Upload
scott-schluter
View
21
Download
0
Tags:
Embed Size (px)
DESCRIPTION
From my "pound of paper" for the PE application.
Citation preview
Engineers – Planners – Scientists – Surveyors – Landscape Architects
C:\DOCUME~1\SSCHLU~1.DPW\LOCALS~1\Temp\Temporary Directory 8 for 2608-Brickstone-2.zip\2608-Brickstone-2\Stormwater\1.2608-Office Memo-SWM-scs-1-18-08.doc
Job Number: 1.2608.13 Printed 9/4/2012 11:26:00 AM
OFFICE MEMO To: Paul Keane
From: Scott Schluter
Cc:
Date: January 18, 2008
Re: Brickstone Stormwater Management Ideas
Paul, below is a list of thoughts for Stormwater Management for the Brickstone project. As I discussed with you, the new Stormwater Regulations (310 CMR 10.00) are in effect (thought in flux) and LID is a big push. Also, many of our familiar treatment trains will no longer meet TSS removal requirements without dramatic changes to our designs resulting in larger basins. Infiltration requirements will also be harder to meet with the new volumes (HSGA=.6" HSGB=.35" HSGC=.25" HSGD=.10"). As suggested in the new regulations and draft handbooks, the time to think about stormwater is now, in the design phase at the beginning. Below is an outline of ideas that I think we may want to consider for this project. Note: With the vernal pool onsite, we have to deal with new ORWs regulations. "Stormwater Management to a Certified Vernal Pool *Stormwater management systems should avoid impacts to vernal pool *Must be set back 100 feet and comply with 310 CMR 10.60 *Habitat evaluation required *Must demonstrate will meet performance standard of no adverse impact on habitat functions of a certified vernal pool"
Potential BMPs
Pretreatment BMPs • Vegetated Filter Strips
o 10% TSS 25' wide, 45% TSS 50' wide o Use where curbless pavement is possible? o Lined where vernal pool
• Deep Sump Catch Basins o 25% TSS
Engineers – Planners – Scientists – Surveyors – Landscape Architects
C:\DOCUME~1\SSCHLU~1.DPW\LOCALS~1\Temp\Temporary Directory 8 for 2608-Brickstone-2.zip\2608-Brickstone-2\Stormwater\1.2608-Office Memo-SWM-scs-1-18-08.doc
Job Number: 1.2608.13 Printed 9/4/2012 11:26:00 AM
o Use where curbless pavement isn't possible • Proprietary Separators (Downstream Defender, Stormceptor, etc.)
o TSS removal per Umass study o Use where "soft" BMPs won't fit due to available space
• Sediment Forebays o No TSS removal where used as pretreatment where required (infiltration
basin, stormwater wetlands, etc.) o 25% TSS removal where used as a separate BMP o Use for our ponds if there is room
Treatment BMPs • Bioretention Areas & Rain Gardens
o 90% TSS removal with vegetated filter strip or equivalent o Can be infiltration cells or not o Use for roofs? Infiltrate! o Use for parking areas? Infiltrate if vegetated filter strip can be constructed!
(Need the 44% TSS removal first so 50' strip) o OK for vernal pool o
o • Constructed Stormwater Wetlands
o 80% TSS when forebay used o Will fit in with what Crowe has suggested for the ponds already but will
require design modifications to really be constructed wetlands o No recharge o OK for vernal pool
• Extended Dry Detention Basin o 50% TSS when forebay used o No recharge o BIG to really qualify as extended dry detention basins
24 hour detention of 2 year storm in low stage low flow channel to low stage
o No use at vernal pool
Parking
Forebay
Bioretention
Parking
Engineers – Planners – Scientists – Surveyors – Landscape Architects
C:\DOCUME~1\SSCHLU~1.DPW\LOCALS~1\Temp\Temporary Directory 8 for 2608-Brickstone-2.zip\2608-Brickstone-2\Stormwater\1.2608-Office Memo-SWM-scs-1-18-08.doc
Job Number: 1.2608.13 Printed 9/4/2012 11:26:00 AM
• Sand & Organic Filters o Tree Box Filter
6' diameter 4' high manhole section Tree in center Rip rap splash pad Underdrain No recharge 80% TSS also can be used as a pretreatment device if lined Are there plans for trees down the entrance road???? Not for vernal pools area
• Wet basins
o 80% TSS when forebay used o No recharge o BIG to really qualify as wet basins o This is probably a better fit to the Crowe design o Not for vernal pool areas
Conveyance BMPs • Grassed Channel (Biofilter Swale)
o 50% TSS with sediment forebay o Not suitable for vernal pool o Use in place of pipe system where we can? o No recharge
• Water Quality Swale o 70% TSS removal with a forebay o No recharge o Use in place of pipe system where we can? o Ok for vernal pool areas need 44% TSS removal or lined
Infiltration BMPs • Drywells
Sand soil mix
Underdrain
Tree overflow Pavement
To drainage
Engineers – Planners – Scientists – Surveyors – Landscape Architects
C:\DOCUME~1\SSCHLU~1.DPW\LOCALS~1\Temp\Temporary Directory 8 for 2608-Brickstone-2.zip\2608-Brickstone-2\Stormwater\1.2608-Office Memo-SWM-scs-1-18-08.doc
Job Number: 1.2608.13 Printed 9/4/2012 11:26:00 AM
o 80% TSS o Ok for vernal pool areas
• Infiltration Basins o 80% TSS removal with pretreatment o Needs 44% TSS removal prior to it o We could possibly convert or modify one or more of Crowe's ponds into
one o Ok for vernal pool areas
• Infiltration Trenches o 80% TSS removal with pretreatment o Needs 44% TSS removal prior to it o Use at parking areas? o Ok for vernal pool areas
• Subsurface Structures (Rainstore, Arches, Pipes, etc.) o 80% TSS for non-proprietary (proprietary #s to come out) o Needs 44% TSS removal prior to it o Ok for vernal pool areas
Other BMPs • Dry Detention Basins
o Closer to what we typically design o No TSS removal o No Recharge o Could use this after a TSS treatment train o Not for vernal pool areas
• Green Roofs o If retains the WQV can remove from impervious surface area o Will the area of the garage qualify as roof? If so, would the landscaped
areas qualify it as a green roof? • Porous Pavement
o 80% TSS removal if bed is ½" or 1" WQV and drains in 72 hours o Need permeability of 0.5 inches per hour o Use for the "jug handles"? o Porous asphalt or pavers o Not for vernal pool areas
• Rainbarrels and cisterns o Deduct roof from impervious if sized for ½" or 1" and stored water is used
within 72-hours or is discharged to an infiltration BMP o If we use cisterns for irrigation water we can remove the roof area from
our calculations
E1
E14E16
E17
E6
E7
E8
E9 P10
P11
P12 P13
P15
P18 P19
P2
P20 P21
P22
P23
P3
P30
P31 P32
P33
P4 P41 P42 P43
P44
P45
P5
ROOFHC
ROOFS
BRIGGS
R1
R2
R3
R4
R5 R6
R7
1
2
3
5 6 7 7-1CB
7-2CB
7-3CB
7-4CB
8
8PCB
CBCB
D1
Depression
D2
D3
DMHACB
DMHBCB
Re1
Re2
Re3
VP
W1
W2
W3
W4
W5
Drainage Diagram for 2608-PROPOSED-SITE PLANSPrepared by Tetra Tech Rizzo, Printed 11/7/2008
HydroCAD® 8.50 s/n 005923 © 2007 HydroCAD Software Solutions LLC
Subcat Reach Pond Link
2608-PROPOSED-SITE PLANS Printed 11/7/2008Prepared by Tetra Tech Rizzo
Page 2HydroCAD® 8.50 s/n 005923 © 2007 HydroCAD Software Solutions LLC
Area Listing (all nodes)
Area(acres)
CN Description(subcatchment-numbers)
20.980 30 Woods, Good, HSG A (E14,E16,E17,E6,E7,E8,E9,P10,P11,P13,P5)3.590 39 >75% Grass cover, Good, HSG A (E6,E7,E8,E9,P10,P11,P13,P30,P31,P32,P33,P5)
27.170 55 Woods, Good, HSG B (E7,E8,P12,P13,P15,P2,P3,P4,P5)3.170 61 >75% Grass cover, Good, HSG B (E7,E8,P12,P13,P15,P2,P4,P5)
71.770 70 Woods, Good, HSG C (E1,E6,E7,E8,P10,P11,P12,P13,P2,P3,P4,P42,P43,P5)7.280 74 >75% Grass cover, Good, HSG C (E1,E7,P10,P13,P2,P20,P21,P30,P4,P42,P43,P44,P5)
37.710 77 Woods, Good, HSG D (E1,E14,E16,E17,E6,E7,E8,E9,P12,P13,P2,P3,P4,P41,P42,P44,P5)16.290 78 Wetlands, Dry (E17,P13,P3,P4)0.170 79 50-75% Grass cover, Fair, HSG C (P3)
15.960 80 >75% Grass cover, Good, HSG D (E6,E8,P12,P13,P18,P19,P20,P22,P23,P4,P42,P43,P44,P45)0.540 82 Dirt roads, HSG B (P13,P2,P4,P5)2.050 83 Paved roads w/open ditches, 50% imp, HSG A (E6,E7,E8,P10,P11,P5)0.270 84 50-75% Grass cover, Fair, HSG D (P2,P3)0.150 87 Dirt roads, HSG C (P13,P4)0.800 89 Dirt roads, HSG D (P13,P2,P4)0.020 89 Paved roads w/open ditches, 50% imp, HSG B (E1)
13.540 90 Ledge (E7,E8,P12,P13,P18,P19,P2,P20,P3,P4,P41,P42,P43,P5)0.060 90 RIP-RAP (P13)0.360 91 Gravel roads, HSG D (P43,P45)0.170 92 Paved roads w/open ditches, 50% imp, HSG C (E1)1.020 93 Paved roads w/open ditches, 50% imp, HSG D (E1,E7,E8,P10)2.540 98 Basin (P19,P20,P21,P23,P41,P43,P45)0.160 98 Briggs Pond (E14,P11)4.210 98 Existing Paved parking & roofs (offsite) (E6,E7,E8,E9,P10,P2,P5)0.060 98 Golf Hut roof (P43)8.400 98 Paved parking (P18,P19,P20,P21,P23,P43)2.890 98 Paved parking & roofs (E1,P11,P22,P30,P31,P32,P33)1.960 98 Roof (ROOFHC)5.220 98 Roofs (P23,ROOFS)0.170 98 Walk (P42)0.020 98 Walks (P44)
31.920 98 Wetlands, Wet (E14,E7,E8,E9,P10,P11,P12,P2,P33,P4,P5)280.620 TOTAL AREA
Job:
Sha
ron
Hill
sS
heet
No.
1of
1C
alc
by:
SC
SD
ate
11/7
/200
8C
heck
by:
Dat
e
De
Min
imus
Cal
cula
tions
80%
TS
S re
mov
al m
ust b
e ac
hiev
ed o
n an
ave
rage
wei
ghte
d ba
sis
from
the
site
as
a w
hole
usi
ng th
e"W
eigh
ted
Ave
rage
Met
hod"
.(fr
om V
ol. 3
, Ch.
1, P
age
35, M
assa
chus
etts
Sto
rmw
ater
Han
dboo
k)
Are
aS
ize
(ac)
TSS
Rem
oval
(%)
(Are
aXTS
S)
Re2
0.34
97%
0.32
98R
e30.
0797
%0.
0679
P33
0.21
78%
0.16
38S
UM
=0.
62S
UM
=0.
5615
(Are
a 1)(
TSS
1%)+
(Are
a 2)(
TSS
2%)+
(Are
a 3)(
TSS
3%)+
(Are
a 4)(
TSS
4%)…
.
Wei
ghte
d A
vera
ge %
=(A
rea 1
)(TS
S1%
)+(A
rea 2
)(TS
S2%
)+(A
rea n
)(TS
Sn%
)(A
rea 1
+Are
a 2+A
rea n
)
Wei
ghte
d A
vera
ge %
=
Dra
inag
e A
reas
(1)
(1
)(
2)(
2)
(3)
(3
)(
4)(
4)
=0.
5615
0.62
=0.
9191
%M
eets
Dem
inim
us fo
r Tre
atm
ent
=0.
65cf
sM
eets
Dem
inim
us fo
r Dis
char
ge(<
1 cf
s)2
Yea
r Q (P
33)
gg
(Are
a 1+A
rea 2
+Are
a 3 +
Are
a 4+.
..)
Job: Sharon HillsSheet No. 1 of 1Calc by: SCS Date 11/5/2008Check by: Date
Groundwater Determination-Recharge Area 1
Well ID
GZAPVC TopElevation (ft)
PVC Height(aboveground)
(ft)
TtRPVC TopElevation (ft)
Depth to GW from PVC (ft)
GZAGroundwaterElevation(ft)
TtRGroundwaterElevation(ft)
Delta (TtR-GZA)
OW1-20 279.72 2.3 278.92 32.23 247.49 246.69 -0.80OW1 50 277 55 2 1 277 55 25 18 252 37 251 57 0 80OW1-50 277.55 2.1 277.55 25.18 252.37 251.57 -0.80OW1-100 275.79 2.3 274.99 25 250.79 249.99 -0.80OW1-150 268.55 2.9 267.75 20.86 247.69 246.89 -0.80
Groundwater at Recharge Area 1= 251.57 feet (OW1-50)
My Groundwater at Rechrge Area 1= 251.6 feet (OW1-50)delta= -0.03 feetdelta 0.03 feet
MW OW….Casing=PVC=GND=GW(4/14/03)GW(4/14/03)=
"THUMB AREA"CASING PVC GND GW
OW1-20 279.07 278.92 276.62 246.69OW1-50 276.93 276.75 274.65 251.57OW1-100 275.02 274.99 272.69 249.99OW1-150 267 8 267 75 264 85 246 89OW1-150 267.8 267.75 264.85 246.89
Job: Sharon HillsSheet No. 1 of 1Calc by: SCS Date 11/7/2008Check by: Date
Level Spreader Calculations
Width
Use 6 foot Minimum width all level spreaders
LocationPipe D
(ft)
Outlet Apron Width
(ft)
Level Spreader
Width (ft)
FEO1-1 1.50 4.50 6.00FEO2-1 3.00 9.00 10.00FEO7-1 2.00 6.00 6.00FEO7-2 1.00 3.00 6.00FEO8 1 2 00 6 00 00FEO8-1 2.00 6.00 7.00
Depth
Q (Actual)
(ft³/s)
Pipe Diameter
(ft)Slope, s
(ft/ft)Manning's
n
Depth in pipe (ft) Ø (deg)
Area (ft²)
Wetted Perimeter
(ft)
HydraulicRadius
Rh (ft)
Q PIPE (ft³/s)
FEO1-1 3.17 1.50 0.012 0.013 0.5380 147.16 0.570 1.93 0.30 3.17FEO2-1 17.03 3.00 0.028 0.013 0.7950 123.93 1.500 3.24 0.46 17.03FEO2 1 17.03 3.00 0.028 0.013 0.7950 123.93 1.500 3.24 0.46 17.03FEO7-1 26.61 2.00 0.021 0.013 1.3652 137.16 2.285 3.89 0.59 26.61FEO7-2 4.07 1.00 0.026 0.013 0.6210 151.99 0.513 1.82 0.28 4.07FEO8-1 23.76 2.00 0.017 0.013 1.3483 139.23 2.253 3.85 0.58 23.76
Qpipe = 1.486/n*A*(Rh)^(2/3)*s^0.5
LocationQ (cfs)
100 YearPipe
Invert (ft)TW
Elevation (ft)FEO1-1 3.17 301.00 301.54FEO2-1 17.03 305.00 305.80FEO7-1 26.61 263.00 264.37 264.50
Level Spreader Lip Elevation
301.60306.00
FEO7-2 4.07 254.00 254.62FEO8-1 23.76 281.00 282.35
Length
0.5 cfs/ft
LocationQ (cfs)
100 Year Q/.5Min. Length
(ft)FEO1-1 3.17 6.34 6.5FEO2-1 17 03 34 06 35 0
282.50254.70
FEO2-1 17.03 34.06 35.0FEO7-1 26.61 53.22 54.0FEO7-2 4.07 8.14 9.0FEO8-1 23.76 47.52 48.0
```
Job: Sharon HillsSheet No. 1 of 1Calc by: SCS Date 11/7/2008Check by: Date
Recharge CalculationsRequired Recharge VolumeHydrologic Proposed Target Depth RequiredHydrologic Proposed Target Depth RequiredSoil Group Impervious Area X Factor = Recharge
(sf) (in) Volume(cf)
A 21,240 0.60 1,062B 0 0.35 0C 92,693 0.25 1,931D 653,050 0.10 5,442
Sum: 766,983 sf 8,435 cf17 61 ac 0 19 af17.61 ac 0.19 af
Capture Area AdjustmentPond 7 Discharges
Storm
Primary Discharge
(cfs)
Secondary Discahrge
(cfs)RECHARGED
TotalDischarge
(cfs) % Recharged1 9.54 4.26 13.8 30.9%2 15.99 5.88 21.87 26.9%
10 24.31 8.32 32.63 25.5%25 25.12 10.05 35.17 28.6%
100 26.62 10.76 37.38 28.8%Ave= 28%
Impervious Areas Contributing to Pond 7Sub. Area (ac)
P-18 0.46P-19 0.34P 19 0.34P-20 3.85P-21 0.27P-23 5.00
ROOFS 0.30TOTAL= 10.22
TOTAL X AVE % TO RECHARGE= 2.87Impervious to Re2= 0.34Impervious to Re3= 0.07
Total= 3 28Total= 3.28Total Impervious Area: 17.61 ac 65%= 11.45 ac
Area contributing to Recharge systems: 3.28 ac 33%Adjustment factor: 17.61 = 5.36
3.28Adjusted volume: 8,435 x 5.36 = 45,230 cf
1.04 af
1 and 100 Year Storm Infiltration Volume (TR 20 w/HydroCAD)
Volume Infiltrated from Rainfall1 year (af) 100 year (af)
Re1 4.62 5.36Re2 0.07 0.19Re3 0.02 0.04
Total 4.71 5.59In the 1 year storm, 4.5 times the recharge volume is infiltratedIn the 100 year storm, 5.4 times the recharge volume is infiltrated
Job: Sharon HillsSheet No. 1 of 1Calc by: SCS Date 10/23/2008Check by: Date
Downstream Defender Sizing Calculations: DD-P1For sizing "Flow-Through" treatment devices as the Downstream Defender, the Massachusetts Department of Environmental Protection has developed a relation between storm intensity and the depth of runoff (See "Development of a Rational Basis for Designing Recharging Stormwater Control Structures adn Flow And Volume
3.24 (P43)0 06Total Roof Area:
Design Criteria" MADEP 99-06/319). This allows the sizing of the treatment unit based on a flow rate instead of a volume. (See Table x from the report, below)
Based on the first 1.0 inches of rainfall on the mainland (off Cape-Massachusetts) with a 95% probability, use max. storm intensity of 1.67 in/hr (Table 4).
Total Runoff Required to Be Treated
Total Impervious area:0.063.18
Flow = 1.67 x 3.18 x 453 gpm/ac-in/hr = 2,406 gpm5.36 cfs
Q100 Year= 65.92 cfs x 448.8 gal-s/cf-min = 29,585 gpm
Total Roof Area:Total Runoff to Be Treated:
Downstream Defender Sizing
Use 6 ft. diameter Downstream Defender Unit with bypassFlowrate at 60% Removal Efficiency= 8 cfs (see chart)
LOCATION Q Size So n d Ø A WP Rh QFROM TO (Actual)
(ft³/s) (ft) ft/ft) ( - ) (ft) (deg) (ft²) (ft) (ft) (ft³/s)DMH1-9 DMH1-10 5.36 2.00 0.040 0.013 0.4650 115.31 0.554 2.01 0.28 5.36
Invert in Weir Manhole= 311.60Elevation Weir= 312.07
Job: Sharon HillsSheet No. 2 of 2Calc by: SCS Date 11/7/2008Check by: Date
Drawdown Calculations
Time= RvTime= Rv(K)(Bottom Area)
System 1Rv= 233,482 cf K= 2.41 in/hr
Bottom Area= 24,336 sf
Ti 47 8 hTime= 47.8 hours
47.8 < 72 OK
System 2Rv= 8,276 cf K= 2.41 in/hr
Bottom Area= 2,027 sf
Time= 20.3 hours
20.3 < 72 OK
System 3Rv= 1,742 cf K= 2.41 in/hr
Bottom Area= 590 sf
Time= 14 7 hoursTime= 14.7 hours
14.7 < 72 OK
VP elev. Start is 276 Q,V Q,V Q,V Q,V Q,V Q,V Q,V Q,VVP W3 W4 W5 Briggs D1 D2 D3
E 1 yr Q 22.3 13.1 5.0 21.6 13.1 0.0 0.0 0.01 yr VElev 276.7 238.2 274.0 253.7 281.2 263.0 242.0
P 1 yr Q 20.2 12.0 4.4 21.5 12.0 0.0 0.0 0.01 yr VElev 276.6 238.2 274.0 253.7 281.2 263.0 242.0
E 2 yr Q 40.4 28.8 8.0 39.6 28.9 0.1 0.0 0.02 yr VElev 277.0 238.3 274.1 254.1 281.4 263.0 242.0
P 2 yr Q 35.3 25.8 6.5 38.3 26.0 0.1 0.0 0.02 yr VElev 276.9 238.3 274.1 254.1 281.5 263.0 242.0
E 10 yr Q 85.4 77.5 14.9 84.7 81.1 0.5 0.0 0.010 yr VElev 277.7 238.6 274.1 254.4 281.9 263.0 242.4
P 10 yr Q 73.9 67.9 11.4 75.6 73.1 0.4 0.0 0.010 yr VElev 277.4 238.6 274.1 254.4 282.1 263.0 242.9
E 25 yr Q 111.3 108.9 18.7 110.9 121.9 0.8 0.0 0.025 yr VElev 278.0 238.8 274.1 254.6 282.2 263.1 243.0
P 25 yr Q 96.0 95.8 14.1 92.9 110.3 0.7 0.0 0.025 yr VElev 277.7 238.7 274.1 254.6 282.3 263.1 243.4
E 100 yr Q 154.6 166.0 25.1 155.1 201.0 1.4 0.0 0.1100 yr V 24.5 62.1 3.5 23.6 80.7 0.1 0.0 0.0Elev 278.5 239.0 274.1 255.0 282.6 263.4 243.7
P 100 yr Q 132.5 145.1 18.3 122.7 179.4 1.1 0.0 0.2100 yr V 26.1 65.1 1.3 22.2 82.2 0.1 0.0 0.0Elev 278.2 238.9 274.1 255.0 282.8 263.4 244.2
Volumes calculated with 0-850 hour time span
Pond 1 Pond 2 Pond 3 Pond 5Berm 315 Berm 339 Berm 329 Berm 288.0Bottom 307 Qout Bottom 334.5 Qout Bottom 326 Qout Bottom 283.0 Qout
1 308.6 1.3 1 335.3 3.3 1 326.4 0.3 1 283.8 12.42 309.3 1.7 2 335.6 5.2 2 326.6 0.4 2 284.1 17.8
10 310.9 2.4 10 336.2 9.4 10 327.2 0.7 10 285.1 19.625 311.9 2.7 25 336.7 11.1 25 327.5 0.8 25 285.7 20.7
100 313.3 3.2 100 337.9 13.6 100 328.0 1.0 100 286.8 22.6Pond 6 Pond 7 Pond 8Berm 281.0 Berm 274.0 Berm 356.0Bottom 277.0 Qout Bottom 270.0 Qout Bottom 351.5 Qout
1 277.9 16.6 1 271.2 13.8 1 352.0 1.02 278.2 24.7 2 271.5 21.9 2 352.1 1.4
10 278.5 35.0 10 271.9 32.6 10 352.4 2.425 278.6 40.3 25 272.2 35.2 25 352.6 2.9
100 278.9 48.4 100 272.7 37.4 100 352.8 3.5
Re1 Re2 Re3Top 259.10 Rech. Top 253.00 Rech. Top 249.50 Rech.Bottom 255.60 Vol. Bottom 249.50 Vol. Bottom 246.00 Vol.
1 256.54 4.62 1 249.87 0.07 1 246.17 0.022 257.00 2 250.17 2 246.48
10 257.76 10 250.89 10 246.9625 258.06 25 251.40 25 247.28
100 258.99 5.36 100 252.67 0.19 100 247.90 0.04
Des
igne
d B
yD
raw
n B
yA
ppro
ved
By
Che
cked
By
Rev
isio
ns
NO
TIC
E O
F I
NT
EN
TS
HA
RO
N H
ILLS
AC
CE
SS
DR
IVE
SH
AR
ON
, M
A
CO
NS
TRU
CTI
ON
AC
CE
SS
PLA
N &
PR
OFI
LE
1"=
40'
127-
1260
8
2608
NO
I
Oct
ober
1, 2
008
9
Des
igne
d B
yD
raw
n B
yA
ppro
ved
By
Che
cked
By
Rev
isio
ns
NO
TIC
E O
F I
NT
EN
TS
HA
RO
N H
ILLS
AC
CE
SS
DR
IVE
SH
AR
ON
, M
A
WE
TLA
ND
CR
OS
SIN
G &
CH
AN
NE
L D
ETA
ILS
AS
SH
OW
N
127-
1260
8
2608
NO
I
Oct
ober
1, 2
008
10
Des
igne
d B
yD
raw
n B
yA
ppro
ved
By
Che
cked
By
Rev
isio
ns
NO
TIC
E O
F I
NT
EN
TS
HA
RO
N H
ILLS
AC
CE
SS
DR
IVE
SH
AR
ON
, M
A
WE
TLA
ND
CR
OS
SIN
G,
ALT
ER
ATI
ON
&R
EP
LAC
EM
EN
T P
LAN
AS
SH
OW
N
127-
1260
8
2608
NO
I
Oct
ober
1, 2
008
11
Nantucket- Paradise Found In December 2006, Esther’s Island Partners LLC (“EIP”) had a vision to purchase an existing classic beach cottage on 10 waterfront acres on Esther’s Island (off the west end of Nantucket). It was EIP’s intention to rebuild the cottage as a LEED for Homes structure for use by a shared ownership group to be called Esther’s Island Resorts.
During the pre-purchase contingency period, the Environmental Services Group assisted EIP to acquire necessary Conservation Commission, Board of Health and Historic District Commission permits and approvals to allow the purchase and the renovation project to move forward. The approved project provides for a renovated dwelling that includes a fire-placed living room and kitchen, 3 bedrooms, 3 bathrooms and deck areas served by a new well, advanced nitrogen removing septic system and a hybrid wind/solar system to provide for the off-grid power needs. We provided environmental evaluation services to address soils, groundwater, wetland resource area and shellfish and eelgrass issues, construction procedures and protocols. Survey Services provided for all the site survey and Engineering provided for the design and approval of an Innovative/Alternative Nitrogen-reducing septic system to protect groundwater and the waters of Madaket Outer Harbor. Construction commenced in October 2007.
••••••••••••••••••••••••
••••
••••
••••
••••
•••••
••••
••••
••••
••••
•24
" G
aske
ted
Fibe
rgla
ssLi
d W
ith S
.S. B
olts
Sim
plex
Pum
ping
Sys
tem
••••
••••
••••
••••
•••••
••••
••••
••••
••••
•24
" G
aske
ted
Fibe
rgla
ssLi
d W
ith S
.S. B
olts
(typ
.)
Min
. 18"
Dia
.Ta
nk O
peni
ng
Inle
t
Reci
rcul
atin
g Sp
litte
rVa
lve
(RSV
QD
) with
Qui
ck D
isco
nnec
t
Inle
t
AX20
Adv
anTe
x Fi
lter
2" D
ia. V
ent
Biot
ube
Pum
p Va
ult
Mod
el P
VU68
-242
5-L
Side
Vie
wSc
ale:
1"
= 3
'-0"
Top
Vie
wSc
ale:
1"
= 3
'-0"
End
Vie
wSc
ale:
1"
= 3
'-0"
•••
••••
••••
•••••
••••••
••••
Line
Hig
h H
ead
Pum
pM
odel
P30
0511
1,50
0 G
allo
nTw
o-C
ompa
rtm
ent
Ore
nco
Syst
ems,
Inc.
Tank
Flow
-th
roug
hpo
rt
Tank
Sad
dle
11"
64.5
"
13"
24.5
"
28"
25"
90"
167.
9"
71.5
"
11"
•••
•••••
••••
••••
••••
••••••
••••••
••••••
••M
odel
HV1
00
Floa
t Ass
embl
yM
odel
MF3
A
Biot
ube
Filt
er (2
4")
Y G W
15"
99.2
5"
Expe
cted
Influ
ent Q
ualit
yG
reas
e &
Oil:
2
0 m
g/L
BO
D:
150
mg/
L
TSS:
4
0 m
g/L
TK
N:
65
mg/
L
Typi
cal E
fflu
ent Q
ualit
y
B
OD
: <
10 m
g/L
TSS
: <
10 m
g/L
TN
: <
25 m
g/L
Expe
cted
Flo
ws
Q
=
500
gpd
U
p To
4 B
edro
oms
Peak
Des
ign
Not
es
••
••
•••
••••
••••
••••
••••
••••
••••
••••
••••
•Sl
ope
(min
. 1/4
"/ft.
)
Y G W B R
Hig
h Le
vel A
larm
Ove
rrid
e Ti
mer
ON
/OFF
LLA/
ROPu
mp
On
Pum
p O
ff
Floa
t Fun
ctio
ns
Pum
p Ba
sin
Mod
el P
BAX2
472
FI
To D
rain
field
Floa
t Ass
embl
yM
odel
MF3
A
Dis
char
ge A
ssem
bly
Efflu
ent P
ump
Mod
el P
EF33
11
B RY
To C
ontr
ol P
anel
Splic
e bo
x M
odel
SBE
X4(O
ptio
nal M
odel
SB4
not
show
n)
To D
rain
field
Sca
le in
Fee
t
0
Figu
re
2702
-GR
AD
ING
SK
ETC
H.D
WG
June
10,
200
8
10'
1O
ver S
eptic
Com
pone
nts
Pro
pose
d G
radi
ngE
sthe
r's Is
land
Nan
tuck
et, M
A 0
2554
12 O
ak S
treet
Est
her's
Isla
nd P
artn
ers,
LLC