DIVISION -0- Page 1 of 15 Scope of Work Typical-Occupied Office Space Prepare all surfaces to receive paint in all hallway corridors, doors and frames, lobby and offices as listed in the Per Room List Protect all surfaces not to receive paint, including burgundy rubber cove base, re-install components, furniture and cubicle walls, if necessary. Contractor will be responsible for moving and replacing office furniture if needed to access areas for painting. All work must be done after 5 PM and before 7 AM Exterior work may be done during the day with proper sidewalk clearances and front door access Work may be done on weekends, with prior approval 60 calendar days to complete work COVE BASE (apx 850 linear feet, contractor to verify) Remove all lilac (purple) baseboard as indicated and replace with new Install cove base at all locations where the purple has been removed and all locations that currently doesn’t have any. Replacement Color: Johnsonite DC 85 4 x 4 Toe, Burgundy VERTICAL VINYL SHEET GOODS OPTION 1: Large conference room, wainscoting to be covered with vertical vinyl sheet goods Prep wall area as specified for listed product Product is InPro Corporation, Interior and Exterior Architectural Products (or equal) www.inprocorp.com Type: Prism Solid Surface Material is an acrylic modified polyester, combining the depth of polyester with the flexibility of acrylic Color selection samples to be provided to the housing authority for final selection OPTION 2: Deductive Option 2: wainscoting to be covered with vertical laminate Prep wall area as specified for vertical laminate Color selection samples to be provided to the housing authority for final selection Wilson Art (or equal) Choice of Premium Laminate or HD Laminate

Per Room List COVE BASE (apx 850 linear feet, contractor

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Per Room List COVE BASE (apx 850 linear feet, contractor

DIVISION -0- Page 1 of 15

Scope of Work

Typical-Occupied Office Space

• Prepare all surfaces to receive paint in all hallway corridors, doors and frames, lobby and offices as listed in the Per Room List

• Protect all surfaces not to receive paint, including burgundy rubber cove base, re-install components, furniture and cubicle walls, if necessary.

• Contractor will be responsible for moving and replacing office furniture if needed to access areas for painting.

• All work must be done after 5 PM and before 7 AM • Exterior work may be done during the day with proper sidewalk clearances

and front door access • Work may be done on weekends, with prior approval • 60 calendar days to complete work

COVE BASE (apx 850 linear feet, contractor to verify)

• Remove all lilac (purple) baseboard as indicated and replace with new • Install cove base at all locations where the purple has been removed and

all locations that currently doesn’t have any. Replacement Color: Johnsonite DC 85 4 x 4 Toe, Burgundy

VERTICAL VINYL SHEET GOODS OPTION 1:

• Large conference room, wainscoting to be covered with vertical vinyl sheet goods

• Prep wall area as specified for listed product • Product is InPro Corporation, Interior and Exterior Architectural Products (or

equal) www.inprocorp.com • Type: Prism Solid Surface • Material is an acrylic modified polyester, combining the depth of polyester

with the flexibility of acrylic • Color selection samples to be provided to the housing authority for final

selection OPTION 2:

• Deductive Option 2: wainscoting to be covered with vertical laminate • Prep wall area as specified for vertical laminate • Color selection samples to be provided to the housing authority for final

selection • Wilson Art (or equal)

Choice of Premium Laminate or HD Laminate

Page 2: Per Room List COVE BASE (apx 850 linear feet, contractor

DIVISION -0- Page 2 of 15

Typical-Occupied Building-EXTERIOR • Preparation of stucco surfaces where the paint is currently “green”,

preparation should include but not be limited to washing and cleaning, filling of nail holes, cracks and joints, with putty, plaster or other approved fillers, color match exterior paint to match the awning on the front of the building, “Navy blue”.

• Preparation for repainting the roof flashing that over hangs the roof line where it is currently green”, preparation should include but not be limited to washing and cleaning, smoothing surfaces, using sandpaper, brushes or steel wool, for the surface to accept the new exterior paint color, which will match the “navy blue”.

• Preparation for repainting the concrete on the south and east exterior walls, preparation should include but not limited to washing and cleaning, smoothing surfaces to accept the new exterior paint color, using appropriate paint materials for concrete substrate. Manufacturer and final color selection will be made after submittal and color wheel has been provided to EHA’s representative for selection, but will be similar in color to the existing.

Paint Schedule - Low VOC: Provide materials that comply with VOC limits of authorities having jurisdiction

INTERIOR PAINT • Primer shall be the color of paint to be used • Match texture to existing connecting area • Door Frames shall be semi-gloss • Walls shall be semi-gloss

• EHA Off White Paint

Master Painter Paint Semi-Gloss (or Equal) Rodda Paint 4147EM EV08H12941 Off White/Standard 5436015

• Master Painter Paint Semi-Gloss (or Equal)

Rodda Paint 1) Color wheel shall be provided for selected office accent wall color

selection 2) “Lettering” in the large conference room “Everett Housing Authority” shall

match the front awning color of Navy Blue. EHA representative will approve final color selection for the Navy Blue.

• Master Painter Paint Semi-Gloss (or Equal)

Rodda Paint Gray:

Page 3: Per Room List COVE BASE (apx 850 linear feet, contractor

DIVISION -0- Page 3 of 15

Contractor to provide color samples of Master Painter Paint Semi-Gloss Rodda Paint (or Equal) for housing authority selection in multiple shades of “gray”. The housing authority will select 6 shades for sample boards. Contractor to provide 3’x3’ sample boards of the six (6) shades for final choice of three (3) colors. When the three choices have been selected, EHA representative will provide layout of where each color will be used.

EXTERIOR PAINT

• Stucco ReVyvit Solution 1 (or Equal) a. Coatings-

1. Weatherlastic Smooth (an elastomeric coating), (preferred method) 2. Demandit (a high performance acrylic paint in smooth and sanded)

and 3. HDP (a hydrophobic paint that repels water

• Roof Flashing

Contractor shall verify the type of flashing, metal, aluminum, etc for choosing the correct type of method and paint to use to received desired results. 1) Metal surfaces can be painted with various types of paints depending on

the type of metal. 2) If Aluminum, a water based acrylic paint should be used.

• Concrete (south and east walls)

Contractor shall provide to the housing authority samples of appropriate type of materials that should be used on the exterior concrete on the south and east walls for new paint. Manufacturer and final color selection will be made after submittal and color wheel has been provided to EHA’s representative for selection, but will be similar in color to the existing.

• Color is to match the awning on the front of the building, navy blue, EHA representative will give final approval upon sample color(s) provided.

Approved Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: 1. Benjamin Moore & Company 2. Cloverdale Paint 3. Kelly-Moore Paint 4. Park Paint 5. Rodda Paint 6. Sherman-Williams

Page 4: Per Room List COVE BASE (apx 850 linear feet, contractor

DIVISION -0- Page 4 of 15

TYPICAL FOR EXTERIOR AND INTERIOR PAINTING Section includes surface preparation and the application of paint systems on interior substrates. Interior Surfaces preparation for gypsum board, wood and metal, steel and exterior dryvit system. 1. Comply with manufacturer’s written instructions and recommendations in the

“MPI Manual” applicable to substrates indicated. 2. Remove hardware, covers, plates, pictures, clocks, plaques, first aid kits and fire

extinguishers and similar items already in place that are removable and are not to be painted.

a. Only reinstall the hardware, covers, plates, first aid kits and fire

extinguishers, all other items should be turned into the housing authority representative for storage.

b. After completing painting operations, use workers skilled in the trades involved to reinstall items that were removed. Remove surface-applied protection.

3. Clean substrates of substances that could impair bond of paints, including dust,

dirt, oil, grease, and incompatible paints and encapsulants.

a. Remove incompatible primers and re-prime substrate with compatible primers or apply tie coat as required to produce paint systems indicated.

b. At existing metal doors and frames, lightly sand and prep metal for new paint adhesion.

4. Steel substrates: Remove rust, loose mill scale, and shop primer, if any. Clean

using methods recommended in writing by paint manufacturer. 5. Gypsum Board Substrates:

a. Verify the finishing compound is sanded smooth. b. Repair molly bolt holes, nail holes and cracks.

6. Wood Substrates

a. Sand surfaces that will be exposed to view and dust off c. Prime edges, ends, faces, undersides and backsides of wood

Application 1. Apply paints according to manufacturer’s written instructions and to

recommendations in “MPI Manual”.

Page 5: Per Room List COVE BASE (apx 850 linear feet, contractor

DIVISION -0- Page 5 of 15

a. Use applicators and techniques suited for paint and substrate indicated. b. Paint surfaces behind moveable equipment and furniture same as similar

exposed surfaces. c. Paint front and backsides of access panels, removable or hinged covers,

and similar hinged items to match exposed surfaces. d. Apply paints to produce surface films without cloudiness, spotting,

holidays, alps, brush marks, roller tracking, runs, sags, ropiness, or other surface imperfections. Cut in sharp lines and color breaks.

Cleaning and Protection 1. At end of each workday, remove rubbish, empty cans, rags, and other

discarded materials from the Project Site. 2. After completing paint application, clean spattered surfaces. Remove spattered

paints by washing, scraping, or other methods. Do no scratch or damage adjacent finished surfaces.

3. Protect work of other trades against damage from paint application. Correct damage to work of other trades by cleaning, repairing, replacing, and refinishing, as approved by Owner’s representative and leave in an undamaged condition.

4. At completion of construction activities, the EHA representative will conduct a walk thru with the selected contractor and create a punch-list for any touch up, restoring damaged or defaced painted surfaces before accepting the project as completed.

Maintenance Materials Submittals 1. Furnish extra materials from the same product run, that match products, installed

and that are packaged with protective covering for storage and identified with labels describing contents.

a. Paint: 5 percent, but not less than 1 gallon of each material and color applied.

Delivery, Storage and Handling 1. Store materials not in use in tightly covered containers in well-ventilated areas

with ambient temperature continuously maintained.

a. Maintenance containers in clean condition, free of foreign materials and residue.

b. Remove rags and waste from storage area daily. Field Conditions 1. Apply paints only when temperature of surfaces to be painted and ambient air

temperatures are between 50 and 95 deg F (10 and 35 deg C) 2. Do not apply paints when relative humidity exceeds 85 percent; as temperatures

less than 5 deg F (3 deg C) above the dew point; or to damp or wet surfaces.

Page 6: Per Room List COVE BASE (apx 850 linear feet, contractor

DIVISION -0- Page 6 of 15

PER ROOM LIST

Room 100-Lobby (includes the front conference room) • Remove and replace cove base • Room 100-A Prime and paint door frame • Clean and Prep, prime, texture as necessary and paint all walls

Office 102 (Teena’s office) • Patch holes as necessary • Paint office EHA off white except east wall will be accent color • Provide selected paint supplier’s color wheel for selection

Office 103 (Paula’s office)

• Prep and paint paneling EHA off white • Finish should be similar to Office 104

Office 104 • Nothing

Office 105 (Jill’s office) • Repair crack under window • Match existing color and paint as necessary

Office 106 (Wendy A’s office) • Touch up and repair paint under window (match existing) • Touch up and repair paint behind door

Office 107 • Nothing

Office 108 (Chris’s office) • Move furniture to be able to prep and paint all walls • Patch nail holes in north east corner • Patch nail holes above window • Remove hanging light fixture and return to EHA designated staff • Paint office EHA off white

Room 110 (Storage) • This will be converted by others to a hall way, • Clean and prep, patch, prime, texture as necessary and paint all walls • Remove and replace cove base

Room 112 (Large conference room) • Option 1: Installation of vertical vinyl sheet goods as specified on page 1 of

this section • Remove chair rail and cove base

Page 7: Per Room List COVE BASE (apx 850 linear feet, contractor

DIVISION -0- Page 7 of 15

• Install vertical vinyl sheet goods to the chair rail height, per manufacturer’s specification, contractor to provide color sample sheet for final color selection, this should include the trims, which could consist of top cap, vertical divider bar, inside corner, outside corner, wall base.

• Remove, prep and paint letters on east wall, EVERETT HOUSING AUTHORITY, paint. Color will be Navy Blue, match awning on front of building. EHA representative to approve final color match. Reinstall in same location

• Remove white board and reinstall after painting • Clean and prep, prime and texture as necessary and paint all walls above

the vertical vinyl sheeting top cap. • Deductive Alternate Option 2: Retain the chair rail and cove base, clean

and prep the wainscoting area for vertical laminate • Deductive Alternate Option 3: Retain the chair rail and cove base, clean,

prep, prime and texture as necessary and repaint the wainscoting. Room 113

• Nothing Room 114 (Postage/copy room)

• Repair and paint molly bolt holes, multiple holes to be patched behind copy machine.

• Patch 15X20 sheet rock above electrical box • Clean and prep, prime and texture as necessary and paint the room EHA off

white Room 115 (Janitorial Closet)

• Clean and prep, patch, prime and texture as necessary and paint walls EHA Off white

• Paint door and door frames EHA off white Room 133 (Breakroom)

• Paint north section of wall to match existing paint above windows • Hang bulletin boards per owner directions • Clean, prep and paint door that leads to garage (match existing)

Room 134 (Stairs/hallway to breakroom) • Patch and repair all holes • Clean and prep, patch, prime and texture as necessary and paint walls EHA

Off White • Clean, prep and paint to match staff restroom doors and frames Clean,

prep and paint sliding pocket door to match hallway. (both sides) Copy Area 136 (NE Corner Cubicle and hallway)

• Remove and patch multiple molly bolt anchor holes • Clean and Prep, prime, texture, and paint wall and paint conduit to match

Entry Area 137 (Stairwell 138) • Clean and Prep, patch, prime and texture as necessary and paint walls

Page 8: Per Room List COVE BASE (apx 850 linear feet, contractor

DIVISION -0- Page 8 of 15

Hallway 1 • Prime and paint 2X4 supports for printer table (black) • Clean and prep, patch, prime and texture as necessary and paint • Remove molly bolt anchors (4 existing behind emergency cabinet), patch,

prime, texture and paint • Repair dent under window on wall outside of office 104 • Paint conduit to match wall color • Remove and replace cove base, install new cove base

Hallway 2 • Clean and Prep, patch, prime above “band” and texture and paint wall • Clean, prep and paint support columns to match wall/or contrasting color • Paint above work stations 1 and 5, prep as necessary to avoid paint landing

on work stations • Paint walls behind filing cabinets • Clean, repair and paint as needed • Paint the outside of room 109 • Remove all hooks, repair holes and paint • Install new cove base

Hallway 3 • Clean scuffs • Clean and prep, patch, prime above “band” and texture and paint walls • Install new cove base

Hallway 4 • Clean and prep, prime and texture as necessary and paint • Clean, prep and paint support columns to match wall/or contract color • Install blank cover plates to cover old thermostat holes • Remove and install new cove base

Hallway 5 • Prime and paint 2 door frames, one is door to lobby and the other splits the

hallway • Clean, repair, prime, texture and paint pocket door (see also Room 134) • Repair “Z” shaped crack above door • Clean and prep, patch, prime and texture as necessary and paint walls • Remove and install new cove base

Hallway 6 • Clean and prep and paint walls • Install new cove base

Women’s room (Staff)

Page 9: Per Room List COVE BASE (apx 850 linear feet, contractor

DIVISION -0- Page 9 of 15

• Clean and prep the restroom doors (inside and outside doors (2)) and paint EHA Off White

• Clean, repair, prime, texture and paint EHA Off White • Remove, clean, paint to match and reinstall bathroom vents

Men’s room (Staff) • Clean and prep the restroom doors and paint EHA Off White • Clean, repair, prime, texture and paint EHA Off White • Remove, clean, paint to match and reinstall bathroom vents

Public Restrooms in lobby area (Men’s and Women’s) • Clean and prep the restroom doors and paint EHA Off White • Remove, clean, paint to match and reinstall bathroom vents

Contractor shall verify all measurements

Page 10: Per Room List COVE BASE (apx 850 linear feet, contractor

DIVISION -0- Page 10 of 15

P A C I F I C A V E N U E

COLBY AVENUE

Page 11: Per Room List COVE BASE (apx 850 linear feet, contractor

DIVISION -0- Page 11 of 15

Page 12: Per Room List COVE BASE (apx 850 linear feet, contractor

DIVISION -0- Page 12 of 15

Page 13: Per Room List COVE BASE (apx 850 linear feet, contractor

DIVISION -0- Page 13 of 15

3107

CO

LBY

AV

ENUE

(Cor

ner o

f Pa

cific

Ave

nue

and

Col

by

Ave

nue)

A

ll a

rea

s (st

ucco

and

met

al r

oof f

lash

ing)

tha

t are

cur

rent

ly g

reen

will

have

the

new

co

lor m

atc

hing

the

aw

ning

whi

ch is

loca

ted

on

the

Col

by

Ave

nue

side.

Page 14: Per Room List COVE BASE (apx 850 linear feet, contractor

DIVISION -0- Page 14 of 15

Page 15: Per Room List COVE BASE (apx 850 linear feet, contractor

DIVISION -0- Page 15 of 15