www.PEBsteel.com ERECTION MANUAL PEB Steel Buildings Co., Ltd PEB Steel Buildings Co., Ltd HCMC Office: Unit 701, 7 th Floor, C.T Plaza, 60A Truong Son St., Ward 2, Tan Binh Dist., Ho Chi Minh City, Vietnam. Tel : (84) (28) 3 8 475 475 Fax: (84) (28) 3 8 476 476 Factories: Dong Xuyen Industrial Park, Ba Ria Vung Tau Province, Vietnam. Thilawa Special Economic Zone - TSEZ, Yangon, Myanmar. Pithampur, Madhya Pradesh State, India. Year 2017 ERECTION MANUAL For Site Engineers PRE - ENGINEERED BUILDINGS

PEB Steel - Bia Erection... ERECTION MANUAL PEB Steel Buildings Co., Ltd PEB Steel Buildings Co., Ltd HCMC Office: Unit 701, 7th Floor, C.T Plaza, 60A Truong Son St., Ward 2

  • Upload
    others

  • View
    40

  • Download
    8

Embed Size (px)

Citation preview

  • www.PEBsteel.com

    ERECTIO

    N M

    AN

    UA

    L

    PEB Steel Buildings Co., Ltd

    PEB

    Steel B

    uildings Co., Ltd

    HCMC Office:

    Unit 701, 7th Floor, C.T Plaza, 60A Truong Son St., Ward 2, Tan Binh Dist.,Ho Chi Minh City, Vietnam.Tel : (84) (28) 3 8 475 475 Fax: (84) (28) 3 8 476 476

    Factories:

    Dong Xuyen Industrial Park, Ba Ria Vung Tau Province, Vietnam.Thilawa Special Economic Zone - TSEZ, Yangon, Myanmar.Pithampur, Madhya Pradesh State, India.

    Year 2017

    ERECTION MANUALFor Site Engineers

    PRE - ENGINEERED BUILDINGS

  • CO

    NTE

    NTS 1. GENERAL INTRODUCTION 31.1. INTRODUCTION

    1.2. IMPORTANT NOTICE33

    2. BASIC PRINCIPLES 4-72.1. JOB SITE PREPARATION2.2. FOUNDATIONS AND ANCHOR BOLTS2.3. MATERIAL LAYOUT2.4. RECEIVING YOUR BUILDING

    44-6

    77

    3. STORAGE & PROTECTION 8-93.1. FOR ROOF & WALL PANELS3.2. FIBERGLASS BLANKET INSULATION3.3. PROPER STORAGE FOR MAIN FRAME & GALVANIZED MEMBERS

    889

    5. INSTALLATION PROCEDURE FOR ROOFING, CLADDING, FLASHING & TRIMS 31-435.1. GENERAL NOTE5.2. INSTALLATION OF ROOFING FOR LOK-SEAM® & CLADDING5.3. INSTALLATION OF ROOFING FOR PEBSEAM128TM

    5.4. INSTALLATION OF TRIM AND ACCESSORIES

    3131-3940-43

    43

    446. FINAL CHECK

    457. SAFETY ORDERS

    46-528. SAFETY PHOTOS UNDER CONSTRUCTION

    53-549. BASIC ERECTION EQUIPMENTS9.1. LIFTING EQUIPMENT, ROPES AND LINES.9.2. ELECTRICAL EQUIPMENT9.3. HAND TOOLS

    535354

    55-6010. RELATED FORM10.1.10.2.10.3.10.4.10.5.10.6.10.7.10.8.

    SITE DAILY REPORTERECTION WEEKLY REPORTA/B SETTING INSPECTIONPLUMBING INSPECTION HIGHT STRENGTH BOLTS INSPECTION RECORDACCEPTANCE MINUTE WORKFINAL INSPECTION REPORTPUNCH LIST FORM

    555656575859

    60-6162

    4. ERECTION PROCEDURE FOR MAIN FRAMES 10-304.1. STRUCTURAL FRAMING ERECTION PROCEDURE 4.1.1. DETAIL ERECTION GUIDE FOR STRUCTURAL FRAME 4.1.2. RIGID FRAME CONNECTION DETAILS4.2. PEBHYBRID ERECTION PROCEDURE 4.2.1 DESCRIPTION 4.2.2 ADVANTAGES 4.2.3 ERECTION PROCEDURE FOR PEBHYBRID4.3. CHOICE OF THE CRANE4.4. LOAD ON FRAMES AND PURLINS4.5. METHODS OF BOLT TIGHTENING4.6. STRUCTURAL FASTENERS

    10-1710-16

    1718-24

    1818

    18-2425-28

    2929-30

    30

    GENERAL INTRODUCTION

    03

    1.1. INTRODUCTION

    The policy of PEB STEEL is to create satisfied customers. Buildings are designed using sound principles of Engineering. Fabrication is of the highest quality. However, there remains one final and all important phase that must be accomplished. That is, the assembling of the various component parts those make up the building. This final phase is “ERECTION”.

    The term “ERECTION” is generally thought of as applying to the fabricated steel for the building, but it is much more. It actually begins with the foundation, building anchorage and carries through to cleaning up the jobsite on completion of erection. It is our purpose here to help you in obtaining “Quality Erection” there by creating an owner completely satisfied and proud of his PEB STEEL building.

    The methods and procedures suggested by this erection guide are fundamental in nature and represent good, safe erection practices. They can, and should be modified when necessary to adapt to special conditions or circumstances. Before you begin, familiarize yourself with the building details and the sequence of erection. This will enable you to plan your work and avoid unnecessary delays during construction.

    1.2. IMPORTANT NOTICE

    If PEB STEEL erection crews are not being used to erect the building, PEB STEEL accepts no responsibility for erection quality, leakage, defects or collapse due to negligence or improper erection procedures.

    1. GENERAL INTRODUCTION

  • 04

    BASIC PRINCIPLES

    2.2. FOUNDATIONS AND ANCHOR BOLTS

    Any building, regardless of size or type, depends on a good foundation for a satisfactory life expectancy and a minimum maintenance cost during that life. Accurate foundation dimensions and proper anchor bolt locations are critical to the overall erection procedure. Therefore it should be accurate and within the tolerance specified in the erection drawing.

    Job site is clean and ready to receive your building

    2.1. JOB SITE PREPARATION

    If you have not already done so, you must now make a detailed inspection of the job site and note all conditions that will affect building erection.

    Some important points to check are:

    A. Location 1. Job Site – is it clean, level and ready. The ground-soil is hard enough for crane to move 2. Storage locationB. Accessibility for delivery trucks and equipmentsC. Obstructions, below ground, above ground, overhead cablesD. Maneuvering room for equipmentsE. Utilities available.

    Existing conditions should be determined before material delivery and should be considered in pre-construction planning. There are many benefits to a clean and orderly job site.

    2. BASIC PRINCIPLES

    BASIC PRINCIPLES

    05

    STEP 1 STEP 2

    Marking center line and elevationAB Setting

    STEP 3

    Insert AB, template andtack weld hub and AB

    STEP 4

    Pouring concrete

    STEP 5

    Removing template

    Center line marking

    Elevation marking

    Center line marking

    Tack weld hub and A/B

    Elevation marking

    Center line marking

    Tack weld hub and A/B

    Elevation marking

  • 06

    BASIC PRINCIPLES

    Following up during casting concrete to make sure that the position of A/B is not move

    A/B was assembled and connected to steel rod by welding

    07

    BASIC PRINCIPLES

    Some pictures for Unloading at job site

    2.3. MATERIAL LAYOUT

    Materials should be laid out to avoid double handling, layout will depend on size of building and site conditions. Use timber blocks between bundles or members for ease of handling.

    2.4. RECEIVING YOUR BUILDING

    All PEB STEEL buildings are carefully checked and loaded to ensure safe delivery and to avoid shortages. Materials are packaged and can be unloaded by use of heavy duty Fork-lift or by crane. Care should be exercised when handing materials to avoid damages.

    At time of unloading, materials should be checked against Bill of Materials or Packing List. Any shortages must be reported to PEB STEEL within a week. After this time PEB STEEL will not accept responsibility for shortages or transit damage.

  • STORAGE AND PROTECTION

    09

    Cover with canvas tarpaulin to protect from rain » Tie down cover ends to keep from wind blows » Block above ground to keep water out » Wood slabs to serve as platform for laying down the insulations.

    3.3. PROPER STORAGE FOR MAIN FRAME & GALVANIZED MEMBERS

    08

    43 WOOD BOARD

    When galvanized or zincalume panels becomes wet from rain, natural condensation or other causes, white rust may result. This may occur either during transit or due to improper storage at the job site.

    If sheetings are to be stored temporarily in open area and this is absolutely necessary, then they should be covered with tarpaulin or any water proof materials. (Never use plastic since it promotes moisture). If no covering is available, the procedure shown below must be followed to prevent the entry of moisture into the panels and consequent storage stain.

    Panels are to be stacked on top each other and wooden supports need to be placed under the bottom panels to provide air space. The top panels “3” is extended outward at least 900 mm plus or minus and the second panels “2” to be extended down yard to almost near the ground to protect the zincalume panels “1” below. Also wrap the upper portion of the panels “1” below about 300 mm of polythene sheets.

    Note: Zincalume sheets should be keep away from whitewash, cement, lime, mud etc.

    WATER ROOFCOVERING

    300

    900

    SLOPE 15 o - 20 o

    Z/A PANEL

    AIR SPACEDRY GROUND

    PAINTED PANEL

    2

    1

    3

    STORAGE OF FIBERGLASS INSULATION

    DRY GROUND

    1

    4

    TARPAULIN

    TIE

    WOOD BLOCKABOVE GROUND

    ABOVE ALL, TIDINESS IS IMPORTANT FOR SAFETY,AND WILL AVOID LOSS OR DAMAGE OF PARTS

    3.2. FIBERGLASS BLANKET INSULATION

    3.1. FOR ROOF & WALL PANELS

    3. STORAGE AND PROTECTION

    STORAGE AND PROTECTION

  • ERECTION PROCEDURE FOR MAIN FRAMES

    10

    4. ERECTION PROCEDURE FOR MAIN FRAMES

    4.1. STRUCTURAL FRAMING ERECTION PROCEDURE

    4.1.1. DETAIL ERECTION GUIDE FOR STRUCTURAL FRAME

    STEP 1

    - Installing columns, girts, flange brace and wall bracing, tube struts (if have) - Checking alignment of columns before proceeding step 2.

    STEP 2.

    - Using 2 cranes to lift first rafter (Crane capacity should be considered actual weight and height of rafter). - We must start installation with bracing bay

    ERECTION PROCEDURE FOR MAIN FRAMES

    11

    STEP 3.

    - Fixing temporary guide wire as sketch (consider degree max 500). - Quantity of guide wire should be 6 meter/pcs in plane.

    Note: Temporary bracing should keep until completed all items of Main frame.

    200130

    Pipe Ø21x15x2

    Pipe Ø21x15x2

    10

    Pipe Ø42x220x2

    Pipe Ø21x185x2

    Pipe Ø42x700x2

    Sti�ener W3: 60x50x5

    Plate W1: 120x120x5

    Bolt M12x50 (Q’ty 4pcs)

    Plate W2: 300x120x5

    700

    RAFTER

    Detail B

    Ground

    Angle 75x75

    Detail A

    1500

    100

    600

    Temporary cablebracing

    STEP 4.

    - Lifting second rafter as sketch. - Installing full purlins.

  • Purlin block

    ERECTION PROCEDURE FOR MAIN FRAMES

    13

    STEP 6.

    - Continute to lift third rafter as step 2.

    STEP 7.

    When we completed 2 bays. We must start to fix: - Purlin blocks - Sag Arrestor

    Note: (We must install the Purlin Block first and after that Sag Arrestor)

    ERECTION PROCEDURE FOR MAIN FRAMES

    12

    STEP 5.

    - Installing full roof bracing, tube struts and flange brace. - Checking and aligning first bay before next rafter

    WRONG CORRECT

    WRONG WRONG CORRECT

    SMALL FLANGE

    SMALL FLANGEBIG FLANGE

    SMALL FLANGE

    SMALL FLANGE BIG FLANGE

    BIG FLANGE SMALL FLANGE

    BIG FLANGE

    SMALL FLANGE

    BIG FLANGE BIG FLANGE

    * Correct purlin lapping

    * Correct stitch bolt

  • ERECTION PROCEDURE FOR MAIN FRAMES

    15

    STEP 9.

    - Lifting next rafter as sketch. - Installing full purlins.

    STEP 10.

    - Continute to install mainframe till finishing as step 2 to step 9. - Doing alignment all erected frame. - Doing HSB tightening. - Pouring grouting before installation of roof and wall sheeting

    ERECTION PROCEDURE FOR MAIN FRAMES

    14

    STEP 8.

    - Installing roof bracing and flange brace. - In case permanent bracing bays, 100% menbers must be installed. - In case none bracing bay: 50% purlins and 100% flange brace must be installed. 100% girts and flange brace must be installed.

    Sag arrestor

    Tem

    pora

    ry b

    racin

    g 12

    mm

    dia

  • ERECTION PROCEDURE FOR MAIN FRAMES

    16

    Photos reference for structural framing erection

    ERECTION PROCEDURE FOR MAIN FRAMES

    17

    4.1.2. RIGID FRAME CONNECTION DETAILS

    » Refer to Erection Drawings for quantity and size of bolts at every connections » All connections bolts in rigid frames are high strength bolts » All bolts are to be installed using the snug tight method unless noted otherwise. » Install and tighten all bolts at all frame connections as each rigid frame is assembled.

  • ERECTION PROCEDURE FOR MAIN FRAMES

    STEP 2

    - Inserting square tube as sketch. - Fixing bolt and tightening

    19

    ERECTION PROCEDURE FOR MAIN FRAMES

    18

    4.2.2. ADVANTAGES:

    1. Save weight about 15-20% of rafters. 2. Save time fabrication by roll cold formed machines form Galvanized coils no need welding &

    painting. 3. Columns are built-up sections, can design for factories with overhead cranes. 4. Truss structure rafters (open web) better for useful space as fire, air, water…. piping systems. 5. Truss structure rafters also good for roof systems. 6. Galvanized rafters make long life for buildings, reduce maintenance cost. 7. Easier in transportation to jobsites. 8. Friendly for environment

    4.2.3. ERECTION PROCEDURE FOR PEBHYBRID:

    STEP 1

    - Segregating materials and put them on timber support.

    4.2. PEBHYBRID ERECTION PROCEDURE

    4.2.1 DESCRIPTIONS:

    PebHybrid a form of Pre-Engineered Buildings, it was developed by PEB Steel Buildings Company with: - Columns are built-up sections; - Rafters are truss structure from 2 Omegas cold formed section (upper and lower) connected with square tubes hollow sections by bolts. - All purlins, girts, flange bracings, X-bracings… are same PEB structures before.

  • ERECTION PROCEDURE FOR MAIN FRAMES

    21

    STEP 6

    - Fixing temporary guide wire as sketch.

    STEP 7

    - Installing second rafters and completed all of Purlins, Bracing, Flange brace, etc. After that, we must check and align this bay. - Continue to third trusses as sketch. - Installing flange brace for columns and trusses.

    ERECTION PROCEDURE FOR MAIN FRAMES

    20

    STEP 4

    - Installing columns, girts, wall bracing, strut tube and flange brace - Align columns before lifting PebHybrid.

    STEP 3

    - Joining 2 trusses together.

    STEP 5

    - Lifting first PebHybrid truss as sketch.

  • ERECTION PROCEDURE FOR MAIN FRAMES

    22

    STEP 8

    - Continute to lift next truss as sketch. - Keep fixing sag arrestors and purlin blocks as sketch.

    STEP 9

    - Continute to install mainframe till finishing as step 2 to step 8. - Doing alignment all erected frame. - Doing HSB tightening. - Pouring grouting before installation of roof and wall sheeting.

    - Continute to the end

    Purlin block

    ERECTION PROCEDURE FOR MAIN FRAMES

    23

    Photos Referrence for PebHybrid Erection

    1. Fitting up rafters on the ground:

    2. Installation mainframe:

  • ERECTION PROCEDURE FOR MAIN FRAMES

    24

    3. Main frame:

    4. Sheeting:

    5. Testing:

    » The erection of first bay always requires more power. You should prepare all steel member and bring all necessary girts, purlins, bracing cables, flange braces of first bay near to their permanent position and build up the hoisting frame part one day before the erection.

    In other case, use the spreader – bar to support the erection, so you can save the crane-height.

    MIN 45o

    h

    H

    L

    ≥ 45o

    4.3. CHOICE OF THE CRANE

    The necessary height of crane beam depends on the height of permanent position of the highest rafter in the building and on the length of above rafter.

    Say: + Height of highest rafter is “h” + Length of rafter part is “L”

    The crane - height (H) should be more than H = [h + ( L/4 )] The degree between hoisting cable and rafter should be more than 450.

    ERECTION PROCEDURE FOR MAIN FRAMES

    25

  • ERECTION PROCEDURE FOR MAIN FRAMES

    26

    Setting steel column

    Connection between Rafter and column

    Connection between Rafter and Rafter

    ERECTION PHOTOS REFERENCE

    ERECTION PROCEDURE FOR MAIN FRAMES

    27

    The first frame with temporary bracing

    The first bay with full purlins and X-bracing

    Continue to next bay

    ERECTION PHOTOS REFERENCE

  • ERECTION PROCEDURE FOR MAIN FRAMES

    29

    4.4. LOAD ON FRAMES AND PURLINS

    No loads should be supported from the purlins unless the building has been designed for additional loads. In such cases the loads should not be supported from the purlins until the roof sheets have been installed and fully screwed.

    The following sketches show correct and incorrect methods of support from rafters and purlins.

    4.5. METHODS OF BOLT TIGHTENING

    METRIC BOLT AND CAP SCREW TORQUE VALUES

    M36 1150 850 1450 1075 2250 1650 2850 2100 3200 2350 4050 3000 3750 2750 4750 3500M33 900 675 1150 850 1750 1300 220 1650 2500 1850 3150 2350 2900 2150 3700 2750M30 675 490 850 625 1300 950 1650 1200 1850 1350 2300 1700 2150 1600 2700 2000M27 490 360 625 450 950 700 1200 875 1350 1000 1700 1250 1600 1150 2000 1500M24 330 250 425 310 650 475 825 600 925 675 1150 850 1075 800 1350 1000M22 260 190 330 250 510 375 650 475 725 540 925 675 850 625 1075 800M20 190 140 240 180 375 275 475 350 530 400 675 500 625 460 800 580M18 135 100 175 125 260 195 330 250 375 275 475 350 440 325 560 410M16 100 73 125 92 190 140 240 175 275 200 350 225 320 240 400 300M14 63 47 80 60 120 88 150 110 175 130 225 165 205 150 260 190M12 40 29 50 37 75 55 95 70 110 80 140 105 130 95 165 120M10 23 17 29 21 43 32 55 40 63 47 80 60 75 55 95 70M8 12 8.5 15 11 22 16 28 20 32 24 40 30 37 28 47 35M6 4.8 3.5 6 4.5 9 6.5 11 8.5 13 9.5 17 12 15 11.5 19 14.5

    N-m Lb-ft N-m Lb-ft N-m Lb-ft N-m Lb-ft N-m Lb-ft N-m Lb-ft N-m Lb-ft N-m Lb-ft

    DrysLubricated

    Class 4.8

    Size

    Class 10.9Class 8.8 or 9.8 Class 12.9

    Lubricated Lubricated LubricatedDrys Drys Drys

    8.8 9.8

    8.8 9.8

    8.8 9.8

    10.9

    10.9

    10.9

    12.9 12.9

    12.9 12.9

    12.9

    5

    5

    5

    10

    10

    10

    10

    10

    10

    12

    12

    12

    4.8

    4.8

    4.8

    PropertyClass andHeadMarkings

    PropertyClass andNut Markings

    ERECTION PROCEDURE FOR MAIN FRAMES

    28

    …Continue…

    …Continue…

    Completed main frame installing

    ERECTION PHOTOS REFERENCE

    wrong correct

    - For structural frames - For PebHybrid frames

    - For purlins

    CORRECT

  • ERECTION PROCEDURE FOR MAIN FRAMES

    30

    Do not use these values if a di�erence torque value or tightening procedure is give for specific application. Torque values listed are for general use only. Check tightness of fasteners periodically.

    Shear bolts are designed to fail under predetermined loads. Always replace shear bolts with identical property class.

    Fasteners should be replace with the same or higher property class. If higher property class fasteners are used, these should only be tightened to the strength of the original.

    a " Lubricated means coated with a lubricant such as engine oil, or fasteners with phosphate and oil coatings. "Dry" means plain or zinc plated without any lubrication."

    Make sure fasteners threads are clean and that you properly start thread engagement. This will prevent them from failing when tightening.

    Tighten plastic insert or crimped steel-stype lock nuts to the full torque value.

    4.6. STRUCTURAL FASTENERS

    The chart below identifies the most commonly used bolts in PEB Steel Building and indicates where they are used in connecting the various components.

    (ASTM A – 307)Machine Bolt & Nut

    or (DIN 4.6)

    M12

    M12

    30mm, 50mm

    Attachment of secondary& Primary structurals

    bolting forces areminimal.

    (ASTM A – 307)Fin Neck Bolt & Nut

    Or (DIN 4.6)

    30mm

    Used where bolt head willbe exposed in openingwhere flush heads arerequired for clearance

    or appearance.

    STANDARD BOLT METRIC STANDARD SIZE TYPICAL USE

    M 16 45mm, 60mm

    M 20 60mm, 80mm

    M 24 80mm, 100mm

    M 30 120mm

    Attachment of primarystructurals where

    bolting forces are high(moment type connection)

    (ASTM A – 325)High – Strength Bolt,

    Nut & Washeror (DIN 8.8)

    INSTALLATION PROCEDUREFOR ROOFING, CLADDING, FLASHING & TRIMS

    31

    5.1. GENERAL NOTES

    1. Always use a chalk line for accurate drilling and screwing. This gives better appearance and less risk of leakage due to misdrilling 2. At the end of each working day clean the roof with asoft brush. Sweep off old drill bits, pop rivets, swarf from drilling or cutting. These items can cause rusting if they are not removed 3. When walking on the roof, do not stand on high ribs, stand only on the low ribs, preferably over the purlin line. Standing on high ribs can cause severe damage which could lead to possible leakage 4. Do not walk on skylights 5. Mark out the sheeting along the length of the building, this will give correct overlaps and avoid creep.

    5.2. INSTALLATION OF ROOFING FOR LOK-SEAM & CLADDING

    Sheeting installation procedure

    TOO LOOSE TOO TIGHT CORRECT

    1 mm

    5. INSTALLATION PROCEDURE FOR ROOFING, CLADDING, FLASHING & TRIMS

    ®

  • INSTALLATION PROCEDUREFOR ROOFING, CLADDING, FLASHING & TRIMS

    33

    STEP 3

    - Installing first Lokseam panel.- Fixing screw at eave at sketch.

    STEP 4

    - Continute to install Lokseam as step 2 to step 3.

    Clip

    STEP 1.

    - Fixing rack support, rack angle as sketch.

    STEP 2.

    - Laying insulation, fixing inside metal closure with bead mastic.- Spacing among inside metal closures are 470mm.- NFR-1 is always bottom layer as sketch.

    Fiber Glass

    Aluminium Facing (Middle Layer)

    NFR1 Facing (Bottom Layer)

    Rack support

    Expansion clip

    Rack angle

    Bead mastic

    Inside metan closure

    INSTALLATION PROCEDUREFOR ROOFING, CLADDING, FLASHING & TRIMS

    32

  • INSTALLATION PROCEDUREFOR ROOFING, CLADDING, FLASHING & TRIMS

    35

    STEP 7

    - Installing endwall panel as sketch.

    STEP 8

    - Fixing outside foam clousure.

    Fixing outside foam closure

    INSTALLATION PROCEDUREFOR ROOFING, CLADDING, FLASHING & TRIMS

    34

    STEP 5

    - Fixing drip trim, adjustable conner trim as sketch.

    - Fixing inside foam clousure.

    STEP 6

    Installing wall panel as sketch.

    Wall insulation should be clamped at the eave-strut or secured with double-faced tape, and pulled tight before screwing the panel.

    Successive “drops” of insulation should be stapled to the previous by the side tabs. This is important to complete the vapour barrier seal.

    Roof insulation should be fixed or clamped at one eave strut and stretched as tight as possible before fixing at the other eave strut. On average sized buildings one roll of insulation will span the full width, but on wider buildings it may be necessary to splice, this should be done on a purlin. After the roof sheets have been placed, the next run of insulation can be stapled at the side tabs and work continue.

    Process lock with special machine

    Connection between clip and LOK-SEAM® panel

    Adjustable conner trim

  • INSTALLATION PROCEDUREFOR ROOFING, CLADDING, FLASHING & TRIMS

    37

    STEP 11

    - Installing endwall panel as sketch.

    STEP 12

    - Bending top end panel.

    Bending top end panel

    INSTALLATION PROCEDUREFOR ROOFING, CLADDING, FLASHING & TRIMS

    36

    STEP 9

    - Fixing conner trim and eave trim.

    STEP 10

    - Fixing gutter strap as sketch.

    Fixing gutter strap

    Fixing eave trim

  • INSTALLATION PROCEDUREFOR ROOFING, CLADDING, FLASHING & TRIMS

    38

    STEP 13

    - Fixing outside metal closure with bead mastic.

    STEP 14

    - Fixing ridge cap.

    Fixing outside metal closure

    Fixing ridge cap

    39

    INSTALLATION PROCEDUREFOR ROOFING, CLADDING, FLASHING & TRIMS

    STEP 15

    - Fixing PEB peak sign as sketch.

    STEP 17

    - Seaming Lokseam panel and cleaning roof.

    STEP 16

    - Installing downspout as sketch.

    Fixing downspout

    Completed Roof sheeting installing

  • INSTALLATION PROCEDUREFOR ROOFING, CLADDING, FLASHING & TRIMS

    40

    INSTALLATION PROCEDUREFOR ROOFING, CLADDING, FLASHING & TRIMS

    41

    STEP 2

    Installing the support Z clip from the endof purlin 70mm.

    STEP 3

    Installing the TR-0012A on support Z clips.

    STEP 5

    STEP 4

    Installing TR-0003

    5.3. INSTALLATION OF ROOFING FOR PEBSEAM128TM

    Double SC-1002 screw

    TR-0007

    Z clip

    70mm

    STEP 1

    Installing the TR-0007 with double SC-1002 screw at one location. Because length of TR-0007 is 3100mm, each TR-0007 should be had 12 screws at six locations as below figure.

    TR-0012ATR-0012A

    TR-0003

    PEBSEAM inside metal closure

    STEP 6

    Putting the PEBSEAM panel on right location and control straightness of end point of panel. We must fix the first PEBSEAM panel and TR-0003A by SC-1001 screw at 500mm.

    STEP 7

    Assembling PEBSEAM clip and support Z clip with two SC-1002 screws.

    Installing component PEBSEAM clip and support Z clip to purlin with two SC-1002 screws.

    PEBSEAM Clip Z Clip

    SC-1002

    Hook of PEBSEAM Clip

    440mm

    STEP 9

    Putting second PEBSEAM panel on right location and controlling straightness of end point of panel.

    Second panelFirst panel

    STEP 8

    Setting new inside metal closure of PEBSEAM from last inside metal closure 400mm.

    STEP 10

    Installing component PEBSEAM clip and support Z clip to purlin with two SC-1002 screws.

    400mm

    PEBSEAM panel

    500mm

    Covering inside metal closure of PEBSEAM panel by bead mastic and then fix it to TR-0007.

  • 42

    INSTALLATION PROCEDUREFOR ROOFING, CLADDING, FLASHING & TRIMS

    INSTALLATION PROCEDUREFOR ROOFING, CLADDING, FLASHING & TRIMS

    43

    GENERAL NOTES

    » Use the proper tools for cutting: aviation snips for cutting trims, nibbler and shear for cutting sheets

    » Use a chalk line to keep things straight » Use a spirit level to keep things plumb » Always clean-o� your work » Study the standard drawing supplied, these indicate correct trims, and fixing details for each

    application. Take note of spacing of screws and rivets or the number of fasteners per item » Observe where foam closures have to be installed » Be sure that sealant or mastic is applied where required » Read all the notes on the drawing, they are important » Follow manufactures instructions for installation of Roll-up-door, Personnel doors or Special

    Accessories » Use the correct tools » Turn up of panel valley end to form a dam » This should be applied for every roof opening and transition connections.

    5.4. INSTALLATION OF TRIMS AND ACCESSORIES

    Keep it neat - keep it straight, the neatness of trimming and installation of accessories is of paramount importance to give the finished building the quality look.

    Conner Trim, Gable Trim, Louvers and Downspout

    STEP 11

    Fixing SC-1003 and SC-0001 screws at the end of PEBSEAM panel.

    SC-1001 SC-1003

    STEP 14

    Installing TR-0012A on support Z clips.

    TR-0012A

    STEP 12

    Continue from step 8 to step 11.

    STEP 13

    Installing final support Z clip line with 440mm length from last support Z clip line.

    Z clip

    440mm

    STEP 15

    Installing TR-0003

    TR-0012A

    STEP 16

    Putting final PEBSEAM panel on right location, then fixing all screws at the end and side of PEBSEAM panel.

    OVERVIEW

  • 44

    FINAL CHECK

    6. FINAL CHECK

    CLEANING OF 1st LAYER PANEL BEFORE INSULATION & LOK-SEAM® INSTALLATION

    After completing all trims and accessories a final inspection of the building should be made.

    1. All bracing in position and tightened 2. All bolts in place and high strength bolts tightened to correct tension

    3. Check that roof an gutters are clear of debris and ferrous metals

    4. Check for misdrilled screws

    5. Check all roof penetrations for weather tightness

    6. Check operation of all doors

    7. Touch-up any damaged paint

    8. Clean-up the site

    9. Handover keys and the building.

    SAFETY ORDERS

    45

    7 SAFETY ORDERS

    » Safety is top most priority before and during execution of erection works

    » All workers must be, at all times, in presence of mind what ever their work to be

    » It is the responsibility of contractor/ Erector to furnish safety gadgets such as: safety helmet, safety belt, hand gloves, safety shoes and bolt bag

    » Use safety gadgets at all times while on the jobsite

    » What has not happened to you in twenty years may happen it two seconds. Always think safety.

    Toolbox Meeting - 15’ every morning at Site on check list before working

  • 46

    SAFETY PHOTOS UNDER CONSTRUCTION SAFETY PHOTOS UNDER CONSTRUCTION

    47

    8. SAFETY PHOTOS UNDER CONSTRUCTION

  • 48

    SAFETY PHOTOS UNDER CONSTRUCTION SAFETY PHOTOS UNDER CONSTRUCTION

    49

  • SAFETY PHOTOS UNDER CONSTRUCTION

    51

    MAN LIFTMAN LIFT

    50

    SAFETY PHOTOS UNDER CONSTRUCTION

  • BASIC ERECTION EQUIPMENTS

    53

    The following items are basic requirements of a six man erection crew.

    9.1. LIFTING EQUIPMENT, ROPES AND LINES. Telescopic crane. 03 Ton Forklift with 10 m Mast (for Smaller Size) buildings. Spreader Bars – 6 m and 12 m. Assorted Slings, in various sizes and lengths. Steel guy lines of temporary bracing. (minimum 08 no.) Manila ropes for hand lines (minimum 02 no.) “Come-alongs”, “Tirfors”, or Turnbuckles (08 no.)

    9.2. ELECTRICAL EQUIPMENT

    Generator/Welder. Extension Leads and Pigtails. Heavy Duty Drill 1 / 2’’ (01 No.) Heavy Duty Drill 1 / 4’’ (02 No.) Electric Nibbler (01 No.) Electric Shear (01 No.) Angle Grinder (1 No.) Concrete Drill (01 No.)

    Welding MachineElectric Shear Grinder

    Heavy Duty Drill with Reamer Generator

    9. BASIC ERECTION EQUIPMENTS

    52

    SAFETY PHOTOS UNDER CONSTRUCTION

  • 10. RELATED FORM

    54

    BASIC ERECTION EQUIPMENTS

    9.3. HAND TOOLS

    Socket Wrench 3 / 4’’ or 1’’ drive with asst. sockets. Open ended wrenches assorted imperial sizes Spud wrenches, 15/16’’ opening up to 1-1/8’’ Pipe wrench - 12’’ Screw drivers – Standard and Philips. Aviation snip – Left and Right. Pop rivet puller. (02 No.) Vice grips (08 No.) 4lb. Sledge hammer. Hacksaw frame an blades. Wood saw Spirit level and plumb-bob. Chalk line Steel measuring tapes 30 m and 6 m Utility knife. Staple applicators. Cold Chisel. Oxy-Acetylence cutting outfit. Welding hood. Hard hats. Safety belts – Bolt bags. Broom Masonry drill bits 12mm Extension ladders 02 no. Step ladder. Hilti gun, cartriges and nails.

    Pop Rivet Puller

    Screw Gun

    Powder Actuated Tool

    Aviation Snip

    Ratchet SpannerVice Grips

    Nibbler

    Torque Wrench Impact Wrench

    Drill 10mm

    Hard Hat Safety Boots Welding Hood

    Gloves

    Goggles Oxy-AcetyleneCutting Out�e

    Ladders

    RELATED FORM

    55

    SITE DAILY REPORT

    Date / /

    I. Manpover & equipment

    1. Supervisor 4. Worker

    2. Safety O�cer 5. Crane

    3. Warehouse keeper 6. Trailer

    II. Safety

    1. Safety checking: AM PM

    2. Note

    III. Material status

    IV. Erection progress

    V. Weather

    VI. Generat Comments

    Erection Representative PEB Steel Representative

    Item:

    10.1. SITE DAILY REPORT

  • RELATED FORM

    57

    RELATED FORM

    56

    - Main frame col. alignment - Crane beam straightness

    - Crane beam elevation

    10mm+-

    10mm+-

    1:300; 1:500

    PLUMBING RECORD

    Name

    Signature

    Date

    Name

    Signature

    Date

    Name

    Signature

    Date

    Job No.

    1. GENERAL TOLERANCES

    2. RECORD

    3 . NOTE

    Surveyor Contractor PEB-Erection Coordinator

    3 . COMMENTS

    Building No. Ref. Drawing Page

    ACTUAL RESULT

    Grid Line

    - Method

    - Equipment original:

    - Equipment calibrication Yes

    Hand tool Theodolite

    No

    Tolerance DeviationTop Accept Reject

    RemarkBottom

    10.4. PLUMBING INSPECTION

    ANCHOR BOLT INSPECTION REPORT

    Job No.

    Surveyor Contractor PEB-Erection Coordinator

    Grid Line Critical Distance

    a . Temporary plate

    b. Size of Anchor Bolf's Correctness

    c. Projection Correctness

    Name

    Signature

    Date

    Name

    Signature

    Date

    Name

    Signature

    Date

    Yes

    Yes

    Yes

    No

    No

    No

    Bay Spacing Elevation Remark

    1. RECORD DIMENSIONS

    2. ANCHOR BOLT GROUPS

    3. GENERAL COMMENTS

    Building No. Ref. Drawing

    Cladding

    Prepared by Checked by

    ERECTION WEEKLY REPORT

    Job No.

    No. Items

    A/B setting

    Main frame

    Roofing,Ridge vent

    M2

    M2

    M2

    Group

    UnitBOMQty

    Week 1Date

    Week 2Date

    Week 3Date

    Week 4Date

    Week 5Date

    Week 6Date

    Week 7Date

    Week 7Date

    Bldg No. Project Name: Location:

    10.2. ERECTION WEEKLY REPORT

    10.3. A/B SETTING INSPECTION

  • RELATED FORM

    59

    RELATED FORM

    58

    HIGH STRENGTH BOLTS INSPECTION RECORD

    Name

    Signature

    Date

    Name

    Signature

    Date

    Name

    Signature

    Date

    Job No.

    1. RECORD

    2. NOTE

    3. COMMENTS

    Surveyor Contractor PEB-Erection Coordinator

    - Method

    - Check

    Snug-tight

    Random 10%

    Torque wrench

    100% check

    Line Grid Line Connection Qty x Bolt SizeConnection

    Part No. Part No.Remarks

    Building No. Ref. Drawing Page

    10.5. HIGHT STRENGTH BOLTS INSPECTION RECORD 10.6. ACCEPTANCE MINUTE WORK

    ACCEPTANCE MINUTE OF WORK ITEM

    Project No. :

    Project Name:

    Work Item:

    Location:

    Today,

    Mr. : Position:

    Mr. : Position:

    Mr. : Position:

    A. Representative of Owner

    Mr. : Position:

    Mr. : Position:

    Mr. : Position:

    B. Representative of Erector:

    After checking the job site, the parties agreed to sign the minute of acceptance with the followingitems:

    Item I: TECHNICAL & QUANTITY WORK

    Item II: QUANTITY OF WORK

    Item III: CONCLUSION

    OwnerName Signature Name Signature

    Erector

    , at the job site of We are:

  • RELATED FORM

    60

    10.7. FINAL INSPECTION REPORT

    base

    or lean-to

    installed

    corner trims correctly fitted & fastened

    correctly

    FINAL INSPECTION REPORT

    fastened

    fastened

    correctly

    closures

    mastic

    folded

    RELATED FORM

    61

  • RELATED FORM

    62

    10.8. PUNCH LIST FORM

    Revision 2, September 2017, Document for Private Internal Circulation Only.

    “Copyright© 2017 by PEB Steel Buildings Co.,Ltd. All rights reserved. No part of this brochure may be reproduced without the prior written consent of PEB Steel Buildings Co., Ltd.”