42
SO YOU’RE THE NEW WELDING ENGINEER Mike Rice Sr. Corporate Welding Engineer The Importance of Pre and Post-Weld Operations Fabtech 2014

SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

Embed Size (px)

Citation preview

Page 1: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

SO YOU’RE THE NEW WELDING ENGINEER

Mike Rice Sr. Corporate Welding Engineer

The Importance of Pre and Post-Weld Operations Fabtech 2014

Page 2: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

The Importance of Pre and Post-Weld Operations

• Pre-Weld Operations Planning

• Post-Weld Operations Review

Page 3: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

Pre-Weld Operations Questions to ask when you are given a job:

What / When / Where / How

• What is the scope of work? • Code of Construction • In House Specifications • Customer Specifications • Drawings • Materials • NDE Requirements

Page 4: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

Pre-Weld Operations Questions to ask when you are given a job:

• When does fabrication start / to be completed?

• Develop a schedule

Page 5: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

Pre-Weld Operations Questions to ask when you are given a job:

• Where is the fabrication to be performed?

• In the shop • In the field • Both in the shop and the field

Page 6: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

Pre-Weld Operations Questions to ask when you are given a job:

• How is the fabrication to be performed?

• Welding equipment • Welding consumables • Machining equipment • Jigs and fixtures

Page 7: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

What does this look like in real life?

Page 8: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

UREA REACTOR

EXTENSION

Belle Plaine, Saskatchewan, Canada

Page 9: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

What is the Scope of Work?

• Remove top head

• Attach shell and head extension assembly onto existing shell

• Install internals

• Replace nozzle in the bottom head

Page 10: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

Code of Construction • Structural Carbon Steel – AWS D1.1 • Structural Stainless Steel – AWS D1.6 • Piping – B31.1, B31.3 • Pressure Vessel – ASME Section I, VIII (Div. 1 or 2) Nuclear

Section III • Overseas – ISO

• Government Specification – Federal, Military, DOT,

Country Requirements, etc.

Page 11: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

Customer Specification Customers and/or Engineering Firms have additional requirements in addition to Codes

– Acceptable welding processes • No FCAW or GMAW

– Welder Qualifications

– Requirements for preheat and interpass

– Requirements for PWHT

– Additional NDE (hardness, chemistry, etc.)

Page 12: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

Drawings Drawings contain a lot of valuable information.

– Dimensions

– Weld joint locations

– Types of joints (Butt – CJP, PJP, Fillet, etc.)

– Code of Construction

– Materials

– NDE

Page 13: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

Existing Vessel Extension

Dia: 10.5’ Length: 130’ T/T Thickness: 5 1/8”

Addition Length: 16’ Total Length: 146’ T/T Thickness: 4 7/8”

Page 14: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

Materials

• SA-724-B (95 ksi tensile strength) Bottom Shell

• SA-240-316L Mod Stainless Steel Liner

• SA-517-B (115 ksi tensile strength) New Top Shell and Head Assembly

• SA-240-S32906 New Liner (Super Duplex)

Page 15: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

HEAD REMOVAL

Cut Line

5 1/8” thick

Page 16: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

HEAD REMOVAL

• Method to cut the head? (The How ?)

– Oxy-fuel

– Machine

– Water Jet

Page 17: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

WATER JET CUTTING

Page 18: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

WATER JET CUTTING

Page 19: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

MACHINING OF WELD PREP

Page 20: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

MACHINING COMPLETE

Page 21: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

SETTING SHELL VERTICAL

Page 22: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

NEW EXTENSION LIFT

Page 23: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

NEW EXTENSION LIFT

Page 24: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau
Page 25: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau
Page 26: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

WELDING PROCESS AND FILLER

• SMAW process

–Customer driven

• What filler?

–E9018-D1

• Procedure & Welder Qualification – ASME Section IX.

Page 27: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

WELDER QUALIFICATION

• Welders were qualified in Canada to the Canadian Bureau requirements.

• Welders required by customer

specifications to successfully pass additional qualifications for the internal welds.

• Required to weld a 5 inch thick test coupon

Page 28: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

ID IS COMPLETE

Page 29: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

OD IS STARTED

Page 30: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

WELDING OD

Page 31: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

OD IS COMPLETE

Page 32: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

NDE

• MT on backgouge surface

• MT final (ID & OD)

• PT on ID overlay

• Volumetric – RT?

– UT

Page 33: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

UT (PHASED ARRAY) ON ID

Page 34: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

Post-Weld Operations

Post-Weld Operations – Review of the project. This is a time to learn from the project not a time to beat people over the head.

Page 35: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

Post-Weld Operations

Perform a “Lessons Learn” review

• It does not matter the project size • Within the company • With the subcontractors • Customer

Page 36: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

Post-Weld Operations

“Lessons Learn” consists of:

• What went well • What did not go so well • Action items

Page 37: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

Post-Weld Operations

Areas to consider:

– Safety – Lost Time accidents – Near misses

– Quality – Weld reject rate (VT, MT, PT, RT, UT) – Meet customer expectations – What was done to insure quality

Page 38: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

Post-Weld Operations

Areas to consider:

– Planning – Were drawings adequate – Were the specifications clear – Additional training needed

– Tooling – Were the correct tools and quantity on the

job? – Fixtures

Page 39: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

Post-Weld Operations

Areas to consider: – Welding

– Correct process used – Better process – Fit-up – Sequence

– Subcontractors – Communication – What concerns would there be on future

projects – Why would you use them again

Page 40: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

What Made This Project Successful?

• Knowing the job scope: – Very clear scope

• Having time to plan: – Able to have welders make mock-ups

• Communication: – Customer – Licensee Engineering firm – Canadian Welding Bureau – Subcontractors

Page 41: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

JOB WELL DONE

Page 42: SO YOU’RE THE NEW WELDING ENGINEER Code of Construction ... Canadian Bureau requirements. ... –Canadian Welding Bureau

The Importance of Pre and Post-Weld Operations

Ask the key questions: What / When / Where / How