Performing Operation Move and Completion Transactions in WIP_SPD

Embed Size (px)

Citation preview

  • 8/14/2019 Performing Operation Move and Completion Transactions in WIP_SPD

    1/17

    System Process DocumentPerforming Operation Move and Completion

    Transactions in WIP

    Department

    Responsibility/Role

    File Name 27599210.doc

    Revision

    Document Generation Date 14/01/2010 14:04:00

    Date Modified 1/14/2010 02:04:00 PM

    Last Changed by

    Status

    Performing Operation Move and Completion Transactions in WIPTrigger:

    Concept

    You can move assemblies within an operation or from one operation to the next; and backward

    and forward within the routing. Moving assemblies into the To Move, Reject, or Scrap

    intraoperation step of an operation completes those assemblies at that operation. You can move

    assemblies from any enabled intraoperation step - Queue, Run, To move, Reject, or Scrap - as

    required. Intraoperation steps are enabled using the Intraoperation Steps parameter.

    In this topic, you will use the Move Transactionspage to move assemblies in routing operations.

    Required Field(s) Comments

    Output - Result(s) Comments

    Additional Information

    Last changed on: 1/14/2010 02:04:00 PM Page 1

  • 8/14/2019 Performing Operation Move and Completion Transactions in WIP_SPD

    2/17

    System Process DocumentPerforming Operation Move and CompletionTransactions in WIP

    Procedure

    Step Action

    1. Begin by navigating to the Move Transactions page.

    Click the vertical scrollbar.

    Page 2 Last changed on: 1/14/2010 02:04:00 PM

  • 8/14/2019 Performing Operation Move and Completion Transactions in WIP_SPD

    3/17

    System Process DocumentPerforming Operation Move and Completion

    Transactions in WIP

    Step Action

    2. Click the Move Transactions link.

    Last changed on: 1/14/2010 02:04:00 PM Page 3

  • 8/14/2019 Performing Operation Move and Completion Transactions in WIP_SPD

    4/17

    System Process DocumentPerforming Operation Move and CompletionTransactions in WIP

    Step Action

    3. The Move Transactions page is used to perform move transactions for discrete

    jobs and schedules with routings. You can also perform move transactions for non-standard discrete jobs that have assemblies and routing references.

    Step Action

    4. You can search for records by selecting values in the Sales Order, Line,

    Assembly, and Job fields.

    Click in the Job field.

    Page 4 Last changed on: 1/14/2010 02:04:00 PM

  • 8/14/2019 Performing Operation Move and Completion Transactions in WIP_SPD

    5/17

    System Process DocumentPerforming Operation Move and Completion

    Transactions in WIP

    Step Action

    5. Enter the desired information into the Job field. Enter "1234".

    Last changed on: 1/14/2010 02:04:00 PM Page 5

  • 8/14/2019 Performing Operation Move and Completion Transactions in WIP_SPD

    6/17

    System Process DocumentPerforming Operation Move and CompletionTransactions in WIP

    Step Action

    6. Click in the Operations: From Sequence field.

    Step Action

    7. Transaction Type of Move is the default value. You can change this value afterenabling the From Operation Sequence field.

    Enter the desired information into the Operations: From Sequence field. Enter

    "30".

    Page 6 Last changed on: 1/14/2010 02:04:00 PM

  • 8/14/2019 Performing Operation Move and Completion Transactions in WIP_SPD

    7/17

    System Process DocumentPerforming Operation Move and Completion

    Transactions in WIP

    Step Action

    8. The default step value displays the step with a quality value.

    Click in the Operations: From Step field.

    Last changed on: 1/14/2010 02:04:00 PM Page 7

  • 8/14/2019 Performing Operation Move and Completion Transactions in WIP_SPD

    8/17

    System Process DocumentPerforming Operation Move and CompletionTransactions in WIP

    Step Action

    9. The next operation sequence is the default value, it can be changed.

    Page 8 Last changed on: 1/14/2010 02:04:00 PM

  • 8/14/2019 Performing Operation Move and Completion Transactions in WIP_SPD

    9/17

    System Process DocumentPerforming Operation Move and Completion

    Transactions in WIP

    Step Action

    10. Click in the Operations: To Step field.

    Step Action

    11. Enter the desired information into the Operations: To Step field. Enter "Queue".

    Last changed on: 1/14/2010 02:04:00 PM Page 9

  • 8/14/2019 Performing Operation Move and Completion Transactions in WIP_SPD

    10/17

    System Process DocumentPerforming Operation Move and CompletionTransactions in WIP

    Step Action

    12. This operation will be completed when the transaction is saved. The assemblies arenot completed when moving assemblies from the To Move, Scrap, or Reject

    intraoperation steps of one operationto the Queue or Run steps the subsequent

    operation

    Page 10 Last changed on: 1/14/2010 02:04:00 PM

  • 8/14/2019 Performing Operation Move and Completion Transactions in WIP_SPD

    11/17

    System Process DocumentPerforming Operation Move and Completion

    Transactions in WIP

    Step Action

    13. You can accept the unit of measure, quantity, and date defaults; or change these

    values.

    Click the Save button.

    Step Action

    14. Click in the Job field.

    Last changed on: 1/14/2010 02:04:00 PM Page 11

  • 8/14/2019 Performing Operation Move and Completion Transactions in WIP_SPD

    12/17

    System Process DocumentPerforming Operation Move and CompletionTransactions in WIP

    Step Action

    15. Enter the desired information into the Job field. Enter "1234".

    Page 12 Last changed on: 1/14/2010 02:04:00 PM

  • 8/14/2019 Performing Operation Move and Completion Transactions in WIP_SPD

    13/17

    System Process DocumentPerforming Operation Move and Completion

    Transactions in WIP

    Step Action

    16. Click in the Operations: From Sequence field.

    Step Action

    17. Enter the desired information into the Operations: From Sequence field. Enter"40".

    Last changed on: 1/14/2010 02:04:00 PM Page 13

  • 8/14/2019 Performing Operation Move and Completion Transactions in WIP_SPD

    14/17

    System Process DocumentPerforming Operation Move and CompletionTransactions in WIP

    Step Action

    18. Click in the Operations: From Step field.

    Page 14 Last changed on: 1/14/2010 02:04:00 PM

  • 8/14/2019 Performing Operation Move and Completion Transactions in WIP_SPD

    15/17

    System Process DocumentPerforming Operation Move and Completion

    Transactions in WIP

    Step Action

    19. Enter the desired information into the Operations: From Step field. Enter

    "Queue".

    Step Action

    20. The subsequent operation displays as the default value.

    Click in the Operations: To Step field.

    Last changed on: 1/14/2010 02:04:00 PM Page 15

  • 8/14/2019 Performing Operation Move and Completion Transactions in WIP_SPD

    16/17

    System Process DocumentPerforming Operation Move and CompletionTransactions in WIP

    Step Action

    21. Enter the desired information into the Operations: To Step field. Enter "To

    move".

    Page 16 Last changed on: 1/14/2010 02:04:00 PM

  • 8/14/2019 Performing Operation Move and Completion Transactions in WIP_SPD

    17/17

    System Process DocumentPerforming Operation Move and Completion

    Transactions in WIP

    Step Action

    22. Assemblies are complete when you move them from the Queue or Run

    intraoperation steps of an operationtothe To Move, Scrap or Reject steps of a subsequent operation.

    Click the Save button.

    Step Action

    23. You have completed the Performing Operation Move and Completion Transactions

    in WIP procedure.

    End of Procedure.