30
Consolidated Edison Company of New York, Inc. Electric Grid Hardening and Resiliency Initiatives Griffin Reilly Electric Distribution Engineering April 17 th , 2015

Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

  • Upload
    lethien

  • View
    219

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Consolidated Edison Company of New York, Inc.

Electric Grid Hardening and Resiliency Initiatives

Griffin ReillyElectric Distribution EngineeringApril 17th, 2015

Page 2: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Con Edison Electric Distribution SystemNEW YORK CITY and WESTCHESTER

• Population 9,263,869• 604 square miles• Electric customers 3,338,729• 62 Area Substations• 2,194 Distribution Feeders• Peak Load – 13,322 MW• 13% of Capacity is Overhead

• 154 Autoloops• 232 4kV Substations

• 87% of Capacity is Underground• 64 (N-2) Networks• 19 (N-1) Networks

Page 3: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Frequency of Service Interruptions per 1000 Customers

0

200

400

600

800

1000

1200

1400

National New York * ConEd-Overhead ConEd-Overall

Blue Sky Day Reliability Comparison

ConEd-Network* Without Con Edison

Page 4: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Pre-Sandy Hardening and Resiliency Investments

4

Since 1992 nor'easter− Raised critical equipment to enhance

flood protection

− Upgraded pumps and flood gates

− Installed protective moats

Since Hurricane Katrina− New transformers and network

protectors in flood zones must be submersible or installed above flood level

− New submersible equipment tested to operate under 25 feet of brackish water

Limiting Damage to Overhead System– Aggressive tree trimming to reduce storm

damage to power lines

– Monthly aerial inspections and semi-annual ground patrol inspection of transmission line rights-of-way

Additional Investments– Control centers can remotely monitor

power flow, feeder status, and switches

– Operators can remotely operate breakers and switches to manage the grid and improve restoration lines

Page 5: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Storm Preparations: Guided by Corporate Coastal Storm Plan

5

Plan triggered October 24, 2012 based on National Weather Service forecasts

Includes:– 24/7 staffing plans

– Inventory Check

– Equipment vulnerability

– Protection plans for equipment in flood zones

– Need for outside assistance

– Operation Modifications

– Communication Protocols

Page 6: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Historical Storm Comparison

6

6

Page 7: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Worked with city and municipalities to clear roads of trees and debris

Primary concern of safety

70 percent of customers served by overhead systems lost power

Sandy’s Impact:Significant Damage to Overhead System

7

Page 8: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

8

Page 9: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

SSS

Substation Circuit Breaker

Supply

Feeder

Overhead System – Typical Radial Design

Page 10: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Con Edison Overhead Auto-Loop

S

SSS

13 kV SubstationCircuit Breaker

13 kV SupplyFeeder

13 kV SubstationCircuit Breaker

TransformerSupplying

Customer Load

FeederRecloser

MidpointRecloser

Tie Recloser (N.O.)

Fuse

TransformerSupplying

Customer Load

13 kV SupplyFeeder

Page 11: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Con Edison Primary (4kV) Network

• Substations are interconnected as a network

• Reliable because alternate supply provided by other stations

Page 12: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

12

SCADA

Page 13: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Overhead System Hardening

13

Selective Undergrounding

Reduce Segment Size

Advanced Equipment

Sacrificial Components

Page 14: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Overhead Distribution Initiatives

Extend new feeder

Armonk loop into two loops

New storm hardened cable

VRS

Tie

14W03 7W4514W10

Armonk Loop

S/S S/S

Pleasantville Millwood West

Mid-point

Mid-point

VRS

Banksville Loop

Tie

Mid-point

Mid-point

VRS

VRS

14

Page 15: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Con Edison Underground Network System

Page 16: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Underground Distribution System Impact

Preemptively shutdown 3 networks due to exposure to non-submersible 460V equipment primarily residing in customer premises− Bowling Green (Manhattan)

− Fulton (Manhattan)

− Brighton Beach (Brooklyn)

Preemptive removal of 24 distribution feeders from 8 networks because of 460v equipment

16

Page 17: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

17

Battery Park Underpass

Page 18: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Network Impact Fulton and Bowling Green

Restoration Effort

• 5 days to restore with minimum number of energized feeders

•Manually blocked open 261 NWPs

•Live-end capped 51 transformers

Defective Equipment

•28% of all NWPs in each network were damaged

•43 installations were affected ••• ••

•••••

••

• ••••

••••

••••••

•••• •••••••

••••

Fulton

Bowling Green

Note: “•” indicates affected installations

Page 19: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Underground Network Initiatives

Bowling Green: 123 MW

Fulton: 115 MW

New Sub-Networks

Utilize Latest Technology

Harden Components

Mitigate Impact

Facilitate Restoration

19

Page 20: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Underground Network Initiatives Submersible 460 Volt Network Protector

20

Page 21: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Disconnects Customer Installation from Con Ed System– Con Edison Feeder remains active

– Remote Control operation

– Quick Connect / Disconnect

– Faster Restoration Times

70 Installations for High Tension Customers

20 Used for Network Configuration

13 Used in Brighton Beach

Underground Network Initiatives Isolation Switches

21

Page 22: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

The Fiber Optic NetworkFiber Optic Communication Ring

Bowling Green

Fulton

Seaport #2

Seaport #1

Garage

Page 23: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

East River / E 13th Street Complex

231

East River Substation

E13th Street Substation

East 14th Street

East River Gen Station

23

Page 24: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Flooding at Avenue D and East 13th Street

24

Page 25: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Loss of SupplySubstation Impact

E.13th Street Complex– Affected 7 area substations that

supplied 10 networks (221,103 electric customers)

Seaport– Affected 1 area substation that

supplied one network (2,010 electric customers)

25

Page 26: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Station Storm Hardening Objectives

Prevent de-energization of power supply equipment due to flood water intrusion

Maintain relay protection integrity

Maintain remote control and situational awareness (metering and indication)

Minimize equipment damage from salt water

Allow for rapid recovery

26

Page 27: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Immediate Hardening ScopeJune 1st, 2013

New walls/barriers around critical equipment New sump pumps Sealed conduit penetration points with RTV Shrink wrap important control boxes Install backup nitrogen pumps Raised equipment where feasible and economic Valve-off sewer drains

Governing flood control elevation, higher of:1. SLOSH 20102. 2007 FEMA 100-yr flood +2 feet3. Witnessed Sandy level

Breaker

Discon

nectPothead Stand

Breaker

Rel

ay

Hou

se Control Room Pumping

Plant

Power lineControl/protection line(s)Oil line

Terminal boxInsulator To Distribution

From Transmission

Power Transformer

Flood Control Elevation

Discon

nect

Pothead Stand

Sandy Flood Elevation

Sewer Drain

Page 28: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Collaborative StipulationJune 2013 FEMA Map, 100-yr floodplain +3’

Raise existing walls to meet new criterion

Breaker

Discon

nectPothead Stand

Breaker

Rel

ay

Hou

se Control Room Pumping

Plant

Power lineControl/protection line(s)Oil line

Terminal boxInsulator To Distribution

From Transmission

Power Transformer

Flood Control Elevation Di

scon

nect

Pothead Stand

Sewer Drain

Page 29: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Final Hardening Measures2014 through 2016

Distributed and elevation adjustable relay panels Elevate control house Elevate static terminal boxes Change controls to fiber optic Future design basis will accommodate new level

for future projects

Breaker

Discon

nectPothead Stand

Breaker

Rel

ay

Hou

se

Power lineControl/protection line(s)Oil line

Terminal boxInsulator To Distribution

From Transmission

Power TransformerFlood Control 

ElevationDiscon

nect

Pothead Stand

Control Room Pumping

Plant

Sewer Drain

Page 30: Consolidated Edison Company of New York, Inc. Electric ... Grid Hardening and Resiliency Initiatives ... Underground Distribution System Impact ... Electric Grid Hardening and Resiliency

Consolidated Edison Company of New York, Inc.

Electric Grid Hardening and Resiliency Initiatives

Griffin ReillyElectric Distribution EngineeringApril 17th, 2015