PEDESTRIAN SAFETY & CONNECTIVITY: KEY ROUTES & INTERSECTIONS
5TH AVENUE
SPRING AVENUE
N
LEGENDPedestrian / School Walk Route(Existing Sidewalk/Path)Pedestrian / School Walk Route(Existing Sidewalk Gap)Review Pedestrian CrossingHigh-Activity Pedestrian Zone
Boecker Lot
East Burlington Lot
Lower Burlington Lot
Parkview Lot
Washington Jr. High School
Water Tower West
Kroehler Lot
Upper Burlington Loto
NORTH AVENUE
DuPage Children’sMuseum
WA
SHIN
GTO
N S
TREE
T
CEN
TER
STR
EET
ELLS
WO
RTH
STR
EET
BR
AIN
AR
D S
TREE
T
LOO
MIS
STR
EET
WR
IGH
T ST
REE
T
5TH AVENUE
4TH AVENUE
SLEI
GH
T ST
REE
T
SCHOOL STREET
BurlingtonSquare Park
Kendall Park
NOT TO SC ALE
SIDEWALK
SCENARIO BSCENARIO A
CROSS TRAFFIC
DOES NOT STOP
Intersection Crossing: Stop Sign ControlA
APPLICATION
CONSIDERATIONS• At two-way stop, stop sign should be placed on
the lower-volume street
• Stop signs should not be used as speed control or
traffic calming
• May be supplemented with “Stop Ahead” signage
• Crash history
• Observed conflicts
• Limited visibility on one or more approaches
PEDESTRIAN SAFETY & CONNECTIVITY: CROSSING TREATMENTS
NAPERVILLE - 5TH AVENUE REDEVELOPMENT
Midblock Crossing: Standard TreatmentB
APPLICATION
CONSIDERATIONS• Difficult to use safely for pedestrians with visual
impairments (unable to determine gap in traffic
or stopped traffic) compared to a stop condition
• Multi-lane crossings should provide a median or
refuge island
• Review pedestrian visibility (e.g., onstreet
parking, lighting)
• Provide advance crosswalk warning signs for
vehicle traffic
• Facilitate crossings where there is consistent
pedestrian demand
• Create a direct route to key destinations
• Locate away from nearest side street or driveway
so that drivers turning onto the primary street
notice pedestrians
SIDEWALK
NOT TO SC ALE
PEDESTRIAN SAFETY & CONNECTIVITY: CROSSING TREATMENTS
NAPERVILLE - 5TH AVENUE REDEVELOPMENT
C
APPLICATION
CONSIDERATIONS
Mid-Block Crossing: Increased Signage
SIDEWALK
• Difficult to use safely for pedestrians with visual
impairments (unable to determine gap in traffic
or stopped traffic) compared to a stop condition
• Multi-lane crossings should provide a median or
refuge island
• Review pedestrian visibility (e.g., onstreet
parking, lighting)
• Facilitate crossings where there is consistent
pedestrian demand
• Create a direct route to key destinations
• Locate away from nearest side street or driveway
so that drivers turning onto the primary street
notice pedestrians
• Encourage motorist compliance
NOT TO SC ALE
PEDESTRIAN SAFETY & CONNECTIVITY: CROSSING TREATMENTS
NAPERVILLE - 5TH AVENUE REDEVELOPMENT
D
APPLICATION
CONSIDERATIONS
Mid-Block Crossing: Curb Extensions
SIDEWALK
NOT TO SC ALE
• Difficult to use safely for pedestrians with visual
impairments (unable to determine gap in traffic
or stopped traffic) compared to a stop condition
• Must be designed to accommodate drainage
• May require fire hydrant relocation
• Enhance visibility of pedestrians
• Reduce crossing distance
• Facilitate crossings where there is consistent
pedestrian demand
• Create gateway to lower speed area
• Reduce speed of turning vehicles
PEDESTRIAN SAFETY & CONNECTIVITY: CROSSING TREATMENTS
NAPERVILLE - 5TH AVENUE REDEVELOPMENT
E
APPLICATION
CONSIDERATIONS
Mid-Block Crossing: Speed Table
NOT TO SC ALE
MA X. 50’
SIDEWALK
• Difficult to use safely for pedestrians with visual
impairments (unable to determine gap in traffic
or stopped traffic) compared to a stop condition
• Use of distinctive materials may require additional
maintenance but highlight and define the speed
table
• Typically preferred by emergency response over
speed humps
• Existing City of Naperville policy prohibits speed
tables and speed humps
• Enhance visibility of pedestrians
• Traffic calming device
• Create gateway to lower speed area
PEDESTRIAN SAFETY & CONNECTIVITY: CROSSING TREATMENTS
NAPERVILLE - 5TH AVENUE REDEVELOPMENT
F
APPLICATION
CONSIDERATIONS
Mid-Block Crossing: Rectangular Rapid Flashing Beacon
NOT TO SC ALE
SIDEWALK
• Requires FHWA permission for use
• Regular use of RRFBs could decrease effectiveness;
should be used at key uncontrolled intersections
only
• To minimize glare during nighttime conditions, an
automatic signal dimming device should be used
• Increase driver yielding rates to pedestrians
• Lower cost alternative to traffic signal
PEDESTRIAN SAFETY & CONNECTIVITY: CROSSING TREATMENTS
NAPERVILLE - 5TH AVENUE REDEVELOPMENT
G
APPLICATION
CONSIDERATIONS
Mid-Block Crossing: In-Pavement Lighting
SIDEWALK
• Difficult to use safely for pedestrians with visual
impairments (unable to determine gap in traffic
or stopped traffic) compared to a stop condition
• Actuated by pedestrian, lights may be
misinterpreted as control device
• Encourage motorist compliance
• Enhance visibility of crosswalk
NOT TO SC ALE
PEDESTRIAN SAFETY & CONNECTIVITY: CROSSING TREATMENTS
Photo Credit: Lightguard Systems
NAPERVILLE - 5TH AVENUE REDEVELOPMENT
CONSIDERATIONS
Railroad Crossing: Re-Open Cow TunnelA
• Potential for significant utility conflicts and
unknown risks
• ADA access (e.g., elevator or ramp)
• Stormwater drainage
• Amtrak, BNSF, and Metra coordination required
for shutdowns during construction
• Amtrak/BNSF/Metra service disruptions during
construction (could require 48- to 72-hour
shutdown)
• Security concerns associated with a tunnel (e.g.,
limited visibility)
• High-level review suggests the structural
integrity of the cow tunnel may require repairs
• Cost to modernize and repurpose to current code
could exceed cost of a new underpass
• Available right-of-way limitations
Photo Credit: Naperville Cow Tunnel, Chicago Tribune
PEDESTRIAN SAFETY & CONNECTIVITY: RAIL CROSSING TREATMENTS
NAPERVILLE - 5TH AVENUE REDEVELOPMENT
B Railroad Crossing: Construct New Underpass
CONSIDERATIONS• Security concerns associated with a tunnel (e.g.,
limited visibility)
• ADA access (e.g., elevator or ramp)
• Stormwater drainage
• Amtrak, BNSF, and Metra coordination required
for shutdowns during construction
• Amtrak/BNSF/Metra service disruptions during
construction (could require 48- to 72-hour
shutdown)
Photo: Deerfield Road Pedestrian Underpass, Deerfield, IL
PEDESTRIAN SAFETY & CONNECTIVITY: RAIL CROSSING TREATMENTS
COST ESTIMATE: $3-5 million• Structure is not temperature controlled except at
elevators (if provided in lieu of ramps)
• Considers precast box culverts
• Assumes 10 foot clear dimension inside of the
tunnel.
• Excludes site civil and utilities
NAPERVILLE - 5TH AVENUE REDEVELOPMENT
C Railroad Crossing: Construct New Pedestrian Overpass / Skyway
• Create sense of security and desired level of service
• Opportunity to integrate with development or parking deck
• Site impacts and coordination with BNSF, Metra, and Amtrak for closures
during construction
• ADA access (e.g., elevator or ramp)
• Aesthetics and height
• Maintain conductor line of sight to signal stations
PEDESTRIAN SAFETY & CONNECTIVITY: RAIL CROSSING TREATMENTS
CONSIDERATIONS
COST ESTIMATE: $2.5-4 million• Structure is not temperature controlled except at elevators
• Assumes a pre-engineered steel truss; minimal architectural features
• 70-foot span and 12-foot wide truss
• Includes hydraulic elevator at each headhouse
• Reflects headhouse elevation to allowed for the required clear height
between top of rail and bottom of bridge structure
• Excludes site civil and utilities
Photos: Anoka CRTV Pedestrian Bridge, Anoka, MN
NAPERVILLE - 5TH AVENUE REDEVELOPMENT
RAIL CROSSINGS: CASE STUDIES
Photo Credit: Rendering of pedestrian tunnel at Lombard Metra Station, Village of Lombard
LOMBARD METRA STATION - UNDERPASS (COMPLETED)• Construction initiated in Spring 2014, completed in Summer 2015
• Included new ADA ramps and stairs to the platform and tunnel and construction of roof
canopies over the platform
• Removed at-grade crossing
• Construction cost (estimate): $8.1 million + $1.6 million platform rehabilitation
• Coordination with Metra and Union Pacific Railroad
WHEATON COLLEGE - UNDERPASS (COMPLETED)• Included new ADA ramps and stairs to the tunnel
• Removed existing Chase Street at-grade crossing
• Cost estimate roughly $3 million
• Coordination with Metra and Union Pacific Railroad
Photo: Aerial view of pedestrian underpass adjacent to the Wheaton College stadium(former Chase Street right-of-way)
NAPERVILLE - 5TH AVENUE REDEVELOPMENT
RAIL CROSSINGS: CASE STUDIES
Photo Credit: Rendering of pedestrian overpass at Glen Ellyn Metra Station, Village of Glen Ellyn
GLEN ELLYN METRA STATION - OVERPASS (CONCEPT)• Village completed feasibility study to evaluate overpass and underpass alternatives
• ADA access to be provided by elevator or ramp
• Preliminary construction cost estimate roughly $3 million
• Coordination with Metra and Union Pacific Railroad
Photo Credit: Rendering of pedestrian overpass concept at Mundelein Metra Station, Village of Mundelein
MUNDELEIN METRA STATION - OVERPASS (CONCEPT)• 24-feet tall with a tower on each side of the tracks
• Includes stairs, ramps, elevators, and canopies covering walkways
• Preliminary construction cost estimate roughly $5 million
• Construction anticipated early 2019
• Coordination with Metra and Canadian National
NAPERVILLE - 5TH AVENUE REDEVELOPMENT