. Wong limit the audit teams
request for repair to 10 items or fewer items.
BPs Management should have enforced its own audit recommendations.
Instead, BP did nothing.
Before and up to the time of Macondos blowout on April 20, 2010, BPs
Management had no personnel systems and/or supervisory mechanisms in-
place to assure that open items from an audit process were taken care of,
and then, closed out. BPs audit systems utilized no process safety
management systems such as On-site Management Systems, Management-
of-Change and/or Risk Assessment.
8/3/2019 Perkin Expert Report
53/263
GreggS.Perkin,P.E.
EngineeringPartners
International
August26,2011 BLOWOUTPREVENTERMACONDO
31 |
Seven days before the Macondo disaster, BPs Management exercised more
control over BOP maintenance. BP told Transocean not to change the BOP
elastomers during the move to BPs Nile well after Macondo was finished.Transocean had a policy of changing the BOP elastomers between every job.
However, BPs Management decided not to change the elastomers between
jobs. Like so many of BPs Management decisions regarding this BOP, BP
reduced safety in an attempt to save time and money
BPs Management made all the important decisions regarding Macondos
BOP. How the BOP was configured, whether or not the BOP was upgraded,
how the BOP was tested and whether or not this BOP would come out of
service for maintenance and/or repair, all were managed and controlled by
BP. Over a 10-year period, BP did not require, suggest, or implement a
single improvement, or upgrade, that improved the shearing capability of the
blind shear rams.75 Every change made achieved less NPT and saved money.
8/3/2019 Perkin Expert Report
54/263
GreggS.Perkin,P.E.