View
23
Download
0
Embed Size (px)
DESCRIPTION
This presentation was delivered by Dr. Gunter Zeitlow on 29 July 2015 at the ADB headquarters in Manila. This was a joint knowledge sharing session of the Central and West Asia Transport and Communications Division, Operations Network Group and the Transport Sector Group.
Citation preview
1
e-mail: [email protected]
http://www.zietlow.com
http://www.performance-based-road-contracts.com
Dr. Gunter Zietlow
Road Asset Management and
Performance Based Contracts
Asian Development Bank (ADB)
Manila, July 29th 2015
2
Overview of Presentation (1)
Introduction
What is Good Road Asset Management?
PBC concept Background
Characteristics
Brief History
Benefits
Performance standards
Risks
Performance monitoring
Payment and Incentive Systems
3
Overview of Presentation (2)
Key external and internal factors associated with the implementation
of PBCs
Framework (Legal, Financial, Institutional)
Role and capacity of road agencies
Role and capacity of consulting and contracting industry
4
Overview of Presentation (4)
Implementation experiences in developed and developing countries
Lessons learned
Role of financing institutions
5
Introduction
6
Source: Unknown
7
Road Conditions in the 1980s
In spite of their importance, roads in many developing countries are still
under-financed, poorly managed and
badly maintained.
Normally, only 20- 40% of the amounts required is being spent on routine and
periodic maintenance.
1/3 of the main road networks are in good
1/3 in regular and 1/3 in poor condition.
8
Importance of Timely
Maintenance
When roads are in poor condition every $ saved in road conservation will cost:
$ 2 to road users in additional vehicle operating costs and
$ 2 to the road administration (or the tax payer) in reconstruction
and rehabilitation costs.
9
What is Good Road Asset
Management?
10
Road Asset Management (RAM)
Good Road Asset Management is a systematic process of maintaining,
upgrading, expanding and operating
road, bridge and road side assets, using
engineering principles with sound
business practice to effectively and
efficiently allocate and utilize resources
for the provision of well defined levels of
service to satisfy public expectations.
13
In the long run
the best way of effectively and
efficiently manage road related assets
is through Performance Based
Contracting (PBC)
14
PBC Concept
15
Performance Based Road Contracts
Performance Contract (Western Australia)
Asset Management Contract (USA)
Performance-Specified Maintenance Contract (Australia, New Zealand)
Contract for Rehabilitation and Maintenance (Argentina, Brazil)
Area Maintenance Contract (Finland, Ontario/Canada)
Managing Agent Contract (UK)
Output and Performance Road Contract (World Bank)
16
Type of Contracts
Method based contract Unit rates for work items
Payments are based on quantity of completed and measured work
Pure performance contract (PBC) Performance Standards or Service Quality
Levels
Fixed monthly payments if service quality levels are complied with
Hybrid contract (PBC) Mixture of method based contract and
performance contract
17
Characteristics of PBC
Performance or Service Levels define the minimum conditions of road, bridge and traffic
assets as well as the management and operation
of the assets during the entire contract period,
leaving it mainly to the contractor as to how to
achieve them.
Lump sum payments are made periodically (mainly monthly) and might be adjusted in
accordance with the change of certain factors,
like inflation or unexpected increases of traffic
volume.
Major emergency, rehabilitation and improvement works might be paid based on unit prices for
works agreed case by case.
18
Characteristics of PBC (2)
Deductions are being made for non-compliance with terms and conditions of contract, especially
with respect to the service levels.
Duration of contracts should at least include one periodic maintenance cycle (4-5 years for gravel
roads and 8-12 years for bituminous roads). Pure
routine maintenance contracts are normally
between 1-3 years. Pilot contracts may be of
shorter duration.
19
Characteristics of PBC (3)
Complexity
Contract duration in years
2 4 6 12 10 8 14
Routine
maintenance
Routine and periodic
maintenance
Construction, periodic and
routine maintenance
Up to 30 years
20
Characteristics of PBC (4)
Duration of contract
Relationship of required skills as a function
of the duration of PBC
Typical RAM skills Prediction of asset deterioration
Quality assurance management
Typical contractor skills
Skills
21
Characteristics of PBC (5)
Road Network
Management and Operation
Routine
Maintenance
Periodic
Maintenance
Rehabilitation Improvements Emergencies
Potential Scope of Services and Works
Winter
Services
22
Characteristics of PBC (6) Contractual Relationship Full PBC
Client/
Road Administration
Consultant/Contractor
Full Performance Contract
Audit
by Client
or External
Auditor
23
Characteristics of PBC (7) Contractual Relationship with Hybrid Type PBC
Client/
Road Administration
Road Manager
Engineer
New Type
Contractor
Performance or
Conventional Contract Hybrid type PBC
Inspection of Compliance with Service Levels
Supervision for Admeasured Work
Audit
by Client
or External
Auditor
24
Typical Implementation of PBC
Options
A. Paved roads (corridor or network)
1. Pure routine maintenance
a) Off-road maintenance (1-3 years)
b) All routine maintenance, except for risky items (1-5
years)
c) All routine maintenance (4-10 years)
2. Rehabilitation, backlog maintenance, routine
maintenance, winter services, periodic
maintenance, Emergencies
a) Only routine maintenance paid on lump-sum (5-
10years), rest on unit prices
b) Paid on lump-sum (10-30 years)
25
Typical Implementation of PBC
B. Unpaved roads (corridor or network)
1. Pure routine maintenance
a) Off-road maintenance (1-3 years)
b) All routine maintenance (1-4) years)
2. Rehabilitation, backlog maintenance, routine
maintenance, winter services, periodic
maintenance, eEmergencies
a) Only routine maintenance paid on lump-sum (4-5
years)
26
Brief History of PBC
1988 British Columbia, Canada
1990 Argentina
1994-98 Colombia, Uruguay, Chile, Brazil, Peru
1995 Sydney, Australia, Estonia
1996 Virginia, USA
1998 New Zealand, Finland
2001 Chad, Zambia, England, India, Spain
.............
Drivers: efficiency and effectiveness
27
Source: World Bank, 2006
28
Benefits of PBC (1)
Road Agency Reduces maintenance cost (based on
the same level of service!)
Avoids frequent claims and contract amendments to increase quantities of works by contractor
Avoids road rehabilitation
Improves quality of works
Improves control and enforcement of effective road quality service levels
29
Benefits of PBC (2)
Road Users
Provides better and safer roads with consistent conditions
Reduces road user cost
Consultants and Contractors
Guarantees workload over longer period
Provides potential for increased margins
Opens excellent opportunities for business growth
30
Reported Savings by Introducing
Performance Contracts
New Zealand: 15-22%
Australia: 10-35%
Brazil: 15%
USA: 10-18%
Finland: 18%
Alberta, Canada: 20%
Savings are reported against traditional unit price
contracts
In addition, quality improvements were reported
31
Development of Road Maintenance
Cost in Sydney, Australia
0 10 20 30 40 50 60 70
Time (months from June 1991)
0
20
40
60
80
100% 1991 Rates
RTA
SOR Contract
Transfield ContractPerformance Specified Road Maintenance Contract
(Team of the Roads and Traffic Authority of New South Wales)
Private contractor
32
Some Reasons for Reduction in Road
Maintenance Cost
Drivers of savings: Incentives / competition / long-term management
Modern management and work procedures
Increased labour productivity
Total life cycle costing
Just-in-time maintenance
Better use of latest technologies
33
Performance / Service Levels
Objectives
To satisfy the road user accessibility
comfort
travel speed
safety
To minimize total system cost (cost to road users and agency life-cycle cost of assets)
To minimize environmental impacts
34
Service Levels and Response Times
Fulfil objective
Clearly defined
Objectively measurable
Affordable
In compliance with the law (law of public roads, ordinance on maintenance and
protection of roads)
35
Relationship between Objectives
and Service Levels
Improve road safety: Potholes not bigger than 15cm in diameter, ruts 0.4, etc.
Preserve road asset value: Cracks not wider than 3mm, potholes not bigger than 15cm, obstruction of drainage channels 50 km/hr
............
36
Typical Service Levels and Response Times
for Paved Roads
Typical Traffic Volumes
(Vehicles/day)
Less
than 250
250 1000
1000 -
5000
5000 -
plus
Potholes (Max Dia of any single
pothole)
400mm 300mm 200mm 100mm
Repair of potholes (Response time) 28 days 28 days 14 days 7 days
Cleanliness of pavement surface
and shoulders response time for
safety related matters (Response
time)
8 hrs 4 hrs 2 hrs 1 hr
World Bank
37
In-house
Mainte-
nance
Outsourcing
Specific
Maintenance
Works
Performance-Based
Road Management and
Maintenance Contracts
Long-term Road
Concessions (BFOT)
Short-
term
Medium-
term
Long-
term
Risk to contractor increases
Risk to road agency decreases
Distribution of Risk
38
Performance Monitoring
Contractors self-control system with verification by client
Joint inspections by client and contractor at certain time intervals
Road user complaints
39
Payment and Incentive Systems (1)
Fixed periodic payments for scope of works and services contracted under performance or service levels, mainly for routine maintenance works.
Payments based on unit prices and quantities of work performed typically for risky work items such as Emergency and Unforeseen Works and often for periodic maintenance and rehabilitation works as well.
40
Payment and Incentive Systems (2)
Periodic fixed payments to be reduced if contractor does not comply with the performance service levels
Contract to be terminated prematurely for underperformance
Some contracts include bonus payments
Payment and incentive systems vary widely from one country to another
41
Key External and Internal Factors
Associated with the Implementation of
PBCs
42
Framework
Legal Multi-year contracting
Road maintenance regulations
Financial Sufficient funding
Multi-year financing
Dedicated funds
Institutional Separation of client and contractor
Privatization of road maintenance
Competition between contractors
43
Role and Capacity of Road Agency
Role Manage a road asset management
Implementation and development of PBCs
Management and Supervision of PBCs
Capacity Understanding of PBC concept
Change of attitudes
Additional skills
Training and coaching
44
Role and Capacity of Contractors
Role Long-term road asset management
Proactive
Services to the road user
Capacity Understanding of PBC concept
Change of attitudes
New skills (road asset management)
Lack of sufficiently qualified contractors
Training and coaching
45
Role and Capacity of Consultants
Role Promoter
Designer
Supervisor / Manager
Trainer / coach
Capacity Understanding of PBC concept
Change of attitudes
New skills
Training and coaching
Lack of sufficiently qualified consultants
46
Implementation Experiences
47
Complexity of PBCs
Complexity
Contract duration in years
2 4 6 12 10 8 14
Estonia 1995
Estonia 2008
Serbia 2004
New Zealand 1998
Ukraine 2014
US 1997
MAC UK 2004
Finland1998
Croatia 2015
Finland 2008
Birmingham UK
27 years
Micro enterprieses
Latin America
China
Bangladesh
Argentina 1994 (RMC)
Punjab India 2012
Future Malaysia 2016
Malaysia 2000
54
Estonia
1995 the Estonian Road Administration (ERA) launched two pilot performance contracts for
routine road maintenance for national roads
1995 to 2000 - ERA tested several one-year and two-year contracts, including winter
maintenance
Since 2000 several 5-year contracts have been awarded
Since 2006 ERA moved to 7-year contracts
As of 2008 100% of ERAs road network (16500 km, mainly gravel roads) is maintained under
hybrid type performance contracts
58
Asian Countries (1)
India 2013, Tamil Nadu, WB, 5-year PBCs with a total
of 640 km
2009, Andhra Pradesh, WB, 3 OPRCs active , 34 OPRCs implemented or under preparation (10000 km)
2012, Punjab, WB, 10- year OPRC, 203 km
Nepal 2003, WB, 2-year PMBC, 114 km
2005, WB, four 5-year PMBC, about 50 km each
2007, ADB, 5-year PMBC, 77 km
Sri Lanka 2009 , eight 1-year routine maintenance PBCs
2010, two 2-year routine maintenance PBCs
59
Asian Countries (2)
Malaysia 2000, 6 area PBCs for all national roads for 15
years each, in the process of prolongation
Performance based toll road concessions, 1800 km, program started in 1983
Vietnam
2009, WB, one 3-year PBC, 300 km of national highway
China
2009, ADB, 4-year simple PBCs on 1300 km of rural roads with local community groups
(Yunnan Province)
60
Asian Countries (3)
Afghanistan 2006, EC, one 3-year PBC 140 km, routine + winter
maintenance paid on lump sum
2008, 5 PBCs on 1523 km of national and regional roads; 2011 two more PBCs on 250 km
Tajikistan Two 3-year PBCs with initial repairs (10km) each 75 km
long, lump sum for routine and winter maintenance
Indonesia 2010, two 3-year PBCs, 21 and 11 km, basically
rehabilitation contracts
Malaysia 2000, 6 area-wide 15-year PBCs covering all national
roads, only routine maintenance paid on lump sum
66
Lessons Learned (1)
Highly positive in developed countries
Mainly positive in developing countries with few teething problems
Progress depends on the attitude of the road administration, the ability of consultants and
contractors to implement PBC as well as the
political backing of PBC
Substantial cost reductions have been realized with few exceptions
Road conditions have improved
PBC supports efforts to secure long-term financing of road maintenance
67
Lessons Learned (2)
Pilot projects are the best way to implement performance contracts
Performance Contracts have to be tailored to each specific situation
Preferably roads should be in maintainable conditions
Qualification of contractors and supervisory staff of the client is key to
success. To be reflected is PBC design
Risks shall be assigned to the party that can best bear and manage the risk
68
Lessons Learned (3)
Additional lessons learned in developing
countries
Project preparations requires consultants which have experiences in implementing
PBCs in similar environments Right mix of unit price items and performance items
Effective monitoring system
Effective penalty system
A gradual implementation of PBCs seems to be more sustainable
Local contractors should be favoured
69
Lessons Learned (4)
History of road construction and maintenance, a detailed condition survey
and cost estimate needs to be made
available to tenderers
Training and coaching of client and contractors during the implementation
phase helps to adjust to the new
contracting system
Subcontractors need training as well
Overloading problems need to be taken care off
70
Lessons Learned (5)
Payment reductions for non-compliance shall be applied strictly and shall be high
enough to make the contractor to comply
Escalation of payment reductions shall be foreseen for continued non-compliance
Once under PBC roads should remain under PBC
PBCs are not a silver bullet. Conditions need to be conducive!
71
Role of Financing Institutions (1)
International Finance Institutions (ADB, WB, IDB, EBRD) have promoted and
financed performance based road
contracts for more than 15 years
Supporting the institutional and financial reform process
Supporting the Asset Management approach
Support a stepwise and sustainable implementation of PBCs
72
Role of Financing Institutions (2)
Financing of consulting services: awareness seminars, training programs,
feasibility studies, contract design and
bidding process, training and coaching
during project implementation
Financing of works and services
Providing payment guarantees to PBC contractors
74
75
76
Upcoming work
Reference note on Performance Based Road Maintenance Contracts
Analysis of RAM practices in CAREC countries
Compendium of good practices on RAM in CAREC countries
Hands-on project support in CAREC countries
For details contact Ko Sakamoto (CWTC) at